R-2016-151 2016-09-19RESOLUTION NO. R2016-151
A Resolution of the City Council of the City of Pearland, Texas, awarding a
unit cost bid to Lone Star Pavement Services, LLC., for road striping
services, in the estimated amount of $240,000.00, for the period of
September 19, 2016 through September 18, 2017.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That the City recently opened bids for road striping services, and
such bids were evaluated.
Section 2. That the City Council hereby awards the bid to Texas Lone Star
Paving Services, at the unit price amount reflected in Exhibit ''A" attached hereto.
Section 3. The City Manager or his designee is hereby authorized to execute
a contract for road striping services.
PASSED, APPROVED and ADOPTED this the 19th day of
September, A.D., 2016.
ATTEST:
NG LO
SEC': TARY
APPROVED AS TO FORM:
U n»—
6157,4*•-•---
DARRIN
M. COKER
CITY ATTORNEY
c/vill
TOM REID
MAYOR
Bid No. 0716-47
Title Annual Contract for Road Striping Services
Specification Responses
EXHIBIT A - BID TABULATION Cost Estimate for all Streets
Lone Star Pavement Services. LLC
Resolution No. R2O16-151
Exhibit "A"
Stripe -A -Line
Line Description UOM QTY
Unit
Extended
Unit
Extended
1
ROAD STRIPING SERVICES - PAINT
PKG
0
$453.4477
$0.00
$375.95
$0.00
1.1
4" SOLID OR BROKEN WHITE LINE (PAINT) - MATERIAL COST PER LINEAR
FOOT
LF
195936
$0.114
$22,336.704
$0.08
$15,674.88
1.2
4" SOLID OR BROKEN WHITE LINE (PAINT) - LABOR COST PER LINEAR
FOOT
LF
195936
$0.0719
$14,087.7984
$0.08
$15,674.88
1.3
4" SOLID OR BROKEN YELLOW LINE (PAINT) - MATERIAL COST PER
LINEAR FOOT
LF
148003
$0.114
$16,872.342
$0.08
$11,840.24
1.4
4" SOLID OR BROKEN YELLOW LINE (PAINT) - LABOR COST PER LINEAR
FOOT
LF
148003
$0.0719
$10,641.4157
$0.08
$11,840.24
1.5
8" SOLID WHITE LINE (PAINT) - MATERIAL COST PER LINEAR FOOT
LF
4639
$0.86
$3,989.54
$0.15
$695.85
1.6
8" SOLID WHITE LINE (PAINT) - LABOR COST PER LINEAR FOOT
LF
4639
$0.124
$575.236
$0.15
$695.85
1.7
12" SOLID WHITE LINE (PAINT) - MATERIAL COST PER LINEAR FOOT
LF
7021
$0.6169
$4,331.2549
$0.30
$2,106.30
1.8
12" SOLID WHITE LINE (PAINT) - LABOR COST PER LINEAR FOOT
LF
6719
$0.411
$2,761.509
$0.35
$2,351.65
1.9
24" SOLID WHITE LINE (PAINT) - MATERIAL COST PER LINEAR FOOT
LF
2345
$1.23
$2,884.35
$0.55
$1,289.75
1.10
24" SOLID WHITE LINE (PAINT) - LABOR COST PER LINEAR FOOT
LF
2371
$0.82
$1,944.22
$0.60
$1,422.60
1.11
6" LANE LINE SHADOW PAINT (8 FOOT WHITE/8 FOOT BLACK) - MATERIAL
COST PER LINEAR FOOT
LF
36950
$0.27
$9,976.50
$0.30
$11,085.00
1.12
6" LANE LINE SHADOW PAINT (8 FOOT WHITE/8 FOOT BLACK) - LABOR
COST PER LINEAR FOOT
LF
51950
$0.18
$9,351.00
$0.30
$15,585.00
1.13
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING - LABOR COST PER
LINEAR FOOT - 4" Line
LF
15000
$0.514
$7,710.00
$0.33
$4,950.00
1.14
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING - LABOR COST PER
LINEAR FOOT - 6" Line
LF
0
$0.60
$0.00
$0.40
$0.00
1.15
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING - LABOR COST PER
LINEAR FOOT - 8" Line
LF
0
$0.75
$0.00
$0.50
$0.00
1.16
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING - LABOR COST PER
LINEAR FOOT - 12" Line
LF
0
$1.50
$0.00
$0.70
$0.00
1.17
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING - LABOR COST PER
LINEAR FOOT - 24" Line
LF
0
$2.50
$0.00
$1.00
$0.00
1.18
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING - LABOR COST PER
LINEAR FOOT for Arrow or Words
LF
0
$50.00
$0.00
$5.00
$0.00
1.19
WHITE ARROW (PAINT) - MATERIAL COST
EA
101
$33.00
$3,333.00
$55.00
$5,555.00
1.20
WHITE ARROW (PAINT) - LABOR COST
EA
101
$22.00
$2,222.00
$10.00
$1,010.00
1.21
ONLY LEGEND (PAINT) - MATERIAL COST
EA
79
$33.00
$2,607.00
$60.00
$4,740.00
1.22
ONLY LEGEND (PAINT) - LABOR COST
EA
79
$22.00
$1,738.00
$15.00
$1,185.00
1.23
RAILROAD CROSSING LEGEND COMPLETE (PAINT) - MATERIAL COST
EA
2
$123.36
$246.72
$100.00
$200.00
1.24
RAILROAD CROSSING LEGEND COMPLETE (PAINT) - LABOR COST
EA
2
$82.24
$164.48
$25.00
$50.00
1.25
SCHOOL ZONE LEGEND (PAINT) - MATERIAL COST
EA
3
$46.26
$138.78
$80.00
$240.00
1.26
SCHOOL ZONE LEGEND (PAINT) - LABOR COST
EA
3
$30.84
$92.52
$20.00
$60.00
2
ROAD STRIPING SERVICES - THERMO-PLASTIC
PKG
0
$483.213
$0.00
$714.65
$0.00
2.1
4" SOLID OR BROKEN WHITE LINE (THERMO-PLASTIC) - MATERIAL COST
PER LINEAR FOOT
LF
254
$0.37
$93.98
$0.30
$76.20
2.2
4" SOLID OR BROKEN WHITE LINE (THERMO-PLASTIC) - LABOR COST PER
LINEAR FOOT
LF
254
$0.246
$62.484
$0.25
$63.50
2.3
4" SOLID OR BROKEN YELLOW LINE (THERMO-PLASTIC) - MATERIAL COST
PER LINEAR FOOT
LF
3722
$0.37
$1,377.14
$0.32
$1,191.04
Specification Responses
Lone Star Pavement Services. LLC
Stripe -A -Line
2.4
4" SOLID OR BROKEN YELLOW LINE (THERMO-PLASTIC) - LABOR COST
PER LINEAR FOOT
LF
3722
$0.246
$915.612
$0.33
$1,228.26
2.5
8" SOLID WHITE LINE (THERMO-PLASTIC) - MATERIAL COST PER LINEAR
FOOT
LF
60182
$0.431
$25,938.442
$0.50
$30,091.00
2.6
8" SOLID WHITE LINE (THERMO-PLASTIC) - LABOR COST PER LINEAR
FOOT
LF
60182
$0.287
$17,272.234
$0.55
$33,100.10
2.7
12" SOLID WHITE LINE (THERMO-PLASTIC) - MATERIAL COST PER LINEAR
FOOT
LF
19679
$0.86
$16,923.94
$1.85
$36,406.15
2.8
12" SOLID WHITE LINE (THERMO-PLASTIC) - LABOR COST PER LINEAR
FOOT
LF
19679
$0.575
$11,315.425
$0.90
$17,711.10
2.9
24" SOLID WHITE LINE (THERMO-PLASTIC) - MATERIAL COST PER LINEAR
FOOT
LF
8572
$1.788
$15,326.736
$3.50
$30,002.00
2.10
24" SOLID WHITE LINE (THERMO-PLASTIC) - LABOR COST PER LINEAR
FOOT
LF
8572
$1.19
$10,200.68
$1.15
$9,857.80
2.11
WHITE ARROW (THERMO-PLASTIC) - MATERIAL COST
EA
306
$60.00
$18,360.00
$60.00
$18,360.00
2.12
WHITE ARROW (THERMO-PLASTIC) - LABOR COST
EA
306
$40.00
$12,240.00
$75.00
$22,950.00
2.13
ONLY LEGEND (THERMO-PLASTIC) - MATERIAL COST
EA
174
$75.00
$13,050.00
$60.00
$10,440.00
2.14
ONLY LEGEND (THERMO-PLASTIC) - LABOR COST
EA
174
$50.00
$8,700.00
$75.00
$13,050.00
2.15
RAILROAD CROSSING LEGEND COMPLETE (THERMO-PLASTIC) -
MATERIAL COST
EA
5
$77.10
$385.50
$150.00
$750.00
2.16
RAILROAD CROSSING LEGEND COMPLETE (THERMO-PLASTIC) - LABOR
COST
EA
5
$51.40
$257.00
$100.00
$500.00
2.17
SCHOOL ZONE LEGEND (THERMO-PLASTIC) - MATERIAL COST
EA
0
$74.01
$0.00
$100.00
$0.00
2.18
SCHOOL ZONE LEGEND (THERMO-PLASTIC) - LABOR COST
EA
0
$49.34
$0.00
$85.00
$0.00
3
TRAFFIC BUTTON/MARKER
PKG
0
$1,851.00
$0.00
$1,800.50
$0.00
3.1
REMOVAL OF TRAFFIC BUTTONS/MARKERS
EA
0
$1.00
$0.00
$0.50
$0.00
3.2
SUPPLY AND INSTALL ONE SIDED REFLECTOR ON CONCRETE
EA
0
$5.25
$0.00
$4.00
$0.00
3.3
SUPPLY AND INSTALL ONE SIDED REFLECTOR ON ASPHALT
EA
0
$4.00
$0.00
$4.00
$0.00
3.4
SUPPLY AND INSTALL TWO SIDED REFLECTOR ON CONCRETE
EA
230
$5.25
$1,207.50
$5.00
$1,150.00
3.5
SUPPLY AND INSTALL TWO SIDED REFLECTOR ON ASPHALT
EA
0
$4.00
$0.00
$5.00
$0.00
Total
$271,631.043
$335,179.39
RESPONSIVE RESULTS -ORIENTED TRUST -BUILDERS ACCOUNTABLE
Memo
To: Michael Leech
Assistant Director Public Works
From: Edward A. Kupferer Sr.
Traffic Operations Manager
CC:
Date: August 12, 2016
Re: Street Marking FY17
Exhibit B
Traffic Operations is currently planning to remark the following roadways during FY
2017 as the budget allows.
Roadways with more than one lane each direction will be remarked in the
following manner, removal of the old White lane lines and remark with painted 6"
shadow markings (7.5 feet of white followed by 7.5 feet of black, then 15 foot space
them repeat) in the 15 foot space one reflective marker (Clear/Red) will be placed .
Non -divided roadways will be marked with double yellow center line. Divided
roadways will have the median noses remarked with yellow paint.
Intersection markings (Crosswalks, Stop Bars, Arrow and Wording: Only, Right,
Left) will be remarked in Thermo -Plastic.
Roadways with only one lane in each direction will be remarked in the following
manner, Remark with paint (Dash yellow, Double Yellow) for non curbed roadways
if warranted a white edge line will be marked.
Intersection markings (Crosswalks, Stop Bars, Arrow and Wording: Only, Right,
Left) will be remarked in Thermo -Plastic.
1) Magnolia St (Veterans to west city limits)
2) Pearland Parkway (Oiler to north city limits
3) Dixie Farm (north city limits to SH 35)
4) Country Club Dr ( Green Tee to Golfcrest)
5) Green Tee Dr (Country Club to Golfcrest)
6) Yost Blvd (FM 518 to north city limits)
7) Veterans (Walnut to south city limit)
8) Harkey / Oday (FM 518 to north city limits)
9) Garden (FM 518 to north city limits)
10) Roy Rd (FM 518 to north city limits)
11) Max Rd (FM 518 to north city limits)
RESPONSIVE RESULTS -ORIENTED TRUST -BUILDERS ACCOUNTABLE
12) Hughes Ranch (Stone to FM 865)
13) Miller Ranch Rd (FM 518 to Hughes Ranch)
14) Longwood (FM 518 to north city limits)
15) McGinnis (Dixie Farm to Sleepy Hollow)
16) Barry Rose (FM 518 to Pearland Parkway)
17) Hughes Rd. (Pearland Parkway to north city limits)
18) Old Alvin (John Lizer to Orange St, & McHard to north city limits)
19) Orange St (SH 35 to Hatfield)
20) Hatfield ( south city limits to north city limits)
21) Jasper (Hatfield to FM 518)
22) Wells Rd Bailey to south city limits)
23) Business Center (FM 518 to CR 59)
24) McHard (Mykawa to Pearland Parkway)
25)Walnut (McLean to FM 518)
26) Liberty (FM 518 to Shadybend)
27) Mykawa (FM 518 to Orange)
FY17 Pavement Marking Improvements Map
Exhibit C
!--7\
\\ o
0
EKEr C
MANVEL
CITY OF PEARLAND
Pavement Marking
Improvement Areas
for 2017
- Improvement Areas
CityLimits
ETJ
ladadamo
C
4
City of Pearland
3519 Liberty Drive
Pearland, TX 77581
Resolution No. R2016-151
Exhibit "A"
General Services Contract
This Contract (Contract) is made between the City of Pearland, Texas (City), and Contractor.
The City and Contractor agree to the terms and conditions of this Contract, which consists of the
following parts:
I. Summary of Contract Terms
11. Signatures
111. Standard Contractual Provisions
IV. Special Terms and Conditions
V. Additional Contract Attachments
I. Summary of Contract Terms.
Contractor:
Description of Services:
Amount:
Effective Date:
Termination Date:
Renewal:
Lone Star Pavement Services, Inc.
27045 Hanna Road
Conroe, TX 77385
A unit price service contract for Road Striping Services, per the
specifications of City of Pearland Bid #0716-47; City Council
Resolution #R2016-151.
Unit price contract, estimated at $240,000.
September 19, 2016
September 18, 2017
Two (2) one-year renewal options available upon mutual
agreement of both parties.
11. Signatures. By signing below, the parties agree to the terms of this Contract:
CITY OF P_ - LAND:
CONTRACTOR:
Date Title: ,Ae.51131eiv
"Sjgned by: Date:
//City Manager
Assistant City Manager
Director
Program Manager
"Contract Signature Authority:
Date: 9/moi/ -2 e.2 /4.
Program Manager -$5,999 or Tess
Director - $6,000 to $30,000
City Manager/Assistant City Managers - $30,001 to
$50,000
City Council Resolution - $50,000+
III. Standard Contractual Provisions.
A. Definitions.
Contract means this Standard Services Contract.
Services means the services for which the City solicited bids or received proposals as
described in Exhibit A, attached hereto.
B. Services and Payment. Contractor will furnish Services to the City in accordance with the
terms and conditions specified in this Contract. Contractor will bill the City for the Services
provided at intervals of at least 30 days, except for the final billing. The City shall pay
Contractor for the Services in accordance with the terms of this Contract, but all payments to
be made by the City to Contractor, Including the time of payment and the payment of interest
on overdue amounts, are subject to the applicable provisions of Chapter 2251 of the
Govemment Code.
C. Termination Provisions.
(1) City Termination for Convenience. Under this paragraph, the City may terminate
this Contract during its term at any time for the City's own convenience where the
Contractor is not in default by giving written notice to Contractor. If the City
terminates this Contract under this paragraph, the City will pay the Contractor for all
services rendered in accordance with this Contract to the date of termination.
(2) Termination for Default. Either party to this Contract may terminate this Contract
as provided in this paragraph if the other party fails to comply with its terms. The
party alleging the default will give the other party notice of the default in writing citing
the terms of the Contract that have been breached and what action the defaulting
party must take to cure the default. If the party in default fails to cure the default as
specified in the notice, the party giving the notice of default may terminate this
Contract by written notice to the other party, specifying the date of termination.
Termination of this Contract under this paragraph does not affect the right of either
party to seek remedies for breach of the Contract as allowed by law, including any
damages or costs suffered by either party.
(3) Multi -Year Contracts and Funding. If this Contract extends beyond the City's
fiscal year in which it becomes effective or provides for the City to make any payment
during any of the City's fiscal years following the City's fiscal year In which this
Contract becomes effective and the City fails to appropriate funds to make any
required Contract payment for that successive fiscal year and there are no funds
from the City's sale of debt Instruments to make the required payment, then this
Contract automatically terminates at the beginning of the first day of the City's
successive fiscal year of the Contract for which the City has not appropriated funds
or otherwise provided for funds to make a required payment under the Contract.
D. Liability and Indemnity. Any provision of any attached contract document that limits the
Contractor's liability to the City or releases the Contractor from liability to the City for actual
or compensatory damages, loss, or costs arising from the performance of this Contract or
that provides for contractual indemnity by one party to the other party to this Contract is not
applicable or effective under this Contract. Except where an Additional Contract Document
provided by the City provides otherwise, each party to this Contract is responsible for
defending against and liable for paying any claim, suit, or judgment for damages, loss, or
costs arising from that party's negligent acts or omissions in the performance of this Contract
in accordance with applicable law. This provision does not affect the right of either party to
this Contract who is sued by a third party for acts or omissions arising from this Contract to
bring in the other party to this Contract as a third -party defendant as allowed by law.
E. Assignment. The Contractor shall not assign this Contract without the prior written
consent of the City.
F. Law Governing and Venue. This Contract is governed by the law of the State of Texas
and a lawsuit may only be prosecuted on this Contract in a court of competent jurisdiction
located in or having jurisdiction in Brazoria County, Texas.
G. Entire Contract. This Contract represents the entire Contract between the City and the
Contractor and supersedes all prior negotiations, representations, or contracts, either written
or oral. This Contract may be amended only by written instrument signed by both parties.
H. Independent Contractor. Contractor shall perform the work under this Contract as an
independent contractor and not as an employee of the City. The City has no right to
supervise, direct, or control the Contractor or Contractor's officers or employees in the
means, methods, or details of the work to be performed by Contractor under this Contract.
The City and Contractor agree that the work performed under this Contract is not inherently
dangerous, that Contractor will perform the work in a workmanlike manner, and that
Contractor will take proper care and precautions to insure the safety of Contractor's officers
and employees.
I. Dispute Resolution Procedures. The Contractor and City desire an expeditious means to
resolve any disputes that may arise between them regarding this Contract. If either party
disputes any matter relating to this Contract, the parties agree to try in good faith, before
bringing any legal action, to settle the dispute by submitting the matter to mediation before a
third party who will be selected by agreement of the parties. The parties will each pay one-
half of the mediator's fees.
J. Attorney's Fees. Should either party to this Contract bring suit against the other party for
breach of contract or for any other cause relating to this Contract, neither party will seek or
be entitled to an award of attorney's fees or other costs relating to the suit.
K. Severability. If a court finds or rules that any part of this Contract is invalid or unlawful,
the remainder of the Contract continues to be binding on the parties.
IV. Special Terms or Conditions. None.
V. Additional Contract Documents. The following specified documents attached to this Contract
are part of this Contract, except as follows: any provision contained in any of the Contractor's
Additional Contract Documents specified below that conflicts with a Contract provision not included
in the Contractor's Additional Contract Documents, does not apply to this Contract.
A. Contractor's Additional Contract Documents:
1. The contractor's response to Bid #0716-47 shall be construed as additional contract
documents.
B. City's Additional Contract Documents:
1. City standard insurance requirements.
2. Scope of Services, Exhibit A.
Exhibit A
CONTRACTOR'S SCOPE OF SERVICES
Scope of services provided shall consist of conducting road striping services as needed for the City
of Pearland Bid #0716-47 and Contractor's response to the same, as listed below:
Specification Responses
Lone Star
Pavement
Services, LLC
Line Description UOM QTY
Unit
1
ROAD STRIPING SERVICES - PAINT
PKG
1
$453.4477
1.1
4" SOLID OR BROKEN WHITE LINE (PAINT) - MATERIAL
COST PER LINEAR FOOT
LF
1
$0.114
1.2
4" SOLID OR BROKEN WHITE LINE (PAINT) - LABOR COST
PER LINEAR FOOT
LF
1
$0.0719
1.3
4" SOLID OR BROKEN YELLOW LINE (PAINT) - MATERIAL
COST PER LINEAR FOOT
LF
1
$0.114
1.4
4" SOLID OR BROKEN YELLOW LINE (PAINT) - LABOR COST
PER LINEAR FOOT
LF
1
$0.0719
1.5
8" SOLID WHITE LINE (PAINT) - MATERIAL COST PER
LINEAR FOOT
LF
1
$0.86
1.6
8" SOLID WHITE LINE (PAINT) - LABOR COST PER LINEAR
FOOT
LF
1
$0.124
1.7
12" SOLID WHITE LINE (PAINT) - MATERIAL COST PER
LINEAR FOOT
LF
1
$0.6169
1.8
12" SOLID WHITE LINE (PAINT) - LABOR COST PER LINEAR
FOOT
LF
1
$0.411
1.9
24" SOLID WHITE LINE (PAINT) - MATERIAL COST PER
LINEAR FOOT
LF
1
$1.23
1.10
24" SOLID WHITE LINE (PAINT) - LABOR COST PER LINEAR
FOOT
LF
1
$0.82
1.11
6" LANE LINE SHADOW PAINT (8 FOOT WHITE/8 FOOT
BLACK) - MATERIAL COST PER LINEAR FOOT
LF
1
$0.27
1.12
6" LANE LINE SHADOW PAINT (8 FOOT WHITE/8 FOOT
BLACK) - LABOR COST PER LINEAR FOOT
LF
1
$0.18
1.13
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING -
LABOR COST PER LINEAR FOOT - 4" Line
LF
1
$0.514
1.14
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING -
LABOR COST PER LINEAR FOOT - 6" Line
LF
1
$0.60
1.15
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING -
LABOR COST PER LINEAR FOOT - 8" Line
LF
1
$0.75
1.16
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING -
LABOR COST PER LINEAR FOOT - 12" Line
LF
1
$1.50
1.17
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING -
LABOR COST PER LINEAR FOOT - 24" Line
LF
1
$2.50
1.18
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING -
LABOR COST PER LINEAR FOOT for Arrow or Words
LF
1
$50.00
1.19
WHITE ARROW (PAINT) - MATERIAL COST
EA
1
$33.00
1.20
WHITE ARROW (PAINT) - LABOR COST _
EA
1
$22.00
1.21
ONLY LEGEND (PAINT) - MATERIAL COST
EA
1
$33.00
1.22
ONLY LEGEND (PAINT) - LABOR COST
EA
1
$22.00
1.23
RAILROAD CROSSING LEGEND COMPLETE (PAINT) -
MATERIAL COST
EA
1
$123.36
1.24
RAILROAD CROSSING LEGEND COMPLETE (PAINT) - LABOR
COST
EA
1
$82.24
1.25
SCHOOL ZONE LEGEND (PAINT) - MATERIAL COST
EA
1
$46.26
1.26
SCHOOL ZONE LEGEND (PAINT) - LABOR COST
EA
1
$30.84
2
ROAD STRIPING SERVICES - THERMO-PLASTIC
PKG
1
$483.213
2.1
4" SOLID OR BROKEN WHITE LINE (THERMO-PLASTIC) -
MATERIAL COST PER LINEAR FOOT
LF
1
$0.37
2.2
4" SOLID OR BROKEN WHITE LINE (THERMO-PLASTIC) -
LABOR COST PER LINEAR FOOT
LF
1
$0.246
2.3
4" SOLID OR BROKEN YELLOW LINE (THERMO-PLASTIC) -
MATERIAL COST PER LINEAR FOOT
LF
1
$0.37
2.4
4" SOLID OR BROKEN YELLOW LINE (THERMO-PLASTIC) -
LABOR COST PER LINEAR FOOT
LF
1
$0.246
2.5
8" SOLID WHITE LINE (THERMO-PLASTIC) - MATERIAL COST
PER LINEAR FOOT
LF
1
$0.431
2.6
8" SOLID WHITE LINE (THERMO-PLASTIC) - LABOR COST
PER LINEAR FOOT
LF
1
$0.287
2.7
12" SOLID WHITE LINE (THERMO-PLASTIC) - MATERIAL
COST PER LINEAR FOOT
LF
1
$0.86
2.8
12" SOLID WHITE LINE (THERMO-PLASTIC) - LABOR COST
PER LINEAR FOOT
LF
1
$0.575
2.9
24" SOLID WHITE LINE (THERMO-PLASTIC) - MATERIAL
COST PER LINEAR FOOT
LF
1
$1.788
2.10
24" SOLID WHITE LINE (THERMO-PLASTIC) - LABOR COST
PER LINEAR FOOT
LF
1
$1.19
2.11
WHITE ARROW (THERMO-PLASTIC) - MATERIAL COST
EA
1
$60.00
2.12
WHITE ARROW (THERMO-PLASTIC) - LABOR COST
EA
1
$40.00
2.13
ONLY LEGEND (THERMO-PLASTIC) - MATERIAL COST
EA
1
$75.00
2.14
ONLY LEGEND (THERMO-PLASTIC) - LABOR COST
EA
1
$50.00
2.15
RAILROAD CROSSING LEGEND COMPLETE (THERMO-
PLASTIC) - MATERIAL COST
EA
1
$77.10
2.16
RAILROAD CROSSING LEGEND COMPLETE (THERMO-
PLASTIC) - LABOR COST
EA
1
$51.40
2.17
SCHOOL ZONE LEGEND (THERMO-PLASTIC) - MATERIAL
COST
EA
1
$74.01
2.18
SCHOOL ZONE LEGEND (THERMO-PLASTIC) - LABOR COST
EA
1
$49.34
3
TRAFFIC BUTTON/MARKER
PKG
1
$1,851.00
3.1
REMOVAL OF TRAFFIC BUTTONS/MARKERS
EA
1
$1.00
3.2
SUPPLY AND INSTALL ONE SIDED REFLECTOR ON
CONCRETE
EA
100
$5.25
3.3
SUPPLY AND INSTALL ONE SIDED REFLECTOR ON
ASPHALT
EA
100
$4.00
3.4
SUPPLY AND INSTALL TWO SIDED REFLECTOR ON
CONCRETE
EA
100
$5.25
3.5
SUPPLY AND INSTALL TWO SIDED REFLECTOR ON
, ASPHALT
EA
100
$4.00