R-2013-092-2013-06-10RESOLUTION NO. R2013-92
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, AWARDING A BID FOR CONSTRUCTION SERVICES
ASSOCIATED WITH THE OLD ALVIN WATERLINE PROJECT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That the City opened bids for construction services associated with the
Old Alvin Water Line Project, and such bids have been reviewed and tabulated.
Section 2. That the City Council hereby awards the bid to SER Construction
Partners, LLC, in the amount of $3,398,483.00, and appropriates all additional funds
necessary for construction of the Project .
Section 3. The City Manager or his designee is hereby authorized to execute a
contract for construction services associated with the Old Alvin Water Line Project.
PASSED, APPROVED and ADOPTED this the 10th day of June, A.D., 2013.
TOM REID
MAYOR
ATTEST:
/.l!. /I%
Y• i` G Lei
Cl17 SE ETARY
APPROVED AS TO FORM:
DARRIN M. COKER
CITY ATTORNEY
Project Manual
for:
Old Alvin Road Water Line
from
John Lizer Road to McHard Road
Resolution No. R2013-92
Exhibit "A"
Bid No.: 0413-50
May 2013
Prepared By:
4.. _ s t
-. %\ * 4
i LEON E. HOCH i
et
it82670 i
jo. E0. c $'
1xFS• LS/'CENS.... • ENS'\_
C',71 o -t
,.
,--&-4/,,//,
CHARLES D. GOODEN CONSULTING ENGINEERS, INC.
TBPE Firm No. 4176
2320 Holmes Road, Suite A
Houston, TX 77051
Phone (713) 660-6905 1 Fax (713) 660-8817
OLD ALVIN ROAD WATER LINE FROM
JOHN LIZER ROAD TO MCHARD ROAD
CITY OF PEARLAND
BRAZORIA COUNTY,TEXAS
TABLE OF CONTENTS
SECTION TITLE NO. OF PAGES
DIVISION 0—BIDDING AND CONTRACT DOCUMENTS
00100 Invitation to Bid 3
00200 Instructions to Bidders 7
00300 Bid Proposal 3
00300A Bid Proposal Exhibit"A" 4
00500 Standard Form of Agreement 7
00610 Performance Bond 2
00611 Payment Bond 2
00612 One-Year Maintenance Bond 2
00615 Partial Waiver of Lien and Payment Affidavit 1
00700 General Conditions of Agreement 36
00800 Special Conditions of Agreement 2
00811 Wage Scale for Engineering Construction 1
00900 Form of Addendum 1
DIVISION 1—GENERAL REQUIREMENTS
01100 Summary of Work 1
01140* Contractor's Use of Premises 4
01200* Measurement and Payment Procedures 3
01290* Change Order Procedures 4
01310*. Coordination and Meetings 3
01350* Submittals 6
01380* Construction Photographs 3
01420* Referenced Standards 5
01430* Contractor's Quality Control 2
01440* Inspection Services 1
01450* Testing Laboratory Services 2
01500 Temporary Facilities and Controls 9
01505 Mobilization 1
01550* Stabilized Construction Exit 4
01555* Traffic Control and Regulation 4
01560* Filter Fabric Fence 3
01561* Reinforced Filter Fabric Bather 3
01562* Waste Material Disposal 3
01563* Tree and Plant Protection 4
01564* Control of Ground Water and Surface Water 8
01565 TPDES Requirements 3
00010- 1 of 4
CITY OFPEARLAND TABLE OF CONTENTS
SECTION TITLE NO. OF PAGES
01566* Source Controls for Erosion and Sedimentation 5
01570* Trench Safety System 4
01580* Project Identification Signs 4
01600* Material and Equipment 3
01630* Product Options and Substitutions 3
01720* Field Surveying 2
01750* Starting Systems 2
01760* Project Record Documents 2
01770* Contract Closeout 2
DIVISION 2—SITE WORK
02105 Sampling and Analysis in Potentially Petroleum Contaminated Areas 8
02200* Site Preparation 4
02220S Site Demolition 1
02220* Site Demolition 5
02252* Cement Stabilized Sand 3
02255* Bedding, Backfill,and Embankment Materials 6
02316* Excavation and Backfill for Roadways 4
02317* Excavation and Backfill for Structures 7
02318* Excavation and Backfill for Utilities 12
02330* Embankment 5
02335* Subgrade 7
02370* Geotextile 2
02371* RipRap 4
02415* Augering Pipe or Casing for Sewers 7
02417* Augering Pipe or Casing for Water Lines 6
02510* Water Mains 10
02510S Water Mains 1
02511* Water Meters 2
02512* Polyethylene Wrap 4
02514* Fire Hydrant Assembly 6
02515 Water Tap and Service Line Installation 6
REST OF PAGE INTENTIONALLY LEFT BLANK
00010-2of4
CITY OF PEARLAND TABLE OF CONTENTS
SECTION TITLE NO. OF PAGES
02520* Valve Boxes,Meter Boxes, and Meter Vaults 4
02530* Gravity Sanitary Sewers 20
02531* Sanitary Sewer Service Leads or Reconnections 6
02532* High Density Polyethylene(HDPE) Solid Wall Pipe 4
02533* Sanitary Sewage Force Mains 5
02534 PVC Pipe 6
02540* Tapping Sleeves and Valves 3
02541* Water and Wastewater Line Valves 8
02542* Concrete Manholes and Accessories 10
02582* Thermoplastic Pavement Markings 2
02603* Frames, Grates,Rings,and Covers 3
02624* Structural Plate Culvert Structures 7
02630* Storm Sewers 10
02633* Adjusting Manholes,Inlets, and Valve Boxes 3
02634S Ductile Iron Pipe and Fittings 1
02634* Ductile Iron Pipe and Fittings 5
02635* Steel Pipe and Fittings 10
02636* Polyurethane Coating on Steel or Ductile Iron Pipe 6
02710* Base Course for Pavement 12
02741* Asphaltic Concrete Pavement 7
02742* Prime Coat 4
02743* Tack Coat 3
02744* Single Course Surface Treatment 4
02751* Concrete Pavement 15
02762* Temporary and Removable Reflectorized Pavement Marking 4
02770* Curb, Curb &Gutter, and Headers 4
02811* Landscape Irrigation 5
02820* Wood Fences and Gates 3
02821* Chain Link Fences and Gates 4
02910* Topsoil 3
02921* Hydromulch Seeding 4
02922* Sodding 4
02931* Landscape and Tree Planting 15
02980* Pavement Repair and Resurfacing 3
02981* Blast Cleaning of Pavement 2
REST OF PAGE INTENTIONALLY LEFT BLANK
00010-3 of 4
CITY OF PEARLAND TABLE OF CONTENTS
SECTION TITLE NO. OF PAG
ES
DIVISION 13—Computer Equipment
13730 Computer Equipment 5
REFERENCED TXDOT SPECIFICATIONS
416^ Drilled Shaft Foundations
420^ Concrete Structures
• 421^ Hydraulic Cement Concrete
422^ Reinforced Concrete Slab
424^ Precast Concrete Structures (Fabrication)
425^ Precast Prestressed Concrete
426^ Prestressing
429^ Concrete Structure Repair
434^ Elastometric Bridge Bearing
440^ Reinforcing Steel
REPORTS INCLUDED BY ATTACHMENT
1. Geotechnical Report by HVJ Associates, Inc.Titled "Geotechnical Investigation
Old Alvin Road Water Line Replacement From McHard Road to John Lizer
Road,Pearland, Texas"—Report No. HG 1019721,Dated May 7, 2013.
("n\
2. Phase I Environmental Site Assessment by HVJ Associates,Inc.Titled "Phase I
Environmental Site Assessment Old Alvin Road Waterline Project John Lizer
Road to McHard Road No. WA1101,Pearland,Brazoria County, Texas"—
Report No. HE1019720,Dated August 2011
3. Phase II Environmental Site Assessment by HVJ Associates, Inc. Titled "Phase II
Environmental Site Assessment Old Alvin Road Waterline Project John Lizer
Road to McHard Road No. WA1101,Pearland,Brazoria County, Texas"—
Report No. HE1019720,Dated October 12, 2011
Section numbers followed by an asterisk(*)are included by reference and are available on the City
of Pearland's Engineering Department Website.
Section numbers followed by an `S' are special provisions to a Standard City of Pearland
Specification. Special provisions appear in this project manual.
Section numbers followed by a `^' are Specifications included by reference from the Texas
Department of Transportation"Standard Specifications for Construction and Maintenance of
Highways, Streets, and Bridges"dated June 1,2004.
END OF SECTION
00010-4 of 4
CITY OF PEARLAND INVITATION TO BID
Section 00100
INVITATION TO BID
CITY OF PEARLAND,TEXAS
Lowest Responsible Bidder
Sealed Electronic Bids will be accepted for the following project, in the City's E-bid System.
Electronic bids shall be submitted through the City's web site at: www.cityofpearland.ora/bids.
All interested Bidders are required to register as a "supplier" on the City's E-bid System at the
above web address and clicking on "Supplier Registration". Registration provides automatic
access to any changes to the Plans, Specifications or Bid time and date.
However, submission of an E-bid requires completing a short registration questionnaire found on
this web site. For more information regarding registration instructions, see INSTRUCTIONS TO
BIDDERS, Section 00200, included in the project bid documents viewable on the web site.
Questions regarding electronic bidding should be directed to City Purchasing Officer at
ebids(aci.pear(and.tx.us. All Bids submitted electronically will remain confidential until the
opening date and time when they will be opened and read into the public record.
Bids, shall be submitted on the form provided in the E-bid System and submitted electronically
through this system to the City Purchasing Officer, City of Pearland, City Hall located at 3519
Liberty Drive, Pearland, Texas 77581. Electronic bids will be accepted until 2:00 p.m.,
Thursday, May 30, 2013. All Bids shall reference the following project information in the
nappropriate locations in provided electronic format. All properly submitted bids shall be publicly
"opened" and read aloud into the public record following the closing of the acceptance period for
the construction of:
Old Alvin Road Water Line from John Lizer Rd.to McHard Rd.
City of Pearland,Texas
COP PN: WA1101
BID NO.: 0413-50
A mandatory pre-bid conference will be held at the City of Pearland City Hall at 3519 Liberty
Drive,Pearland, Texas 77581 at 9:00 a.m. on May 16, 2013.
The project will entail the construction of a 20" diameter water line with all associated
appurtenances including valves, service line connections, and fire hydrants. Tree protection and
pavement removal and replacement are also included. Additionally, there will be storm sewer
removal and replacement from Linwood Street to Town Ditch. Control of surface and ground
water; preparation and implementation of a traffic control plan and storm water pollution
prevention plan, and all associated construction related permits are included in the scope.
C
10-2012 00100- 1 of 3
CITY OF PEARLAND INVITATION TO BID
Upon award of a contract, the successful Bidder will be required to utilize the City's web based
project management software, "Pro-Trak" for the administration of the construction project,
including but not limited to, all transmittals and material submittals, RFI's, RFC's, Change
Orders, Applications for Payment and all project communications with the City, its Construction
Manager and Engineer. This system has certain hardware, internet access and operation
requirements that form the basis for all project communications, documentation and records for
the project. For more information, see INSTRUCTIONS TO BIDDERS, Section 00200.
Electronic Bid Documents: including Contract Documents, Plans and Technical Specifications
are available for download on the City's Website at: www.citvofpearland.or2/bids upon
registration. The documents are NOT viewable without registration. These same documents are
also available at the following locations.
City'of Pearland, City Hall (281) 652-1600
Purchasing Department
3519 Liberty Drive
Pearland, Texas 77581
Amtek Plan Room (713) 956-0100
4001 Sherwood
Houston, TX 77092
The Associated General Contractors of America, Inc. (713) 334-7100
2400 Augusta, Suite 350
Houston, TX 77057
Virtual Builders Exchange (832) 613-0201
7035 W. Tidwell Building J, Suite 112
Houston, TX 77092
McGrawHill Construction—Dodge Reports 1-800-393-6343
No plan fees or deposits are required for plans and bid documents obtained through the City's E-
bid System. BIDDERS MUST .REGISTER AS A SUPPLIER ON THE CITY'S E-BID
SYSTEM IN ORDER TO SUBMIT A BID EVEN IF BID DOCUMENTS ARE OBTAINED
VIA ONE OF THE PLAN HOUSES.
Bidders accept sole responsibility for downloading all of the required documents, plans,
specifications bid forms and addenda required for bidding.
No bid may be withdrawn or terminated for a period of ninety (90) days subsequent to the bid
opening date without the consent of the City of Pearland. Unless otherwise expressly provided
herein, all references to "day(s)"shall mean calendar day(s).
10-2012 00100-2 of 3
CITY OF PEARLAND INVITATION TO BID
Bid Security and Bonds: Bid Security in the form of Cashier's Check, Certified Check, or Bid
Bond payable to the City of Pearland in the amount of 5% of the total base bid price must
accompany each proposal. Bidders submitting bids electronically through the E-bid System shall
scan and up-load a copy of the sealed Bid Bond as an attachment to their bid. Original
documents for Bid Security shall be requested by the City from the lowest two bidders and
delivered to the City's Purchasing Officer within 48 business hours of the Bid Opening.
Bid Security shall be delivered to: Office of City Purchasing, Finance Department, 2nd Floor City
Hall, 3519 Liberty Drive, Pearland,Texas 77581.
The successful Bidder must furnish Performance and Payment Bonds as required by Chapter
2253 of the Texas Government Code or other applicable law, as amended, upon the form
included in the Contract Documents, in the amount of one hundred percent (100%) of the
contract price, such bonds to be executed by a corporate surety duly authorized to do business in
the State of Texas, and named in the current list of"Treasury Department Circular No. 570",
naming the City of Pearland, Texas as Obligee. Additionally, the successful bidder shall be
required to provide a one year Maintenance Bond for the improvements installed as part of this
work, as provided in the Special Conditions of Agreement.
Equal Opportunity: All responsible bidders will receive consideration for award of contract
without regard to race, color, religion, sex, or national origin.
Selection Criteria: The Contract is to be awarded on the basis of Lowest Responsible Bidder.
In identifying this criteria the City will consider: 1) lowest total bid price for all work listed and
specifically requested, including but not limited to: Base Bid, Extra Work items and selected
Alternates. The City of Pearland reserves the right to award a contract based on any combination
of the above considered to be in its best interests or to reject any or all bids.
A bid that has been "opened" may not be changed for the purposes of correcting an error in the
bid price.
Young Lorfing, TRMS
City Secretary,
City of Pearland
First Publication date May 8, 2013
Second Publication date May 15, 2013
C
10-2012 00100-3 of 3
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
Section 00200
INSTRUCTIONS TO BIDDERS
1. Defined Terms
1.1 The term "Owner" hereinafter is defined as the City of Pearland and is used
interchangeably with the term"the City". Both terms are synonymous and refer to the City.
1.2 The term "Bidder" means one who submits a Bid Proposal directly to Owner, as
distinct from a sub-bidder, who submits a bid to a Bidder. The term "Successful Bidder"
means the lowest responsible Bidder to whom the Owner (on the basis of Owner's evaluation
as hereinafter provided) makes an award. The term "Bid Documents" includes the Invitation
to Bidders, Instructions to Bidders, the Bid Proposal, and the proposed Contract Documents
(including all Addenda issued prior to receipts of bids).
1.3 The term"E-bid System"refers to the City's electronic bidding system. This is a web-
based system that provides all Bid Documents electronically to potential Bidders and forms the
pathway for interested Bidders to submit bids in response to advertisement and invitation. The
term "e-bid" and/ or"electronic bid" means the Bidders' electronic response submitted on the
electronic Bid Proposal to the Owner by way of the E-bid System. The terms "electronic bid"
or"e-bid" are used inter-changeably to describe the above bid process to submit an authorized
bid to the City in response to an Invitation to Bidders.
7\, 1.4 The term "Pro-Trak" means the City's web-based contract administration and
construction records management system used by involved parties to administer the project.
This system serves as the web accessed centralized information distribution hub for
communications and document management, pay application processing and record retention
for all project documentation. Operational instructions for this system will be issued to the
successful Bidder at the pre-Construction Meeting.
1.5 All other definitions set out in the Contract Documents are applicable to terms used in
the Bidding Documents.
1.6 Unless otherwise expressly provided herein, all references to "day(s)" shall mean
consecutive calendar day(s).
2. Registration for E-bid System
2.1 The Owner's E-bid System is accessible via the City's web site at
www.cityofpearland.org/bids. Bid documents can be viewed by simply selecting a specific
project from the BID OPPORTUNITIES list and clicking on that project AFTER registration
as a Supplier.
Potential Bidders MUST REGISTER as a "Supplier" by clicking on the Supplier
Registration button and completing the registration form. Registrants must provide data for
all categories marked with a"*"and must select the following project bid categories:
Building Construction Services,New(includes Maintenance and Repair)
Construction Services, General
10-2012 00200-1 of 8
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
Construction Services,Heavy " "
Construction Services,Trade (new construction)
Select the appropriate Time Zone for the Bidder's location and whether that location observes
Daylight Savings time. Complete the registration information providing all required contact
information and establish password security for the E-bid System. Once complete, "suppliers"
will receive emails notifying of bid opportunities. Downloading any project bid data will
automatically place the bidder's contact information on the list of plan holders list and the E-
bid System will automatically send any and all updates, changes or addenda associated with
that project.
2.2 The electronic Bid Proposal can only be submitted through this system. The form can
be printed for Bidder's use, but the Bid Proposal MUST be submitted on the electronic form
within the E-bid System.
2.3 Questions regarding use of the E-bid System may be directed by email to:
ebids@ci.pearland.tx.us.
3. Copies of Bidding Documents
3.1 Complete sets of "electronic" Bidding Documents are available for download to
registered Bidders at No Cost from the City's E-bid System at: www.cityofpearland.org/bids.
Interested Bidders must register as a "Supplier" on this site in order to receive the Bid
Documents, and all Addenda or other notifications of changes, including communications
from the Owner or Engineer. All Bid Documents are available to download and print.
CP.\ 3.2 The Bidder accepts sole responsibility for ensuring that he obtains a full set of these
documents by completing the registration and executing a full and complete download of the
project documents. Downloading of Bid Documents automatically ensures receipt of any and
all subsequent communications from the City or its Engineer.
3.2 Copies of Bidding Documents are available or may be viewed at any of the Plan
Houses listed in the Invitation to Bidders. It is recommended that all interested Bidders,
whether bidding directly to the Owner or Sub-bidders bidding to a Bidder, register as a
Supplier and download the project Bid Documents.
3.3 Complete sets of Bidding Documents must be used in preparing Bid Proposals; neither
Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from
the use of incomplete sets of Bidding Documents including, but not limited to all. Addenda
issued prior to bid.
3.4 Owner and Engineer, in making copies of Bidding Documents available on the above
terms, do so only for the purpose of obtaining Bid Proposals on the Work, and do not confer a
license or grant for any other use.
4. Qualifications of Bidders
4.1 In determining to whom to award a contract, the City of Pearland may consider, in
addition to the other selection criteria identified in section 16 of these Instructions to Bidders,
the following Qualifications of Bidder, and each Bidder must be prepared to submit within two
(2) days of Owner's request any or all of such Qualifications requested:
10-2012 00200-2 of 8
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
(1.-\ 1) A brief narrative of previous experience of the Bidder with projects of a similar nature and
scope;
2) A list, including owner name and project location, of on-going projects and contracts for
construction of projects of the Bidder which are not yet substantially complete;
3)A list of proposed subcontractors and suppliers for the project being bid;
4) A list of name, address and telephone number of references for projects completed by
Bidder; and
5) A Financial Statement of Bidder, consisting of the balance sheet and annual income
statement of Bidder for the Bidder's last fiscal year end preceding the submission of the Bid
Proposal, which has been audited or examined by an independent certified public accountant.
The Financial Statement of Bidder shall be used to determine a Bidder's net working capital,
which is defined as current assets less current liabilities. A Bidder's net working capital shall
be considered evidence of the Bidder's ability to provide sufficient fmancial management of
the project being bid. The Bidder's Financial Statement shall be clearly and conspicuously
marked as "confidential", and shall be deemed and treated as confidential and excepted from
the Public Information disclosure requirements of Texas Government Code Section 552.001 et
seq., as such information, if released, would give advantage to a competitor or bidder, and/or
would cause substantial competitive harm to Bidder.
5. Examination of Contract Documents and Site
5.1 It is the responsibility of each Bidder before submitting a Bid Proposal, to (a) examine
the Bidding Documents thoroughly, (b) visit the site to become familiar with local conditions
that may affect cost, progress, performance or furnishing of the Work, (c) consider federal,
state and local laws and regulations that may affect cost, progress, performance or furnishing
of the Work, (d) study and carefully correlate Bidder's observations with the Contract
Documents, and (e) notify Engineer of all conflicts, errors, omissions or discrepancies in the
Contract Documents, (f) to recognize and plan for use of the City's "Pro-Trak" software to
administer the construction process and perform the work of the project.
5.2 Any reports of explorations and tests of conditions at the site which have been utilized
by the Engineer in preparation of the Contract Documents will be made available to Bidders
for review, but such reports are not part of the Contract Documents. Bidder may not and
should not rely upon the accuracy of the data contained in such reports, interpretations or
opinions contained therein, or the completeness thereof, for the purposes of bidding or
construction.
5.3 Information and data reflected in the Contract Documents with respect to underground
utilities, equipment or other underground facilities at or contiguous to the site is based upon
information and data furnished to Owner and Engineer by owners of such underground
facilities or others, and Owner does not assume responsibility for the accuracy or completeness
thereof.
5.4 Before submitting a Bid Proposal, each Bidder will, at Bidder's own expense, make or
obtain any additional examinations, investigations, explorations, tests and studies and obtain
any additional information and data which pertain to the physical conditions (surface,
subsurface and underground facilities) at or contiguous to the site or otherwise which may
affect cost, progress, performance or furnishing of the Work and which Bidder deems
10-2012 00200-3 of 8
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
necessary to determine its Bid Proposal prices for performing and furnishing the Work in
accordance with the Contract Time, Contract Price and other terms and conditions of the
Contract Documents.
5.5 On request in advance, Owner will provide each prospective Bidder access to the site
to conduct such explorations and tests as each prospective Bidder deems necessary for
submission of a Bid Proposal. Prospective Bidders shall fill all holes, clean up and restore the
site to its former condition upon completion of such explorations.
5.6 The lands upon which the Work is to be performed, rights-of-way and easements for
access thereto and other lands designated for use by Contractor in performing the Work are
identified in the Contract Documents. All additional lands, access thereto or contractual
arrangements for use by the Contractor required for temporary construction facilities or storage
of materials and equipment are to be provided by Contractor. Easements for permanent
structures or permanent changes in existing structures are to be obtained and paid for by
Owner unless otherwise provided in the Contract Documents.
5.7 The submission of a Bid Proposal will constitute an incontrovertible representation by
Bidder that Bidder has complied with every requirement of this Article 4, that without
exception the Bid Proposal is premised upon performing and furnishing all of the Work
required by the Contract Documents and such means, methods, techniques, sequences or
procedures of construction as may be indicated in, required by or reasonably inferred from the
Contract Documents, and that the Contract Documents are sufficient in scope and detail to
indicate and convey understanding of all terms and conditions for performance and furnishing
of the Work.
6. Interpretations and Addenda
6.1 All questions about the meaning or intent of the Contract Documents are to be directed
to Engineer. Interpretations or clarifications considered necessary by Engineer in response to
such questions will be issued by Addenda delivered or transmitted by electronic means to all
registered Bidders in the City's E-bid System. Questions received less than five(5) days prior
to the date for opening of Bid Proposals may not be answered. Only questions answered by
formal written Addenda will be binding. Oral and other interpretations or clarifications will be
without legal effect.
6.2 Addenda may also be issued to modify the Bidding Documents as deemed advisable by
Owner or Engineer. Addenda will automatically be made available to all registered Bidders
that have downloaded Bid Documents from the City's E-bid System.
7. Bid Security
7.1 Each Bid Proposal must be accompanied by bid security made payable to Owner in
an amount of five percent (5%) of the Bidder's maximum Bid Proposal price, in the form of a
certified check, cashier's check or a Bid Bond("Bid Security").
7.2 Bidders submitting bids through the E-bid System shall scan and up-load a copy of their
Bid Security (sealed Bid Bond, Certified Check or Cashier's Check ) as an attachment to
their electronic bid. Original documents for Bid Security shall be requested by the City
from the lowest two bidders and delivered to the City's Purchasing Officer within 48
10-2012 00200-4 of 8
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
C'n
business hours of the Bid Opening. Bid Security shall be delivered to: Office of City
Purchasing,Finance Department,2nd Floor City Hall, 3519 Liberty Drive,Pearland,Texas 77581.
7.3 The Bid Security of the Successful Bidder will be retained until such time as Bidder
has executed the Standard Form of Agreement, and furnished the required Performance and
Payment Bonds, whereupon the Bid Security of both bidders will be returned. If the
Successful Bidder fails to execute and deliver the Standard Form of Agreement and furnish the
required performance and payment bonds within ten (10) days after the Notice of Award,
Owner may annul the Notice of Award and shall be entitled to make a claim against the Bid
Security. The Bid Security of other Bidders will be retained until the Contract is awarded and
the Standard Form of Agreement becomes effective, or all bids are rejected, whereupon Bid
Security furnished by all such Bidders will be returned.
8. Contract Time
8.1 The number of days in which the Work is to be Substantially Completed, as set forth in
the Bid Proposal form and the Standard Form of Agreement, subject to such extension of time
as may be due under the terms and conditions of the Contract Documents ("Contract Time").
All references to"time"or"days" shall be interpreted as consecutive calendar days.
9. Liquidated Damages and Early Completion Bonus
9.1 Provisions for liquidated damages and early completion bonus, if any, are set forth in
the Standard Form of Agreement.
10. Substitute or"Or-Equal" Items
10.1 The Contract, if awarded, will be on the basis of the selected materials and equipment
described in the Plans or specified in the Specifications without consideration of possible
substitute or "or-equal" items. Whenever it is indicated in the Plans or specified in the
Specifications that a substitute or "or-equal" item of material or equipment may be furnished
or used by the Contractor if acceptable to Engineer, application for such acceptance will not be
considered by Engineer until after the Agreement becomes effective. All "or-equal" references
shall be interpreted to mean "or approved equal". The procedure for submission of any such
application by Contractor and consideration by Engineer is set forth in the Contract
Documents.
11. Bid Form
11.1 The Bid Proposal form (Section 00300 — Bid Proposal) is included with the Bidding
Documents when downloaded. This Document must be printed and signed, as required below,
and then uploaded as an Attachment to the Bid.
All E-bids must be submitted on the City's official E-bid System Bid Proposal document. All
blanks on the Bid Proposal form must be completed or filled in. The Bidder shall bid all
Alternates,if any. Incomplete Bid Proposals may be cause for rejection.
11.2 Bid Proposals by corporations must be executed in the corporate name by the president
or a vice-president (or other corporate officer accompanied be evidence of authority to sign)
10-2012 00200-5 of 8
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
and the corporate seal must be affixed and attested by the secretary or an assistant secretary.
The corporate address and state of incorporation must be shown below the signature. Once
executed the document is to be uploaded as an attachment to the Bid.
11.3 Bid Proposals by partnerships must be executed in the partnership name and signed by
a general partner, whose title must appear under the signature, and if a corporate general
partner, executed as required above for corporations and the official address of the partnership
must be shown below the signature. All names must be typed or printed below the signature.
Once executed the document is to be uploaded as an attachment to the Bid.
11.4 The Bidder shall acknowledge receipt of all Addenda (the number of which must be
filled in on the Bid Proposal form).
11.6 The address and telephone number for communications regarding the Bid Proposal
must be shown on the Bid Proposal form.
12. Submission of Bid Proposals
12.1 The place, date and/or time designated for opening Bid Proposals may be changed in
accordance with applicable laws, codes and ordinances. Any such changes to the Bid Schedule
shall be made by Addenda.
12.2 Electronic Bids shall be submitted per the requirements, instructions, terms and
conditions as stated in the registration and submittal instructions of the City's E-bid System
electronic bidding software. All Bidders utilizing this system MUST register as a potential
supplier, (Bidder). E-Bids are submitted directly via the City's Web based system located at
www.cityofpearland.org/bids.
Bid Proposals submitted after the bid date and time will be rejected.
13. Modification and Withdrawal of Bid Proposals
13.1 Prior to submission, E-bid Bid Proposals may be modified or withdrawn without
prejudice.
13.2 Once submitted, Bid Proposals may only be modified by an appropriate document duly
executed(in the manner that a Bid Proposal must be executed) and delivered to Office of City
Purchasing, Finance Department, 2nd Floor City Hall, 3519 Liberty Drive, Pearland, Texas
77581 and submitted any time prior to the opening of Bid Proposals.
13.3 A Bidder may not modify or withdraw its Bid Proposal by facsimile or verbal means.
A withdrawn Bid Proposal may be resubmitted prior to the designated time for opening Bid
Proposals. No bid may be withdrawn or terminated for a period of sixty(60) days subsequent
to the bid opening date without the consent of the City of Pearland.
13.4 If, within twenty-four (24) hours after Bid Proposals are opened, any Bidder files a
duly signed, written notice with Owner and promptly thereafter demonstrates to the reasonable
satisfaction of Owner that there was a material mistake in the preparation of its Bid Proposal,
that Bidder may request to withdraw its Bid Proposal and the bid security may be returned or,
at the discretion of the Owner, Owner may make a claim against the bid security. Thereafter,
that Bidder will be disqualified from further bidding on the Project to be provided under the
(47 Contract Documents.
10-2012 00200-6 of 8
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
14. Opening of Bid Proposals
14.1 Bid Proposals will be opened and (unless obviously non-responsive) read aloud
publicly. An abstract of the amounts of the base Bid Proposals and major alternates (if any)
will be made available to Bidders after the opening of Bid Proposals. Bid Proposals, in their
entirety, shall be open for public inspection after the contract is awarded, with the exception of
any trade secrets or confidential information contained therein, provided Bidder has expressly
identified any specific information contained therein as being trade secrets or confidential
information.
15. Bid Proposals to Remain Subject to Acceptance
15.1 All Bid Proposals will remain subject to acceptance for sixty (60) days after the day of
the Bid Proposal opening, but Owner may, in its sole discretion, release any Bid Proposal and
return the bid security prior to that date.
16. Award of Contract
16.1 Owner reserves the right to reject any and all Bid Proposals, to waive any and all
informalities not involving price, time or changes in the Work and to negotiate contract terms
with the Successful Bidder. Owner may reject a bid as non-responsive if: 1) Bidder fails to
provide required Bid Security; 2) Bidder improperly or illegibly completes or fails to complete
all information required by the Bidding Documents; 3) Bidder fails to sign the Bid Proposal or
improperly signs the Bid Proposal; 4) Bidder qualifies its Bid Proposal; 5) Bidder tardily or
otherwise improperly submits its Bid Proposal; 6) Bidder fails to submit the Qualifications of
Bidder as required under section 3 of these Instructions to Bidders; or 7) Bid Proposal is
otherwise non-responsive. Contracts are awarded on the basis of one of the following criteria:
A)provision of the"Best Value'or
B) Lowest Responsible Bidder
16.2 Best Value. In determining the best value for the Owner, and in determining to whom
to award a contract, Owner may consider: 1) purchase price; 2) reputation of the Bidder and
Bidder's goods or services; 3) quality of Bidder's goods or services; 4) extent to which the
goods or services meet the Owner's needs; 5) Bidder's past relationship with the Owner; 6)
impact on the ability of Owner to comply with laws and rules relating to contracting with
historically underutilized businesses and nonprofit organizations employing persons with
disabilities; 7) total long-term cost to Owner to acquire Bidder's goods or services; 8) the
Qualifications of Bidder; and 9) any other relevant criteria specifically listed in the Bidding
Documents. A contract to be awarded to the Bidder offering the Best Value may be let on
either a lump sum basis or a unit cost basis dependent on the Bid Proposal format.
16.3 Lowest Responsible Bidder. In determining Lowest Responsible Bidder, Owner will
consider: Lowest Total Bid price for all work including Base Bid, Extra Work and Alternates,
if any, and any other cost criteria. Additional evaluation criteria may include: the
Qualifications of the Bidders, whether or not the Bid Proposals comply with the prescribed
requirements, and such alternates, unit prices and other data, as may be requested in the Bid
Proposal form or prior to the Notice of Award. Discrepancies in the multiplication of units of
10-2012 00200-7of8
CITY OF PEARLAND INSTRUCTIONS TO BIDDERS
Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the
indicated sum of any column of figures and the correct sum thereof will be resolved in favor of
the correct sum.
A contract to be awarded to the Lowest Responsible Bidder may be let on either a lump sum
basis or a unit cost basis dependent on the Bid Proposal format.
Acceptance of any and all bids may be conditioned on compliance with the requirement for
attendance of the mandatory pre-bid meeting.
16.4 In either case, Owner may conduct such investigations as Owner deems necessary to
assist in the evaluation of any Bid Proposal and to establish the responsibility, qualifications
and financial ability of Bidders, proposed Subcontractors, suppliers and other persons and
organizations to perform and furnish the Work in accordance with the Contract Documents, to
Owner's satisfaction,within the Contract Time.
17. Contract Security
17.1 When the Successful Bidder delivers the executed Standard Form of Agreement to
Owner, it must be accompanied by the Performance, Payment, Maintenance and Surface
Correction Bonds required by the Contract Documents. Bonds may be on the forms provided
herein or an equal form containing no substantive changes,as determined by Owner.
18. Signing of Agreement
18.1 When Owner gives a Notice of Award to the Successful Bidder, it will be accompanied
by the required number of unsigned counterparts of the Standard Form of Agreement, and the
required Performance and Payment Bond forms. Within ten (10) days thereafter Contractor
shall sign and deliver the required number of counterparts of the Standard Form of Agreement
to Owner with the required Bonds. Within ten (10) days thereafter, Owner shall deliver one
fully signed counterpart to Contractor. There shall be no contract or agreement between
Owner and the Successful Bidder until proper execution and attestation of the Standard Form
of Agreement by authorized representatives of the Owner.
19. Pre-bid Conference
19.1 A pre-bid conference will be held as indicated in the Invitation to Bid. Attendance at
the pre-bid conference is MANDATORY to fulfill the prerequisite requirements for Bidders
bidding directly to the Owner.
20. Retainage
20.1 Provisions concerning retainage are set forth in the Contract Documents.
(1'N, END OF SECTION
10-2012 00200-8 of 8
CITY OF PEARLAND BID PROPOSAL
Section 00300
BID PROPOSAL
Part A
Date: May 30th,2013
Bid of SER Construction Partners,LLC. ,an individual proprietorship/a
corporation organized and existing under the laws of the State of Texas/a partnership consisting
of ,for the construction of:
Old Alvin Road Water Line from John Lizer Road to McHard Road.
City,of Pearland,Texas
COP PN:WA1101
BID NO.: 0413-50
(Submitted in Electronic format)
To: The Honorable Mayor and City Council of Pearland •
City of Pearland
3519 Liberty Drive
Pearland,Texas 77581
Pursuant to the published Invitation to Bidders, and Instructions to Bidders, the undersigned
Bidder hereby proposes to perform all the work and furnish all necessary superintendence, labor,
machinery, equipment, tools and materials, and whatever else may be necessary to complete all
the work described in or reasonably inferable from the Contract Documents for the construction of
the Old Alvin Road Water Line from John Lizer Road to McHard Road. with all related
appurtenances, complete, tested, and operational, in accordance with the Plans and Specifications
prepared by the Engineer, Charles D. Gooden Consulting Engineers (TBPE # F-4176), 2320
Holmes Road, Suite A, Houston, TX 77051, Engineer-of-Record: Leon E. Hoch, P.E., for the unit
prices or applicable prices set forth in Exhibit "A", the electronic bid form as contained in the
City's E-bid system, which, once fully executed and submitted shall constitute a legal and
executable proposal from the Bidder. It is understood that, in the event any changes are ordered
on any part of the Work, the applicable unit prices bid shall apply as additions to or deductions
from the total prices for the parts of the Work so changed.
•
The Bid Security required under the Instructions to Bidders is included and has been uploaded as
an attachment within the E-bid system and, that a fully executed, signed and sealed hard copy has
been delivered to the Office of City Purchasing, Finance Department, 2nd Floor, City Hall, 3519
Liberty Drive, Pearland,Texas 77581.
The Bidder agrees to submit to the Owner the Qualifications of Bidder, including the Financial
Statement of Bidder, as required by the Instructions to Bidders if requested to do so as a condition
of the Bid review.
The Bidder binds himself, upon acceptance of his proposal, to execute the Standard Form of
Agreement and furnish an acceptable Performance and Payment Bond and Maintenance Bond,
each in the amount of one hundred percent (100%) of the total Contract Price, according to the
forms included in the Contract Documents, for performing and completing the said work within
Bidder's Initial's:
10-2012 00300- 1 of 3
CITY OF PEARLAND BID PROPOSAL
the time stated and for the prices stated in Part B of this proposal along with all required insurance
in the required amounts.
The undersigned Bidder agrees to commence work within 10 days of the date of a written Notice
to Proceed. It is understood that the Work is to be Substantially Complete within ninety(90) days
after the date of the Notice to Proceed. Time for Substantial Completion shall begin on the date
established by the Notice to Proceed. The Contractor will pay liquidated damages in the
amount(s) specified in Document 00500— Standard Form of Agreement, in the event the Work is
not Substantially Complete within the Contract Time.
The undersigned agrees that the amounts bid in this Bid Proposal will not be withdrawn or
modified for ninety (90) days following date of Bid Proposal opening, or such longer period as
may be agreed to in writing by the City of Pearland and Bidder.
It is understood that in the event the Successful Bidder fails to enter into the Standard Form of
Agreement and/or to furnish an acceptable Performance and Payment Bond and Maintenance
Bond, each in the amount of one hundred (100) percent of the Contract Price, along with all
required insurance in the stated amounts within ten (10) days of the Notice of Award, the
Successful Bidder will forfeit the Bid Security as provided in the Instructions to Bidders. Unless
otherwise expressly provided herein,all references to "day(s)"shall mean calendar day(s).
The Bidder acknowledges that the following Addenda have been received. The modifications to
the Bidding Documents noted therein have been considered and all costs thereto are included in
the Bid Proposal prices.
Addendum No.: 1 Date: 5/13/2013 Addendum No.: Date:
Addendum No.: 2 Date: 5/28/2013 Addendum No.: Date:
Bidder hereby represents that the only person or parties interested in this offer as principals are
those named. Bidder has not directly or indirectly entered into any agreement, participated in any
collusion,or otherwise taken any action in restraint of free competitive bidding.
Firm Name: SER Construction Partners,LLC.
By: Rosbel E.Ramos
Title: President
Address: 3636 Pasadena Blvd.,Pasadena,Texas 77503
Phone No: 713-473-7900
ATTEST:
, .el ;.Ra os (Seal,if Bidder is a Corporation)
(Typ•d or 'rinte 1 f
rif
Si: .ture
Date: Ma 30th, 2l
n�
!`
Bidder's Initial's:�-
10-2012 00300-2 of 3
CITY OF PEARLAND BID PROPOSAL
END OF SECTION
Bidder's Initial's:
10-2012 00300-3 of 3
•
City of Pearland Texas (Projects Department)
Supplier Response
Bid Information Contact Information Ship to Information
Bid Creator Patty Patke Program Address 3519 Liberty Drive Address 3519 Liberty Drive
Specialist Suite 201
Email ppatke@ci.pearland.tx.us Pearland,TX 77581 Pearland,TX 77581
Phone (281)652-1756 Contact Patty Patke Contact
Fax (281)652-1706 Projects
Department Department
Bid Number 0413-50 Addendum 2 Building City Hall Building City Hall
Title Old Alvin Water Line from 2nd Floor
John Lizer Rd.to McHard Rd. Floor/Room Floor/Room
Bid Type Invitation to Bid Telephone (281)652-1756 Telephone 281 (652) 1738
Issue Date 05/09/2013 Fax (281)652-1706 Fax
Close Date 5/30/2013 2:00:00 PM CT Email Email ebids@ci.pearland.tx.us
Need by Date ppatke@ci.pearland.tx.us
Supplier Information
Company SER Construction Partners, LLC
Address 3636 Pasadena Blvd
Pasadena,TX 77503
Contact
Department
Building
Floor/Room
("Telephone 1 (713)473 7900
Fax 1 (713)473 7919
Email
Submitted 5/30/2013 12:44:34 PM CT
Total $3,398,483.00
Signature
Supplier Notes
Bid Notes
The project will entail the construction of a 20"diameter water line with all associated
appurtenances including valves, service line connections, and fire hydrants. Tree protection and
pavement removal and replacement are also included. Additionally,there will be storm sewer
removal and replacement from Linwood Street to Town Ditch.Control of surface and ground
water; preparation and implementation of a traffic control plan and storm water pollution
prevention plan,and all associated construction related permits are included in the scope.
Bid Activities
Date Name Description
5123/2013 2:00:00 PM Mandatory Pre-Bid Meeting A mandatory pre-bid conference will be held at the City of Pearland City Hall at 3519
Liberty
Drive,Pearland,Texas 77581 at 2:00 p.m.on May,23,2013.
0413-50 Addendum 2-Page 1 of 17
•
Bid Messages
- Date Subject Message
05/15/13 Mandatory Pre-Bid Meeting Please see Addendum 1 for date and time of Mandatory Pre-Bid Meeting
05/17/13 Mandatory Pre-Bid Meeting Due to conflicting information regarding the date and time of the Mandatory Pre-Bid meeting for Old Alvin
Rd Waterline,the City of Pearland will hold a second Mandatory Pre-Bid meeting on May 23rd,at 2:00pm,
as was specified in the original Invitation to Bidders. Bidders who intend to submit a bid for this project and
did not attend the May 16th meeting,are required to attend on May 23rd. Please contact the City if you
have any questions.
Please review the following and respond where necessary
# Name Note Response
1 Response Attachment Bidder understands and has completed the following:The Submitted
Bid Proposal and Bid Security required under the
Instructions to Bidders has been uploaded as an
attachment within the E-bid system and,a fully executed,
signed and sealed hard copy of the Bid Bond will be
delivered upon request to the Office of City Purchasing,
Finance Department, 2nd Floor,City Hall,3519 Liberty
Drive,Pearland,Texas,77581.
2 Non-collusion Statement Bidder has submitted a completed and signed copy of the Submitted
Non-Collusion Statement
3 General Conditions Bidder has read and agrees to the General Conditions set Agrees
forth by the City of Pearland.
4 Specification Acknowledgement Bidder has reviewed specifications and agrees that their Agrees
bid adheres fully.
5 Local Bidder Bidder claims Pearland local bidder preference,pursuant Not Local Bidder
to provisions of Local Bidder Preference claim form and
Texas Local Govemment Code,Chapter 271.9051
C
0413-50 Addendum 2- Page 2 of 17
Page 1 of 4 Charles D. Gooden Consulting Engineers, Incorporated-TBPE 4176 June 3,2013
,�� Bids Opened: May 30,2013,2PM
( ' Bid Tabulation
City of Pearland
Old Alvin Road Waterline-John Lizer Road to McHard Road
Project No.WA1101
Bid No. 0413-50 Addendum 2
Bid Opening: May 30,2013 at 2:00 pm
Specification Responses SER Construction Partners, LLC
'Line Description UOM QTY 'Unit 'Extended
1 Base Bid 1 0 1
Mobilization (MAXIMUM VALUE IS LIMITED
1.1 TO 3%OF TOTAL BID) LS 1 $100,000.00 $100,000.00
1.2 Traffic control and regulation LS 1 $40,000.00 $40,000.00
1.3. Flagmen LS 1 $40,000.00 $40,000.00
1.4 Tree and plant protection LS 1 $35,000.00 -$35,000.00
Storm water pollution prevention plan
1.5 implementation LS 1 $364.00 $364.00
1.6 Reinforced Filter Fabric Barrier LF 11950 $2.00 $23,900.00
1.7 Inlet Protection Barrier LF 1800 $7.00 $12,600.00
1.8 Sediment Control Fence LF 250 $3.00 - $750.00
1.9 Sand Bags EA 10 $55.00 $550.00
1.10 Stabilized Construction Exit(Install) SY 1200 $20.00 '.$24,000.00
1.11 Stabilized Construction Exit(Remove) SY 1200 $2.00 $2,400.00
1.12 Trench Safety System LF 12660 $0.10 . $1,266.00
1.13 Project Identification Signs EA 2 $641.00 $1,282.00
1.14 Clearing and Grubbing AC 11 $2,000.00 . $22,000.00
Remove and Dispose-Concrete Sidewalk-
1.15 6'Width SY 980 $6.00 .' $5,880.00
1.16 Replace Concrete Sidewalk-6'Width SY 980 $40.00 $39,200.00
1.17 Remove and Dispose-Concrete Driveways SY 286 $7.00 $2,002.00
1.18 Replace Concrete Driveways SY 286 $41.00 $11,726.00
1.19 Remove and Dispose-Asphalt Driveways SY 164 $8.00 - $1,312.00
1.20 Replace Asphalt Driveways-See Detail SY 164 $38.00 '_ $6232.00
Remove and Dispose-Asphalt Roadway
1.21 (For Open Cut Water Line Installation) SY 294 $9.00 .$2,646.00
Replace Asphalt Roadway-See Detail (For
1.22 Open Cut Water Line Installation) SY 294 $37.00 ; $10,878.00
Remove and Dispose-Concrete Roadway
1.23 (For Open Cut Water Line Installation) SY 199 $8.00 $1,592:00
Replace Concrete Roadway-See Detail (For
1.24 Open Cut Water Line Installation) SY 199 $43.00 ; $8,557.00
1.25 Hydromulch Seeding AC 11 $1,300.00 $14,306.00
1.26 Sodding SY 50 $5.00 , ` $250.00
Prepatory Work related to Underground Utility
Construction in Potentially Petroleum
1.27 Contaminated Area (PPCA) LS 1 $22,000.00 $22,000.00
Remove& Replace Existing Iron Fence(STA
1.28 51+46 to STA 54+35) LS 1 $2,600.00 $2,600.00
Install&Remove Temporary Chain Link
1.29 Fence(STA 51+46 to STA 54+35) LS 1 $5,600.00 ' $5,600.00
1.30 Remove& Reinstall Existing Street Signs LS 1 $5,000.00 ' $5,000.00
( 1°P..\
Page 2 of 4 Charles D.Gooden Consulting Engineers, Incorporated-TBPE 4176 June 3,2013
Bids Opened: May 30,2013,2PM
Specification Responses SER Construction Partners, LLC
20-inch Ductile Iron Pipe(Class 52)w/welded
36 steel casing Inc! Restrained joints, FKM
Viton Gaskets&appurtenances complete-in-
place(Auger)in PPCA. Excavation,
handling, and disposal of contaminated
ground water and soils is also included in this
1.31 line item-(at FM 518/Old Alvin crossing) LF 184 $970.00 $1.78,48000
20-inch pvc water main and Appurtenances
1.32 Complete-in-place(open cut) LF 8702 $102.00 $887,604.00
20-inch pvc water main and Appurtenances
. 1.33 Complete-in-place(auger) LF 339 $193.00 ' $65,427.00
20-inch Ductile Iron Pipe (Class 52)pipe
w/welded 36 steel casing Inc! Restrained
joints&appurtenances complete-in-place .
1.34 (Auger)- (Drainage Culvert Sta 65+25) LF 60 $732.00 . $43,920.00
20-inch Ductile Iron Pipe (Pressure Class _
250)pipe Inc! Restrained joints&
appurtenances complete-in-place (Open Cut)
1.35 (at Swenson St-Sta 24+50)and (Sta.94+50) LF 470 $134.00 $62,98000
20-inch Ductile Iron Pipe (Pressure Class
250)pipe Inc! Restrained joints& .
appurtenances complete-in-place (Open Cut)
1.36 -(at Walnut Road) LF 143 $170.00 $24,310.00
20-inch PVC Water Main Inc! Restrained
joints&appurtenances complete-in-place
1.37 (Open Cut) LF 2018 $90.00 $181;62000
16-inch Ductile Iron Pipe (Pressue Class ..
250) pipe Ind Restrained joints&
appurtenances complete-in-place (Open Cut)
1.38 (by FM 518 16-inch connection) LF 60 $330.00 .$19,800:00
20-inch Steel Pipe Above Ground (Sta.
1.39 26+00 and 94+50)per AWWA requirements LF 338 $225.00 $76,050.00 .
12-inch Steel casing for 8-inch SDR-26 PVC .
1.40 Pipe(Sta. 61+90) LF 20 $250.00 $5,00000
20-inch Ductile Iron Pipe (Pressure Class
250)w/welded 36 steel casing Inc! _
Restrained joints&appurtenances complete-
in-place (Open cut)- (Drainage Culvert Sta
1.41 68+60) LF 60 $400.00 . --$24,000.00
1.42 10-inch PVC pipe include Restrained Joint LF 25 $200.00 $6,000 00
1.43 8-inch pvc pipe include Restrained Joint LF 778 $80.00 $62,240.00
20-inch Ductile Iron Pipe (Pressure Class •
250) pipe&appurtenances complete-in-place
1.44 (Open Cut)- (Sta 57+15 to 65+87) LF 315 $144.00 $45,360.00
1.45 3-inch pvc pipe include Restrained Joint LF 63 $40.00 $2,520.00
1.46 6-inch pvc pipe include Restrained Joint LF 787 $60.00 $47,220.00
1.47 6-inch pvc pipe(Auger) LF 55 $70.00 . - $3,850.00
Page 3 of 4 Charles D.Gooden Consulting Engineers, Incorporated-TBPE 4176 June 3,2013
Bids Opened: May 30,2013,2PM
Specification Responses SER Construction Partners, LLC
Water tap&Polyethylene service Line short
1.48 side(1") EA 1 $750.00 $750.00
Water tap&Polyethylene service Line long
1.49 side(1") EA 11 $1,300.00 $14,300.00
Water tap& Polyethylene service Line short
1.50 side(2") EA 1 $1,300.00 $1,300.00
Water tap&Polyethylene service Line long
1.51 side(2") EA 5 $2,200.00 $11,000.00
Water tap&PVC service Line short side (3"
1.52 thru 4") EA 3 $500.00 $1,500.00
Water tap&PVC service Line long side(3"
1.53 thru 4") EA 1 $1,500.00 $1,500.00
1.54 3"Wet Connection EA 2 $350.00 ` $700.00
1.55 4"Wet Connection EA 3 $500.00 $1,500.00
1.56 6"Wet Connection EA 4 $700.00 $2,800.00
1.57 8"Wet Connection EA 8 $900.00 $7,200.00
1.58 10"Wet Connection EA 2 $1,000.00 - $2,000.00
1.59 20"Wet Connection EA 2 $3,800.00 $7,600.00
1.60 16"Tapping Sleeve and Valve EA 1 $15,000.00 $15,000.00
1.61 Cut,Plug&Abandon Exist. 12"Water Line EA 1 $400.00 $400.00
1.62 Cut,Plug&Abandon Exist. 10"Water Line EA 1 $400.00 $400.00
1.63 Cut,Plug&Abandon Exist. 8"Water Line EA 11 $300.00 $3,300.00
1.64 Cut,Plug&Abandon Exist. 6"Water Line EA 4 $200.00 $800.00
1.65 Cut, Plug&Abandon Exist.4"Water Line EA 2 $120.00 $240.00
1.66 Cut, Plug&Abandon Exist. 3"Water Line EA 1 $110.00 $110.00
Fire hydrant Assembly Ind6"branch, gate
1.67 valve&box complete-in-place EA 35 $5,000.00 $175,000.00
1.68 Remove&salvage fire hydrant EA 9 $200.00 $1,800.00
Remove& replace 20 LF of 12" SDR 26 San.
1.69 Swr. Centered over prop.WL EA 2 $3,500.00 , $7,000.00
Remove&replace 20 LF of 8"SDR 26 San. '
1.70 Swr. Centered over prop. WL EA 3 $3,000.00 $9,000.00
1.71 20-inch Butterfly Valve complete in place EA 17 $3,200.00 . $54,400.00
Air Release Valves on 20-inch Steel Water
1.72 Line EA 2 $1,300.00 $2,600.00
Air Release Valve on 20-inch PVC in
1.73 Manhole EA 1 $17,000.00 $17,000:00
"Elevated Water Line Crossings Including '
Drilled Piers, Box Beam, and Appurtenances, ,
1.74 at Mary's Creek and Town Ditch" LS 2 $80,000.00 ' $160,000.00
1.75 Regrade Existing Swales and Roadside Ditch LF 4685 $4.00 $18,740.00
Remove and dispose of asphaltic/concrete -
surfacing with or without base, all
1.76 thicknesses SY 6400 $6.00 ' $38,400.00
1.77 Pavement Repair and Resurfacing SY 6400 $36.00 $230,400.00
Remove and dispose of 18-24-inch RCP All
1.78 Depths LF 86 $20.00 ' $1,720.00
Page 4 of 4 Charles D. Gooden Consulting Engineers, Incorporated-TBPE 4176 June 3,2013
Bids Opened: May 30,2013,2PM
Specification Responses SER Construction Partners, LLC
Remove and dispose of 36-48-inch RCP All
1.79 Depths LF 942 $25.00 $23,550.00
Removed and dispose of Sanitary Sewer-All
1.80 Depths LF 20 $28.00 $560.00
Remove and dispose storm sewer inlet-All
1.81 Types EA 13 $200.00 ` $2,600.00
1.82 Cut Plug Abandon exist 18"Storm Sewer EA 2 $300.00 $600.00
1.83 Cut Plug Abandon exist 24"Storm Sewer EA 1 $400.00 $400.00
Type"A" Inlet on 5'x 4'Precast Reinforced
1.84 Concrete Box Storm Sewer EA 12 $2,300.00 -$27,60000
1.85 Type"A" Inlet on 36" RCP Storm Sewer EA 2 $3,400.00 $6,800.00
Type"C"manhole for 42-inch diameter and
1.86 smaller sewers EA 2 $2,100.00 $4,200.00
Precast Manhole on 5'x 4' Precast
1.87 Reinforced Concrete Box Storm Sewer EA 4 $900.00 $3,600.00
18-inch diameter RCP storm sewer by open
1.88 cut LF 10 $82.00 _$820.00
24-inch diameter RCP storm sewer by open •
1.89 cut LF 95 $83.00 ._. $7,885.00
36-inch diameter RCP storm sewer by open "
1.90 cut LF 285 $124.00 $35,34000
5'x 4' Precast Reinforced Concrete Box
1.91 Storm Sewer LF 810 $300.00 .$243,000.00
Pre-Cast Junction Box(See details on -
1.92 Sheets 45B and 45C) EA 1 $8,000.00 : $8,00000
1.93 Curb, Curb&Gutter, and Headers LF 140 $25.00 $3,500:00
These items are extra work items and are to -
be used only if ordered by the Owner's
Engineer or Construction Manager. No '
compensation will be received for any part of
the quantities unless they are ordered and
used on the job. The cost of these items
should be included in the total construction
2 bid.
Groundwater control for open cut - -
2.1 construction LF 500 $28.00 $14,000.00
2.2 20-inch Butterfly Valve complete in place EA 5 $3,500.00 ' ` .$17,50000
Additional Removal of Concrete Pavements,
2.3 With or Without base SY 300 $6.00 $1,800:00
Additional Replacement of Concrete
2.4 Pavements SY 300 $45.00- -- -$13,500.00
Additional Removal of Asphalt Pavements, •
2.5 With or Without base SY 300 $6.00 $1',800.00.
Additional Replacement of Asphalt
2.6 Pavements SY 300 $45.00 • $13500.00
2.7 Hand Excavation CY 10 $20.00 -,- $200.00
Total ; $3,398,483.00
CITY OF PEARLAND STANDARD FORM OF AGREEMENT
Section 00500
STANDARD FORM OF AGREEMENT
THIS AGREEMENT is by and between City of Pearland (hereinafter called OWNER or City) and
SER Construction Partners, LLC (hereinafter called CONTRACTOR).
OWNER and CON TRACTOR, in consideration of the mutual covenants hereinafter set forth,
agree as follows:
Article 1. WORK
CONTRACTOR shall complete all work as specified or indicated in or reasonably
inferable from the Contract Documents (hereinafter the "Work"). The Work is generally
described as follows:
Old Alvin Road Water Line
From John Lizer Road to McHard Road
City of Pearland,Texas
COP PN: WA1101
BID NO.: 0413-50
Article 2. ENGINEER
The Work has been designed by Charles D. Gooden Consulting Engineers (TBPE # F-
4176), 2320 Holmes Road, Suite A, Houston, TX 77051, Engineer-of-Record: Leon E.
Hoch, P.E. who is hereinafter called ENGINEER and who is to assume all duties and
responsibilities and have the rights and authority assigned to ENGINEER in the Contract
Documents in connection with completion of the Work in accordance with the Contract
Documents.
Article 3. CONTRACT TIME
3.1 The Work will be Substantially Complete (as defined in Article 1 of the General
Conditions) within one-hundred eighty (180) days (including weekends and
holidays) from the date when the Contract Time commences to run as provided in
paragraph 5.01 of the General Conditions (as revised in the Special Conditions if
applicable), and completed and ready for Final Payment within two-hundred ten
(210) days from the date when the Contract Time commences to run. No work will
be allowed on Sundays.
3.2 Liquidated Damages. OWNER and CONTRACTOR recognize that time is of the
essence of this Agreement and that OWNER will suffer financial loss if the Work is
not completed within the times specified in paragraph 3.1 above, plus any
extensions thereof allowed in accordance with Article 5 of the General Conditions.
OWNER and CONTRACTOR also recognize the delays, expense, and difficulties
involved in proving in a legal or arbitration preceding the actual loss suffered by
OWNER if the Work is not completed on time. Accordingly, instead of requiring
any such proof, OWNER and CONTRACTOR agree that as liquidated damages for
10-2012 00500- 1 of7
CITY OF PEARLAND STANDARD FORM OF AGREEMENT
delay(but not as a penalty) CONTRACTOR shall pay OWNER one-hundred fifty
dollars ($150.00) for each day that expires after the time specified in paragraph 3.1
for Substantial Completion until the Work is substantially complete. After
Substantial Completion, if CONTRACTOR shall neglect, refuse or fail to complete
the remaining Work within the time set out in the Certificate of Substantial
Completion or any proper extension thereof granted by OWNER, CONTRACTOR
shall pay OWNER one-hundred fifty dollars ($150.00) for each day that expires
after the time specified in the Certificate of Substantial Completion for completion
and readiness for Final Payment.
3.3 Inspection Time. Working hours for the Pearland Inspection personnel are from
7:30 a.m. to 4:30 p.m., Monday through Friday, excluding City approved holidays.
The Contractor shall notify the OWNER of any required inspection overtime work
at least 48 hours in advance and shall pay the overtime wages for the required City
inspections.
Article 4. CONTRACT PRICE
4.1 OWNER shall pay CON TRACTOR for completion of the Work in strict
accordance with the Contract Documents in current funds $3,398,483.00
(the"Contract Price").
The Contract Price includes the Base Bid as shown in Document 00300 — Bid
Proposal.
Article 5. PAYMENT PROCEDURES
CONTRACTOR shall submit Applications for Payment in accordance with Section 6.0
"Measurement and Payment" of the General Conditions. Application for Payment will be
processed by ENGINEER as provided in the General Conditions.
5.1 Progress Payments. OWNER shall make progress payments on account of the
Contract Price on the basis of CONTRACTOR's Application for Payment as
recommended by ENGINEER as provided below. All progress payments will be
on the basis of the progress of the Work and actual quantity of Work completed, in
accordance with Article 6 "Measurement and Payment" of the General Conditions.
5.1.1 Prior to Substantial Completion, progress payments will be made in an
amount equal to the percentage or actual quantity of Work complete, but, in
each case, less the aggregate of payments previously made and less such
amounts as ENGINEER shall determine, or OWNER may withhold, in
accordance with the General Conditions. The OWNER shall make payment
within 30 days of receipt of application for payment by the ENGINEER.
5.1.2 Each progress payment shall be less retainage as specified in Paragraph 6.06
of the General Conditions, and further less all previous payments and all
further sums that may be retained by the OWNER under the terms of this
Agreement. It is understood, however, that in case the whole work be near
to completion and some unexpected and unusual delay occurs due to no
10-2012 00500-2 of 7
CITY OF PEARLAND STANDARD FORM OF AGREEMENT
(4.26` fault or neglect on the part of the CONTRACTOR, the OWNER may upon
written recommendation of the ENGINEER pay a reasonable and equitable
portion of the retained percentage to the CONTRACTOR, or the
CONTRACTOR at the OWNER's option, may be relieved of the obligation
to fully complete the Work and, thereupon, the CONTRACTOR shall
receive payment of the balance due him under the contract subject only to
the conditions stated under"Final Payment."
5.2 Final Payment. Upon final completion and acceptance of the Work in accordance
with paragraph 6.09of the General Conditions, OWNER shall pay the remainder of
the Contract Price as recommended by ENGINEER as provided in said paragraph
6.09.
Article 6. INTEREST
Interest on any overdue payment from OWNER to CONTRACTOR shall be paid in
accordance with the provisions of Chapter 2251.025 of the Texas Government Code, as
amended.
Article 7. CONTRACTOR'S REPRESENTATIONS
In order to induce OWNER to enter into this Agreement CONTRACTOR makes the
following representations:
7.1 CONTRACTOR has familiarized himself with the nature and extent of the Contract
Documents, Work, site, locality, and all local conditions and Laws and Regulations
that in any manner may affect cost, progress, performance, or furnishing of the
Work.
7.2 CONTRACTOR has studied carefully all available surveys, assessments, reports of
explorations, investigations, and tests of subsurface conditions and drawings of
physical conditions of the site. Such technical reports and drawings are not
Contract Documents, and Owner makes no representations or warranties as to the
accuracy of such documents or information, or to whether or not they are complete,
comprehensive, or all-inclusive.
7.3 CONTRACTOR has obtained and carefully studied (or assumes responsibility for
obtaining and carefully studying) all such examinations, investigations,
explorations, tests, reports, and studies (in addition to or to supplement those
referred to in paragraphs 7.2 above) which pertain to the subsurface or physical
conditions at or contiguous to the site or otherwise may affect the cost, progress,
performance or furnishing of the Work ,and CONTRACTOR assumes the risk of
such subsurface and physical conditions, and shall furnish the Work at the Contract
Price, within the Contract Time and in accordance with the other terms and
conditions of the Contract Documents; and no additional examinations,
investigations, explorations,tests,reports, and studies or similar information or data
are or will be required by CONTRACTOR for such purposes.
rik\
10-2012 00500-3 of 7
CITY OF PEARLAND STANDARD FORM OF AGREEMENT
Cimk\, 7.4 CONTRACTOR has reviewed and checked all information and data shown or
indicated on the Contract documents with respect to existing underground facilities
at or contiguous to the site and assumes responsibility for the accurate location of
said underground facilities. No additional examinations, investigations,
explorations, tests, reports, studies or similar information or data in respect of said
underground facilities are or will be required by CONTRACTOR in order to
perform and finish the Work at the Contract Price, within the Contract Time and in
accordance with the other terms and conditions of the Contract Documents.
7.5 CONTRACTOR has correlated the results of all such observations, examinations,
investigations, explorations, tests,reports, and studies with the terms and conditions
of the Contract Documents.
7.6 CONTRACTOR has given ENGINEER written notice of all conflicts, errors or
discrepancies in the Contract Documents of which Contractor knew or should have
known, and CONTRACTOR shall perform the Work at the Contract Price, within
the Contract Time and in accordance with the other terms and conditions of the
Contract Documents, including any written resolution of any such conflict, error or
discrepancy by ENGINEER. In the event of a conflict that was not brought to the
OWNER's or ENGINEER's attention prior to the bid, the CONTRACTOR is
assumed to have bid the most expensive alternative.
Article 8. CONTRACT DOCUMENTS
The Contract Documents, which comprise the entire agreement between OWNER and
CONTRACTOR concerning the Work, consist of the following, each of which are
incorporated herein by reference:
8.1 Standard Form of Agreement(Section 00500).
8.2 Performance, Payment, and/or Maintenance Bonds (Sections 00610, 00611, and
00612).
8.3 General Conditions of Agreement (Section 00700), including Attachment No. 1
Workers' Compensation Insurance Coverage, Attachment No. 2 Agreement for
Final Payment and Contractor's Sworn Release, and Attachment No. 3 Owner's
Insurance Requirements of Contractor.
8.4 Special Conditions of Agreement(Section 00800).
8.5 Plans, consisting of sheets numbered 1 through 81, Total of ninety-two (92)
sheets, inclusive with attachments with each sheet bearing the following general
title: Old Alvin Road 20-Inch Water Line
8.6 Instructions to Bidders and CONTRACTOR's Bid Proposal, including any
Addenda referenced therein.
8.7 Technical Specifications for the Work.
10-2012 00500-4 of 7
CITY OF PEARLAND STANDARD FORM OF AGREEMENT
8.8 The following, which may be delivered or issued after this Agreement becomes
effective: Any Change Orders or other documents amending, modifying, or
supplementing the Contract Documents in accordance with the General Conditions.
There are no Contract Documents other than those listed above in this Article 8. The
Contract Documents may only be amended,modified or supplemented as provided in the
General Conditions.
Article 9. MISCELLANEOUS
9.1 Terms used in this Agreement which are defined in Section 1, `Definitions and
Interpretations" of the General Conditions will have the meanings indicated in the
General Conditions.
9.2 No assignment by a party hereto of any rights under or interests in the Contract
Documents will be binding on another party hereto without the written consent of
the party sought to be bound; and specifically but without limitation moneys that
may become due and moneys that are due may not be assigned without such
consent (except to the extent that the effect of this restriction may be limited by
law), and unless specifically stated to the contrary in any written consent to an
assignment, no assignment will release or discharge the assignor from any duty or
responsibility under the Contract Documents.
9.3 OWNER and CONTRACTOR each binds itself, its partners, successors, assigns
(lb.\ and legal representative to the other party hereto, its partners, successors, assigns
and legal representatives in respect of all covenants, agreements and obligations
contained in the Contract Documents.
9.4 CONTRACTOR agrees to warranty the Work for a period of one (1) year from
Substantial Completion against defects in materials and workmanship.
CONTRACTOR agrees to repair or replace any defective work within this warranty
period immediately unless such repairs require long lead time materials and
equipment in which case CONTRACTOR shall provide an agreeable schedule for
repairs at no additional cost to OWNER.
9.5 The Work will be completed according to the Contract Documents and in
accordance with codes, ordinances, and construction standards of the City of
Pearland, and all applicable laws, codes and regulations of governmental
authorities.
9.6 In the event any notice period required under the Contract Documents is found to
be shorter than any minimum period prescribed by applicable law, the notice period
required shall be construed to be the minimum period prescribed by applicable law.
9.7 This Contract and the Contract Documents, insofar as they relate in any part or in
any way to the Work undertaken therein, constitute the entire agreement between -
the parties hereto, and it is expressly understood and agreed that there are no
rumn‘ agreements or promises by and between said parties, except as aforesaid, and that
any additions thereto or changes shall be in writing.
10-2012 00500-5 of 7
CITY OF PEARLAND STANDARD FORM OF AGREEMENT
9.8 The provisions of this Contract shall be applied and interpreted in a manner
consistent with each other so as to carry out the purposes and the intent of the
parties, but if for any reason any provision is unenforceable or invalid, such
provisions shall be deemed severed from this Contract and the remaining
provisions shall be carried out with the same force and effect as if the severed
provision had not been part of this Contract.
9.9 The headings of the paragraphs are included solely for the convenience of reference
and if there is any conflict between the headings and the text of this Contract, the
Contract text shall control.
9.10 The waiver of any breach hereof shall not constitute a waiver of any subsequent
breach of the same or any other provision hereof. Failure by the OWNER in any
instance to insist upon observance or performance by CONTRACTOR shall not be
deemed a waiver by CONTRACTOR of any such observance or performance. No
waiver will be binding upon OWNER unless in writing and then will be for the
particular instance only. Payment of any sum by OWNER to CONTRACTOR with
knowledge of any breach or default will not be deemed a waiver of such breach or
default or any other breach or default.
9.11 The CONTRACTOR acknowledges that the OWNER(through its employee
handbook)considers the following to be misconduct that is grounds for termination
of an employee of the OWNER: Any fraud, forgery,misappropriation of funds,
receiving payment for services not performed or for hours not worked,mishandling
or untruthful reporting of money transactions, destruction of assets, embezzlement,
accepting materials of value from vendors, or consultants, and/or collecting
reimbursement of expenses made for the benefit of the OWNER. The
CONTRACTOR agrees that it will not,directly or indirectly; cause an employee of
the OWNER to engage in such misconduct.
10-2012 00500-6 of 7
CITY OF PEARLAND STANDARD FORM OF AGREEMENT
IN WITNESS WHEREOF, OWNER and CONTRACTOR have signed this Agreement in
duplicate. One counterpart each has been delivered to OWNER and one to
CONTRACTOR.
This Agreement will be effective upon execution and attestation by authorized representatives of
the City of Pearland and upon the following date: , 20—
OWNER: CONTRACTOR:
CITY OF PEARL SER Construction P ers LL .
By: By: Rosbel E. Ramos
Title: Title: President
Date: ( -/6-J,' Date:
orpor ea1Y'
ATTEST • ATTEST
Addr s for givin tires
'QE ..... 36 6 Pasade Blvd.
_ Pasadena, Texas 77503
U:, i�trs
3r,
Phone: 713-473-7900
Fax: 713-473-7919
Agent for service of process:
Rosbel E. Ramos
END OF SECTION
10-2012 00500-7 of 7
CITY OF PEARLAND PERFORMANCE BOND
Section 00610 Bond No. 46BCSGK9823
PERFORMANCE BOND
STATE OF TEXAS §
COUNTY OF BRAZORIA §
KNOW ALL MEN BY THESE PRESENTS: That SER Construction Partners,LLC of the City
of Pasadena , County of Harris , and State of Texas, as principal, and
Hartford Fire Insurance Company authorized under the laws of the State of Texas to act
as surety on bonds for principals, are held and firmly bound unto City of Pearland as Obligee
(Owner), in the penal sum of$ 3,398,483.00 for the payment whereof, the said
Principal and Surety bind themselves, and their heirs, administrators, executors, successors, and
assigns,jointly and severally, by these presents:
WHEREAS, the Principal has entered into a certain written contract with the Owner, effective as
of the day of , 20_, (the "Contract") to commence and complete the
construction of certain improvements described as follows:
Old Alvin Road Water Line
from John Lizer Road to McHard Road
City of Pearland,Texas
COP PN:WA1101
BID NO.: 0413-50
which Contract, including the Contract Documents as defined therein, is hereby referred to and
made a part hereof as fully and to the same extent as if copied at length herein.
NOW THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said
Principal shall faithfully perform said Contract Work and shall in all respects duly and faithfully
observe and perform all and singular the covenants, conditions, and agreements in and by said
Contract agreed and covenanted by the Principal to be observed and performed, and according to
the true intent and meaning of said Contract and Contract Documents, then this obligation shall be
void; otherwise to remain in full force and effect;
PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Chapter 2253
of the Texas Government Code as amended and all liabilities on this bond shall be determined in
accordance with the provisions of said Statute to the same extent as if it were copied at length
herein.
Surety, for value received, stipulates and agrees that no change, extension of time, alteration or
addition to the terms of the contract, or to the Work performed thereunder, or the plans,
specifications, or drawings accompanying the same, shall in any way affect its obligation on this
bond, and it does hereby waive notice of any such change, extension of time,alteration or addition
to the terms of the Contract, or to the Work to be performed thereunder.
12/2007 00610-1 of 2
CITY OF PEARLAND PERFORMANCE BOND
IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this instrument
this day of ,20—
Principal:SER Construction Partners,LLC Surety: art..i d Fir; I urance Company
By: By: 'hill a Ba!r
Rosbe . os,President ,
Title: Title:Attorney-In-Fact
Address: Address:
P.O.Box 891145 3000 Internet Boulevard,Suite 600 =
Houston,Texas 77289 Frisco.TX 75034
Telephone: (713)473-7900 Telephone: (800)873-8212 - . -Fax: (713)473-7919 Fax: (866)275-5989
NOTICE:THE ADDRESS OF THE SURETY COMPANY TO WHICH ANY NOTICE
OF CLAIM SHOULD BE SENT MAY BE OBTAINED FROM THE TEXAS
DEPARTMENT OF.INSURANCE BY CALLING ITS TOLL-FREE TELEPHONE
NUMBER; 1-800-252-3439.
END OF SECTION
J 12n007 00610-2 61'2
CITY OF PEARLAND PAYMENT BOND
Section 00611 Bond No. 46BCSGK9823
PAYMENT BOND
STATE OF TEXAS §
COUNTY OF BRAZORIA §
KNOW ALL MEN BY THESE PRESENTS: That SER Construction Partners, LLC of the City
of Pasadena , County of Harris , and State of Texas, as principal, and
Hartford Fire Insurance Company authorized under the laws of the State of Texas to act
as surety on bonds for principals, are held and firmly bound unto City of Pearland as Obligee
(Owner), in the penal sum of$ 3,398,483.00 for the payment whereof, the said
Principal and Surety bind themselves, and their heirs, administrators. executors, successors, and
assigns,jointly and severally, by these presents:
WHEREAS, the Principal has entered into a certain written contract with the Owner, effective as
of the day of , 20 , (the "Contract") to commence and complete the
construction of certain improvements described as follows:
Old Alvin Road Water Line
from John Lizer Road to McHard Road
City of Pearland,Texas
COP PN: WA1101
BID NO.:0413-50
which Contract, including the Contract Documents as defined therein, is hereby referred to and
made a part hereof as fully and to the same extent as if copied at length herein.
NOW THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said
Principal shall pay all claimants supplying labor or material to him or a subcontractor in the
prosecution of the Work provided for in said Contract, then, this obligation shall be void;
otherwise to remain in full force and effect;
PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Chapter 2253
of the Texas Government Code as amended and all liabilities on this bond shall be determined in
accordance with the provisions of said Statute to the same extent as if it were copied at length
herein.
Surety, for value received, stipulates and agrees that no change, extension of time, alteration or
addition to the terms of the contract, or to the Work performed thereunder, or the plans,
specifications, or drawings accompanying the same, shall in any way affect its obligation on this
bond,and it does hereby waive notice of any such change, extension of time, alteration or addition
to the terms of the Contract, or to the Work to be performed thereunder.
7\
07/2006 00611 - 1 of 2
CITY OF PEARLAND PAYMENT BOND
IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this instrument
this day of ,20—
Principal:SER Construction Part LLC Surety: art iird F re Insu!a a Company
By: By lip Rosbel E.Rf( : Phjj
President
Title: Title:Attorne -Fact
Address: Address:
P.O.Box 891145 3000 Internet Boulevard,Suite 600
Houston,Texas 77289 Frisco,TX 75034
Telephone: (713)473-7900 =
P Telephone: (800)873-8212 - —
Fax: (713)473-7919 Fax: (866)275-5989
NOTICE: THE ADDRESS OF THE SURETY COMPANY TO WHICH ANY NOTICE
OF CLAIM SHOULD BE SENT MAY BE OBTAINED FROM THE TEXAS
DEPARTMENT OF INSURANCE BY CALLING ITS TOLL-FREE TELEPHONE
NUMBER; 1-800-252-3439.
END OF SECTION
\ ; 07/2006 00611 -2 oft
CITY OF PEARLAND ONE-YEAR MAINTENANCE BOND
Section 00612 Bond No. 46BCSGK9823
ONE-YEAR MAINTENANCE BOND
STATE OF TEXAS §
COUNTY OF BRAZORIA §
KNOW ALL MEN BY THESE PRESENTS: That SER Construction Partners, PLC of the City
of Pasadena , County of Harris , and State of Texas, as principal, and
Hartford Fire Insurance Company authorized under the laws of the State of Texas to act
as surety on bonds for principals, are held and firmly bound unto City of Pearland as Obligee
(Owner), in the penal sum of$ 3,398,483.00 for the payment whereof, the said
Principal and Surety bind themselves, and their heirs, administrators, executors, successors, and
assigns,jointly and severally, by these presents:
WHEREAS, the Principal has entered into a certain written contract with the Owner, effective as
of the day of , 20_, (the "Contract") to commence and complete the
construction of certain improvements described as follows:
Old Alvin Road Water Line
from John Lizer Road to McHard Road
City of Pearland,Texas
COP PN: WA1101
BID NO.:0413-50
which Contract is hereby referred to and made a part hereof as fully and to the same extent as if
copied at length herein.
NOW THEREFORE, THE CONDITION OF THIS OBLIGATION IS SUCH, that if the said
Principal shall faithfully correct all such work not in accordance with the Contract Documents
discovered within the one-year period from the date of substantial completion,then this obligation
shall be void; otherwise to remain in full force and effect;
PROVIDED, HOWEVER, that this bond is executed pursuant to the provisions of Chapter 2253
of the Texas Government Code as amended and all liabilities on this bond shall be determined in
accordance with the provisions of said Statute to the same extent as if it were copied at length
herein.
Surety, for value received, stipulates and agrees that no change, extension of time, alteration or
addition to the terms of the contract, or to the work performed thereunder, or the plans,
specifications, or drawings accompanying the same, shall in any way affect its obligation on this
bond, and it does hereby waive notice of any such change, extension of time, alteration or addition
to the terms of the contract,or to the work to be performed thereunder.
07/2006 00612- 1 oft
CITY OF PEARLAND ONE-YEAR MAINTENANCE BOND
IN WITNESS WHEREOF, the said Principal and Surety have signed and sealed this instrument
this day of ,20_
Princip : R Construction Partners,LLC Surety- art d ire In/ r nce Company
By: By:WINk
Rosbel E.
Title: , resident
Title:Attorne -Fact
Address: Address:
P.O.Box 891145 3000 Internet Boulevard,Suite 600 - -
Houston,Texas 77289 Frisco,TX 75034
Telephone: (713)473-7900 Telephone: (800)873-8212 / \
Fax: (713)473-7919 Fax: (866)275-5989
Cub.'
NOTICE: THE ADDRESS OF THE SURETY COMPANY TO WHICH ANY NOTICE
OF CLAIM SHOULD BE SENT MAY BE OBTAINED FROM THE TEXAS
DEPARTMENT OF INSURANCE BY CALLING ITS TOLL-FREE TELEPHONE
NUMBER; 1-800-252-3439.
END OF SECTION
07/2006 00612-2 of 2
Direct Inquiries/Claims to:
POWER OF ATTORNEY THE HARTFORD
BOND,T-4
ONE HARTFORD PLAZA
HARTFORD,CONNECTICUT 06155
call:888-266-3488 or fax:860-757-5835
r:NOW ALL PERSONS BY THESE PRESENTS THAT: Agency Code: 61-615323
X Hartford Fire Insurance Company,a corporation duly organized under the laws of the State of Connecticut
X Hartford Casualty Insurance Company,a corporation duly organized under the laws of the State of Indiana
Hartford Accident and Indemnity Company, a corporation duly organized under the laws of the State of Connecticut
Hartford Underwriters Insurance Company,a corporation duly organized under the laws of the State of Connecticut
Twin City Fire Insurance Company, a corporation duly organized under the laws of the State of Indiana
Hartford Insurance Company of Illinois,a corporation duly organized under the laws of the State of Illinois
Hartford Insurance Company of the Midwest, a corporation duly organized under the laws of the State of Indiana
Hartford Insurance Company of the Southeast,a corporation duly organized under the laws of the State of Florida
having their home office in Hartford, Connecticut, (hereinafter collectively referred to as the"Companies")do hereby make, constitute and appoint,
up to the amount of unlimited:
Edward Arens, Philip Baker,Michele Bonnin
of
The Woodlands, TX
their true and lawful Attorney(s)-in-Fact, each in their separate capacity if more than one is named above, to sign its name as surety(ies)only as
delineated above by ®, and to execute, seal and acknowledge any and all bonds, undertakings, contracts and other written instruments in the
nature thereof,on behalf of the Companies in their business of guaranteeing the fidelity of persons,guaranteeing the performance of contracts and.
executing or guaranteeing bonds and undertakings required or permitted in any actions or proceedings allowed by law.
In Witness Whereof, and as authorized by a Resolution of the Board of Directors of the Companies on August 1, 2009 the Companies
have caused these presents to be signed by its Vice President and its corporate seals to be hereto affixed,duly attested by its Assistant Secretary.
Further, pursuant to Resolution of the Board of Directors of the Companies,the Companies hereby unambiguously affirm that they are and will be
bound by any mechanically applied signatures applied to this Power of Attorney.
lancer
.s7fr1 ,. },itrs y t wf!! .
,�1 ;�,ta•a!•rti.f a vim _ ^_ 3
,' F'�..�t+Vo !t rOnahtvt r�®IM' l8 Z®F•_ ;- tD 7 9 • ..'
�. �.' irA��19�� ► ;`y oi5inu••• -�z,FriWJ
Wesley W.Cowling,Assistant Secretary M.Ross Fisher,Vice President
STATE OF CONNECTICUT
ss. Hartford
COUNTY OF HARTFORD
On this 12th day of July, 2012, before me personally came M. Ross Fisher, to me known, who being by me duly sworn, did depose and
say:that he resides in the County of Hartford, State of Connecticut;that he is the Vice President of the Companies, the corporations described in
and which executed the above instrument;that he knows the seals of the said corporations;that the seals affixed to the said instrument are such
corporate seals;that they were so affixed by authority of the Boards of Directors of said corporations and that he signed his name thereto by like
authority.
MKT
tl/R_It.L ,A-,j-}t?inA a tf
• iiusuc"fir • Kathleen T.Maynard
Notary Public _ • -_
CERTIFICATE My Commission Expires July 31,2016
I, the undersigned, Vice President of the Companies, DO HEREBY CERTIFY that the above and foregoing is a true and correct copy of
the Power of Attorney executed by said Companies,which is still in full force effective as of
Signed and sealed at the City of Hartford.
0.-rt W ta ..
oswp ��r. x��ltrs_yf tw g iw� ,..�.gp��
O r v `it• r�t4et rl E.ftt�f a �us r -� f"! r!p•-:- ouse•o .-<�:,
1 ..Su. Vu.r.r 401.. : 1 9 7 9 j.•Yt 1 9s.
4.1
� 4 �f-��..•\: �Me�sN� +Ip-�!•.l • V•�•••�t L1�p15 rims•'
•
Gary W.Stumper,Vice President
. , WI'
IJ:IE �`'
JIARTFORD
Inquiries Regarding Claims
Hartford Fire Insurance Company Twin City Insurance Company
Hartford Casualty Insurance Company Hartford Insurance Company of Illinois
Hartford Accident and Indemnity Company Hartford insurance Company of the Midwest
Hartford Underwriters Insurance Company Hartford Insurance Company of the Southeast
Please address inquiries regarding Claims for all surety and fidelity products issued by
The Hartford's underwriting companies to the following:
Phone Number : 888-266-3488
Fax - Claims : 860-757-5835 or 860-547-8265
E-mail : claims@lstepsurety.com
Mailing Address : The Hartford
The Hartford Fidelity&Bonding (BOND)
Hartford Plaza
690 Asylum Avenue
Hartford, CT 06115
CITY OF PEARLAND PARTIAL WAIVER OF LIEN
Section 00615
PARTIAL WAIVER OF LIEN
AND PAYMENT AFFIDAVIT
The undersigned contracted with City of Pearland to furnish Construction of Old Alvin
Road Water Line from John Lizer Road to McHard Road in connection with certain
improvements to real property located in the City of Pearland, TX and owned by the City
of Pearland which improvements are described as follows: Old Alvin Road Water Line
from John Lizer Road to McHard Road. Approximately 13,000 linear feet of new 20-
inch diameter water line and associated service transfers,water line abandonment,
pavement removal and replacement, and storm sewer removal and replacement. .
In consideration of Pay Estimate No. in the amount of$ the
undersigned, on oath, states that all persons and firms who supplied labor and materials to
the undersigned in connection with said Project will be fully paid within 30 days of the
date of this document by the undersigned for such work through
In consideration of the payment herewith made,the undersigned does fully and
finally release and hold harmless the City of Pearland and its surety, if any, through the
above date from any and all claims, liens,or right to claim or lien, arising out of this
Project under any applicable bond, law or statue.
It is understood that this affidavit is submitted to induce payment of the above
sum and for use by the City of Pearland in assuring the Owner and others that all liens
and claims relating to the said Project furnished by the undersigned are paid.
Signature
Printed Name&Title
Company Name
State of
County of
Subscribed and sworn to,before me,this day of , 20
My Commission Expires:
Notary Public
5-12-12
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
Section 00700
GENERAL CONDITIONS OF AGREEMENT
TABLE OF CONTENTS Page
No.
1.0 DEFINITIONS AND INTERPRETATIONS 1
1.01 Owner, Contractor and Engineer
1.02 Contract Documents
1.03 Subcontractor
1.04 Written Notice
1.05 Work
1.06 Extra Work
1.07 Work Day
1.07-1 Rain Day
1.07-2 Impact Day
1.08 Calendar Day
1.09 Substantially Completed
1.10 Interpretation of Words and Phrases
1.11 Referenced Standards
1.12 Contract Time
1.13 Construction Inspector
1.14 Balancing Change Order
2.0 RIGHTS AND RESPONSIBILITIES OF THE OWNER 4
2.01 No Warranty of Design
2.02 Right of Entry
(116.'\ 2.03 Ownership of Plans
10-2012 00700-i
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
2.04 Changes and Alterations
2.05 Damages
3.0 RIGHTS AND RESPONSIBILITIES OF THE ENGINEER 6
3.01 Owner-Engineer Relationship
3.02 Keeping of Plans and Specifications Accessible
3.03 Preliminary Approval
3.04 Inspection by Engineer
3.05 Determination of Questions and Disputes
3.06 Recommendation of Payment
4.0 RIGHTS AND RESPONSIBILITIES OF THE CONTRACTOR 8
4.01 Independent Contractor
4.02 Contractor's Understanding
4.03 Laws and Ordinances
4.04 Assignment and Subletting
4.05 Performance and Payment Bonds [and Maintenance Bond]
4.06 Insurance
4.07 Permits and Fees
4.08 Texas State Sales Tax
4.09 Contractor's Duty and Superintendence
4.10 Character of Workers
4.11 Labor,Equipment,Materials, Construction Plant and Buildings
4.12 Sanitation
4.13 Cleaning and Maintenance
4.14 Performance of Work
(111.1.
4.15 Right of Owner to Accelerate the Work
10-2012 00700-ii
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
4.16 Layout of Work
4.17 Shop Drawings
4.18 Engineer-Contractor Relationship; Observations
4.19 Observation and Testing
4.20 Defects and Their Remedies
4.21 Liability for Proper Performance
4.22 Protection Against Accident To Employees and the Public
4.23 Protection of Adjoining Property
4.24 Protection against Claims of Subcontractors, Laborers,Materialmen,
and Furnishers of Equipment,Machinery and Supplies
4.25 Protection Against Royalties or Patented Invention
4.26 Indemnification
4.27 Losses From Natural Causes
4.28 Guarantee
5.0 PROSECUTION AND PROGRESS 18
5.01 Time and Order of Completion
5.02 Extension of Time
5.03 Hindrances and Delays
5.04 Suspension of Work
5.05 Liquidated Damages for Delay
5.06 Change of Contract Time
5.07 Delays Beyond Owner's and Contractor's Control
6.0 MEASUREMENT AND PAYMENT 21
6.01 Discrepancies and Omissions
(111'\ 6.02 Quantities and Measurements
10-2012 00700-iii
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(°.b 6.03 Estimated Quantities
6.04 Price of Work
6.05 Payments
6.06 Partial Payments
6.07 Use of Completed Portions &Punchlist
6.08 Substantial Completion
6.08-1
6.09 Final Payment
6.10 Correction of Work Before Final Payment
6.11 Correction of Work After Final Payment
6.12 Payments Withheld
6.13 Delayed Payments
Culb'\ 7.0 EXTRA WORK AND CLAIMS 27
7.01 Differing Site Conditions
7.02 Change Orders
7.03 Change Orders
7.04 Request for Work Approval for Work on Non-Work Days
7.05 Minor Changes
7.06 Extra Work
7.07 Time of Filing Claims
8.0 DEFAULT 30
8.01 Default by Contractor
8.02 Supplementation of Contractor Forces
8.03 Cumulative Remedies& Specific Performance
8.04 Cross-Default
10-2012 00700-iv
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
7\: 8.05 Insolvency
8.06 Contingent Assignment
8.07 Waiver of Consequential Damages
8.08 Termination for Convenience
8.09 Default by Owner
9.0 DISPUTE RESOLUTION 35
ATTACHMENT NO. 1: WORKERS' COMPENSATION INSURANCE COVERAGE Al
ATTACHMENT NO. 2: AGREEMENT FOR FINAL PAYMENT AND CONTRACTOR'S
SWORN RELEASE B1
ATTACHMENT NO. 3: OWNER'S INSURANCE REQUIREMENTS OF CONTRACTOR Cl
•
(sulk\
10-2012 00700-v
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Clumh\ Section 00700
GENERAL CONDITIONS OF AGREEMENT
1.0 DEFINITIONS AND INTERPRETATIONS
1.01 OWNER, CONTRACTOR AND ENGINEER. The OWNER, the
CONTRACTOR and the ENGINEER are those persons or organizations identified as such in the
Agreement. The term ENGINEER as used in these General Conditions shall refer to the Engineer
or Architect identified in the Agreement, as applicable, and means a person authorized to act as a
representative of the entity designated by the OWNER to provide professional services required in
connection with the preparation of plans and specifications of this Contract. The term
CONSTRUCTION MANAGER as used in these General Conditions shall refer to the
Construction Manager identified in the Agreement, as applicable, and means a person authorized
to act as representative of the entity designated by the OWNER to provide professional services
required in connection with the performance of the work of this Contract. The Owner's
representative on the project site shall be the CONSTRUCTION MANAGER or ENGINEER as
designated. •
1.02 CONTRACT DOCUMENTS. The Contract Documents shall consist of all of the
documents identified in Article 8 of the Standard Form of Agreement, which documents,
excluding such documents as may be delivered or issued after the Effective Date of the
Agreement, as referenced in Article 8, shall be bound together in a Project Manual for the Work.
C116.\, All references to the "Contract" or the "Agreement" in these General Conditions of Agreement
shall include the Contract Documents.
The Contract Documents are complementary, and what is required by one shall be binding as if
required by all. In the event of any conflict among the Contract Documents, the Contract
Documents shall govern in the following order:
(1) Modifications in writing and signed by both parties,including any Change Orders;
(2) Standard Form of Agreement;
(3) Special Conditions of Agreement;
(4) General Conditions of Agreement, including Attachment No. 1 — Workers'.
Compensation Insurance Coverage, Attachment No. 2 — Agreement for Final
Payment and CONTRACTOR'S Sworn Release, and Attachment No. 3 — Owner's
Insurance Requirements of Contractor;
(5) Addenda, if any;
(6) Plans and Specifications referenced or included in the Project Manual;
(7) Instructions to Bidders;
(8) Bid Proposal; and
10-1012 00700- 1 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
(9) Exhibits: The following Exhibits, if any,attached hereto, are incorporated herein,
and are a part of this Contract:
In the event a conflict or inconsistency remains between or within the Contract Documents, or the
Contract Documents and applicable standards, codes and ordinances, CONTRACTOR shall
provide the greater quantity or better quality, or CONTRACTOR shall comply with the more
stringent requirements, as determined by ENGINEER.
Terms or phrases used in the Contract Documents with a well-known technical or construction
industry meaning shall have such recognized meanings. References to standards, specifications,
manuals or codes of any technical society, organization or association, or to the laws or
regulations of any governmental authority, shall mean the latest in effect on the effective date of
the Contract,unless otherwise stated in the Contract Documents.
1 .03 SUBCONTRACTOR. The term "subcontractor", as employed herein, includes
those entities having a contract with the CONTRACTOR or a subcontractor for performance of
work on the Project. OWNER shall have no responsibility to any subcontractor for performance of
work on the Project contemplated by these Contract Documents, and any such subcontractor shall
look exclusively to CONTRACTOR for any payments due subcontractor.
1.04 WRITTEN NOTICE. Written Notice shall be deemed to have been duly served if
delivered in person or by electronic means through the Pro-Trak to the individual or to a partner of
the partnership or joint venture, or to an officer of the corporation or company for whom it is
,� intended, or if delivered at or sent by Certified Mail, Return Receipt Requested, to the last known
tl business address or registered office of such individual,partnership,joint venture or corporation or
company, or to the address for giving notices listed in the Standard Form of Agreement.
1.05 WORK. Unless otherwise stipulated, the CONTRACTOR shall provide and pay
for all materials, supplies, machinery, equipment, tools, superintendence, labor, services,
insurance, and all water, light, power, fuel, transportation and all other facilities or services of any
nature whatsoever necessary for the execution and completion of the Work described in the
Standard Form of Agreement. Unless- otherwise specified, all materials shall be new, and both
workmanship and materials shall be of good quality. The CONTRACTOR shall, if required by the
ENGINEER as representative of the OWNER, furnish satisfactory evidence as to the kind and
quality of materials. Materials or work described in words which so applied have well-known,
technical or trade meaning shall be held to refer to such recognized standards. All work shall be
done and all materials shall be furnished in strict conformity with the Contract Documents.
1.06 EXTRA WORK. The term "Extra Work", as used in this Contract, shall be
understood to mean and include all work that may be required by the ENGINEER as
representative of the OWNER,to be performed by the CONTRACTOR to accomplish any change,
alteration or addition to the work shown in the plans. Extra work shall be authorized in writing by
the ENGINEER prior to commencement. Extra Work items are paid for on an as needed, as
authorized basis only.
1.07 WORK DAY: As used herein, a "Work Day" is defined as any Monday through
Friday, not a legal holiday, and any Saturday or Sunday specifically approved by the OWNER, in
which the CONTRACTOR can perform six or more hours of work per the current construction
schedule. CONTRACTOR agrees to request specific approval from the Construction Manager or
10-1012 00700-2 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Owner, in advance, to perform work on Saturdays or Sundays and in so doing agrees to pay all
charges and costs for Inspection and or Construction Management services required during the
performance of any such approved work. Refer to paragraph 7.05 for procedure to determine cost
for Construction Management and Inspection Services for work on non-work days.
1.07-1 RAIN DAY: As used herein, is defined as any WORK DAY during which weather
related conditions prevent the CONTRACTOR from performing four (4) or more consecutive
hours of work on critical path items as identified in the current construction schedule.
CONTRACTOR shall record Rain Days on the Pay Application each month for the review and
possible approval by the OWNER. The approved Rain Day is then added to the Contract Time.
(See 1.12 Contract Time below)
1.07-2 IMPACT DAY: As used herein, is a day that is added to the CONTRACT TIME
by the OWNER by Change Order to extend the Contract Time by one full Work Day. (See 1.12
Contract Time below) Impact Days, once approved by the OWNER, shall extend the Contract
Time on a one-to-one basis to replace a Work Day lost to conditions that prevented the
CONTRACTOR from performing four (4) or more consecutive hours of work on critical path
items. Impact Days are added to the Contract Time by Change Order only at the end of the work
and then only if, in the opinion of the OWNER, a time extension is warranted due to delays
beyond the control of the Contractor and required to complete the work within the Contract Time.
1.08 CALENDAR DAY. A "calendar day" is any day of the week, month or year no
days being excepted. Unless otherwise expressly provided, all references to "day(s)" shall mean
calendar day(s).
1 .09 SUBSTANTIALLY COMPLETED: The terms "Substantially Completed", or
"Substantially Complete" or"Substantial Completion" as used in this Contract, shall mean that all
major process components of the facility or work have been made suitable for use or occupancy,
including appropriate documentation from the equipment suppliers that all of the individual
components have been installed in accordance with the specifications and manufacturer's
recommendations,the installations have been approved by the ENGINEER and the items have met
the start-up and testing requirements of the contract documents or is deemed to be in a condition to
serve its intended purpose or requires only minor miscellaneous work and adjustment to achieve
Final Completion and Acceptance as determined by the ENGINEER. Upon compliance with the
above referenced criteria,ENGINEER shall issue a Certificate of Substantial Completion.
PARTIAL SUBSTANTIAL COMPLETION: designation will be given on components of
the Work that must be placed into service prior to the completion of the entire Work. The
contractor's One Year Warranty period for these items shall begin on the date of Partial
Substantial Completion as designated by the ENGINEER. The ENGINEER shall determine and
make all such designations.
1.10 INTERPRETATION OF WORDS AND PHRASES. Whenever the words
"directed", "permitted", "designated", "required", "ordered", "considered necessary", "prescribed"
or words of like import are used, it shall be understood that the direction, requirement,permission,
order, opinion designation or prescription of the ENGINEER as the OWNER's representative is
intended. Similarly, the words "approved", "acceptable", "satisfactory" or words of like import
(001", shall mean that no exception is taken by ENGINEER, but does not relieve CONTRACTOR of
responsibility for compliance with the Contract Documents.
10-1012 00700-3 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
7\1
Whenever in the Specifications or Plans of the Contract Documents, the terms of description of
various qualities relative to finish, workmanship or other qualities of similar kind which cannot,
from their nature, be specifically and clearly described and specified,but are necessarily described
in general terms, the fulfillment of which must depend on individual judgment, then, in all such
cases, any question of the fulfillment of said Specifications shall be decided by the ENGINEER as
the OWNER's representative, and said work shall be done in accordance with his interpretations
of the meaning of the words,terms or clauses defining the character of the work.
1.11 REFERENCED STANDARDS. No provision of any referenced standard
specification, or manual shall be effective to change the duties and responsibilities of the Owner,
Engineer, Contractor, or their consultants, employees, or representatives from those set forth in the
Contract Documents, nor shall it be effective to assign to the Engineer or its consultants,
employees, or representatives any duty or authority to supervise or direct the furnishing or
performance of the Work or any duty or authority to undertake responsibilities contrary to
provisions of the Contract Documents.
1.12 CONTRACT TIME The term Contract Time as used herein, refers to the number
of Calendar days provided to complete the work or the date, stated in the Agreement: (i) to achieve
Substantial Completion, and (ii) to complete the Work so that it is ready for fmal payment as
evidenced by ENGINEER's written recommendation of fmal payment in accordance with
Paragraph 6.09 and as modified as a result of any authorized Extensions.
C116*\ The established Contract Time includes 40 Rain Days per year, based on the average
number of rain days per year for the period of June 1898 to December 1996 as recorded by the
Alvin Weather Center Record. The Contract Time shall only be extended by (a) the addition of
Rain Days equal to the number of actual Rain Days in excess of 40 days per year and (b) the
number of Impact Days granted for delays, in the opinion of the Owner, beyond the control of the
Contractor. The extension of the Contract Time shall be the CONTRACTOR's sole and exclusive
remedy for delays.
1.13 CONSTRUCTION INSPECTOR The term "Construction Inspector" here in
includes those professionals engaged by the OWNER to ensure CONTRACT work's compliance
with the specifications and any applicable statutory requirements.
1.14 BALANCING CHANGE ORDER is a change order executed during the close-out
process that may add/remove pay items, or adjust quantities of existing items or remove unused
pay items or quantities Balancing Change Orders are used to reconcile the unit cost of the work
performed or installed by the Contractor.
2.0 RIGHTS AND RESPONSIBILITIES OF THE OWNER
2.01 NO WARRANTY OF DESIGN. It is understood that the OWNER MAKES NO
WARRANTY OF THE ADEQUACY, ACCURACY OR SUFFICIENCY OF THE PLANS AND
SPECIFICATIONS OR ANY OTHER DESIGN DOCUMENTS, AND OWNER HEREBY
EXPRESSLY DISCLAIMS ANY SUCH WARRANTY, EXPRESSED OR IMPLIED. Prior to
commencing each portion of the Work, CONTRACTOR shall carefully study and compare the
Ch"\. relevant Contract Documents, shall observe conditions at the site affecting the Work, and shall
take field measurements of existing conditions related to the Work. Any errors, omissions or
10-1012 00700-4 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
inconsistencies in the Contract Documents noted by the CONTRACTOR, and/or any variance
between the Contract Documents and applicable codes,standards or ordinances, shall be promptly
reported by CONTRACTOR to ENGINEER in writing as a Request for Information. Work
performed prior to a Request for Information shall be at the Contractor's risk. If CONTRACTOR
fails to perform its obligations under this paragraph, CONTRACTOR shall pay such costs and
damages to OWNER as would have been avoided if CONTRACTOR had reported any errors,
omissions, inconsistencies or variances in the Contract Documents noted by CONTRACTOR or
which should have been noted by a careful study of the Contract Documents. CONTRACTOR
shall comply with the Contract Documents, all approved modifications thereof and additions and
alterations thereto approved in writing by the OWNER. The burden of proof of such compliance
shall be upon the CONTRACTOR to show that he has complied with the requirements of the
Contract Documents and approved modifications thereof and all approved additions and
alterations,thereto, as the same shall have been interpreted by the ENGINEER.
2.02 RIGHT OF ENTRY. The OWNER reserves the right to enter the property or
location on which the work herein contracted for is to be performed, constructed or installed, for
itself or such agent or agents as it may select, for the purpose of inspecting the work, or for the
purpose of performing, constructing or installing such collateral work as the OWNER may desire.
The OWNER shall have the right to make inspections at all reasonable times, and the
CONTRACTOR hereby waives any claims for extension of time and/or compensation for any loss
or damage if his work shall be delayed by reason of such inspection, performance, construction or
installation of collateral work.
2.03 OWNERSHIP OF PLANS. All plans, specifications and copies thereof furnished
by the OWNER shall not be reused on other work and, with the exception of the sets forming the
part of the signed Contract Documents, are to be returned to the OWNER on request at the
completion of the Work. All plans and models are the property of the OWNER.
2.04 CHANGES AND ALTERATIONS. The CONTRACTOR further agrees that the
Owner may make such changes and alterations, additions and deletions as the OWNER may see
fit, in the Work, including but not limited to changes in line, grade, form, dimensions, plans or
specifications for the Work herein contemplated, or any part thereof, either before or after the
beginning of construction, without affecting the validity of this Contract and the corresponding
Performance and Payment Bonds.
If such changes or alterations or deletions diminish the quantity or the value of the Work to be
done, they shall not constitute the basis for a claim for compensation or damages, including lost or
anticipated profits on the Work that may be affected. If the amount of Work is increased and the
work can fairly be classified under the specifications, such increase shall be paid for according to
the quantity actually done and at the unit price, if any, established for such work under this
Contract, otherwise, such additional work shall be paid for as provided under Article 7 hereof for
Extra Work. In case the OWNER shall make such changes or alterations as shall make useless
any Work already done or material already furnished or used in said Work, then the OWNER shall
compensate the CONTRACTOR for any material or labor so used and for any actual loss
occasioned by such change due to actual expenses incurred in preparation for the Work as
originally planned.
2.05 DAMAGES. In the event the OWNER is damaged in the course of the work by
the act, negligence, omission, mistake or default of the CONTRACTOR, or should the
10-1012 00700-5 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
CONTRACTOR unreasonably delay the progress of the work being done by others on the job so
as to cause loss for which the OWNER becomes liable, then the CONTRACTOR shall reimburse
the OWNER for such loss.
3.0 RIGHTS AND RESPONSIBILITIES OF THE ENGINEER
3.01 OWNER-ENGINEER RELATIONSHIP. The ENGINEER shall serve as the
OWNER'S representative during construction. The duties, responsibilities and limitations on the
authority of the ENGINEER as the OWNER's representative during construction are set forth in
the Contract Documents; and the ENGINEER shall not have authority to extend the OWNER's
liability or to bind the OWNER for any additional liability of any nature whatsoever without the
written consent of the OWNER. Any communications by the OWNER to the CONTRACTOR
regarding the Work shall be issued through the ENGINEER.
It is the intent of this Agreement that there shall be no delay in the execution of the Work;
therefore, written decisions or directions rendered by the ENGINEER as the OWNER's
representative shall be promptly carried out, and any claim arising therefrom shall be resolved as
provided in Article 7. Unless otherwise specified, it is mutually agreed between the parties to this
Agreement that the OWNER'S representative shall have the authority to issue written stop work
orders whenever such stoppage may be necessary to insure the performance of the Work in
accordance with the Contract Documents.
3.02 KEEPING OF PLANS AND SPECIFICATIONS ACCESSIBLE. The
ENGINEER shall furnish the CONTRACTOR with four(4) copies of all Plans and Specifications
without expense to the CONTRACTOR, and the CONTRACTOR shall keep one full size copy of
the same constantly accessible on the job site, with the latest revisions noted thereon. The
CONTRACTOR shall be responsible for preserving the Plans and Specifications, timely and
accurately updated, for reference and review by the OWNER or the ENGINEER and submittal of
redlines during closeout.
3.03 PRELIMINARY APPROVAL. The ENGINEER shall not have the power to
waive the obligations imposed under this Contract for the furnishing by the CONTRACTOR of
new material of good quality, and for good and workmanlike performance of the Work as herein
described, and in full accordance with the Contract Documents, without alteration, deletion or
change. No failure or omission of the OWNER'S representative to discover, object to or condemn
any non-conforming or defective work or material, or to stop work, shall release the
CONTRACTOR from the obligation to fully and properly perform the Contract, including without
limitation, the obligation to at once remove and properly replace any defective work or material at
any time prior to final acceptance, upon discovery of such non-conforming or defective work or
material.
Any questioned Work may be ordered taken up or removed for inspection by the ENGINEER
prior to final acceptance, and if found not to be in accordance with the Contract Documents, all
expense of removing, inspection and repair or replacement shall be borne by the CONTRACTOR;
otherwise the expense thus incurred shall be allowed as Extra Work and shall be paid for by the
OWNER, provided that where inspection or approval is specifically required by the Specifications
prior to performance of certain work, should the CONTRACTOR proceed with such work without
risik requesting prior inspection or approval, he shall bear all expense of taking up, removing and
replacing this work if so directed by the ENGINEER.
10-1012 00700-6 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
3.04 INSPECTION BY ENGINEER. The ENGINEER will make periodic visits to the
site to observe the progress and quality of the executed Work and to determine if such Work
generally meets the essential performance and design features and the technical, functional /or
engineering requirements of the Contract Documents, and is in all other respects being performed
in compliance with the Contract Documents. However, the ENGINEER shall not be responsible
for making any detailed, exhaustive, comprehensive or continuous on-site inspections to check the
quality and/or quantity of the work, nor shall the ENGINEER be in any way responsible, directly
or indirectly, for the construction means, methods, techniques, sequences, quality, procedures,
programs, safety precautions or lack of same incident to the Work being performed or any part
thereof. The ENGINEER shall use reasonable care to prevent deviation from the intent and
substance of the Contract Documents by the CONTRACTOR in the performance of the Work and
any part thereof and, on the basis of such on-site observations, will keep the OWNER informed of
the progress of the work and will endeavor to guard the OWNER against defects and deficiencies
in the Work of the CONTRACTOR. Notwithstanding any other provision of this Agreement or
any other Contract Document, the ENGINEER shall not be in any way responsible or liable for
any acts, errors, omissions or negligence of the CONTRACTOR, any subcontractors, agents,
servants or employees or any other person, firm or corporation performing or attempting to
perform any of the Work.
3.05 DETERMINATION OF QUESTIONS AND DISPUTES. In order to prevent
delays and disputes and to discourage litigation, it is agreed that the ENGINEER shall, in all cases,
determine the quantities and qualities of the several kinds of Work, which are to be paid for under
this Contract. The ENGINEER shall address all questions in relation to said Work and the
construction thereof, as well as all claims, disputes and other matters in question between the
CONTRACTOR and the OWNER relating to the execution or progress of the Work or the
interpretation of the Contract Documents. In the event the ENGINEER shall become aware of or
shall receive information that there is a dispute or a possible dispute as to the reasonable
interpretation of the terms and conditions of the Contract Documents, or any other dispute or
question, the ENGINEER shall, within a reasonable time, provide a written interpretation of the
Contract Documents or a written decision on all questions arising relative to the execution of the
Work, copies of which shall be delivered to all parties to the Contract. If the CONTRACTOR or
OWNER desires to take exception to any directions, order, interpretation or instructions of the
ENGINEER, CONTRACTOR or OWNER shall present any such claim to the ENGINEER in
accordance with the provisions of Section 7.04.
3.06 RECOMMENDATION OF PAYMENT. The ENGINEER shall review the
CONTRACTOR's application for payment and supporting documents, shall determine the amount
owed to the CONTRACTOR and shall provide written recommendation to the OWNER for
payment to the CONTRACTOR in such amount. Such recommendation of payment to
CONTRACTOR shall constitute a representation to the OWNER of the ENGINEER's judgment
that the work has progressed to the point indicated, to the best of his knowledge, information and
belief; however, such recommendation of an application for payment to CONTRACTOR shall not
be deemed an acceptance of any defective or non-conforming Work. Any recommendation of
payment by the ENGINEER shall be subject to OWNER's rights to withhold payment under
Section 6.11 and as otherwise provided in the Contract.
10-1012 00700-7 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
4.0 RIGHTS AND RESPONSIBILITIES OF THE CONTRACTOR
4.01 INDEPENDENT CONTRACTOR. CONTRACTOR is, and shall remain, an
independent contractor, solely responsible for the manner and method of completing the Work
under this Contract, with full and exclusive power and authority to direct, supervise and control
his own employees and to determine the means, method and manner of performing such Work, so
long as such methods comply with the requirements of the Contract Documents, and do not
adversely affect the completed improvements or any other property abutting or adjoining the Work
area, the OWNER and ENGINEER being interested only in the result obtained and conformity of
such completed improvements to the Plans, Specifications and Contract Documents. The fact that
the OWNER or ENGINEER as the Owner's representative shall have the right to observe
CONTRACTOR's work during his performance and to carry out the other prerogatives which are
expressly reserved to and vested in the OWNER and the ENGINEER hereunder, is not intended to
and shall not at any time change or affect the status of the CONTRACTOR as an independent
contractor with respect to either the OWNER or the ENGINEER as the OWNER's representative
or to the CONTRACTOR's own employees or to any other person, firm or corporation.
4.02 CONTRACTOR'S UNDERSTANDING. It is understood and agreed that the
CONTRACTOR has, by careful examination, satisfied himself as to the nature and location of the
Work, the conformation of the ground, the character, quality and quantity of the materials to be
encountered, the character of equipment and facilities needed preliminary to and during the
prosecution of the Work, the general and local conditions, including but not limited to weather,
access, lay down and storage areas, and all other matters which in any way affect the Work under
this Contract. It is further understood that the CONTRACTOR has satisfied himself as to the
(vilmaN' terms, meaning, intent and requirements of all of the Contract Documents, and applicable laws,
codes, regulations and ordinances. CONTRACTOR hereby warrants and represents that it has
taken into consideration all of the foregoing factors, and CONTRACTOR shall perform the Work
for the Contract Price and within the Contract Time. No verbal agreement or conversation with
any officer, agent or employee of the OWNER or the ENGINEER, either before or after the
execution of this Contract, shall affect or modify any of the terms or obligations herein contained.
4.03 LAWS AND ORDINANCES. The CONTRACTOR shall at all times observe and
comply with all federal, state or local laws, codes, ordinances, permits and regulations, regardless
of whether the same are adopted before or after the execution of this Contract, which in any
manner affect the Contract or the work, and shall indemnify, save and hold harmless the OWNER
and the ENGINEER against any claim arising out of the violation of any such laws, ordinances
and regulations, whether by the CONTRACTOR or his agents, employees, subcontractors or
vendors. If the CONTRACTOR observes that the Plans and Specifications are at variance with
federal or state laws or codes or the ordinances or regulations of the City, he shall promptly notify
the ENGINEER in writing, and any necessary changes shall be made as provided in the Contract
for changes in the work. If the CONTRACTOR performs any work knowing it to be contrary to
such laws, codes, ordinances, rules or regulations, or if CONTRACTOR reasonably should have
known of any such violation, and without such notice to the ENGINEER, CONTRACTOR shall
bear all costs arising therefrom.
The OWNER is a Political Subdivision of the State of Texas, and the law from which it derives its
powers, insofar as the same regulates the objects for which, or the manner in which, or the
conditions under which the OWNER may enter into contracts, shall be controlling and shall be
considered as part of this Contract to the same effect as though embodied herein. Neither the act
10-1012 00700-8 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
of OWNER entering into this Contract, nor OWNER's performance hereunder, shall constitute a
waiver of any immunity from suit enjoyed by OWNER under applicable law, all such rights and
defenses being hereby expressly reserved, notwithstanding any term or provision herein to the
contrary. The Code of Ordinances and other applicable regulations of the OWNER shall be
deemed to be embodied in this Contract.
The prevailing wage rates applicable to this Project shall be either Document 00811 —Wage
Scale for Engineering Construction, or Document 00813—Wage Scale for Building
Construction, or both, as set out in the Project Manual.
4.04 ASSIGNMENT AND SUBLETTING. The CONTRACTOR further agrees that he
will retain personal control and will give his personal attention to the fulfillment of this Contract
and that he will not assign, by power of attorney or otherwise, or sublet said Contract, or any
rights, duties or obligations arising thereunder, in whole or in part, without the prior written
consent of the OWNER, and that no part or feature of the Work will be sublet to anyone
objectionable to the ENGINEER or the OWNER. In addition, the OWNER reserves the right to
disapprove the subletting of this Contract or any portion hereof on any basis whatsoever. The
CONTRACTOR further agrees that the subletting of any portion or feature of the Work or
materials required in the performance of this Contract shall not relieve the CONTRACTOR from
his obligations to the OWNER,as provided for by this Agreement.
4.05 PERFORMANCE,PAYMENT AND MAINTENANCE BONDS. In the event the
Contract Price shall be in excess of $25,000.00, the CONTRACTOR shall execute separate
Performance,Payment and Maintenance Bonds, each in the sum of one hundred percent(100%) of
the Contract Price, and each in accordance with the provisions of Chapter 2253 of the Texas
Government Code. If the Contract Price does not exceed $25,000.00, the statutory bonds will not
be required. All required Bonds shall be payable to OWNER and on forms approved by the
OWNER, and shall be executed by a corporate surety in accordance with Article 7.19-1 of the
Texas Insurance Code. It is agreed that the Contract shall not be in effect until such original
Performance, Payment and Maintenance Bonds are delivered to and approved by the OWNER.
The cost of the premium for the Performance, Payment and Maintenance Bonds, should
Maintenance Bonds be required, shall be included in the CONTRACTOR's Bid Proposal. All
bonds shall be issued by Texas Department of Insurance approved surety companies.
4.06 INSURANCE. The CONTRACTOR, at his own expense, shall procure, maintain
and keep in force throughout the duration of the Work, and throughout the Guarantee Period,
insurance as specified in Attachment No. 1 hereto with regard to Workers' Compensation
Insurance, and as specified in Attachment No. 3 hereto with regard to all other Insurance. Such
insurance shall be carried with an insurance company licensed to transact business in the State of
Texas and shall cover all operations in connection with this Contract, whether performed by the
CONTRACTOR or a subcontractor, or others for whom CONTRACTOR is responsible.
4.07 PERMITS AND FEES. Unless otherwise provided in the Contract Documents,the
Contractor shall secure and pay for all permits, licenses, and inspections necessary for proper
execution and completion of the Work, and which are legally required at the time bids are
received. Permits required by the City of Pearland will be issued as a NO FEE permit.
4.08 TEXAS STATE SALES TAX. Materials incorporated into this project are exempt
from State Sales according to provisions of the Texas Tax Code, Chapter 151, Subsection H.
10-1012 00700-9 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(.1"`.
The Contractor must obtain a limited sales, excise and use tax permit or exemption certificate
which shall enable him to buy the materials to be incorporated into the Work without paying tax at
due time of purchase.
4.09 CONTRACTOR'S DUTY AND SUPERINTENDENCE. The CONTRACTOR
shall give adequate attention to the faithful prosecution and completion of this Contract and shall
keep on the work, during its progress, a competent superintendent and any necessary assistants, all
satisfactory to the ENGINEER as the OWNER'S representative. The superintendent shall
represent the CONTRACTOR in his absence and shall act as the agent of the CONTRACTOR,
and all directions given to him shall be binding as if given to the CONTRACTOR. Adequate
supervision by competent and reasonable representatives of the CONTRACTOR is essential to the
proper performance of the Work, and lack of such supervision shall be an act of default, and
grounds for suspending operations of the CONTRACTOR. The Superintendent cannot be
removed from the project without the consent of the Owner; the Superintendent must speak and
understand the English language; the Superintendent must be on site when any work on the project
is being done, even when a subcontractor is performing the work.
The Work, from its commencement to completion, shall be under the exclusive charge and control
of the CONTRACTOR, and all risk in connection therewith shall be borne by the
CONTRACTOR.
Neither the OWNER nor the ENGINEER as the OWNER's representative will be responsible for
the acts or omissions of the CONTRACTOR, its subcontractors or any of its agents or employees,
or any other persons performing any of the Work.
4.10 CHARACTER OF WORKERS. The CONTRACTOR agrees to employ only orderly and
competent workers, skillful in the performance of the type of work required under this Contract, to
do the Work, and agrees that whenever the ENGINEER shall inform him in writing that any
worker or workers on the Work are, in his opinion, incompetent,unfaithful or disorderly, or in the
ENGINEER's opinion, are not using their best efforts for the progress of the Work, such worker
or workers shall be discharged from the Work and shall not again be employed on the Work
without the ENGINEER's written consent. OWNER reserves the right to bar any person,
subcontractor, or supplier found to be incompetent, unfaithful, disorderly, or not using their best
efforts to progress work or considered to be a threat to the health, safety and welfare to the project
or workforce.
4.11 LABOR, EQUIPMENT, MATERIALS, CONSTRUCTION PLANT, AND
BUILDINGS. The CONTRACTOR shall provide all labor, services, tools, equipment, machinery,
supplies, facilities, utilities and materials necessary in the prosecution and completion of this
Contract where it is not otherwise specifically provided that the OWNER shall furnish same; and
further, the CONTRACTOR shall be responsible for the care, preservation, conservation and
protection of all materials, supplies,machinery, equipment, tools, apparatus, accessories, facilities,
all means of construction and any and all parts of the Work, whether the CONTRACTOR has
been paid, partially paid or not paid for such Work, until the entire Work is completed and
accepted.
The building or placement of structures for housing workers or offices, or the erection of tents or
other forms of protection, will be permitted only with the ENGINEER's written permission, and at
10-1012 00700- 10 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
such places as the ENGINEER shall direct, and the sanitary conditions of the grounds in or about
such structures shall at all times be maintained in a manner satisfactory to the ENGINEER. Any
structures of any nature constructed, placed or erected by the CONTRACTOR for the purposes
herein set out, shall be the sole responsibility of the CONTRACTOR as to the proper erection,
placement or construction thereof; and the CONTRACTOR agrees to indemnify and hold the
ENGINEER or OWNER harmless from any claims of any nature whatsoever brought against
either of them for damages allegedly sustained by anyone by reason of the erection, placement,
construction or maintenance of CONTRACTOR's buildings or structures.
4.12 SANITATION. Necessary sanitary conveniences for the use of laborers and others
on the Work site, properly secluded from public observation, shall be constructed and maintained
by the CONTRACTOR in such manner and at such points as shall be approved by the
ENGINEER, and their use shall be strictly enforced. Any structures of any nature constructed or
erected by the CONTRACTOR for the purposes herein set out, shall be the sole responsibility of
the CONTRACTOR as to the proper erection or construction thereof, and the CONTRACTOR
agrees to indemnify and hold the ENGINEER and OWNER harmless from any claims of any
nature whatsoever brought against either of them for damages allegedly sustained by anyone by
reason of the erection, construction or maintenance of CONTRACTOR's buildings.
4.13 CLEANING AND MAINTENANCE. The CONTRACTOR shall at all times keep
and maintain the premises free from accumulation of debris, trash and waste. The
CONTRACTOR shall remove waste, debris and trash at the end of each work day.
CONTRACTOR shall remove all such debris, trash and waste, tools, scaffolding and surplus
materials, and shall leave the Work broom-clean or its equivalent, upon completion of the Work.
The Work shall be left in good order and condition. In case of dispute, the OWNER may remove
the debris, trash,waste and surplus materials, and charge the cost to the CONTRACTOR.
4.14 PERFORMANCE OF WORK. It is further agreed that it is the intent of this
Contract that all Work must be done and all material must be furnished in accordance with the
generally accepted practice for such materials furnished or work completed, unless otherwise
provided in the Contract Documents.
4.15 RIGHT OF OWNER TO ACCELERATE THE WORK. If at any time the
methods or equipment used by the CONTRACTOR, or the work force supplied are found to be
inadequate to achieve the progress required to Substantially Complete the Work within the
Contract Time, the OWNER or the ENGINEER as the OWNER's representative, may order the
CONTRACTOR in writing to supplement its forces and/or equipment, or work shifts or overtime,
or otherwise improve its efficiency and rate of progress to achieve Substantial Completion of the
Work within the Contract Time, and the CONTRACTOR shall comply with such order, at its own
cost and expense.
4.16 LAYOUT OF WORK. Except as specifically provided herein, the
CONTRACTOR shall be responsible for laying out work by means of construction surveying and
shall accomplish this work in a manner acceptable to the ENGINEER and in conformance with the
Contract Documents.
4.17 SHOP DRAWINGS. The CONTRACTOR shall submit to the ENGINEER, with
such promptness as to cause no delay in his own Work or in that of any other contractor, six (6)
checked copies, unless otherwise specified, of all shop and/or setting drawings and schedules
10-1012 00700- 11 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(#"*\, required for the work of the various trades. Contractor will check and approve shop drawings for
compliance with requirements of Contract Documents and will so certify by stamp on each
drawing prior to submittal to ENGINEER. Any drawings submitted without Contractor's stamp of
approval will not be considered and will be returned to him for proper submission. The
ENGINEER shall pass upon them with reasonable promptness, indicating desired corrections.
The CONTRACTOR shall make any corrections required by the ENGINEER, file with him two
(2) corrected copies and furnish such other copies as may be needed. The ENGINEER's approval
of such drawings or schedules shall not relieve the CONTRACTOR from responsibility for
deviations from the Contract Documents, unless he has, in writing, called the ENGINEER's
attention to such deviations at the time of the submission, and the ENGINEER has acknowledged
and accepted such deviations in writing, nor shall it relieve him from responsibility for errors of
any sort in shop drawings or schedules. It shall be the CONTRACTOR's responsibility to fully
and completely review all shop drawings to ascertain their effect on his ability to perform the
required Contract Work in accordance with the Contract Documents, and within the Contract
Time.
Such review by the ENGINEER shall be for the sole purpose of determining the apparent
sufficiency of said drawings or schedules to result in finished improvements in conformity with
the Contract Documents, and shall not relieve the CONTRACTOR of his duty as an independent
contractor as previously set forth, it being expressly understood and agreed that the ENGINEER
does not assume any duty to pass upon the propriety or adequacy of such drawings or schedules,
or any means or methods reflected thereby, in relation to the safety of either person or property
during CONTRACTOR's performance hereunder, and any action taken by the ENGINEER shall
not relieve the CONTRACTOR of his responsibility and liability to comply with the Contract
Documents.
OWNER, CONSTRUCTION MANAGER, ENGINEER, and CONTRACTOR shall make all
submittals, review comments, notes, corrections, schedules and updates, testing results, payment
applications, instructions and other communications by means of the OWNER'S Pro-Trak. The
OWNER,ENGINEER and CONTRACTOR shall each retain such hard copies form this system as
are required for their specific record keeping requirements. No documents shall be removed from
this system or destroyed except those being replaced by the systems protocols as a latest version
document.
All requirements for written communications, submittals, comments, instructions or other
documents processed by means of this system shall have the same legal or time sensitive status as
if they had been hand delivered in hard copy to their intended addressee.
4.18 ENGINEER-CONTRACTOR RELATIONSHIP; OBSERVATIONS. It is agreed
by the CONTRACTOR that the ENGINEER, as the OWNER's representative, shall be and is
hereby authorized to appoint such subordinate engineers, representatives or observers as the said
ENGINEER may from time to time deem proper to observe the materials furnished and the Work
done under this Agreement. The CONTRACTOR shall furnish all reasonable aid and assistance
required by the subordinate engineers, representatives or observers for the proper observation and
examination of the work. The CONTRACTOR shall regard and obey the directions and
instructions of any subordinate engineers, representatives or observers so appointed, when such
directions and instructions are consistent with the obligations of this Agreement and the Contract
Documents, provided, however, should the CONTRACTOR object to any orders by any
10-1012 00700- 12 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
subordinate engineer, representative or observer, the CONTRACTOR may, within three (3) days,
make written appeal to the ENGINEER for his decision.
4.19 OBSERVATION AND TESTING. The OWNER or the ENGINEER as the
OWNER's representative shall have the right at all reasonable times to observe, inspect and test
the Work. The CONTRACTOR shall make all necessary arrangements and provide proper
facilities and access for such observation, inspection and testing at any location wherever Work is
in preparation or progress. The CONTRACTOR shall ascertain the scope of any observation,
inspection or testing which may be contemplated by the OWNER or the ENGINEER and shall
give ample notice as to the time each part of the Work will be ready for such observation,
inspection or testing. The OWNER or the ENGINEER may reject any Work found to be defective
or not in accordance with the Contract Documents, regardless of the stage of its completion or the
time or place of discovery of such deficiencies, and regardless of whether the ENGINEER has
previously accepted the Work through oversight or otherwise. If any Work is covered without
approval or consent of the OWNER, it must, if requested by the OWNER or the ENGINEER, be
uncovered for examination, at the sole expense of the CONTRACTOR. In the event that any part
of the Work is being fabricated or manufactured at a location where it is not convenient for the
OWNER or the ENGINEER to make observations of such Work or require testing of said Work,
then in such event, the OWNER or the ENGINEER may require the CONTRACTOR to furnish
the OWNER or the ENGINEER with certificates of inspection, testing or approval made by
independent persons competent to perform such tasks at the location where that part of the work is
being manufactured or fabricated. All such tests will be in accordance with the methods prescribed
by the American Society for Testing and Materials or such other applicable organization as may
be required by law or the Contract Documents.
If any Work, which is required to be inspected, tested or approved, is covered up without written
approval or consent of the OWNER or the ENGINEER, it must, if requested by the OWNER or
the ENGINEER, be uncovered for observation and testing, at the sole expense of the
CONTRACTOR. The cost of all such inspections, tests and approvals shall be borne by the
CONTRACTOR unless otherwise provided herein. Any Work which fails to meet the
requirements of such tests, inspections or approval, and any Work which meets the requirements
of any such tests or approval but does not meet the requirements of the Contract Documents shall
be considered defective. Such defective Work and any other work affected thereby shall be
corrected at the CONTRACTOR'S expense.
Neither observations by the OWNER or by the ENGINEER, nor inspections, certifications, tests
or approvals made by the OWNER, the ENGINEER or other persons authorized under this
Agreement to make such inspections, tests or approvals, shall relieve the CONTRACTOR from
his obligation to perform the Work in accordance with the requirements of the Contract
Documents.
4.20 DEFECTS AND THEIR REMEDIES. It is further agreed that if the Work or any
part thereof or any material brought on the site of the Work for use in the Work or selected for the
same, shall be deemed by the ENGINEER as unsuitable or not in conformity with the Contract
Documents, the CONTRACTOR shall, after receipt of written notice thereof from the
ENGINEER, forthwith remove such material and rebuild or otherwise remedy such Work so that
it shall be in full accordance with this Contract, It is further agreed that any such remedial action
contemplated herein shall be at CONTRACTOR's expense.
10-1012 00700- 13 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
(00`N.
4.21 LIABILITY FOR PROPER PERFORMANCE. Engineering construction
drawings and specifications, as well as any additional instructions and information concerning the
Work to be performed, passing from or through the ENGINEER, shall not be interpreted as
requiring or allowing the CONTRACTOR to deviate from the Contract Documents, the intent of
such drawings, specifications and any other such instructions being to define with particularity the
agreement of the parties as to Work the CONTRACTOR is to perform. CONTRACTOR shall be
fully and completely liable and contractually bound, at his own expense, for design, construction,
installation and use or non-use of all items and methods incident to the performance of the
Contract, including, without limitation, the adequacy of all temporary supports, shoring, bracing,
scaffolding, machinery or equipment, safety precautions or devices, similar items or devices used
by him during construction, and work performed either directly or incident to construction, and for
all loss, damage or injury incident thereto, either to person or property, whether such damage be
suffered by the ENGINEER, the OWNER or any other person not a party to this Contract.
Any review of Work in progress or any visit or observation during construction, or any
clarification of Contract Documents by the ENGINEER or OWNER, or any agent, employee or
representative of either of them, whether through personal observation on the Project site or by
means of approval of shop drawings for construction or construction processes, or by other means
or methods, is agreed by the CONTRACTOR to be for the purpose of observing the extent and
nature of Work completed or being performed, as measured against the Contract Documents, or
for the purpose of enabling the CONTRACTOR to more fully understand the Contract Documents
so that the completed construction Work will conform thereto, and shall in no way relieve the
CONTRACTOR from full and complete responsibility for proper performance of his Work on the
7b.\ Project, including, without limitation, the propriety of means and methods of the CONTRACTOR
in performing said Contract, and the adequacy of any designs, plans or other facilities for
accomplishing such performance. Any action by the ENGINEER or the OWNER in visiting or
observing during construction, or any clarification of Contract Documents shall not constitute a
waiver of CONTRACTOR'S liability for damages as herein set out. Deviation by the
CONTRACTOR from Contract Documents, whether called to the CONTRACTOR's attention or
not, shall in no way relieve CONTRACTOR from his responsibility to complete all work in
accordance with said Contract Documents, and further shall not relieve CONTRACTOR of his
liability for loss, damage or injury as herein set out.
4.22 PROTECTION AGAINST ACCIDENT TO EMPLOYEES AND THE PUBLIC.
The CONTRACTOR shall be solely responsible for the safety of himself, his employees and
persons entering the project site, as well as for the protection of the improvements being erected
and the property of himself or any other person, as a result of his operations hereunder. The
CONTRACTOR shall take out and procure a policy or policies of Workers' Compensation
Insurance with an insurance company licensed to transact business in the State of Texas, which
policy shall comply with the Workers' Compensation laws of the State of Texas. The
CONTRACTOR shall at all times exercise reasonable precautions for the safety of employees and
others on or near the Work and shall comply with all applicable provisions of federal, state and
municipal laws and building and construction codes. All machinery and equipment and other
physical hazards shall be guarded, as a minimum, in accordance with the "Manual of Accident
Prevention in Construction" of the Associated General Contractors of America, except where
incompatible with federal, state or municipal laws or regulations. The CONTRACTOR shall
provide all necessary machinery guards, safe walkways, ladders, bridges, gangplanks, barricades,
fences, traffic control,warning signs and other safety devices.
10-1012 00700- 14 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
No alcoholic beverages, non-prescription drugs, or unsafe practices shall be allowed on the Work
site. CONTRACTOR shall dismiss anyone participating in any of the above from the Work site
for the duration of the Project. Only prescription drug uses with a doctor's authorization to
perform construction activities shall be allowed on the Work site. Violation of this provision is a
default under the Contract. The use, possession, sale, transfer, purchase or being under the
influence of alcohol, drugs or any other illegal or unlawful substance by CONTRACTOR or
CONTRACTOR's employees, or CONTRACTOR's subcontractors and employees at any time at
the Work site or while on company business is prohibited. CONTRACTOR shall institute and
enforce appropriate drug testing guidelines and program.
All accidents or injuries to CONTRACTOR's employees working on the job site must be reported
verbally and in writing to the ENGINEER immediately, and within no more than eight(8)hours.
The safety precautions actually taken and their adequacy shall be the sole responsibility of the
CONTRACTOR, in his sole discretion as an independent contractor. Inclusion of this paragraph in
the Agreement, as well as any notice which may be given by the OWNER or the ENGINEER as
the OWNER's representative concerning omissions under thus paragraph as the Work progresses,
are intended as reminders to the CONTRACTOR of his duty and shall not be construed as any
assumption of duty by ENGINEER, or OWNER's representative to supervise safety precautions
by either the CONTRACTOR or any of his subcontractors.
4.23 PROTECTION OF ADJOINING PROPERTY. The CONTRACTOR shall
employ proper means to protect the adjacent or adjoining property or properties in any way
encountered, which might be injured or seriously affected by any process of construction to be
undertaken under this Agreement, from any damage or injury by reason of said process of
construction; and he shall be liable for any and all claims for such damage on account of his
failure to fully protect all adjacent or adjoining property. THE CONTRACTOR AGREES TO
INDEMNIFY; DEFEND, SAVE AND HOLD HARMLESS THE CONSTRUCTION
MANAGER, OWNER AND ENGINEER AGAINST ANY CLAIM OR CLAIMS FOR
DAMAGES, LOSS, COSTS OR EXPENSES, INCLUDING BUT NOT LIMITED TO
ATTORNEY'S FEES, DUE TO ANY INJURY TO ANY ADJACENT OR ADJOINING
PROPERTY, ARISING OR GROWING OUT OF THE PERFORMANCE OF THE
CONTRACT, REGARDLESS OF WHETHER OR NOT SUCH DAMAGE, LOSS, COST OR
EXPENSE IS CAUSED IN PART BY THE NEGLIGENCE, GROSS NEGLIGENCE OR
STRICT LIABILITY OF OWNER AND/OR ENGINEER.
4.24 PROTECTION AGAINST CLAIMS OF SUBCONTRACTORS, LABORERS,
MATERIALMEN AND FURNISHERS OF MACHINERY, EQUIPMENT AND SUPPLIES.
THE CONTRACTOR AGREES THAT HE WILL PROMPTLY PAY WHEN DUE, AND WILL
INDEMNIFY, SAVE AND HOLD THE OWNER AND THE ENGINEER HARMLESS FROM
ALL CLAIMS GROWING OUT OF THE DEMANDS OF SUBCONTRACTORS, LABORERS,
WORKERS, MECHANICS, MATERIALMEN AND FURNISHERS OF MACHINERY AND
PARTS THEREOF, EQUIPMENT, POWER TOOLS AND ALL SUPPLIES, INCLUDING
COMMISSARY, INCURRED IN THE FURTHERANCE OF THE PERFORMANCE OF THIS
CONTRACT. When so desired by the OWNER, the CONTRACTOR shall furnish satisfactory
evidence that all obligations of the nature hereinabove designated have been paid, discharged or
waived. If the CONTRACTOR fails to do so, then the OWNER may, at the option of the
(ilk\ OWNER, either pay directly any unpaid bills of which the OWNER has written notice, or
withhold from the CONTRACTOR's unpaid compensation a sum of money deemed reasonably
10-1012 00700-15 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
\sub\ sufficient to liquidate any and all such claims until satisfactory evidence is furnished that all
liabilities have been fully discharged, whereupon payments to the CONTRACTOR shall be
resumed in full, in accordance with the terms of this Contract.
Any and all communications between any parties under this paragraph shall be in writing.
Nothing contained in this paragraph or this Agreement shall create, establish or impose any
relationship, contractual or otherwise,between OWNER and any subcontractor, laborer or supplier
of CONTRACTOR, nor shall it create, establish or impose any duty upon OWNER to pay or to
see to the payment of any subcontractor, laborer or supplier of CONTRACTOR.
4.25 PROTECTION AGAINST ROYALTIES OR PATENTED INVENTION. The
CONTRACTOR shall pay all royalties and license fees and shall provide for the use of any
design, device, material or process covered by letters patent or copyright, by suitable legal
agreement with the patentee or owner thereof THE CONTRACTOR SHALL DEFEND ALL
SUITS OR CLAIMS FOR INFRINGEMENT OF ANY PATENT OR COPYRIGHT AND
SHALL INDEMNIFY, SAVE AND HOLD THE OWNER AND THE ENGINEER HARMLESS
FROM ANY LOSS OR LIABILITY ON ACCOUNT THEREOF, EXCEPT SUCH SUITS AND
CLAIMS ARISING OUT OF A PARTICULAR DESIGN, DEVICE, MATERIAL OR PROCESS
OR THE PRODUCT OF A PARTICULAR MANUFACTURER OR MANUFACTURERS
SPECIFIED OR REQUIRED BY THE OWNER; PROVIDED, HOWEVER, IF CHOICE OF
ALTERNATE DESIGN, DEVICE, MATERIAL OR PROCESS IS ALLOWED TO THE
CONTRACTOR, OR IF CONTRACTOR KNEW OR SHOULD HAVE KNOWN OF THE
PATENT OR COPYRIGHT AND FAILED TO PROMPTLY NOTIFY OWNER IN WRITING,
THEN THE CONTRACTOR SHALL INDEMNIFY, DEFEND, SAVE AND HOLD THE
OWNER HARMLESS FROM ANY LOSS OR LIABILITY ON ACCOUNT THEREOF.
4.26 INDEMNIFICATION. THE CONTRACTOR AGREES TO DEFEND,
INDEMNIFY AND HOLD THE ENGINEER AND THE OWNER HARMLESS FROM ANY
CLAIMS OR DEMANDS OF ANY NATURE WHATSOEVER MADE BY ANY EMPLOYEE,
EMPLOYEES, AGENTS OR SUBCONTRACTORS OF CONTRACTOR, OR BY ANY
UNION, TRADE ASSOCIATION, WORKER'S ASSOCIATION OR OTHER GROUPS,
ASSOCIATIONS OR INDIVIDUALS,ALLEGEDLY REPRESENTING EMPLOYEES OF THE
CONTRACTOR, IN ANY DISPUTE BETWEEN THE CONTRACTOR AND HIS
EMPLOYEES, DIRECTLY OR INDIRECTLY INVOLVING, GROWING OUT OF OR
ARISING FROM CLAIMS BY SUCH EMPLOYEES FOR WAGES, SALARY,
COMPENSATION, BENEFITS, WORKING CONDITIONS OR ANY OTHER. SIMILAR
COMPLAINT OR CLAIM WHICH MAY BE MADE.
THE CONTRACTOR, HIS SURETIES AND INSURANCE CARRIERS SHALL DEFEND,
INDEMNIFY AND HOLD HARMLESS THE OWNER AND THE ENGINEER AND THEIR
RESPECTIVE OFFICERS, REPRESENTATIVES, AGENTS AND EMPLOYEES FROM AND
AGAINST ALL DAMAGES, CLAIMS, LOSSES, DEMANDS, SUITS, LIABILITIES,
JUDGMENTS AND COSTS OF ANY CHARACTER WHATSOEVER, INCLUDING
REASONABLE ATTORNEY'S FEES AND EXPENSES, AND SHALL BE REQUIRED TO
PAY ANY JUDGMENT THEREFOR, WITH COSTS, WHICH MAY BE OBTAINED ,
AGAINST THE OWNER AND/OR THE ENGINEER OR ANY OF THEIR OFFICERS,
REPRESENTATIVES, AGENTS OR EMPLOYEES, ARISING OUT OF OR RESULTING
FROM OR ALLEGEDLY ARISING OUT OF OR RESULTING FROM THE PERFORMANCE
10-1012 00700- 16 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(4.1*\' OF THE WORK, PROVIDED THAT ANY SUCH DAMAGES, CLAIM, LOSS, DEMAND,
SUIT, LIABILITY,JUDGMENT,COST OR EXPENSE:
(A) ARISES OUT OF OR RESULTS FROM IN WHOLE OR IN PART, OR
ALLEGEDLY ARISES OUT OF OR RESULTS FROM IN WHOLE OR IN
PART, ANY BREACH OF THIS AGREEMENT OR BREACH OF
WARRANTY BY CONTRACTOR; OR
(B) IS ATTRIBUTABLE TO BODILY INJURY, SICKNESS, DISEASE OR
DEATH OR INJURY TO OR DESTRUCTION OF TANGIBLE PROPERTY,
INCLUDING THE LOSS OF USE RESULTING THEREFROM; AND
IS CAUSED IN WHOLE OR IN PART OR IS ALLEGEDLY CAUSED IN
WHOLE OR IN PART BY ANY NEGLIGENT ACT OR OMISSION OF THE
CONTRACTOR, ANY SUBCONTRACTOR, THEIR AGENTS OR
EMPLOYEES OR ANYONE DIRECTLY OR INDIRECTLY EMPLOYED BY
ANY ONE OF THEM OR ANYONE FOR WHOSE ACTS ANY OF THEM
MAY BE LIABLE, REGARDLESS OF WHETHER OR NOT IT IS CAUSED
IN PART OR ALLEGEDLY CAUSED IN PART BY THE NEGLIGENCE,
GROSS NEGLIGENCE OR STRICT LIABILITY OF OWNER, ENGINEER
AND/OR A PARTY INDEMNIFIED HEREUNDER.
('° \ Notwithstanding the foregoing or anything in the Agreement to the contrary, in accordance with
the provisions of Section 130.002 of the Texas Civil Practice and Remedies Code,
CONTRACTOR shall not be obligated to indemnify or hold harmless the ENGINEER,his agents,
servants or employees, from liability for damage that is caused by or results from defects in plans,
designs or specifications prepared, approved or used by the ENGINEER, or negligence of the
ENGINEER in the rendition or conduct of professional duties called for or arising out of any
construction contract and the plans, designs or specifications that are a part of the construction
contract, and arises from personal injury or death, property injury, or any other expense that arises
from personal injury, death, or property injury.
This indemnity agreement is a continuing obligation, and shall survive notwithstanding
completion of the Work, Final Payment, expiration of the warranty period, termination of the
Contract, and abandonment or takeover of the Work.
CONTRACTOR's indemnification obligations hereunder shall not be limited by a limitation on
amount or type of damages, compensation or benefits payable by or for the CONTRACTOR or a
subcontractor under workers' compensation acts, disability benefit acts or other employee benefit
acts, and shall not be limited by any limitation on amounts or coverage of insurance provided or to
be provided under this Contract.
4.27 LOSSES FROM NATURAL CAUSES. All loss, cost, expense or damage to the
CONTRACTOR arising out of the nature of the Work to be done or from any unforeseen
circumstances in the prosecution of the same, or from the action of the elements, or from unusual
obstructions or difficulties which may be encountered in the prosecution of the Work, shall be
sustained and borne by the CONTRACTOR at his own cost and expense.
10-1012 00700- 17 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
4.28 GUARANTEE. The CONTRACTOR hereby guarantees all the Work under the
Contract to be free from defects or deficiencies in material in every particular and free from
defects or deficiencies in workmanship; and against unusual damage from proper and usual use;
and agrees to replace or to re-execute without cost to the OWNER such Work as may be found to
be defective, deficient or otherwise not in conformance with the Contract Documents, and to make
good all damages caused to other work or material, due to such defective Work or due to its
required replacement or re-execution. This guarantee shall cover a period of one year from the
date of Substantial Completion or Partial Substantial Completion of Work under the Contract, as
evidenced by the Certificate of Substantial Completion. Neither the Certificate of Substantial
Completion, Final Payment, nor any provision in the Contract Documents shall relieve the
CONTRACTOR of the responsibility for defective, deficient or non-conforming material or
workmanship during the period covered by the guarantee. The one-year period of guarantee will
not limit the OWNER'S other rights under common law with respect to any defects, deficiencies
or non-conforming Work discovered after one year. If this one-year guarantee conflicts with other
warranties or guarantees, the longer period of warranty or guarantee will govern.
5.0 PROSECUTION AND PROGRESS
5.01 TIME AND ORDER OF COMPLETION. It is the meaning and intent of this
Contract, unless otherwise herein specifically provided, that the CONTRACTOR shall be allowed
to prosecute his Work at such times and seasons, in such order of precedence, and in such manner
as shall be most conducive to economy of construction; provided, however, that the order and the
time of prosecution shall be such that the Work shall be Substantially Completed as a whole and in
part, in accordance with this Contract and the Contract Time; provided, also, that when the
OWNER is having other work done, either by contract or by his own forces, the ENGINEER may
direct the time and manner of constructing the Work done under this Contract, so that conflict will
be avoided and the construction of the various works being done for the OWNER shall be
harmonized, and the CONTRACTOR shall fully cooperate and coordinate its Work with OWNER
or such other contractors.
The CONTRACTOR shall submit, an updated schedule with every pay estimate for review by the
ENGINEER, schedules which shall show the order in which the CONTRACTOR proposes to
carry on the Work, with dates on which the CONTRACTOR will start the several parts of the
work, and estimated dates of completion of the several parts. Such schedules shall show
completion of the Work within the Contract Time, and/or shall show such recovery efforts as
CONTRACTOR intends to undertake in the event Substantial Completion of the Work is delayed.
5.02 EXTENSION OF TIME. The CONTRACTOR agrees that he has submitted his
Bid Proposal in full recognition of the time required for the completion of this Project, taking into
consideration the average climatic range and industrial conditions prevailing in this locality, and
has considered the liquidated damage provisions as hereinafter set forth, and that he shall not be
entitled to, nor will he request, an extension of time on this Contract, except when Substantial
Completion of the Work has been delayed solely by strikes, lockouts, fires, Acts of God, or by any
other cause which the ENGINEER shall decide justifies the delay. The CONTRACTOR shall give
the ENGINEER prompt notice, in writing and within three (3) days of the start of any such delay,
of the cause of any such delay, and its estimated effect on the Work and the schedule for
completion of the Work. Upon receipt of a written request for an extension of the Contract Time
from the CONTRACTOR, supported by relevant and all requested documentation, the
10-1012 00700- 18 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
ENGINEER shall submit such written request, together with his written recommendation, to the
OWNER for consideration. If the delay is not attributable in whole or in part to any act or
omission of CONTRACTOR, its subcontractors or suppliers, and if the OWNER determines that
CONTRACTOR is entitled to an extension of time under the terms of the Contract, the OWNER
shall grant an extension of time for Substantial Completion of the Work, sufficient to compensate
for the delay, and such extension of time shall be CONTRACTOR's sole and exclusive remedy,
except as may be otherwise provided herein. No extensions of Contract Time shall be made for
delays occurring prior to the Contractor's mobilization as defined in Section 01505
MOBILIZATION.
The Contract Time as defined in the Bid Proposal and other sections herein incorporates
40 Rain Days per calendar year or an average of 3.33 days per calendar month. The
CONTRACTOR is required to keep record of all weather related delays and to submit the monthly
count on each Pay Application. The Owner's Representative shall review and sign off on this
record as a part of the Pay Application approval process every month. If, during preparation of the
Balancing Change Order, the status of the work progress requires an extension of the Contract
Time, Impact Days shall be added to the Completion Date equal to the total number of Weather or
Impact Days approved less the original 40 days resident in the original Contract Time. The
Addition of Weather or Impact Days will only alter the Contract Time when added by Change
Order. If the Work is completed prior to the Completion Date, No Days will be added. The
addition of Weather or Impact Days shall be the CONTRACTOR"s sole remedy for delays to the
completion of the Work and their addition to the Contract Time shall not affect the Contract Price
through any"per diem" adjustment to the General Conditions costs, Temporary Facilities costs or
any other costs associated with the extension of the Contract Time.
Clieb\ 5.03 HINDRANCES AND DELAYS. In executing the Contract, the CONTRACTOR
agrees that in undertaking to complete the Work within the time herein fixed, he has taken into
consideration and made allowances for all interference, disruption, hindrances and delays incident
to such Work, whether growing out of delays in securing material, workmen or otherwise. No
claim shall be made by the CONTRACTOR for damages, loss, costs or expense resulting from
interference, disruption, hindrances or delays from any cause during the progress of any portion of
the Work embraced in this Contract, except where the Work is stopped or suspended by order of
the OWNER"s representative and such stoppage or suspension is not attributable to any act or
omission of CONTRACTOR.
5.04 SUSPENSION OF WORK. OWNER may, without cause, order the
CONTRACTOR in writing to suspend the Work, in whole or in part, for such period of time as
OWNER may request. The Contract Price and/or Contract Time shall be adjusted for any increase
in the cost of or the time required for performance of the Work caused by such suspension. No
adjustment shall be made to the extent performance was or would have been suspended by a cause
for which CONTRACTOR is responsible, or to the extent an adjustment is made or denied under
another provision of the Contract Documents.
5.05 LIQUIDATED DAMAGES FOR DELAY: It is understood and agreed that time
is of the essence, and that the CONTRACTOR will commence the Work on the date specified
herein or in any Notice to Proceed, and will Substantially Complete the Work within the Contract
Time. It is expressly understood and agreed, by and between the CONTRACTOR and the
OWNER, that the time for the Substantial Completion of the Work described herein is reasonable
time for the completion of the same, taking into consideration the average climatic range and
conditions and usual industrial conditions prevailing in this locality. The CONTRACTOR further
10-1012 00700- 19 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
agrees that a failure to complete on time will cause damage to the OWNER and that such damages
cannot be accurately measured or that ascertainment will be difficult. Therefore, the parties agree
that for each and every calendar day the Work or any portion thereof shall remain uncompleted
after the expiration of the Contract Time, the CONTRACTOR shall pay, as liquidated damages
and as a reasonable estimate of OWNER's damages, and not as a penalty,the amount set out in.the
Standard Form of Agreement.
However, the foregoing agreement as to liquidated damages constitutes only an agreement by the
OWNER and the CONTRACTOR as to the amount of damages which the OWNER will sustain
by reason of the CONTRACTOR'S failure to complete the work within the Contract Time. Should
the OWNER suffer damage by reason of any other breach by CONTRACTOR, the OWNER may
recover such actual damages in addition to any liquidated damages due.
The OWNER shall have the right to deduct and withhold the amount of any and all such damages
whether it be the minimum amount stipulated above or otherwise, from any monies owing by it to
said CONTRACTOR, or the OWNER may recover such amount from the CONTRACTOR and
the sureties of his bond; all of such remedies shall be cumulative and the OWNER shall not be
required to elect any one nor be deemed to have made an election by proceeding to enforce any
one remedy.
5.06 CHANGE OF CONTRACT TIME: The Contract Time may only be changed by a
Change Order. Any claim for an adjustment of Contract Time shall be based on written notice
delivered by the party making such claim to the other party and to the ENGINEER promptly, but
in no event later than ten(10) days after the event-giving rise to the claim. Notice of the extent of
the claim, along with supporting data, shall be delivered within thirty (30) days of the occurrence
and shall be accompanied by the claimant's written representation that the adjustment claimed is
the entire adjustment to which the claimant has reason to believe it is entitled as a result of the
occurrence of said event. All claims for adjustment in Contract Time shall be determined by the
ENGINEER in accordance with the requirements of this paragraph. Contractor shall submit, as a
minimum,the following data:
A. Information showing that the time requested is not included in the existing
Contract and in addition to the Contract.
B. Information documenting that the number of days requested is accurate for the
event.
C. Revised, current construction schedule showing that the time requested affects
the project's critical path.
5.07 DELAYS BEYOND OWNER'S AND CONTRACTOR'S CONTROL: Where
CONTRACTOR is prevented from completing any part of the Work within the Contract Time due
to delays beyond the control of the OWNER and the CONTRACTOR, including, but not limited
to, interference by utility owners or other contractors performing other work, Contractor shall be
entitled to an extension of the Contract Time in an amount equal to the time lost. CONTRACTOR
shall not be entitled to any increase in Contract Price as a result of such delays. IN NO EVENT
SHALL OWNER BE LIABLE TO CONTRACTOR FOR DAMAGES ARISING OUT OF OR
RESULTING FROM (i) Delays caused by, or within the control of, the CONTRACTOR, or (ii)
Delays beyond the control of both parties including, but not limited to, interference by utility
owners or other contractors performing other work, fires, floods, epidemics, abnormal weather
(111 conditions, acts of God, even if such delays are due in part to the negligence, other fault,breach of
contract or warranty, violation of the Texas Deceptive Trade Act, or strict liability without regard
10-1012 00700-20 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
to fault of OWNER. An extension of Contract time shall be CONTRACTOR's sole and exclusive
remedy for any such delays.
Delays attributed to, and within the control of, a Subcontractor or Supplier shall be
deemed to be delays within the control of the CONTRACTOR.
6.0 MEASUREMENT AND PAYMENT
6.01 DISCREPANCIES AND OMISSIONS. If the CONTRACTOR knows or
reasonably should have known of any discrepancies or omissions in the Contract Documents, he
shall notify the ENGINEER and obtain a clarification by Addendum before the bids are received,
and if no such request is received by the ENGINEER prior to the opening of bids, then it shall be
considered that the CONTRACTOR fully understands the Work to be performed and has provided
sufficient sums in his Bid Proposal to complete the Work in accordance with the Contract
Documents. It is further understood that any request for clarification must be submitted no later
than five(5) days prior to the opening of bids.
6.02 QUANTITIES AND MEASUREMENTS. No extra or customary measurements
of any kind will be allowed, but the actual measured and/or computed length, area, volume,
number and weight only shall be considered,unless otherwise specifically provided.
6.03 ESTIMATED QUANTITIES. This Agreement, including the Contract
Cmb Documents, and including any estimates contained therein, is intended to convey all Work to be
done and material to be furnished hereunder. Where the estimated quantities are shown for the
various classes of Work to be done and material to be furnished under this Contract, they are
approximate and are to be used only as a basis for estimating the probable cost of the Work and
for comparing the Bid Proposals offered for the Work. It is understood and agreed that the actual
amount of Work to be done and the materials to be furnished under this Contract may differ from
the estimates and that the items listed or estimated quantities stated, and/or any difference between
estimated and actual Work, shall not give rise to a claim by the CONTRACTOR against the
OWNER for loss, cost, expense, damages,unit price adjustment, quantity differences,unrecovered
overhead or lost or anticipated profits, or other compensation.
6.04 PRICE OF WORK. It is agreed that it is the intent of this Contract that all Work
described in the Bid Proposal, and Contract Documents, is to be done for the prices bid by the
CONTRACTOR and that such prices shall include all appurtenances necessary to complete the
Work in accordance with the intent of these Contract Documents as interpreted by the
ENGINEER, and all costs, expenses, bond and insurance premiums, taxes, overhead, and profit.
In consideration of the furnishing of all the necessary labor, equipment and material and the
completion of all Work by the CONTRACTOR, and upon the completion of all Work and the
delivery of all materials embraced in this Contract in full conformity with the Contract
Documents, the OWNER agrees to pay to the CONTRACTOR the prices set forth in the Standard
Form of Agreement, OWNER and CONTRACTOR agree that the Contract is a unit cost
agreement, unless stated otherwise, and that the final Contract amount is equal to the unit cost
multiplied by the number of units authorized, installed and approved by the Owner.
The OWNER does not assume any obligation to pay for any services or material not
actually authorized and used. The CONTRACTOR hereby agrees to receive such prices as
payment in full for furnishing all materials and all labor required for the aforesaid Work, and for
10-1012 00700-21 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
all expenses incurred by him, and for full performance of the Work and the whole thereof in the
manner and according to this Agreement, Contract Documents, and the requirements of the
ENGINEER.
6.05 PAYMENTS. No payments made or approvals or certificates given shall be
considered as conclusive evidence of the performance of the Contract, either in whole or in part,
nor shall any certificate, approval or payment be considered as acceptance of defective, deficient
or non-conforming Work. CONTRACTOR shall, at any time requested during the progress of the
Work, furnish the OWNER or the ENGINEER with an affidavit showing the CONTRACTOR's
total outstanding indebtedness in connection with the Work. Before Final Payment is made, the
CONTRACTOR shall satisfy the OWNER, by affidavit or otherwise, that there are no unpaid
claims due subcontractors, suppliers or laborers by reason of any Work under the Contract.
Acceptance by CONTRACTOR of Final Payment shall constitute a waiver of any and all claims
of whatsoever nature against OWNER, arising out of or related to the Contract, or the Work, or
any acts or omissions of OWNER or ENGINEER, which have not theretofore been timely filed as
provided in this Contract.
6.06 PARTIAL PAYMENTS. When the Contract Price is a lump sum amount,prior to
the first Application for Payment, CONTRACTOR shall submit to ENGINEER for review and
approval a Schedule of Values, which shall fairly allocate the entire Contract Price among the
various portions of the Work and shall be prepared in such form and supported by such data to
substantiate its accuracy as the ENGINEER may reasonably require. The Schedule of Values
shall follow the trade divisions of the Specifications so far as practicable. Upon approval, this
Schedule of Values shall be used by ENGINEER as the basis for reviewing the Contractor's
Application for Payment. Applications for Payment shall indicate the percentage of completion of
each portion of the Work as of the end of the period covered by the Application for Payment.
On or before the tenth day of each month, the CONTRACTOR shall prepare and submit to the
ENGINEER, for approval or correction, an application for partial payment, being a statement
showing as completely as practicable, the agreed unit quantities and extended total value of the
Work done by the CONTRACTOR up to and including the twenty-fifth day of the preceding
month; said statement shall also include the value of all conforming materials to be fabricated into
the Work and stored in accordance with manufacturer's recommendations and as approved by the
OWNER or ENGINEER at the Work site only. No payment will be made for materials stored until
OWNER has approved in writing storage at the Work site. The ENGINEER shall then review
such statement of unit quantities and application for partial payment and the progress of the Work
made by the CONTRACTOR and, within ten days after the date ENGINEER receives
CONTRACTOR's application for payment, if the application is found to be accurate and correct
and the WORK conforming to the requirements of the Contract Documents, the ENGINEER shall
certify the application for partial payment and shall deliver his preliminary certification for
payment to the OWNER and the CONTRACTOR; or, if the ENGINEER finds that
CONTRACTOR's application for payment contains an error or is otherwise disputed, he shall
notify CONTRACTOR of such error or dispute, and shall prepare a preliminary certificate for
partial payment for the undisputed amount of the application for payment due CONTRACTOR,
and deliver it to the OWNER and CONTRACTOR. ENGINEER'S notice to CONTRACTOR that
a bona fide dispute for payment exists shall include a list of the specific reasons for nonpayment.
All payment applications made by CONTRACTOR and delivered to ENGINEER and all
verifications and certification of such applications shall be made and transmitted within the Pro-
Trak system and signed with the appropriate electronic signatures as provided for in the software.
10-1012 00700-22 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Such applications for payment shall not be considered complete unless accompanied by the
CONTRACTOR'S Partial Waiver of Lien and Payment Affidavit, Section 00615, duly executed
by an authorized representative of the CONTRACTOR and reflecting the correct corresponding
amount of the payment application.
The OWNER shall then pay the CONTRACTOR, within thirty (30) days of the date of
ENGINEER's receipt of the application for payment, the undisputed balance due, less applicable
retainage, and further less all previous payments and all further sums that may be retained or
withheld by the OWNER under the terms of this Agreement. CONTRACTOR may submit a
corrected application for payment after its receipt of the ENGINEER's notice of error or dispute,
and such corrected application for payment shall be reviewed by the ENGINEER and disputed or
paid under the same procedure and within the same time limits set out above.
As a condition of any progress payment under this Agreement, CONTRACTOR shall execute and
deliver to ENGINEER and OWNER a full release of all claims, direct or indirect, at law or in
equity, arising out of or related to the Work to date, excluding retainage or any claims previously
submitted as required under the terms of the Contract, and specifically identified and excluded by
CONTRACTOR in the release.
OWNER shall be entitled to retain from each progress payment five percent (5%) of the amount
thereof. Such retainage shall be retained until Final Completion and satisfaction of all conditions
for Final Payment. It is understood, however, that in case the whole Work be near to completion,
as certified by the ENGINEER, and some unexpected or unusual delay occurs, through no neglect
or fault on the part of the CONTRACTOR, the OWNER may, upon written recommendation of
the ENGINEER, pay a reasonable and equitable portion of the retained percentage to the
CONTRACTOR, or the CONTRACTOR, at the OWNER'S option, may be relieved of the
obligation to fully complete the Work, and thereupon, the CONTRACTOR shall receive, at the
OWNER'S option, payment of the balance due him under the Contract for Work completed in
accordance with the Contract Documents, subject to OWNER's rights to otherwise withhold or
retain payments, and subject to the conditions set forth under"6.08 FINAL PAYMENT."
The Owner at its option and in compliance with Texas law may reduce retainage to less than the
above-stated percentages.
6.07 USE OF COMPLETED PORTIONS & PUNCHLIST. The OWNER shall have
the right to take possession of and use any completed or partially completed portions of the Work,
notwithstanding that the time for completing the entire work or such portions may not have
expired; but such taking possession and use shall not be deemed an acceptance of any work not
completed in accordance with the Contract Documents. If such prior use increases the cost of or
delays the Work, the CONTRACTOR shall promptly and within three (3) days of OWNER's
taking possession, give OWNER written notice of same, and CONTRACTOR may be entitled to
such extra compensation or extension of time, or both, as may be determined in accordance with
the provisions of this Agreement.
•
6.08 SUBSTANTIAL COMPLETION. The CONTRACTOR shall notify the OWNER
AND ENGINEER, by letter executed by a duly qualified officer of CONTRACTOR, that in
CONTRACTOR's opinion, the Work of the Contract, or an agreed portion thereof, is
"Substantially Complete". Such notification shall include a list of all outstanding or incomplete
items. Upon receipt, and within a reasonable time thereafter, of such notice, the ENGINEER and
the CONTRACTOR shall jointly perform a walk-through and inspection of the Work to determine
10-1012 00700-23 of 36
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
the status of all or the identified portion of the work, and the ENGINEER shall prepare a detailed
list of unfinished, incomplete, defective and/or non-conforming Work ("Punchlist"). If the
ENGINEER determines that the Work is Substantially Complete in accordance with the Contract
Documents, the ENGINEER shall issue to the OWNER and the CONTRACTOR a Certificate of
Substantial Completion. OWNER shall have seven (7) days after receipt of Certificate to make
written objection to the ENGINEER as to any provision of the Certificate or the attached list of
non-conforming work. If ENGINEER concludes that the Work is not Substantially Complete,
ENGINEER will, within fourteen (14) days, notify CONTRACTOR of the reason he believes the
Work is not Substantially Complete. Upon Substantial Completion of the Work, ENGINEER will
deliver to OWNER and CONTRACTOR a written recommendation as to division of
responsibilities, pending fmal payment and acceptance, with respect to security, maintenance,
utilities and damage to the Work, except as otherwise provided in the Certificate of Substantial
Completion. NEITHER THE SUBSTANTIAL COMPLETION OF THE WORK, NOR THE
OMISSION OF AN ITEM FROM THE PUNCHLIST, SHALL EXCUSE THE CONTRACTOR
FROM PERFORMING ALL OF THE WORK UNDERTAKEN, WHETHER OF A MINOR OR
MAJOR NATURE, AND THEREBY COMPLETING THE WORK IN ACCORDANCE WITH
THE CONTRACT DOCUMENTS. The Certificate of Substantial Completion shall establish the
time period within which CONTRACTOR shall complete the Work for Final Acceptance by the
Owner and ENGINEER.
6.08-1 OWNER shall have the right to exclude CONTRACTOR from the Work after the
date of Substantial Completion, for security requirement reasons. OWNER may establish an
access procedure to facilitate CONTRACTOR's uninterrupted access to the Work for the purposes
of completing and correcting all items on the Punchlist in an expeditious manner.
6.09 FINAL PAYMENT. Final payment of the Retainage withheld from the Contract
Price shall be made by the OWNER to the CONTRACTOR at such time as:
(a) the Work, including all Change Orders and including all Punchlist work,has been
fully completed in strict accordance with the Contract Documents;
(b) the Contract has been fully performed except for the CONTRACTOR's
responsibility to correct nonconforming Work during the warranty period set forth
in the Contract Documents,and to satisfy other requirements, if any,which
necessarily survive fmal payment;
(c) CONTRACTOR delivers to OWNER a certificate evidencing that insurance
required by the Contract Documents to remain in force after final payment is
currently in effect and will not be cancelled or allowed to expire until at least 30
days prior written notice has been given to OWNER;
(d) CONTRACTOR delivers to OWNER a Consent of Surety, if any, to fmal payment;
(e) CONTRACTOR delivers to OWNER a complete set of As-Built Drawings,
reflecting all deviations from the Plans, Specifications and approved shop drawings
in the Work actually constructed, and delivers all maintenance and operating
manuals and/or instructions;
10-1012 00700-24 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Club'\ (f) CONTRACTOR delivers to OWNER all building certificates required prior to
occupancy and all other required inspections/approvals/acceptances by city,
county, state governmental entities or other authorities having jurisdiction;
(g) CONTRACTOR delivers to OWNER assignments of all guarantees and warranties
from subcontractors, vendors, suppliers or manufacturers, as well as names,
addresses and telephone numbers of contacts for each subcontractor,vendor,
supplier or manufacturer;
(h) CONTRACTOR removes all equipment,tools, temporary facilities, surplus
materials and rubbish from the site,and final cleans the site to OWNER's
satisfaction;
(i) CONTRACTOR delivers to OWNER a Full and Final Release and Affidavit of
Bills Paid in the form attached hereto as Attachment No. 2, executed by
CONTRACTOR;
(j) CONTRACTOR delivers to OWNER all other documentation required to be
submitted to OWNER pursuant to the Contract Documents, including but not
limited to any special guarantees or warranties, operation and maintenance
manuals, etc'. in each case in a form satisfactory to OWNER as determined in
OWNER's sole discretion; and
(k) the Final Application for Payment has been approved by the ENGINEER and
OWNER.
Acceptance of Final Payment by the CONTRACTOR shall constitute a waiver of all claims by
CONTRACTOR against OWNER other than any claims previously made in writing by
CONTRACTOR against OWNER, and still unsettled, and except for claims arising out of third
party actions, cross-claims and counterclaims. No interest shall be due or payable by OWNER to
CONTRACTOR on any sums retained or withheld by OWNER pursuant to the terms or
provisions of the Contract Documents, except as otherwise provided by applicable law. Neither
the Certificate of Substantial Completion nor the Final Payment nor possession or acceptance of
the Work shall relieve the CONTRACTOR of its obligation for correction of defective or non-
conforming Work, or for fulfillment of any warranty, which may be required by law or by the
Contract Documents.
6.10 CORRECTION OF WORK BEFORE FINAL PAYMENT. The CONTRACTOR
shall promptly remove from OWNER's premises all materials, equipment or Work which is
defective or otherwise not in conformance with the Contract Documents, whether actually
incorporated in the Work or not, and CONTRACTOR shall, at his own expense, promptly replace
such materials, equipment or Work with other materials conforming to the requirements of the
Contract. The CONTRACTOR shall also bear the expense of restoring all work of
CONTRACTOR or other contractors damaged by any such removal or replacement. If
CONTRACTOR does not remove and replace any such unsuitable Work within ten(10) business
days after receipt of a written notice from the OWNER or the ENGINEER, the OWNER may
remove, replace and remedy such work at CONTRACTOR's expense.
10-1012 00700-25 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(''�`. 6.11 CORRECTION OF WORK AFTER FINAL PAYMENT. If within one (1) year
\\ from the date of Substantial Completion or such longer period of time as may be prescribed by law
or by the terms of any applicable special warranty required by the Contract Documents, any of the
Work is found to be defective or not in accordance with the Contract Documents, CONTRACTOR
shall, at its sole cost, correct it and any other work affected thereby promptly after receipt of a
written notice from OWNER to do so. In addition, CONTRACTOR shall be responsible for any
damage to building contents, when such damage results from the CONTRACTOR's use of faulty
materials or defective workmanship; to the extent such damage is not covered by OWNER's
insurance. This warranty period shall renew and recommence for each corrected item of Work
upon completion of the remedial work. This time period for correction by CONTRACTOR is in
addition to, and not in lieu of, all warranties or remedies,which exist at common law or by statute.
These warranty obligations shall survive the termination of this Contract, and shall be enforceable
by a decree of specific performance, in addition to such other rights and remedies available to
OWNER at law or in equity.
6.12 PAYMENTS WITHHELD. The OWNER may withhold, or on account of
subsequently discovered evidence nullify and demand immediate repayment of, the whole or part
of any certificate for payment or payment, to such extent as may be necessary to protect OWNER
from loss on account of:
(a) Defective or non-conforming Work not remedied;
(b) Claims filed or reasonable evidence indicating probable filing of claims;
(c) Failure of the CONTRACTOR to make payments promptly to subcontractors or
for material or labor;
(d) Damage to another contractor, OWNER, existing improvements on the site, or to
adjacent or adjoining property;
(e) Reasonable doubt that the Work can be completed for the unpaid balance of the
Contract amount;
(f) Reasonable indication that the Work will not be completed within the Contract
Time;
(g) Failure on the part of the CONTRACTOR to execute any and -all documents,
releases or other documents presented to the CONTRACTOR for execution, as
provided for herein or otherwise;
(h) Liquidated or other damages due to late completion; and/or
(i) Any breach by CONTRACTOR of this Contract or any other agreement between
OWNER and CONTRACTOR.
When the above grounds are removed to OWNER's satisfaction, the withheld payment shall be
made promptly. If the said causes are not so remedied,OWNER may remedy the same for
CONTRACTOR's account, charge the entire cost thereof to CONTRACTOR and deduct such cost
10-1012 00700-26 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(1.1h\ from the.Contract Sum or from any payments due or to become due under any other agreement
between OWNER and CONTRACTOR.
6.13 DELAYED PAYMENTS. Should the OWNER fail to make payment to the
CONTRACTOR when payment is due in accordance with the terms of the Contract Documents,
any interest due CONTRACTOR for late payments shall accrue and be paid in accordance with
the provisions of Chapter 2251 of the Texas Government Code, as amended, and payment of such
interest shall fully liquidate and compensate any injury to the CONTRACTOR growing out of
such delay in payment. Should OWNER fail to pay CONTRACTOR an undisputed amount due
within the time limits provided in the Contract or applicable law, CONTRACTOR shall give the
notice required and comply with the provisions of Section 2251.051 of the Texas Government
Code,and shall thereupon be entitled to the rights and remedies provided therein.
7.0 EXTRA WORK AND CLAIMS
7.01 DIFFERING SITE CONDITIONS. During the progress of the work, if subsurface, latent
physical conditions or unknown physical conditions of an unusual nature are encountered at the
site that differ materially from those indicated in the contract or from those ordinarily encountered
and generally recognized as inherent in the work provided for in the contract, the CONTRACTOR
shall notify the OWNER's Representative in writing within three(3) calendar days of the specific
differing conditions before the site is disturbed and before the affected work is performed.
(a)Upon written notification,the ENGINEER will investigate the conditions, and if it is
determined that the conditions materially differ and cause an increase or decrease in the
cost or time required for the performance of any work under the contract,an adjustment,
excluding anticipated profits,will be made and the contract modified in writing
accordingly. The ENGINEER will notify the CONTRACTOR in writing of the
determination whether or not an adjustment of the contract is warranted.
(b)No contract adjustment which results in a benefit to the CONTRACTOR will be
allowed unless the CONTRACTOR has provided the required written notice.
(c)No contract adjustment will be allowed under this clause for any effects caused on
unchanged work.
7.02 SUSPENSIONS OF WORK ORDERED BY THE ENGINEER. If the performance of all
or any portion of the work is suspended by the ENGINEER in writing for seven(7) calendar days
and the CONTRACTOR believes that additional compensation and/or contract time is due as a
result of such suspension,the CONTRACTOR shall submit a written request for adjustment to the
ENGINEER within seven(7) calendar days of receipt of the notice to resume work. The request
shall set forth the reasons and support for such adjustment.
(a) Upon receipt, the ENGINEER will evaluate the CONTRACTOR's request. If the
ENGINEER agrees that the cost and/or time required for the performance of the contract
has increased as a result of such suspension and the suspension was caused by conditions
beyond the control of and not the fault of the CONTRACTOR, its suppliers, or
subcontractors at any approved tier, and not caused by weather, the ENGINEER will make
10-1012 00700-27 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(1.1'\ an adjustment(excluding profit)and modify the contract in writing accordingly. The
CONTRACTOR will be notified of the ENGINEER's determination, in writing, whether or
not an adjustment of the contract is warranted.
(b)No contract adjustment will be allowed unless the CONTRACTOR has submitted the
request for adjustment within the time prescribed.
(c)No contract adjustment will be allowed under this clause to the extent that performance
would have been suspended by any other cause, or for which an adjustment is provided or
excluded under any other term or condition of this contract.
7.03 CHANGE ORDERS.Without invalidating this Agreement, the OWNER may, at
any time or from time to time, order additions, deletions or revisions to the Work; such changes
will be authorized by Change Order to be prepared by the ENGINEER for execution by the
OWNER and the CONTRACTOR. The Change Order shall set forth the basis for any change in
Contract Price, as hereinafter set forth for Extra Work, and any change in Contract Time,which
may result from the change.
7.04 In accordance with paragraph 1.07 CONTRACTOR'S request to work weekends,
the Owner's Construction Manager shall,upon receipt of written notice by the CONTRACTOR of
the need to conduct work on otherwise non-Work Days,prepare a cost estimate for providing
Construction Management and Inspection services during the requested period and submit this to
,4011 both OWNER and CONTRACTOR. If approved by both parties the Construction Manager shall
prepare a Deductive Change Order in the amount stated in the estimate for the signature of the
CONTRACTOR and the OWNER for inclusion in the next Pay Application. The Deductive
Change Order must be signed and executed by both the OWNER and CONTRACTOR prior to
start of work on any non-Work Day.
7.05 MINOR CHANGES. The ENGINEER may authorize minor changes in the Work
not inconsistent with the overall intent of the Contract Documents and not involving an increase in
Contract Price or time. If the CONTRACTOR believes that any minor changes authorized by the
ENGINEER involves Extra Work or entitles him to an increase in the Contract Price or the
Contract Time, the CONTRACTOR shall give notice of same by written request to the
ENGINEER for a written Work Order, with a copy to OWNER. Any such notice and request by
the CONTRACTOR shall be given prior to beginning the changed work. CONTRACTOR's
commencement of any minor change in the Work prior to such written notice and request shall
constitute a waiver of any and all claims for an increase in the Contract Price or the Contract Time
arising out of or related to such changed work.
7.06 EXTRA WORK. It is agreed that the CONTRACTOR shall perform all work
when presented with a written Change Order, Work Change Directive or Work Order signed by
the ENGINEER, subject, however, to the right of the CONTRACTOR to require written
confirmation of such Change Order, Work Change Directive or Work Order by the OWNER. It is
agreed that the basis of compensation or adjustment to the CONTRACTOR for work either
altered, added or deleted by a Change Order or Work Change Directive, or for which a claim for
Extra Work is made, shall be determined by one or more of the following methods:
Method(A) --By Contract unit prices applicable to the work, if any; or
10-1012 00700-28 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
7\1
Method(B) --By agreed unit prices or agreed stipulated lump sum pric
e;
Method(C) --If neither Method(A) nor Method (B) can be agreed upon before the Extra
Work is commenced, then the CONTRACTOR shall be paid the "Actual Field Cost" of
the work plus:
a) For subcontractors performing work mark-up shall be limited to fifteen percent,
ten(10%) for the subcontractor plus five (5%) for the General Contractor or
b)For the General Contractor alone, self-performing the extra work,without
subcontractor, the mark-up shall not exceed ten percent (10%), as full and final
compensation for the Extra Work and all costs and expenses, direct or indirect,
arising out of or related thereto.
In the event said Extra Work or Change Order or Work Change Directive work is performed and
paid for under Method(C), then the provisions of this paragraph shall apply and the"Actual Field
Cost" is hereby defined as the cost to the CONTRACTOR of all workers, such as foremen,
timekeepers, mechanics and laborers, and materials, supplies, trucks, rentals of machinery and
equipment, for the time actually employed or used on such Extra Work or Change Order or Work
Change Directive work, plus actual transportation charges necessarily incurred together with all
power, fuel, lubricants, water and similar operating expenses, plus all necessary incidental
expenses incurred directly on account of such Extra Work, including Social Security, Old Age
Benefits and other payroll taxes, and a rateable proportion of premiums on Performance and
Payment Bonds and Maintenance Bonds, Public Liability and Property Damage and Workers'
Compensation, and all other insurance as may be required by law or ordinance, or the Contract
Documents,plus all payments to subcontractors for such work.
The ENGINEER may direct the form in which accounts of the "Actual Field Cost" shall be kept
and the records of these accounts shall be made available to the ENGINEER. The ENGINEER or
OWNER may also specify in writing, before the work commences, the method of doing the work
and the type and kind of machinery and equipment to be used; otherwise these matters shall be
determined by the CONTRACTOR. Unless otherwise agreed upon, the prices for the use of
machinery and equipment shall be determined by using one hundred percent (100%), unless
otherwise specified, of the latest schedule of Equipment Ownership Expense adopted by the
Associated General Contractors of America where practicable. The mark-up of the "Actual Field
Cost" to be paid to the CONTRACTOR, shall cover and compensate him for his profit, overhead,
and all other elements of cost and expense not embraced within the"Actual Field Cost" as herein
defined, save that where the CONTRACTOR's field office must be maintained solely on account
of such Extra Work, then the cost to maintain and operate the same shall be included in the
"Actual Field Cost."
No claim for Extra Work of any kind will be allowed unless ordered by the ENGINEER in a
written Work Order. In case any orders or instructions, either oral or written, appear to the
CONTRACTOR to involve Extra Work for which he should receive compensation or an
adjustment in the Contract Time, he shall make written request to the ENGINEER for a written
Work Order authorizing such Extra Work within ten (10) days of ENGINEER's orders or
instructions, otherwise the orders or instructions will be considered minor changes. The issuance
of a Work Order by the ENGINEER shall not constitute or be construed as an agreement or
10-1012 00700-29 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Cab\' acknowledgement by the ENGINEER that the work which is the subject of the Work Order is
Extra Work outside the scope of the Contract Work, but shall merely constitute a direction to the
CONTRACTOR to perform the work, and the CONTRACTOR shall proceed with the work, and
shall keep an accurate account of the "Actual Field Cost" thereof, as provided under Method (C).
Upon completion of the alleged Extra Work, the CONTRACTOR shall promptly and within ten
(10) days submit his claim to the ENGINEER by proper certification and attestation, on forms
provided by the ENGINEER. The ENGINEER shall render a written decision on
CONTRACTOR's claim within ten (10) days. It is mutually agreed between the parties that the
ENGINEER's decision on all claims or questions in relation to the Work, CONTRACTOR's
performance of the Work, any changes in the Work or Extra Work, the Contract Price and/or the
Contract Time, shall be fmal and conclusive and binding upon the parties. If the ENGINEER
shall fail to respond in writing to CONTRACTOR's claim within thirty (30) days of the date of
submission, or if CONTRACTOR shall dispute or object to ENGINEER's decision on any claim,
and CONTRACTOR fails to file a Request for Mediation of such claim in accordance with the
provisions of Article 9.0, within sixty(60) days after the date of submission to the ENGINEER, or
such longer period as the parties may agree to in writing, the CONTRACTOR shall lose and
forfeit his right to make such claim for Extra Work at any later date, and all such claims held by
the CONTRACTOR shall be deemed waived, forfeited and forever barred. CONTRACTOR shall
continue to diligently prosecute the Work notwithstanding any pending claim, dispute, or dispute
resolution process between OWNER and CONTRACTOR.
7.07 TIME OF FILING CLAIMS. Except as otherwise provided herein, all questions
of dispute or adjustment shall be made within the Pro-Trak system and filed with the ENGINEER
Cis'\ within three (3) days after the ENGINEER has given any directions, order or instruction to which
the CONTRACTOR desires to take exception. The ENGINEER shall reply within thirty(30) days
to such written exceptions, and render his final decision in writing. It is mutually agreed between
the parties that the ENGINEER's decision on all claims or questions in relation to the Work,
CONTRACTOR's performance of the Work, any changes in the Work or Extra Work, the
Contract Price and/or the Contract Time, shall be final and conclusive and binding upon the
parties. In case the CONTRACTOR should desire to appeal from the ENGINEER's decision, the
CONTRACTOR may request a meeting between representatives of the OWNER and the
CONTRACTOR for the purposes of appealing the ENGINEER's decision directly to the
OWNER, such meeting to occur within ten (10) days after the date of the CONTRACTOR's
request, or such longer period as may be agreed to by the parties in writing. If the
CONTRACTOR shall still be aggrieved after a meeting with the OWNER and/or his
representative, the CONTRACTOR shall have sixty (60) days after the date of the meeting, or
such longer period as the parties may agree to in writing, to file a Request for Mediation of such
claim in accordance with the provisions of Article 9.0. In the event the CONTRACTOR shall fail,
for any reason, to timely file a Request for Mediation,the OWNER shall be released of any and all
liability, and the CONTRACTOR's failure to timely file a Request for Mediation shall constitute a
waiver, forfeit and fmal bar of all such claims held by the CONTRACTOR against the OWNER.
CONTRACTOR shall continue to diligently prosecute the Work notwithstanding any pending
claim, dispute, or dispute resolution process between OWNER and CONTRACTOR.
8.0 DEFAULT
8.01 DEFAULT BY CONTRACTOR. In case the CONTRACTOR should abandon
and fail or refuse to resume Work within five (5) days after written notification from the OWNER
10-1012 00700-30of36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
or the ENGINEER, or if the CONTRACTOR fails to comply with the orders of the ENGINEER
when such orders are consistent with the Contract Documents, or if the CONTRACTOR otherwise
defaults on its obligations under the Contract, OWNER shall have the right, if it so elects and
without prejudice to any other rights it may have, after giving five (5) days written notice of
default to CONTRACTOR and any surety, to terminate the Contract or any part thereof and/or to
take over or cause others to take over the Work or any part thereof, and to complete such Work for
the account of CONTRACTOR. Where Performance and Payment Bonds exist, the sureties on
these bonds shall be directed to complete the Work in conjunction with the notice of default, and a
copy of said notice shall be delivered to the CONTRACTOR.
After receiving said notice of default,the CONTRACTOR shall promptly and within no more than
three (3) days, remove from the Work any machinery, equipment, or tools then on the job, not
intended for incorporation into the Work. Should CONTRACTOR fail to promptly remove such
machinery, equipment or tools, OWNER may remove such machinery, equipment or tools and
store same at CONTRACTOR's expense; return such machinery, equipment or tools to their
purported owner; or otherwise dispose of such machinery, equipment or tools as OWNER sees fit.
Any materials, supplies and/or equipment delivered for use in the Work, may be used in the
completion of the Work by the OWNER or the surety on the Performance Bond, or another
contractor in completion of the Work; it being understood that the use of such equipment, supplies
and materials will ultimately reduce the cost to complete the Work and be reflected in the final
settlement.
Where there is no Performance Bond or in case the surety should fail to commence compliance
with the notice for completion hereinabove provided for within ten (10) days after the service of
such notice, then the OWNER may provide for completion of the Work in either of the following
elective manners:
(a) The OWNER may thereupon employ such force of workers and use such
machinery, equipment, tools, materials and supplies as the OWNER may deem
necessary to expeditiously complete the Work, and charge the expense of such
labor, machinery, equipment, tools, materials and supplies to said
CONTRACTOR, and expense so charged shall be deducted and paid by the
OWNER out of such monies as may be due or that may thereafter at any time
become due to the CONTRACTOR under and by virtue of this Agreement or any
other agreement between OWNER and CONTRACTOR. In case such expense is
less than the sum which would have been payable under this Contract if the same
had been completed by the CONTRACTOR, then said CONTRACTOR shall be
credited with the difference. In case such expense is greater than the sum which
would have been payable under this Contract if the same had been completed by
such CONTRACTOR, then the CONTRACTOR and/or his surety shall promptly
pay the amount of such excess to the OWNER upon demand; or
(b) The OWNER, under sealed bids, under the times and procedures provided for by
law, may let the contract for completion of the Work under substantially the same
terms and conditions which are provided in this Contract. In case of any increase in
cost to the OWNER under the completion contract, as compared to what would
have been the cost under this Contract, such increase shall be charged to the
Club'\ CONTRACTOR, and the amount of such increase may be deducted by the
OWNER out of such monies as may be due or that may thereafter at any time
10-1012 00700-31 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
become due to the CONTRACTOR under and by virtue of this Agreement or any
other agreement between OWNER and CONTRACTOR, or the CONTRACTOR
and/or his surety shall promptly pay the amount of such increase to the OWNER
upon demand. However, should the cost to complete any such completion contract
prove to be less than what would have been the cost to complete under this
Contract, the CONTRACTOR and/or his surety shall be credited therewith.
In the event of a default by CONTRACTOR, no further payments shall be made to
CONTRACTOR under the Contract until the Work is Finally Completed. When the Work shall
have been Finally Completed,the CONTRACTOR and his surety shall be so notified. A complete
itemized statement of the Contract accounts, certified by the ENGINEER as being correct, shall
then be prepared and delivered to the CONTRACTOR and his surety, whereupon the
CONTRACTOR and/or his surety shall pay the balance due as reflected by said statement. The
OWNER, prior to incurring an obligation to make payment hereunder, shall have such statement
of completion attested to by the CONTRACTOR and the surety as accurate, and in exchange for
payment of the sum stated therein, the OWNER shall be entitled to a full and final release of any
claims or demands by the CONTRACTOR or the surety.
In the event the statement of accounts shows that the cost to complete the work is less than that
which would have been the cost to the OWNER had the work been completed by the
CONTRACTOR under the terms of this Contract, or when the CONTRACTOR and/or his surety
shall pay the balance shown to be due by them to the OWNER, then all machinery, equipment,
tools or supplies left on the site of the Work shall be turned over to the CONTRACTOR and/or his
(0'11'N, surety. Should the cost to complete the Work exceed the Contract Price, and the CONTRACTOR
and/or his surety fail to pay the amount due the OWNER within the time designated above, and
there remains any machinery, equipment, tools, materials or supplies which are the property of
CONTRACTOR on the site of the Work, notice thereof, together with an itemized list of such
equipment and materials, shall be mailed to the CONTRACTOR and his surety at the respective
addresses designated in the Contract, provided, however, that actual written notice given in any
manner will satisfy this condition. After mailing or other giving of such notice, such property
shall be held at the risk of the CONTRACTOR and his surety, subject only to the duty of the
OWNER to exercise ordinary care to protect such property. After fifteen (15) days from the date
of such notice, the OWNER may sell such property, equipment, tools, materials or supplies, and
apply the net sum derived from such sale to the credit of the CONTRACTOR and his surety. Such
sale may be made at either public or private sale, with or without notice, as the OWNER may
elect. The OWNER shall release any machinery, equipment, tools, materials or supplies, which
remain on the Work, and belong to persons other than the CONTRACTOR or his surety, to their
reputed owners.
8.02 SUPPLEMENTATION OF CONTRACTOR FORCES. If CONTRACTOR at any
time shall, in OWNER'S sole opinion, fail to furnish skilled workers, suitable materials, supplies
or adequate equipment sufficient for the prompt, timely and diligent prosecution of the Work in
accordance with OWNER's direction, OWNER shall have the right, without prejudice to the
exercise of other remedies for the same default and without fully taking over the Work, to
supplement CONTRACTOR's forces and to expedite delivery of and to procure and furnish such
workers, materials, tools, supplies or equipment for CONTRACTOR's account by employing
other contractors and suppliers engaged in the same class of work and charge the entire cost
Calk`, thereof to CONTRACTOR, said cost to be deducted from sums due or to become due to
10-1012 00700-32 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
CONTRACTOR under the Contract or any other agreement with OWNER or any parent,
subsidiary or affiliate of OWNER.
8.03 CUMULATIVE REMEDIES & SPECIFIC PERFORMANCE. All rights and
remedies of OWNER, under the terms of the Contract and/or available at law or in equity, are
cumulative. In the event CONTRACTOR or any of its subcontractors, vendors or suppliers fails
or refuses for any reason to provide timely manufacture, fabrication, delivery, installation,
erection, construction or completion of any supplies, materials, expendables, equipment,
machinery, accessories or appurtenances to be furnished hereunder, CONTRACTOR
acknowledges and agrees that such items are required, necessary, essentially unique to the Project
and the Work and will cause irreparable harm to OWNER and the Project if not furnished in
accordance with the Contract, and OWNER shall have the right to obtain a decree of specific
performance and mandatory injunctive relief from any Court of competent jurisdiction to ensure
the timely furnishing of such items.
8.04 CROSS-DEFAULT. If, for any reason, CONTRACTOR is declared in default
and/or terminated by OWNER under any other agreement with OWNER, whether related to the
Project or not related to the Project, OWNER shall have the right to offset and apply any amounts
which might be owed to OWNER by CONTRACTOR under any other such agreements against
any earned but unpaid amounts owing to CONTRACTOR by OWNER under the Contract, any
retainage earned by CONTRACTOR under the Contract or any unearned, unpaid amount under
the Contract.
8.05 INSOLVENCY. It is recognized that if CONTRACTOR becomes a debtor in
Ca ' voluntary or involuntary bankruptcy proceedings, makes a general assignment for the benefit of
creditors, or if a receiver is appointed on account of his insolvency, such events could seriously
impair or frustrate CONTRACTOR's performance of the Work. Accordingly, it is agreed that
should CONTRACTOR become a debtor in bankruptcy, either voluntary or involuntary,
CONTRACTOR shall notify OWNER in writing within twenty-four (24) hours of the filing with
the bankruptcy court. Further, it is agreed that upon occurrence of any one or more such events,
OWNER shall be entitled to request of CONTRACTOR or its successors, trustees or receivers,
adequate assurances of future performance. In the event such adequate assurances are not given to
the reasonable satisfaction of OWNER within seventy-two (72) hours of such request, OWNER
shall have the right to immediately invoke the remedies of this Section 8 or as provided by law.
Pending receipt of such adequate assurances of such future performance, OWNER may proceed
with the Work on a temporary basis and deduct the costs, plus reasonable overhead and profit,
from any amounts due or which may become due to CONTRACTOR under the Contract or any
other agreement with OWNER. In this regard, OWNER and CONTRACTOR agree that delays in
performance could result in more damages to CONTRACTOR than would be sustained if
OWNER failed to exercise such remedies.
8.06 CONTINGENT ASSIGNMENT. CONTRACTOR hereby assigns to OWNER, all
of CONTRACTOR's rights under and interest in any and all subcontracts and/or purchase orders
entered into by CONTRACTOR pursuant to this Agreement, such assignment to become effective
upon CONTRACTOR's default under this Agreement or OWNER's termination of this Contract,
and OWNER's acceptance of such assignment. Upon CONTRACTOR's default or OWNER's
termination of this Contract, OWNER may, in the event there is no performance bond for the
Contract, or in the event the performance bond surety fails to complete the Contract, or if OWNER
otherwise so elects in its sole discretion, accept such assignment by written notice of such
10-1012 00700-33 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
acceptance to CONTRACTOR and subcontractor, and may require subcontractors to perform all
of the then unperformed duties and obligations under the subcontract, for the direct benefit of
OWNER. In the event OWNER requires such performance by a subcontractor, then OWNER
shall be obligated to pay such subcontractor any amounts due and owing under the terms of the
subcontract/purchase order, at the subcontract prices and rates, and subject to any rights of
withholding or offset and other terms and conditions of the subcontract, for all work properly
performed by such subcontractor, to the date of OWNER's acceptance and thereafter. OWNER's
liability in this connection, however, shall not exceed the amount obtained by subtracting all
payments made by CONTRACTOR to subcontractor from the Subcontract Price at the time of
CONTRACTOR's default or OWNER's termination of CONTRACTOR. CONTRACTOR shall
include a provision in its subcontracts that allows such assignment and allows OWNER to take
these actions, and further provides that in the event of CONTRACTOR's termination for default,
the subcontractor agrees to give the OWNER or its agent the right to inspect all books and records
of subcontractor relating to the Work.
8.07 WAIVER OF CONSEQUENTIAL DAMAGES. CONTRACTOR expressly
waives any and all claims for consequential damages against OWNER arising out of or related to
this Contract, or any other agreements between CONTRACTOR and OWNER, including,but not
limited to, claims for damages incurred by CONTRACTOR for principal office expenses,
including the compensation of personnel stationed there, losses of financing, bonding capacity,
business and reputation, and claims for lost profit,whether on this Contract or otherwise.
8.08 TERMINATION FOR CONVENIENCE. OWNER may at its sole discretion,
upon five (5) days written notice to CONTRACTOR, terminate this Contract, in whole or in part,
if and when OWNER determines that it is in the best interest of OWNER to do so. Upon receipt
of such written notice from OWNER, CONTRACTOR shall cease all terminated Work and take
reasonable precautions to protect and preserve such work, and shall take all reasonable measures
after consultation with OWNER to terminate or assign to OWNER all subcontracts, purchase
orders or other commitments related to the Work or the Project on terms and conditions acceptable
to OWNER. CONTRACTOR will be paid for all Work performed in strict accordance with the
Contract Documents, based upon the Contract Price and the percentage of completion on the date
of termination, and less amounts previously paid, subject to any reasonable backcharges
attributable to CONTRACTOR's failure to comply with any of the provisions of this Contract and
further subject to the other terms of this Contract regarding payment. In no event will
CONTRACTOR receive or be entitled to any payment or compensation whatsoever for
interruption of business or loss of business opportunities, any other items of consequential
damages, for overhead or loss of profits on the unperformed Work and/or services and unfurnished
materials or for any intangible, impact or similarly described cost, damages or expense, and under
no circumstances shall the total sum paid to or received by CONTRACTOR under this Contract
exceed the Contract Price. The compensation provided herein shall be CONTRACTOR's sole and
exclusive remedy arising out of a termination for convenience.
8.09 DEFAULT BY OWNER. In case the OWNER shall default on its material
obligations under this Contract, other than OWNER's failure to pay CONTRACTOR a disputed
amount due within the time limits provided in the Contract or applicable law, as addressed by
Section 6.13 of this Agreement, and shall fail or refuse to cure, or to commence and diligently
pursue cure of such default within fifteen (15) days after written notification by the
CONTRACTOR,.then the CONTRACTOR may suspend or wholly abandon the Work, and may
remove therefrom all machinery, tools and equipment, and all materials on the site of the Work
10-1012 00700-34 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
that have not been included in payments to the CONTRACTOR and have not been incorporated
into the Work. And thereupon, the ENGINEER shall make an estimate of the total amount earned
by the CONTRACTOR, which estimate shall include the value of all Work actually completed by
said CONTRACTOR (at the Contract Prices), the value of all partially completed Work at a fair
and equitable price, and the amount of all Extra Work performed at the prices agreed upon, or
provided for by the terms of this Contract, and a reasonable sum to cover the cost of any
provisions made by the CONTRACTOR to carry the whole Work to completion and which cannot
be utilized. The ENGINEER shall then make a final statement of the balance due the
CONTRACTOR by deducting from the above estimate all previous payments by the OWNER and
all other sums that may be retained by the OWNER under the terms of this Agreement, and shall
present the same to the OWNER, and OWNER's payment of said sum to the CONTRACTOR, on
or before thirty (30) days after OWNER's receipt of such statement, shall satisfy any and all
rights, claims or causes of action of CONTRACTOR arising out of or related to such default by
OWNER, and shall be CONTRACTOR's sole and exclusive remedy for such default. A disputed
or unilateral claim by the Contractor cannot by itself constitute a default hereunder.
9.0 DISPUTE RESOLUTION
Any dispute or pending claim or dispute resolution process between OWNER and
CONTRACTOR shall not excuse or relieve CONTRACTOR of its obligations under the Contract,
and CONTRACTOR shall diligently prosecute the Work notwithstanding any pending claim,
dispute,or dispute resolution process'between OWNER and CONTRACTOR.
(1.6.\
All claims, disputes and other matters in question arising out of or relating to, the Contract,
or the breach thereof, shall be subject to mediation as a condition precedent to any other dispute
resolution process as may be selected by OWNER. Unless mutually agreed otherwise the
mediation shall be conducted by a third party who will be selected by agreement between
OWNER and CONTRACTOR, and Request for Mediation shall be filed with the other party. The
parties shall share the mediator's fee and any filing fees equally.
If a claim, dispute or other matter in question between OWNER and CONTRACTOR
involves the work of a subcontractor or supplier, OWNER or CONTRACTOR may join such
subcontractor or supplier as a party to any mediation proceeding between OWNER and
CONTRACTOR hereunder. CONTRACTOR shall include in all subcontracts and/or purchase
orders related to the Work a specific provision whereby the subcontractor or supplier consents to
being joined in mediation between OWNER and CONTRACTOR involving the work of such
subcontractor or supplier.
This Contract shall be governed by the laws of the State of Texas and shall be considered
performable in Brazoria County, Texas, for venue purposes. Further, the OWNER and
CONTRACTOR stipulate that venue for any dispute resolution proceeding involving or touching
upon the Contract other than the conduct of an arbitration hearing shall be in Brazoria County,
Texas, or, if such choice of venue is prohibited or unenforceable by law, shall be held in the
county where the Project is located.
CONTRACTOR agrees to pay OWNER all reasonable attorneys' fees incurred by
OWNER in the event OWNER seeks to enforce any provision of this Contract whether by
arbitration or other dispute resolution process. Further, in the event OWNER defends any claim
instituted by CONTRACTOR against OWNER, whether in arbitration or other dispute resolution
10-1012 00700-35 of 36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Clua
process, CONTRACTOR agrees to pay OWNER all reasonable attorneys' fees incurred by
OWNER in defending such claim provided OWNER is the prevailing party, in whole or in part,in
such proceeding.
CI's\
10-1012 00700 36 of36
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
("'\ ATTACHMENT NO. 1 TO GENERAL CONDITIONS
WORKERS' COMPENSATION INSURANCE COVERAGE
A. DEFINITIONS:
Certificate of coverage ("certificate") . A copy of a certificate of insurance, a
certificate of authority to self-insure issued by the commission, or a coverage
agreement (TWCC81, TWCC-82, TWCC-83 or TWCC-84), showing statutory
workers' compensation insurance coverage for the person's or entity's employees
providing services on a project for the duration of the Project.
Duration of the Project includes the time from the beginning of the Work on the
Project until the contractor's/person's work on the Project has been completed and
the Project warranty period has expired.
Persons providing services on the project includes persons or entities performing
all or part of the services the contractor has undertaken to perform on the project,
regardless of whether that person contracted directly with due contractor and
regardless of whether that person has employees. This includes, without
limitation, independent contractors, subcontractors, motor carriers and owner-
operators, (as defined at Section 406.121 of the Texas Labor Code), leasing
companies, and employees of any such entity, or employees of any entity which
furnishes persons to provide services on the project. "Services" include, without
limitation, providing, hauling, or delivering equipment or materials, or providing
labor, transportation, or other service related to a project. "Services" does not
include activities unrelated to the project, such as food/beverage vendors, office
supply deliveries, and delivery of portable toilets.
B. The CONTRACTOR shall provide coverage, based on proper reporting of classification
codes and payroll amounts and filing of any coverage agreements, which meets the
statutory requirements of Texas Labor Code, Title 5 Workers' Compensation, Subtitle A
Texas Workers' Compensation Act, for employees of the contractor providing services on
the project, for the duration of the project.
C. The CONTRACTOR must provide a certificate of coverage to the OWNER prior to being
awarded the Contract.
D. If the coverage period shown on the CONTRACTOR's current certificate of coverage
ends during the duration of the project, the CONTRACTOR must, prior to the end of the
coverage period, file a new certificate of coverage with the OWNER showing that
coverage has been extended.
E. The CONTRACTOR shall obtain from each subcontractor or other person providing
services on a project, and provide to the OWNER:
(I) a certificate of coverage, prior to that person beginning work on the Project, so the
Club' OWNER will have on file certificates of coverage showing coverage for all
persons providing services on the Project; and
05/2007 00700-Al
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(2) no later than seven days after receipt by the CONTRACTOR and prior to the end
of the coverage period, a new certificate of coverage showing extension of
coverage, if the coverage period shown on the current certificate of coverage ends
during the duration of the Project.
F. The CONTRACTOR shall retain all required certificates of coverage for the duration of
the Project and for one year thereafter.
G. The CONTRACTOR shall notify the OWNER in writing by certified mail or personal
delivery, within 10 days after the CONTRACTOR knew or should have known, of any
changes that materially affect the provision of coverage of any person providing services
on the Project.
H. The CONTRACTOR shall post on each Project site a notice, in the text, form and manner
prescribed by the Texas Workers' Compensation Commission, informing all persons
providing services on the Project that they are required to be covered, and stating how a
person may verify coverage and report lack of coverage.
NOTICE
REQUIRED WORKERS' COMPENSATION COVERAGE
"The law requires that each person working on this site or providing
services related to this construction project must, be covered by
workers' compensation insurance. This includes persons providing,
hauling, or delivering equipment or materials, or providing labor or
transportation or other service related to the project, regardless of
the identity of their employer or status as an employee."
"Call the Texas Workers' Compensation Commission at (512) 440-
3789 to receive information on the legal requirements for coverage,
to verify whether your employer has provided the required coverage,
or to report an employer's failure to provide coverage."
The CONTRACTOR shall contractually require each person with whom it contracts to
provide services on a project, too:
(1) provide coverage, based on proper reporting of classification codes and payroll
amounts and filing of any coverage agreements, which meets the statutory
requirements of Texas Labor Code, Title 5 Workers' Compensation, Subtitle A
Texas Workers' Compensation Act, for all of its employees providing services on
the Project, for the duration of the Project;
(2) provide to the CONTRACTOR,prior to that person beginning work on the
Project, a certificate of coverage showing that coverage is being provided for all
employees of the person providing services on the project, for the duration of the
7`, Project:
05/2007 00700-A2
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
(3) provide the CONTRACTOR,prior to the end of the coverage period, a new
certificate of coverage, showing extension of coverage, if the coverage period
shown on the current certificate of coverage ends during the duration of the
Project;
(4) obtain from each other person with whom it contracts, and provide to the
CONTRACTOR:
(a) a certificate of coverage,prior to the other person beginning work on the
Project; and
(b) a new certificate of coverage showing extension of coverage,prior to the
end of the coverage period, if the coverage period shown on the current
certificate of coverage ends during the duration of the Project;
(5) retain all required certificates of coverage on file for the duration of the Project
and for one year thereafter;
(6) notify the OWNER in writing by certified mail or personal delivery, within 10 days
after the person knew or should have known,of any change that materially affects
the provision of coverage of any person providing services on the Project; and
(7) contractually require each person with whom it contracts,to perform as required by
paragraphs(1) - (7),with the certificates of coverage to be provided to the person
for whom they are providing services.
J. By signing this Contract or providing or causing to be provided a certificate of coverage,
the CONTRACTOR is representing to the OWNER that all employees of the
CONTRACTOR who will provide services on the Project will be covered by workers'
compensation coverage for the duration of the Project, that the coverage agreements will
be based on proper reporting of classification codes and payroll amounts, and that all
coverage agreements will be filed with the appropriate insurance carrier or, in the case of a
self-insured, with the commission's Division of Self-Insurance Regulation. Providing false
or misleading information may subject the CONTRACTOR to administrative penalties,
criminal penalties, civil penalties, or other civil actions.
K. The CONTRACTOR's failure to comply with any of these provisions is a breach of
contract by the CONTRACTOR, which entitles the OWNER to pursue all rights and
remedies available to it under the Contract,at law or in equity, if the CONTRACTOR does
not remedy the breach within ten days after receipt of notice of breach from the OWNER.
05/2007 00700-A3
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
ATTACHMENT NO.2 TO GENERAL CONDITIONS •
AGREEMENT FOR FINAL PAYMENT
AND CONTRACTOR'S SWORN RELEASE
In consideration of the Final Payment under that certain contract between [Contractor's
Company Name] (hereafter "CONTRACTOR") and the City of Pearland (hereafter "OWNER")
for the Project known as [Official Project Title] (the "Contract"), the CONTRACTOR makes the
following representations to OWNER, either individually if a proprietorship, or jointly and
severally by all general partners if a partnership, or if a corporation, by action of the president and
secretary of said corporation, as duly authorized by appropriate action of the stockholders and/or
board of directors of said corporation, their signatures hereon constituting a representation under
oath by said individuals that they have the authority to execute this Agreement for and on behalf
of the said corporation:
1. The undersigned CONTRACTOR represents to OWNER that the Application for
Payment for the Final Payment under the Contract, and the final Change Order
issued under the Contract if any, whether or not modified, corrected or changed in
some way by the ENGINEER, the CONTRACTOR or the OWNER, a copy of
which are attached hereto and marked Exhibit "A", are true, correct and accurate,
and that CONTRACTOR has received payment in full for all other Applications for
Payment submitted under the Contract, and that CONTRACTOR has been fully
compensated for all labor, materials, equipment and/or services furnished in
connection with the Contract, except for the Final Payment.
2. It is agreed and stipulated by the undersigned CONTRACTOR that upon the
receipt of Final Payment in the amount as set out on the attached Application for
Payment, the CONTRACTOR, by execution of this instrument of release, does,
therefore, RELEASE and FOREVER DISCHARGE OWNER of and from all
manner of debts, claims, demands, obligations, suits, liabilities and causes of action
of any nature whatsoever, at law or in equity, in contract or in tort, now existing or
which may hereafter accrue, arising out of or related to the Contract, any Change
Orders or Work Orders, the Work, or any labor, materials, equipment or services
furnished by CONTRACTOR to OWNER.
3. The CONTRACTOR, acting by and through the person or persons whose names
are subscribed hereto, does solemnly swear and affirm that all bills and claims have
been paid to all materialmen, suppliers, laborers, subcontractors, or other entities
performing services or supplying materials or equipment, and that OWNER shall
not be subject to any bills, claims, demands, litigation or suits in connection
therewith.
4. It is further specifically understood and agreed that this Agreement for Final
Payment and Contractor's Sworn Release shall constitute a part of the Contract, and
it is also specifically understood and agreed that this Agreement shall not act as a
modification, waiver or renunciation by OWNER of any of its rights or remedies as
set out in the Contract itself, but this Agreement for Final Payment and
Contractor's Sworn Release shall constitute a supplement thereto for the additional
protection of OWNER.
05/2007 00700-B 1
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
r
SIGNED and EXECUTED this,the day of , 20 .
CONTRACTOR:
By:
Signature
Print Name:
Title:
[If CONTRACTOR is a proprietorship, owner must sign; if a partnership, each general partner
must sign; if a corporation, the following language should be used.]
SIGNED and EXECUTED this,the day of
20 by , a Texas corporation,under authority
granted to the undersigned by said corporation as contained in the Charter, By-Laws or Minutes of
a meeting of said corporation regularly called and held.
CONTRACTOR:
By:
President
ATTEST:
Corporate Secretary
(Corporate Seal)
[This form is for use by either a proprietorship or a partnership. In the event CONTRACTOR is a
partnership or a joint proprietorship,additional signature lines should be added for each
individual.]
(111
05/2007 00700-B2
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
AFFIDAVIT
STATE OF TEXAS §
COUNTY OF §
BEFORE ME,the undersigned authority, on this day personally appeared the person or
persons whose name(s) are subscribed to the above and foregoing Agreement for Final Payment
and Contractor's Sworn Release,who each, after being by me duly sworn, on their oaths deposed
and said:
I(We) am(are)the person(s)who signed and executed the above and foregoing
Agreement for Final Payment and Contractor's Sworn Release, and I(we)have read the
facts and statements as therein set out and the representations as made therein, and I(we)
state that the above and foregoing are true and correct.
CONTRACTOR-Affiant
SWORN TO AND SUBSCRIBED TO before me,the day of 20_.
Notary Public, State of Texas
My Commission Expires:
[This form is for use in the event CONTRACTOR is a corporation.]
07/2006 00700-B3
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
AFFIDAVIT
STATE OF TEXAS §
COUNTY OF §
BEFORE ME,the undersigned authority, on this day personally appeared the persons
who signed and executed the above and foregoing Agreement for Final Payment mid Contractor's
Sworn Release,whose names are set out above,who each, after being by me duly sworn, on their
oaths deposed and said:
We each are the persons whose names are subscribed above, and hold respectively the
offices in the corporation as set out above, and each state under oath that we have the
authority to execute this Agreement for Final Payment and Contractor's Sworn Release
for and on behalf of said corporation,pursuant to authority granted to us in the Charter of
said corporation,the By-Laws of said corporation and/or the Minutes of said corporation;
and the facts, statements and representations as set out in the instrument to which this
Affidavit is attached, are true and correct.
SWORN TO AND SUBSCRIBED TO before me this,the day of
20
Notary Public, State of Texas
(1.1h\
My Commission Expires:
07/2006 00700-B4
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
ATTACHMENT NO.3 TO GENERAL CONDITIONS
OWNER'S INSURANCE REQUIREMENTS OF CONTRACTOR
1. Definitions. For purposes of this Agreement:
1.1 Owner Parties. "Owner Parties" means (a) the City of Pearland, its successors and
assigns, and the Engineer, (b) any officers, employees, or agents of such persons or
entities, and(c)others as required by the Contract Documents, if any.
1.2 Contractor. "Contractor" shall mean the vendor providing the service or work to be
performed under this Agreement.
1.3 Subcontractor. "Subcontractor"shall include subcontractors of any tier.
1.4 ISO. "ISO"means Insurance Services Office.
2. Contractor Insurance Representations to Owner Parties
2.1 It is expressly understood and agreed that the insurance coverages required herein:
2.1.1 represent Owner Parties' minimum requirements and are not to be
construed to void or limit the Contractor's indemnity obligations as contained in
this Agreement nor represent in any manner a determination of the insurance
coverages the Contractor should or should not maintain for its own protection; and
2.1.2 are being, or have been, obtained by the Contractor in support of the
Contractor's liability and indemnity obligations under this Agreement. Neither the
requirements as to insurance to be carried as provided for herein, the insolvency,
bankruptcy or failure of any insurance company carrying insurance of the
Contractor, nor the failure of any insurance company to pay claims accruing, shall
be held to affect,negate or waive any of the provisions of this Agreement.
2.2 Failure to obtain and maintain the required insurance shall constitute a material
breach of, and default under, this Agreement. If the Contractor shall fail to remedy
such breach within five (5)business days after notice by the Owner, the Contractor
will be liable for any and all costs, liabilities, damages and penalties resulting to the
Owner Parties from such breach, unless a written waiver of the specific insurance
requirement(s) is provided to the Contractor by the Owner. In the event of any
failure by the Contractor to comply with the provisions of this Agreement, the
Owner may, without in any way compromising or waiving any right or remedy at
law or in equity, on notice to the Contractor, purchase such insurance, at the
Contractor's expense, provided that the Owner shall have no obligation to do so
and if the Owner shall do so, the Contractor shall not be relieved of or excused
from the obligation to obtain and maintain such insurance amounts and coverages.
10-2012 00700-Cl
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
3. Conditions Affecting All Insurance Required Herein
3.1 Cost of Insurance. All insurance coverage shall be provided at the Contractor's
sole expense.
3.2 Status and Rating of Insurance Company. All insurance coverage shall be written
through insurance companies authorized to do business in the state in which the
work is to be performed and rated no less than A-: VII in the most current edition
of A. M. Best's Key Rating Guide.
3.3 Restrictive, Limiting, or Exclusionary Endorsements. All insurance coverage shall
be provided to the Owner Parties in compliance with the requirements herein and
shall contain no endorsements that restrict, limit, or exclude coverage required
herein in any manner without the prior express written approval of the Owner.
3.4 Limits of Liability. The limits of liability may be provided by a single policy of
insurance or by a combination of primary and umbrella policies, but in no event
shall the total limits of liability available for any one occurrence or accident be less
than the amount required herein.
3.5 Notice of Cancellation, Nonrenewal, or Material Reduction in Coverage. All
insurance coverage shall contain the following express provision:
In the event of cancellation, non-renewal, or material reduction in
coverage affecting the certificate holder, thirty (30) days prior
written notice shall be given to the certificate holder by certified
mail or registered mail,return receipt requested.
3.6 Waiver of Subrogation. The Contractor hereby agrees to waive its rights of
recovery from the Owner Parties with regard to all causes of property and/or
liability loss and shall cause a waiver of subrogation endorsement to be provided in
favor of the Owner Parties on all insurance coverage carried by the Contractor,
whether required herein or not.
3.7 Deductible/Retention. Except as otherwise specified herein, no insurance required
herein shall contain a deductible or self-insured retention in excess of $25,000
without prior written approval of the Owner. All deductibles and/or retentions shall
be paid by, assumed by, for the account of, and at the Contractor's sole risk. The
Contractor shall not be reimbursed for same.
4. Maintenance of Insurance. The following insurance shall be maintained in effect
with limits not less than those set forth below at all times during the term of this
Agreement and thereafter as required:
10-2012 00700-C2
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Club 4.1 Commercial General Liability Insurance
4.1.1 Coverage. Such insurance shall cover liability arising out of all locations
and operations of the Contractor, including but not limited to liability
assumed under this contract (including the tort liability of another assumed
in a business contract). Defense shall be provided as an additional benefit
and not included within the limit of liability.
4.1.2 Form. Commercial General Liability Occurrence form (at least as broad as
an unmodified ISO CG 0001 0798 or its equivalent).
4.1.3 Amount of Insurance. Coverage shall be provided with limits of not less
than:
Each Occurrence Limit $1,000,000
General Aggregate Limit $2,000,000
Product-Completed Operations Aggregate Limit $2,000,000
Personal and Advertising Injury Limit $1,000,000
4.1.4 Required Endorsements
a. Additional Insured. Additional insured status shall be provided in
favor of the Owner Parties on any of the following:
i. ISO form CG 20 10 11 85; or
ii. ISO form CG 20 26 11 85; or
iii. a combination of ISO forms CG 20 33 10 01 and CG 20 37
10 01; or
iv. any form providing equivalent protection to Owner.
b. Designated Construction Project(s) Aggregate Limit. The aggregate
limit shall apply separately to this Agreement through use of an ISO
CG 25 03 03 97 endorsement or its equivalent.
c. Notice of Cancellation, Nonrenewal or Material Reduction in
Coverage, as required in 3.5, above.
d. Personal Injury Liability. The personal injury contractual liability
exclusion shall be deleted.
e. Primary and Non-Contributing Liability. It is the intent of the
parties to this Agreement that all insurance required herein shall be
primary to all insurance available to the Owner Parties. The
obligations of the Contractor's insurance shall not be affected by
any other insurance available to the Owner Parties and shall seek no
contribution from the Owner Parties' insurance, whether primary,
excess contingent, or on any other basis. The Contractor's insurance
coverage shall be endorsed to provide such primary and non-
contributing liability.
f. Waiver of Subrogation, as required in 3.6, above.
10-2012 00700-C3
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
4.1.5 Continuing Commercial General Liability Insurance. The Contractor shall
maintain such insurance in identical coverage, form and amount, including
required endorsements, for at least one (1) year following Date of
Substantial Completion of the Work to be performed under this Agreement.
The Contractor shall provide written representation to Owner stating Work
completion date.
4.2 Auto Liability Insurance
4.2.1 Coverage. Such insurance shall cover liability arising out of any auto
(including owned,hired, and non-owned).
4.2.2 Form. Business Auto form (at least as broad as an unmodified ISO CA
0001 or its equivalent).
4.2.3 Amount of Insurance. Coverage shall be provided with a limit of not less
than$1,000,000.
4.2.4 Required Endorsements
a. Notice of Cancellation, Nonrenewal or Material Reduction in
Coverage, as required in 3.5, above.
b. Waiver of Subrogation, as required in 3.6, above.
4.3 Employer's Liability Insurance
4.3.1 Coverage. Employer's Liability Insurance shall be provided as follows:
4.3.2 Amount of Insurance. Coverage shall be provided with a limit of not less
than:
Employer's Liability: $1,000,000 each accident and each disease.
4.3.3 Required Endorsements
a. Notice of Cancellation, Nonrenewal or Material Reduction in
Coverage, as required in 3.5, above.
b. Waiver of Subrogation,as required in 3.6, above.
4.4 Umbrella Liability Insurance
4.4.1 Coverage. Such insurance shall be excess over and be no less broad than all
coverages described above and shall include a drop-down provision for
exhaustion of underlying limits.
4.4.2 Form. This policy shall have the same inception and expiration dates as the
commercial general liability insurance required above.
10-2012 00700-C4
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
4.4.3 Amount of Insurance. Coverage shall be provided with a limit of not less
than$5,000,000.
4.4.4 Continuing Umbrella Liability Insurance. The Contractor shall maintain
such insurance in identical coverage, form and amount, including required
endorsements, for at least one (1) year following Date of Substantial
Completion of the Work to be performed under this Agreement. The
Contractor shall provide written representation to the Owner stating Work
completion date.
4.5 Professional Liability Insurance
4.5.1 Coverage. The Contractor shall provide professional liability insurance for
any professional design or engineering drawing required by the work. Such
insurance shall indemnify the Owner from claims arising from the negligent
performance of professional services of any type, including but not limited
to design or design/build services as part of the Work to be performed.
4.5.2 Form. This insurance shall include prior acts coverage sufficient to cover
all services rendered by the Contractor and by its consultants under this
Agreement. It is recognized that this coverage may be provided on a
Claims-Made basis.
4.5.3 Amount of Insurance. Coverage shall be provided with a limit of not less
than$1,000,000.
4.5.4 Continuing Professional Liability Insurance. The Contractor shall maintain
such insurance in identical coverage, form and amount for at least one (1)
year following Date of Substantial Completion of the Work to be performed
under this Agreement. The Contractor shall provide written representation
to the Owner stating Work completion date.
4.6 Builder's Risk
4.6.1 Insureds. Insureds shall include:
a. Owner, General Contactor and all Loss Payees and Mortgagees as
Named Insureds; and
b. subcontractors of all tiers in the Work as Additional Insureds.
10-2012 00700-C5
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
CIL\
4.6.2 Covered Property. Such insurance shall cover:
a. all structure(s) under construction, including retaining walls, paved
surfaces and roadways, bridges, glass, foundation(s), footings,
underground pipes and wiring, excavations, grading, backfilling or
filling;
b. all temporary structures (e.g., fencing, scaffolding, cribbing, false
work, forms, site lighting, temporary utilities and buildings) located
at the site;
c. all property including materials and supplies on site for installation;
d. all property including materials and supplies at other locations but
intended for use at the site;
e. all property including materials and supplies in transit to the site for
installation by all means of transportation other than ocean transit;
and
f. other Work at the site identified in the Agreement to which this
Exhibit is attached.
Form
a. Coverage shall be at least as broad as an unmodified ISO Special
form, shall be provided on a completed-value basis, and shall be
primary to any other coverage insurance available to the insured
parties, with that other insurance being excess, secondary and non-
contributing.
b. No protective safeguard warranty shall be permitted.
c. Required coverage shall further include:
i. Additional expenses due to delay in $TBD
completion of project(where applicable)
ii. Agreed value Included without sublimit
iii. Damage arising from error, omission or Included without sublimit
deficiency in construction methods,
design, specifications,workmanship or
materials, including collapse
iv. Debris removal additional limit 25%of direct damage
loss
v. Earthquake(where applicable) $TBD
vi. Earthquake sprinkler leakage(where $ TBD
applicable)
vii. Expediting expenses $TBD
viii. Flood(where applicable) $TBD
ix. Freezing Included without sublimit
x. Mechanical breakdown, including hot& Included without sublimit
cold testing(where applicable)
xi. Notice of cancellation,non-renewal or Included
10-2012 00700-C6
CITY OFPEARLAND GENERAL CONDITIONS OF AGREEMENT
(11.4\ material reduction—60 days prior
written notice to each insured
xii. Occupancy clause,as required in F, Included
below
xiii. Ordinance or law Included without sublimit
xiv. Pollutant clean-up and removal $TBD
xv. Preservation of property Included without sublimit
xvi. Replacement cost Included
xvii. Theft Included without sublimit
xviii. Waiver of subrogation as required in G, Included
below.
4.6.3 Amount of Insurance. Coverage shall be provided in an amount equal at all
times to the full replacement value and cost of debris removal for any single
occurrence.
4.6.4 Deductibles. Deductibles shall not exceed the following:
a. All Risks of Direct Damage,Per $5,000
Occurrence, except
b. Delayed Opening Waiting Period 5 Days
c. Flood,Per Occurrence $25,000 or excess of
NFIP if in Flood Zone A,
B or V
d. Earthquake and Earthquake Sprinkler $25,000
Leakage, Per Occurrence
4.6.5 Termination of Coverage. The termination of coverage provision shall be
endorsed to permit occupancy of the covered property being constructed so
long as such occupancy does not exceed 20% of the usable area of the
property. This insurance shall be maintained in effect, unless otherwise
provided for in the Contract Documents, until the earliest of the following
dates:
a. the date on which all persons and organizations who are insureds
under the policy agree that it shall be terminated;
b. the date on which final payment, as provided for in the Agreement
to which this Exhibit is attached,has been made; or
c. the date on which the insurable interests in the Covered Property of
all insureds other than Contractor have ceased.
(11.1k\
10-2012 00700-C7
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
Cub's
4.6.6 Waiver of Subrogation. The waiver of g subrogation provision shall be
endorsed as follows:
a. A waiver of subrogation shall be provided in favor of all insureds.
b. The waiver of subrogation provisions shall be endorsed as follows:
Should a covered loss be subrogated, either in whole
or in part, your rights to any recovery will come first,
and we will be entitled to a recovery only after you
have been fully compensated for the loss.
5. Intentionally left blank.
6. Evidence of Insurance
6.1 Provision of Evidence. Evidence of the insurance coverage required to be
maintained by the Contractor, represented by certificates of insurance, evidence of
insurance, and endorsements issued by the insurance company or its legal agent,
and must be furnished to the Owner prior to commencement of Work and not later
than fifteen (15) days after receipt of this Agreement. New certificates of
insurance, evidence of insurance, and endorsements shall be provided to the Owner
prior to the termination date of the current certificates of insurance, evidence of
insurance, and endorsements.
6.2 Form
6.2.1 All property insurance required herein shall be evidenced by ACORD form
28, "Evidence of Property Insurance".
6.2.2 All liability insurance required herein shall be evidenced by ACORD form
25, "Certificate of Insurance".
6.3 Specifications. Such certificates of insurance, evidence of insurance, and
endorsements shall specify:
6.3.1 The Owner as a certificate holder with correct mailing address.
6.3.2 Insured's name,which must match that on this Agreement.
6.3.3 Insurance companies affording each coverage, policy number of each
coverage, policy dates of each coverage, all coverages and limits described
herein, and signature of authorized representative of insurance company.
6.3.4 Producer of the certificate with correct address and phone number listed.
6.3.5 Additional insured status required herein.
6.3.6 Amount of any deductibles and/or retentions.
6.3.7 Cancellation, non-renewal and material reduction in coverage notification
as required by this Agreement. Additionally, the words "endeavor to" and
"but failure to mail such notice shall impose no obligation or liability of any
kind upon Company, it agents or representatives" shall be deleted from the
cancellation provision of the ACORD 25 certificate of insurance form.
10-2012 00700-C8
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
6.3.8 Designated Construction Project Aggregate Limits required herein.
6.3.9 Personal Injury contractual liability required herein.
6.3.10 Primary and non-contributing status required herein.
6.3.11 Waivers of subrogation required herein.
6.4 Required Endorsements. A copy of each of the required endorsements shall also be
provided.
6.5 Failure to Obtain. Failure of any Owner Party to demand such certificate or other
evidence of full compliance with these insurance requirements or failure of any
Owner Party to identify a deficiency from evidence that is provided shall not be
construed as a waiver of the Contractor's obligation to maintain such insurance.
6.6 Certified Copies. Upon request of any Owner Party, the Contractor shall provide to
the Owner a certified copy of all insurance policies required herein within ten (10)
days of any such request. Renewal policies, if necessary, shall be delivered to the
Owner prior to the expiration of the previous policy.
6.7 Commencement of Work. Commencement of Work without provision of the
required certificate of insurance, evidence of insurance and/or required
endorsements, or without compliance with any other provision of this Agreement,
shall not constitute a waiver by any Owner Party of any rights. The Owner shall
have the right, but not the obligation, of prohibiting the Contractor or any
subcontractor from performing any Work until such certificate of insurance,
evidence of insurance and/or required endorsements are received and approved by
the Owner.
7. Insurance Requirements of Contractor's Subcontractors
7.1 Insurance similar to that required of the Contractor shall be provided by all
subcontractors (or provided by the Contractor on behalf of subcontractors) to cover
operations performed under any subcontract agreement. The Contractor shall be
held responsible for any modification in these insurance requirements as they apply
to subcontractors. The Contractor shall maintain certificates of insurance from all
subcontractors containing provisions similar to those listed herein (modified to
recognize that the certificate is from subcontractor) enumerating, among other
things, the waivers of subrogation, additional insured status, and primary liability
as required herein, and make them available to the Owner upon request.
7.2 The Contractor is fully responsible for loss and damage to its property on the site,
including tools and equipment, and shall take necessary precautions to prevent
damage to or vandalism, theft, burglary, pilferage and unexplained disappearance
of property. Any insurance covering the Contractor's or its subcontractor's property
shall be the Contractor's and its subcontractor's sole and complete means or
recovery for any such loss. To the extent any loss is not covered by said insurance
or subject to any deductible or co-insurance, the Contractor shall not be reimbursed
for same. Should the Contractor or its subcontractors choose to self insure this risk,
it is expressly agreed that the Contractor hereby waives, and shall cause its
10-2012 00700-C9
CITY OF PEARLAND GENERAL CONDITIONS OF AGREEMENT
subcontractors to waive, any claim for damage or loss to said property in favor of
the Owner Parties.
8. Use of the Owner's Equipment. The Contractor, its agents, employees, subcontractors or
suppliers shall use the Owner's equipment only with express written permission of the
Owner's designated representative and in accordance with the Owner's terms and
condition for such use. If the Contractor or any of its agents, employees, subcontractors or
suppliers utilize any of the Owner's equipment for any purpose, including machinery,
tools, scaffolding, hoists, lifts or similar items owned, leased or under the control of the
Owner, the Contractor shall defend, indemnify and be liable to the Owner Parties for any
and all loss or damage which may arise from such use.
9. Release and Waiver. The Contractor hereby releases, and shall cause its subcontractors to
release, the Owner Parties from any and all claims or causes of action whatsoever which
the Contractor and/or its subcontractors might otherwise now or hereafter possess resulting
in or from or in any way connected with any loss covered by insurance, whether required
herein or not, or which should have been covered by insurance required herein, including
the deductible and/or uninsured portion thereof, maintained and/or required to be
maintained by the Contractor and/or its subcontractors pursuant to this Agreement.
10-2012 00700-C 10
CITY OF PEARLAND SPECIAL CONDITIONS OF AGREEMENT
Clibk\
Section 00800
SPECIAL CONDITIONS OF AGREEMENT
The following Special Conditions modify the General Conditions, Document 00700. Where a
portion of the General Conditions is modified or deleted by these Special Conditions, the unaltered
portions of the General Conditions shall remain in effect.
ARTICLE 1 DEFINITIONS AND INTERPRETATIONS
1.01 Add the following paragraph to the end of Article 1.01:
The OWNER'S representative on the project site is:
Cara Davis telephone: 281. 652. 1642
The CONSTRUCTION MANAGER is: Curtis Villarreal,P.E.telephone: 713.953.5120
The CONSTRUCTION INSPECTOR is: telephone:
ARTICLE 4 RIGHTS AND RESPONSIBILITIES OF THE CONTRACTOR
4.05 Add the following paragraph to Article 4.05:
A Maintenance Bond in accordance with Document 00612 of the Project Manual is required for
this Project. The cost of this bond shall be included in the CONTRACTOR'S Bid Proposal.
Attachment No.3 To General Conditions, Owner's Insurance Requirements of Contractor,
Article 4.6 Builder's Risk—Builder's Risk Insurance is NOT Required for this project.
ARTICLE 5 PROSECUTION AND PROGRESS
5.08 Add Article 5.08:
The Contract Time as defined in the bid and other sections of the Contract Documents includes a
certain number of rain days. Based on the Alvin Weather Center Records, the average annual rain
days from June 1898 to December 1996 is 40 days calculated from all precipitation days of record.
The CONTRACTOR is required to keep a record of rain days at the site. The record of rain days
must be accepted and signed by the City Inspector monthly, and shall be reported on the monthly
pay estimate submittal. At the end of the contract, the CONTRACTOR will be credited only for
the number of accepted rain days that exceed 40 rain days per year,proportionate to the original
Contract Time.
General Notes:
Sections 00100 Invitation to Bidders,00200 Instructions to Bidders and 01505 Mobilization
all make reference to provision by the CONTRACTOR of a laptop computer for use by the
(11.b\ OWNER'S representative or CONSTRUCTION MANAGER. BIDDER is Required to provide
2-24-12 00800- 1 of 2
CITY OF PEARLAND SPECIAL CONDITIONS OF AGREEMENT
this equipment or include this cost in the Bid. See Section 13730 for full details regarding this
computer equipment.
Section 01500 Temporary Facilities requires CONTRACTOR to provide high speed internet
access in the Field Office. BIDDER is Requiredto provide either a Field Office or any internet
access for this project. All other requirements remain and will be required per the section.
It is the responsibility of the Contractor to coordinate with the Owner for all Traffic Control
Documents.Contractor to coordinate with the Owner for procurement of Traffic Control Documents
prior to permitting. Contractor is to keep a minimum of one lane open at all times,in both directions.
No lane closures to extend beyond the defined work day.
Contractor Will be required to provide an on-site construction office for the duration of this project.
END OF SECTION
2-24-12 00800-2 of 2
CITY OF PEARLAND WAGE SCALE FOR ENGINEERING CONSTRUCTION
Section 00811
WAGE SCALE FOR ENGINEERING CONSTRUCTION
1.01 In accordance with the Prevailing Wage law on Public Works (Article 2258 of the Texas
Government Code), the public body awarding the contract does hereby specify the rates
shown in Table 00811-A following to be the general prevailing rates in the locality in
which the work is being performed.
1.02 This prevailing wage rate does not prohibit the payment of more than the rates stated.
1.03 The wage scale for engineering construction is to be applied to all site work greater than
five(5) feet from an exterior wall of new building under construction or from an exterior
wall of an existing building.
(Attach the current wage rates. Number the pages 00811-2, 00811-3, etc.)
10-2012 00811 Page 1 of 4
General Decision Number: TX130044 03/29/2013 TX44
Superseded General Decision Number: TX20120044
State: Texas
Construction Type: Heavy
County: Brazoria County in Texas.
HEAVY CONSTRUCTION PROJECTS (Including Water and Sewer Lines
(Does Not Include Flood Control)
Modification Number Publication Date
0 01/04/2013
1 03/29/2013
* 5FTX0669-001 01/01/2013
Rates Fringes
SPRINKLER FITTER (Fire
Sprinklers) $ 25.84 16.62
SUTX2005-018 05/18/2005
Rates Fringes
Carperter $ 14.38 0.00
CEMENT MASON/CONCRETE FINISHER $ 11.37 1.13
cLECTRICIAN $ 18.40 1.34
Formbuilder/Formsetter $ 9.83 1.69
IRONWORKER, REINFORCING $ 11.29 0.00
Laborers:
Common $ 8.99 1.25
Landscape $ 7.35 0.00
Mason Tender Cement $ 9.96 0.00
Pipelayer $ 9.63 1.50
PIPEFITTER $ 17.00 0.04
POWER EQUIPMENT OPERATOR:
Backhoe $ 12.74 0.00
Bulldozer $ 12.46 0.00
Crane $ 11.00 0.74
Excavator $ 16.74 0.00
Front End Loader $ 10.47 1.28
Grader $ 12.20 1.48
Tractor $ 11.29 1.45
TRUCK DRIVER $ 14.42 1.00
WELDERS - Receive rate prescribed for craft performing
operation to which welding is incidental.
00811-2 of 4
Unlisted classifications needed for work not included within
the scope of the classifications listed may be added after
award only as provided in the labor standards contract clauses
(29CFR 5.5 (a) (1) (ii) ) .
The body of each wage determination lists the classification
and wage rates that have been found to be prevailing for the
cited type(s) of construction in the area covered by the wage
determination. The classifications are listed in alphabetical
order of "identifiers" that indicate whether the particular
rate is union or non-union.
Union Identifiers
An identifier enclosed in dotted lines beginning with
characters other than "SU" denotes that the union
classification and rate have found to be prevailing for that
classification. Example: PLUM0198-005 07/01/2011. The first
four letters , PLUM, indicate the international union and the
four-digit number, 0198, that follows indicates the local union
number or district council number where applicable , i.e.,
Plumbers Local 0198. The next number, 005 in the example, is
an internal number used in processing the wage determination.
The date, 07/01/2011, following these characters is the
effective date of the most current negotiated rate/collective
bargaining agreement which would be July 1, 2011 in the above
example.
OFIA'cInion prevailing wage rates will be updated to reflect any
changes in the collective bargaining agreements governing the
rates.
0000/9999: weighted union wage rates will be published annually
each January.
Non-Union Identifiers
Classifications listed under an "SU" identifier were derived
from survey data by computing average rates and are not union
rates; however, the data used in computing these rates may
include both union and non-union data. Example: SULA2004-007
5/13/2010. SU indicates the rates are not union majority rates,
LA indicates the State of Louisiana; 2004 is the year of the
survey; and 007 is an internal number used in producing the
wage determination. A 1993 or later date, 5/13/2010, indicates
the classifications and rates under that identifier were issued
as a General Wage Determination on that date.
Survey wage rates will remain in effect and will not change
until a new survey is conducted.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can
be:
00811-3 of 4
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on
a wage determination matter
a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests
for summaries of surveys, should be with the Wage and Hour
Regional Office for the area in which the survey was conducted
because those Regional Offices have responsibility for the
Davis-Bacon survey program. If the response from this initial
contact is not satisfactory, then the process described in 2. )
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal
process described here, initial contact should be with the
Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations
Wage and Hour Division
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an
interested party (those affected by the action) can request
review and reconsideration from the Wage and Hour Administrator
(See 29 CFR Part 1.8 and 29 CFR Part 7) . Write to:
Wage and Hour Administrator
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
rihe request should be accompanied by a full statement of the
interested party's position and by any information (wage
payment data, project description, area practice material,
etc.) that the requestor considers relevant to the issue.
3. ) If the decision of the Administrator is not favorable, an
interested party may appeal directly to the Administrative
Review Board (formerly the Wage Appeals Board) . Write to:
Administrative Review Board
U.S. Department of Labor
200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION
r
00811-4 of 4
CITY OF PEARLAND ADDENDUM
Section 00900
ADDENDUM NO. 1
Date: 05/13/2013
PROJECT: Old Alvin Road Water Line from John Lizer Road to McHard Road
BID NO.: 0413-50
BID DATE: May 30,2013; 2:00PM
FROM: Leon E. Hoch, P.E.
Civil Engineer
Charles D. Gooden Consulting Engineers,Inc.
2320 Holmes Road, Suite A,Houston,TX 77051
To: Prospective Bidders and Interested Parties
This addendum forms a part of the bidding documents and will be incorporated into the Contract
Documents, as applicable. Insofar as the original Contract Documents, Specifications, and
Drawings are inconsistent, this Addendum shall govern. Please acknowledge receipt of this
7s) Addendum on the Bid Proposal form, Section 00300 submitted to the City of Pearland.
FAILURE TO ACKNOWLEDGE RECEIPT OF ADDENDA ON THE BID PROPOSAL
FORM MAY BE CAUSE FOR DISQUALIFICATION.
CONTRACT DOCUMENTS:
This addendum corrects a discrepancy in the time and date of the mandatory pre-bid meeting for
this project. Section 00100 is updated to read as follows: "A mandatory pre-bid conference will be
held at the City of Pearland City Hall at 3519 Liberty Drive,Pearland,TX 77581 at 9:00 AM on
May 16,2013.
SPECIFICATIONS:.
NO CHANGES
CONSTRUCTION DRAWINGS:
Construction Drawings on Pearland's E-Bid Website are re-issued for improved printing.
END OF ADDENDUM NO. 1
[Leon E. Hoch,P.E.]
1
[Civil Engineer]
2-22-12 00900- 1 of 1
CITY OF PEARLAND ADDENDUM
Section 00900
ADDENDUM NO. 2
Date: 05/28/2013
PROJECT: Old Alvin Road Water Line from John Lizer Road to McHard Road
BID NO.: 0413-50
BID DATE: May 30,2013; 2:OOPM
FROM: Leon E. Hoch,P.E.
Civil Engineer
Charles D. Gooden Consulting Engineers, Inc.
2320 Holmes Road, Suite A, Houston,TX 77051
To: Prospective Bidders and Interested Parties
This addendum forms a part of the bidding documents and will be incorporated into the Contract
Documents, as applicable. Insofar as the original Contract Documents, Specifications, and-
Drawings are inconsistent, this Addendum shall govern. Please acknowledge receipt of this
(1.11'\ Addendum on the Bid Proposal form, Section 00300 submitted to the City of Pearland.
FAILURE TO ACKNOWLEDGE RECEIPT OF ADDENDA ON THE BID PROPOSAL
FORM MAY BE CAUSE FOR DISQUALIFICATION.
CONTRACT DOCUMENTS:
Revised Bid Proposal Document as of May 28, 2013.
SPECIFICATIONS:
NO CHANGES
CONSTRUCTION DRAWINGS:
Sheets 3 of 92, 14 of 92, and 21 of 92 are re-issued and dated 5/24.
MEETING MINUTES:
Meeting minutes from both pre-bid meetings(5/16/2013 and 5/23/2013) are included.
END OF ADDENDUM NO. 2
Cib.‘
2-22-12 00900- 1 of 2
CITY OF PEARLAND ADDENDUM
[Leon E. Hoch, P.E.]
[Civil Engineer]
2-22-12 00900-2 of 2
ADDENDUM NO.2-MAY 28,2013 Exhibit"A"-Bid Proposal 'City of Pearland Project No.WA1101
Old Alvin Road Water Line
Item No. Spec No. Description Unit Quantity Unit Price Total Price
A.GENERAL REQUIREMENTS
1 01505 Mobilization(MAXIMUM VALUE IS LIMITED TO 3%OF TOTAL BID) LS 1
2 01555 Traffic control and regulation LS 1
3 01555 Flagmen LS 1
4 01563 Tree and plant protection LS 1
5 01565 Storm water pollution prevention plan implementation LS 1
6 01561 Reinforced Filter Fabric Barrier LF 11,950
7 01561 Inlet Protection Barrier LF 1,800
8 01561 Sediment Control Fence LF 250
9 01561 Sand Bags EA 10
10 01550 Stabilized Construction Exit(Install) SY 1,200
11 01550 Stabilized Construction Exit(Remove) SY 1,200
12 01570• Trench Safety System LF 12,660
13 01580 Project Identification Signs EA 2
14 02200 Clearing and Grubbing AC 11
15 02220 Remove and Dispose-Concrete Sidewalk-6'Width SY 980
02220S
16 02751 Replace Concrete Sidewalk-6'Width SY 980
17 02220 Remove and Dispose-Concrete Driveways SY 286
02220S
18 02751 Replace Concrete Driveways SY 286
19 02220 Remove and Dispose-Asphalt Driveways SY 164
02220S
20 02741 Replace Asphalt Driveways-See Detail SY 164
02980 •
21 02220 Remove and Dispose-Asphalt Roadway(For Open Cut Water Line Installation) SY 294
02220S
22 02741 Replace Asphalt Roadway-See Detail(For Open Cut Water Line Installation) SY 294
02980
23 02220 Remove and Dispose-Concrete Roadway(For Open Cut Water Line Installation) SY 199
02220S
24 02751 Replace Concrete Roadway-See Detail(For Open Cut Water Line Installation) SY 199
02980
25 02921 Hydromulch Seeding AC 11
26 02922 Sodding SY 50
27 02105 Prepatory Work for related to Underground Utility Construction in Potentially Petroleum LS 1
Contaminated Area(PPCA)
28 02220 Remove&Replace Existing Iron Fence(STA 51+46 to STA 54+35) LS 1
29 02821 Install&Remove Temporary Chain Link Fence(STA 51+46 to STA 54+35) LS 1
30 02220 Remove&Reinstall Existing Street Signs LS 1
A. SUBTOTAL GENERAL REQUIREMENTS S
0300A-ADDENDUM NO.2-MAY 28,2013
Page 1 of 4 Bidder's Initials:
ADDENDUM NO.2-MAY 28,2013 Exhibit"A"-Bid Proposal City of Pearland Project No.WA1101
Old Alvin Road Water Line
Clig..‘ B. WATER LINE IMPROVEMENTS
Item No. Spec No. Description Unit Quantity Unit Price Total Price
02417 20-inch Ductile Iron Pipe(Class 52)w/welded 36"steel casing Ind Restrained joints,FKM
31 02634 Viton Gaskets&appurtenances complete-in-place(Auger)in PPCA. Excavation,handling, LF 184
02634S and disposal of contaminated ground water and soils is also Included in this line item-(at
02105 FM 518/Old Alvin crossing)
02318
32 02510 20-inch pvc water main and Appurtenances Complete-in-place(open cut) LF 8702
02510S
02510
33 20-inch pvc water main and Appurtenances Complete-in-place(auger) LF 339
02510S
02417 20-inch Ductile Iron Pipe(Class 52)pipe w/welded 36"steel casing Inc!Restrained joints&
34 02634 appurtenances complete-in-place(Auger)- (Drainage Culvert Sta 65+25) LF 60
02634S
02318 20-inch Ductile Iron Pipe(Pressure Class 250)pipe Intl Restrained joints&
35 LF 470
02634 appurtenances complete-in-place(Open Cut)
02634S
02318 20-inch Ductile Iron Pipe(Pressure Class 250)pipe Intl Restrained joints&appurtenances
36 02510 complete-in-place(Open Cut)-(at Walnut Road) LF 143
02510S
02318- 20-inch PVC Water Main Intl Restrained joints&appurtenances complete-in-place
37 02510 LF 2.018
02510S 'Open Cut)
16-inch Ductile Iron Pipe(Pressue Class 250)pipe Inc!Restrained ioints&
38 02634 LF 60
02634S- appurtenances complete-in-place(Open Cut)(by FM 518 16-Inch connection)
39 02635 20-inch Steel Pipe Above Ground(Sta.26+00 and 94+50)per AWWA requirements LF 338
40 02417 12-inch Steel casing for 8-inch SDR-26 PVC Pipe(Sta.61+90) LF 20
02635
41 02634 20-inch Ductile Iron Pipe(Pressure Class 250)w/welded 36"steel casing Inca Restrained LF 60
02634S joints&appurtenances complete-in-place(Open cut)- (Drainage Culvert Sta 68+60)
42 02534 10-inch PVC pipe include Restrained Joint LF 25
•
43 02534 8-inch pvc pipe include Restrained Joint LF 778
02634 20-inch Ductile Iron Pipe(Pressure Class 250)pipe&appurtenances complete-in-44 LF 315
02634S place(Open Cut)
45 02534 3-inch pvc pipe include Restrained Joint LF 63
46 02534 6-inch pvc pipe include Restrained Joint LF 787
47 02534 6-inch pvc pipe(Auger) LF 55
48 02515 Water tap&Polyethylene service Line short side(1") EA 1
- 49 02515 Water tap&Polyethylene service Line long side(1") EA 11
50 02515 Water tap&Polyethylene service Line short side(2") EA 1
51 02515 Water tap&Polyethylene service Line long side(2") EA 5
(1116‘. .
•
0300A-ADDENDUM NO.2-MAY 28.2013
Page 2 of 4 Bidder's Initials:
ADDENDUM NO.2-MAY 28,2013 Exhibit"A"-Bid Proposal City of Pearland Project No.WA1101
Old Alvin Road Water Line
COW, WATER LINE IMPROVEMENTS CONTINUED
Item No. Spec No. Description Unit Quantity Unit Price Total Price
52 02515 Water tap&PVC service Line short side(3"thru 4") EA 3 .
53 02515 Water tap&PVC service Line long side(3"thru 4") EA 1
54 02510 3"Wet Connection EA 2
55 02510 4"Wet Connection EA 3
56 02510 6"Wet Connection EA 4
57 02510 8"Wet Connection EA 8
58 02510 10"Wet Connection EA 2
59 02510 20"Wet Connection EA 2
60 02540 16"Tapping Sleeve and Valve. EA 1
61 02510 Cut,Plug&Abandon Exist.12"Water Line EA 1
62 02510 Cut,Plug&Abandon Exist.10"Water Line EA 1
63 02510 Cut,Plug&Abandon Exist.8"Water Line EA 11
111117
I° 64 02510 Cut,Plug&Abandon Exist.6"Water Line EA 4
•
\ 65 02510 Cut,Plug&Abandon Exist.4°Water Line EA 2
66 02510 Cut,Plug&Abandon Exist.3"Water Line EA 1
67 02510 Fire hydrant Assembly Inc!6"branch,gate valve&box complete-in-place EA 35
02514
68 02200 Remove&salvage fire hydrant EA 9
69 02530 Remove&replace 20 LF of 12"SDR 26 San.Swr.Centered over prop.WL EA 2
70 02530 Remove&replace 20 LF of 8°SDR 26 San.Swr.Centered over prop.WL EA 3
71 02541 20-inch Butterfly Valve complete in place EA 17
72 02541 Air Release Valves on 20-inch Steel Water Line EA 2
73 02541 Air Release Valve on 20-inch PVC in Manhole EA 1
TxDOT Elevated Water Line Crossings Including Drilled Piers,Box Beam,and Appurtenances,at
73 Specs LS 2
Mary's Creek and Town Ditch
See TOC
74 02200 Regrade Existing Swales and Roadside Ditch LF 4,685
B.SUBTOTAL WATER LINE IMPROVEMENTS S
0300A-ADDENDUM NO.2-MAY 28,2013
Page 3 of 4 Bidder's Initials:
• ADDENDUM NO.2-MAY 28,2013 Exhibit"A"-Bid Proposal City of Pearland Project No.WA1101
Old Alvin Road Water Line
C. STORM SEWER IMPROVEMENTS
Item No. Spec No. Description Unit Quantity Unit Price Total Price
75 02220 Remove and dispose of asphaltic/concrete surfacing with or without base,all thicknesses SY 6,400
02220S
76 02980 Pavement Repair and Resurfacing SY 6,400
77 02220 Remove and dispose of 18-24-inch RCP All Depths LF 86
78 02220 Remove and dispose of 36-48-inch RCP All Depths LF 942
79 02220 Removed and dispose of Sanitary Sewer-All Depths . LF 20
80 02220 Remove and dispose storm sewer inlet-All Types EA 13
81 02630 Cut Plug Abandon exist 18"Storm Sewer EA 2
82 02630 Cut Plug Abandon exist 24"Storm Sewer EA 1
83 02631 Type"A"Inlet on 5'x 4'Precast Reinforced Concrete Box Storm Sewer EA 12 .
84 02631 Type"A"Inlet on 36"RCP Storm Sewer EA 2
85 ' 02631 Type"C"manhole for 42-inch diameter and smaller sewers EA 2 .
86 02542 Precast Manhole on 5'x 4'Precast Reinforced Concrete Box Storm Sewer EA 4
87 02630 18-inch diameter RCP storm sewer by open cut LF -10
Cillib1/4, 88 02630 24-inch diameter RCP storm sewer by open cut LF 95
89 02630 36-inch diameter RCP storm sewer by open cut LF 285
90 02630 5'x 4'Precast Reinforced Concrete Box Storm Sewer LF 810
91 02630 Pm-Cast Junction Box(See details on Sheets 45B and 45C) .EA 1
92 02770 Curb,Curb&Gutter,and Headers LF 140 •
C.SUBTOTAL STORM SEWER IMPROVEMENTS $ „ _
t
D. EXTRA UNIT PRICES
Item No.' Spec No. - Description Unit Quantity Unit Price Total Price
93 02318 Groundwater control for open cut construction LF 500
94 02541 20-inch Butterfly Valve complete In place EA 5
95 02220 Additional Removal of Concrete Pavements,With or Without base SY 300
96 02751 Additional Replacement of Concrete Pavements SY 300
97 02220 Additional Removal of Asphalt Pavements,With or Without base SY 300
98 02741 Additional Replacement of Asphalt Pavements SY 300 .
99 02318 Hand Excavation CY 10
D. SUBTOTAL EXTRA UNIT PRICES b '
C. TOTAL BID PRICE = A + B + C + D $
0300A-ADDENDUM NO.2-MAY 28,2013
Page 4 of 4 Bidder's Initials:
. I./....)
./.7)
•
•
Gana to CMS IFILI.U.-DLNC-CS
_.C.ONSIELIC1 ION EMILE slot,.srKCLVINS'FNCI ION M;TfS ';L?REE1 JEJS,ICE ANC nI.0 1,5_-may - WAY Nnlf
IRu[I nesTLvaRR Cn[[+IM STSIfI.S .ifR 4nL5,SrOrle WlANnpl P.Sf11U' xxl.�I�x[SPW6INILI IT d L[O+fxnL IIN IL
Cf`L . -1AT(SI If411I WY.E rE VUH(n'IOK,_�v S.wWLI C'tA I Iv
lilul D [ _ult SlLCUICl,In'1S r CO Ov T[L1r 0 LARN1n `FPift i15' C fLK lut ,U 1•
S'D YnC 5 I s' 1100.1. aNll V I Iln>1:.PrIG
C,rL WM LP CONS., ] IL NIMLLLAD(I C"LLWED IS'
D,A"`i[Ir Ill[ I dWAnLF I In CIIN d" AREAS rm.ON P✓M Alain Br I'L•'C.Cl.I nRNS v`I.ACLcDxS
1 VU! A a..7"LU U IAIL IMIM,w1U 6PLC11 ILAI 5 AS.11.CAN.E Iel OSP..nil fn1Y COSMOIED 0 NO1.LL`I,An O.O11a11LRIM'
]O ti PC< If n 'i<f IKN <nAt <M' TI 0 C I 4I II EIp[""N"eyr`LjxlinwnxlifPF'XNS L dP' 1 1PLD WhfSS SNpw UIaLrIu:51A ,xINGs. �<nOCIM Del.',POUR 10 MI.num.O
�:. F IIn"-s cn�ioa rc At c I L p 8ma m 1M xE
rs J•• Ie1,LZ2V✓K:t L Bl''Pr' FKO NIw L.INA A.101LRt PROI wnvIs Iv NW"`
ill nJ'Y Ls e p OEM. au N '[G
JI 51�Wt D [s U . C[5 0 E WC Pn N FIG.i Anf CA•CO In 1AllU.NO LURB .L.PRCvVC Bt..N MALE Unutt r,x[[
vi`` JJ CC rw /ON All -fLRO N:"IO W UWI wLL
<IfWN lnn f fx, ,.. �1 C 6 O[s S pn LlSI fW rnVP.ICFIG.DU. !L00010U b'"Cx rfE.IN]Lu0 rF 1drGEO TOR LEADS NC GiuIM,SIRS enIN. rv.¢n Lwr rfwsrnueuM IS C.I.lrn
u Gutlr.'tPm nn w c t'N, nrt n b I wm.,cEPn,wrn �[Nd,rt[x,vrcs "xnan"c.rc,Ifp as p NLcID u.,rrn•T.wviM r•"1iH sin sue IrN. nu 'rNl MO II)n P]nl I uc M. Y,
5 10TRINCLL SHIM. HD.01110.CDST WI6PIVn^',,W;:xLCN tE 11N[DItru'C' /•rum,Fa,M Nlx,l Irn I rr1461•5,Ni IIfR S.JI,< FrLi I01110. J raslwL VnwNln S'VeCf runs_ C v(
p RV SIN,DMD QIRIL 0WY11E0 . c CLI.PG(0 OF
VUC N1NOr Cerro D all,NDH,nI[OfN Df, DIv CIS ir[r. ]Y•-65]-EOO,r� e. r , ro s vuy O[ I , .. V[ C CWVTw ,ALL GI REPLACED ,W
BYi'CCI ILn51<tl OWt9 iVnpN 10 C0. nr.np CUN.1 iUtIIpN x eM nlKn M.4.[I I N. fli Tu:[St u[n4aN0 SI'�11D.n05
5 C of fM .c[ ( DV VIV CUMry nl IIuwS a,Rwwr,CATTI ulKw eu�1I,u.N.SPIMIAL Py,n di µle.gni l90. 1 d
`lu.'vin�ar s1xUL1UAI I. L COxSt Aia(l Yl [51(NL 10 fUSilxG •IC 6 'WeIT,aL I[ _
W,wt. , I l US
rsn.ulll¢`'cn•«,r¢D u�wDxi lr.i.irElsD TNAFf IC Nall-c • .n g11!°,u'. 1:Lrl4'1Yp".w"e"I i l.“-l' '[r'd"
G C9nr(uC1 W1 AW1I LUJ Vn IF Ln IC51 Utlyyx I1llll OSx"HLSUL wy nl,p,(E 1 p n[COOS..00 V.I.I.Ol00 00.61rax,W.�1rr. fpnW llOn PRIOR rC STIQ'Ix[MAN
' "
(dNrfxwyl %kal. ANC L,aLIC�• 44 CIIY+r I'1p llN6 1 1UV.COOS M DO LI,N I.I./1..1 INC C
GiOf nAi14 A.cIIIn IIDNs W"iil"Clir[jr PL(10 00 C[WiKKe 4Hv00,+1 O SU"r[Pxm•[`C4[5 Ya.L I.CM1gcCiM SHALL nOvltt nx0 Ign�l:DENIMS L'W'GHNUCf .E.RI[.DV.NO) 910.1.BO D NI.10 nl Ail uNIS WmNL
,[`10000 OP[Ylml Pf s•LANS nI'd'Cx Cu, I (n Imn.. HID.PMI v1 M 1C TCnS RFmOat nlrnM TNilFIL WIRO. ,:Ip.ANDµ .111IC
Cn<CPf c TO Ox E diaWvlCS OC In oVO,., 1....11.11. K(rc DEVICES,NSIMI xCl[4 POST [ENI EOI110w Silo lEc1S'IfwSI 6'LADSO MAI.CONS...MD.9 BE RES1pV0 TO Tor
ptir,il TR: 4[1k C LVZ1V.5 Or BIXif N,S IN,N'IO n„1.1.TI:+NT[nl.'UI CPIS11M,NMAn 11.0 PA[11.111ES Hr.BED,'PLO,MO Fn. MINING GMf1M[l llri N
[AflIAND,flY]NCCn G "'ROYAL l v 0 x rc'rslIrvO 4^..HVA.CnW1 d'of D¢a. 1 .Tv
E EL..Ian I�"N--.(..f6L11.1 Irk- rC0[PTId+.Et SHALL
LE D 6[NI'OSC I w! CIVO 51Lll Wi 11pPO510 LAYIED MNf.
[.Sfr.(Y. [II O^.Yinwl nl n _ - C + x A C(Gv 10 ALL dltKwrS,C
(si Iiiti.Sl Eq 4TPIi( t(rN 11LL �'� �L vRS a4.4 iNw ne<Npl r.6110...OF 0.YLo PANG I DES 110FN71 RLt At ALL 11HE$. A WaER[Iw E xC ar�yrORCwO S10El[nSti US I,(AI..WTpt OOtrL4
EE[S iluAl[U lNOu 1i.( [F`Oi Int 6LI"ewu4 livCS i`�I CnAI[O.lui arc, .rt[ I, Or RE C 10 C.V.. N.ARM4A.DORMS Sx.LL BE 40 IBM5.I�L.G.1:C-C
1RF C <NA Mnl`IAIN 7.-nrRgt RVF.e Bt M'CQI01M lC W 4Lm MIn ra14012 B--IWO Sir 6NTFR Or MOTT.SLAB
CYDfxrlAl.RCnS A.10 6E SODOED TO N.,D,CNSINIL,AND R.OIW.P ARGC AflC TO.DC cIJK RU[IIOv •
rnMrlC[d,litW li•AVI OunIM xlxG In^. -p NOD'OR[Ww
%r4x0•mNAU[ll. .
9.=MIMLTOF 9uLLLCDVER 00EN CACAVR110xS u.1N I'NINASEt 5 COnixn[+OO TC 000.HECCSS,RT PR(CAJllOn6+C Px0IFC1 ERall
YcwHCNLT[ta V"vcuCNl. t rS 000000En PROER.Du0ING NDx:v01.INO IMws. �N TE
NiPL�t SI DlLlilE�fHNn01 A. • SMIL r0.1 4EM. 1 IC VHEN LAMS ARE BLOW°. [L 1 Sv5LEu5 0'9.9UB5.PLu1 5 nxD raCCS ALlmu InE MU Dr 1ZAvnCWn
Ie PI C[r xn t.,"Nisr,, PnNl°21,1+RJtIVe aaei,Y)T'IRx ZW"`en"'"'''''
;'+'ALL'
nE fLvrRACrOR A1ALL COOPIT w0N OSI'A WCUL.NDNS'.HD
Cra iRAC10R 6 NCI WN4JN)rn In nTR.lr M.11Yf n D VIgTLN VA',.Vri.CMInc1 p"r •iT UnlydvCO VOTiCE 0FT1[LN15:/f IAGGEg151 IYPrE A MO d'1[RnS.lnll_CnCCNnwG[nGVAnd14 IxCnCnluV
RCOUI2�10 OIMCt Tnn ,tEn nnEs,RC ROCx[0. 'AA<nMwL
P L 4t5'DCPN+u[I„Ai]D1-d4]-tOWfOR nSdSIANC[VO I[ONrgAC1M 5O l GTf.nM A<l•(�.A O.mAdxG C415tv,L mn`K.AIt(LVI STSrzus I!O.�GFn 6. •IF 1 LORINntld.CNW.S -U UST R U5.rel4Nt 1.1 lx '
D _r[P un' I MIL ItY NCTFS TRAFFIC L.1006 P.a1s• III UST caNs7nucl mei lww.6.
iY"c[t O vlr"nuo to niu a r s 1 7 t �c f _•„__•.•- ._ _.. Is OUTLINED .C T.01 11.11.AS.CLINE r.vYL OS
rr� N.SVING f III P..Al.SUV.11 Rll rC DST EP P PNS•
0 P CC nifnstu%Z.4f a ( 1- "S `•�� _,, I TaL",a,x4,,,[�.t � C�f iO K.NEVIES ONCllinr CON P.R..VTEn 1.4 BnrS PA.
Ir OSLO is LRCM..ON Uv wL,O[ U,1f5NOf SOPRON C U �E [ R11 �RHEnin `mow; AME...H.-MR OIN NE� 31 I•s.
,nle�i+(IL 1.inti vW.l C ER:ONLTieC"OJ 1 v SNOWn EOv+riCSC IXuvl.,lGSEnwc,,.,0 .II.,,.,.i-BE.Olt.otail�.••••""l f6POrs1a COn �"r •T.ESFMR� 1 E NEPHOn.CIOLC L LANv
RLWI4.En16 d NU IL l..I.SM.29 ., Nr�1LL axl es lrE COxtgaC.]F g E xnS.IP
0m1.WF,T 0....Ac:Or
} 10. O 00.1.Ann CO..•�g �n ALL Or la ).MPRN•EO COP IfUs OF•IRArf IE�cONIP0. LRNS'�Lp1vE/�BIDf'v4k
movsl Or I. I. ,sWE Yale ,IL,Tif. IN9P[ei10n,I :5.
1 .L.T.C...51 attn.•l (F..PEm.11•TR.
+� - r�A9 9uLlulN[�,(LL A Rx fn,l,n CITY•5 TRPFFIC N•,w^hn Rl 0*0 t xa1R 0NE11 00 0CLOSING
P Srt � �I� A 1../510E11.1. II. [�uMir�.rrN l`'ST OE MOS AT LENS TIC ILL OUSIMSS
n00 "(01 n�I51WS�WIgiWICBOv1O. 000a10L NOUHS NAT BE RCSTRIGISO OIN .111.64 TNE REOI0Si PAx OE DENIED.IWO
,. nE*(0 Iti_ m,aa•Is GLL]1]-Y3,72.1p FOR AN MPL.IGIION.
•r ilst 14mr m,"Z w IIw rrg.[u SWvrr IIN. 0.NE.Nm] s/]a JH LH
< mNfN0S.HRS.VR a'A.IE INACS...wt.
pI.IU.
6RE/'mml"",D.`C.P.1 0.1 UP PUNK6^,01av5."E(sINSERI.6 _
COIISiWC110"U4.01.FOP V.LILII.s.S
e6 ULn,N( n61.x. LOI
xlcElfa LIB,w6ipw uacju eM ISiRCf l a1.Nu Yf""rA P •
• uoii'i6ic�"..S
• '11gf!a.164.71
•
' Tepn•/(iL.,IL 5/0/2013
CHAALCS 0.ENGINECERS.
TONSULTWC a WieriERS,0.'C,
TO.Bp.m n PRwEssonn
C• CNpncr,(51.6
1JNt1.1.15 RCA" ytr.A
ID3)rei3-bet TO51
p,JlyNM,• D4u>
•
PEARJAND•
City of Readand,Texas
• - OLD'ALVIN ROAD
20-INCH WATER LINE
. GENERAL NOTES,LEGEND,
AND ABBREVIATIONS
N=4..111. 291.cA0 N.t SHEET
C.• San,- NO BCAte 3
c mL,Icel.P.E 00 v]
'.1...") l--) .
•
•
l EN UGEfl "' I-20"x6•TEE I-20. 45' BEND I {a 105' 1 I ;g -�
A 23•B4, G-TOT XIS ELT I-6"NIB, BL STA 24.09.60. l 17' �� 0
n1 TO EX 6'WL BL STA 24.07.30 °
1 39.OL1'-L7 105'DRAIN• EEASEM N
r ! �•'-1 rJ'r 20. I4 SLUE:Kpli i_y ta'
° I BATENAN PLUMBING COM NAY (VOL.1 5.PG.'17.318 BC R P 8 1.20"X6` TEE
1-6"x6` EE °"'' t a.uoxar„ G I S{ D; s PROP'20_MAIER INE 1-GVtB LEGEND
VAN•rte f"fI t-6"GYiBI 1-6"45'°BEND I,:�Eoo.°°a�oj1+M'tu��i,tti•c°Ux w°.r 1 �- 6� = `s;' S I - 1-FN EAST ROW (PROF!
19� W • I 1-6- I ((mT 22 ,. Y { L g'qR �+ L - __i_ _ BC STA-2T SD --" WEST RON lPROF1 ---
In C AN BL STA 2•BO .3 ? C,2 as4 Rs9�` '.`c - LOVE AND REPLACE 79.00'LT EAST DITCH IPROF) _.___( E ,N+ 1ST 24'RCP II RIP AP.
71 JJ,,..se.10' L. / .
. $ ..I .. _ - -- - 5 pp W Gb� ® GROUT AS REOUI REO AT NEST DITCH /PROF) --
I_ me urx. F ° ° EYIST•�-Iw 1°B tl[nA _ LA. �® 01.8 Y6 CONNECT ION US UNE 1 .w TOP OF PAVEMENT a BASELINE
F r __ _ P 8 RR '
j D �S I s r 4 L
1- _ - _ - ."_T�_ -.- •,o_. - -•.., ,. • a°�1E�. rt .1'to o. ,,,,,a,
- NG.a PROP WI. --
•---- 2.,6'•1.5• BEND :I - s el N0 c.*I0 __ __ _ _- AI 10'01* ,s"PIF0000 OL° WATER METER/SERVICE N_ _ 4_ I i I000•s•o-•w°Ic TO BE TRANSFERRED
,mil l-°n-•0F CRITICAL LOCATION _ -
BEGIV AUGER - SEE SPEC 02318 °^�� ° 11--_-nY„ c I I -- f-•-�<=-- tot'or 0o COW7Rgt B£NCM4RRr
CD c) F 43 ° P -�- -'- F. ro-{ TEE ELEV 7ED CROSSING I --- U �///- - -.- BEING A METAL ROD STAMPED"xGCSD
- -sz- / _ DETAILSy MEETS oIxx {_ _ / �f,Y® - N 0.2•/-MILE WEST OF INTERSECTION
M,� 1000,°„ - ,/ - -- T1 1 I.1 ~ =-- 76 1986"LOCATES ON MAGNOLIA RD
N f° ,--- - -- -- R caw°ANN Ip , c000011...NE -- ----I °0n ?c v1 _ - STATE HIGHWAY 35 AND MAGNOLIA.
L./! ///ry p+rnw�n ENERGY - Ip 1 I I BL STA 27.00 ///
Q 0 0�°:E�.1' OLD ALVIN ROAD1.Do is PCCOnE 25.00 IIV N 2• B9' 57.23`N 26.00 I- el �T•00 39.00'Li 29 Q ELEV. 46.OD IH.G.C.S.D. 1987 ADJ.1
f" I lee°-a+n-00001 n BASELINE 0�° $I 4.140.75• c cnEIC BRmc[ El I. { w,�c wuI N
' WIN+PAWNER, O`/ m I 51 I 1
W ''M MAW M /, TBH oA41 91 'I IY LOCATIONS OF EXISTING UTILITIES
Z ratan [•20' 45' BEND�.--+' _ ij // auu ERN CONCRETE nE.o uE aLR 0 PAL �_ L .Z. ARE APPROXIMATE ONLY,
r-c-.. -BL-SYA-Za-2,94 -- c� '. - c�T "0. -p - CO.. _ . �,
/ 4`V"r c c�� C mac-�°RTin -C-[- <. yu 4-cam .L_.T_t___�- -------�C.-s- -fi- J 2.SEE STREET.CROSSING DETNLS
J 35.75' RT - G_ - Ic r I v`TVT[ { 11 �NU_�� _'-- SH 39✓K 41•TRAFFIC:CONTROL
U ___ _[)F -�- slat �\ I ____• E I 1--______ -....�.., - �� S _J 8.., PUNS AND MAILS.
-" l- ww_:- __ --rr- .,+r,xAO...L one s/. �a_e3•:� ----1
1-
.3 I 5' �_.e ��� CO. +[ --------�Boa 'L�.J, -C�Q
ri>;tt • 2a t
461
eA.rt wL0 v I \ I 1 '1E.,I `, • to.. P-{ 5 P P _ NE ¢ _- R Pis,w°u.w v`,-2%• S euL[In[TrRa ii°rmdNo cam .PT 116I1 e v r®c,
I CRITICAL LOCAr IoIiJ, DRAl1�lAGE EASEME T I /y� �•
~ I I 1 SEE SPEC 0231i I No OE WEN INIC -.a VI
k rovvaw �i�. �2D�7�6•�426 BG,� I I I re0�R \\'Qr PRIVATE UTILITY LINES SNDRN
W ° (PIN C PERSON.) 1.00-645-66cM-
u \ J I g
N1 U --1-- - LOPR'NM e �� W I 7 GUNGE
ttvu+x iR r CC tERR01 NMl NE�G�//ELSE LCi iilij�wiji'w�[v
3 2 L. 2 -f qe , I :o 8xYI r�gl I W)d1o,1°PI ,e.,xa RIM.
1 k o 1.711/I I I o 3r1 al al j
° fI I Il •- S.°R�°..l:'FINOWTT.aal,[x1Ll„tjI I pI (BANDONEXI5T6HATERLINE s w °p 1E. °� ND TRANSFER SERVICES TO PROP I Date
/YO`WATER LINE //( • CnTRF0I NT EEC RZ Yo 1'FA[ILIIICS
20•STL PIPE o°.«
•/A''/ / �. /J���,/ /;,/ ENTIRE
DHLNYTHE 100 DEAR F ELEVATED CROSSING. ••. EDncps[CABLE[onanNY
. ... ; ., - � /%/i</ /'/ : NOTE: :AND LIMITS ARE OUPROPOSED WATER L TE0ANDHEiPLAN ARE.
/ DOD PLAIN !n AOOENOUM 2 5124 Jx LN
ON
52 ,/ // / /A / /%/' SIOERSLOPESTi1+tSIIIpEADE THE PLAN MIEN. 52
- [AIR RELEASE-VA[VE - ,. .• 5•
7.7} /// 'BENTS'EFFECTS
CON THE
1 • BOY•PIPE ELEV- TT: T;5
J YLOIP#-7NE CHANNEL. VERSE ELFECTS ON TxE7 • ® 50■ W INEI et oLSCRe WE OM►IELj _ _ FL EAST DITCH -- 4B
II' (PROP 20•
-FREEBOARD
. ....:.... .. i .,.1(X)YEAR w5E
46 : � 127' DRAINAGE A MAINTENANCE EASEI4 NT 1\ `�_ 46 �i)y ���R
.. '1 2O END _ . auL 5/6/2013
I I - i BEO1N 20':RID-END STL P PE• WEST ROW
. .... ELEVATED CROS H ... .. le CONs04Ru Two EENGwE[R9•Dit
44 Nc a PROP WL 44 MIAS BOARD OF FFRESSIONAL
.... 2<LS RCP - DROP 6`HATER LIN\ ..O IA ) ' o [NRRC[RS F-4116
• 1 ' Y INCI ROWER ROAD:SAW A
z 42 - -� - ' -6`45••BEND I i I 42
- TOP47,710:.._. : [ 1 - ....-. ...... .: ;.... .Ex1S7 6r.,L�______ye-_� / T�3]
STORM M 24'(NE)S2.8f1 ���A��`I_��__ -,���- - 6` Fx LEAD
,STOTA7,27 '24-(Sw)'42,91 �A,� ... • 1' MIN CLfl ....� ... 1'Y1'MIN' ( '�\�.
t41Li atilaR1 ......... .. \_/''(\ram. .. /
12•(W)42.92 REP 1 �4. 1 e'....L q �/�)5
TOP a523 J•'•V 7 •24•(SW)42.5n 111111111,r
o -- .. .. .... ... ... , T...t::.:e:•O� City of Pearland,Texas
38 Za"(sw)4z.54 LiRGP •!Oi040e '• 3B OLDALVIN ROAD
1111��
1•••••,1•••••..••.....•4T�!!I�i�•• it ... ...:.\ ..,... ._.. \ \\ 201 CH WATER LINE
. ••.••••••••••••••••••••,•••••.•• ••4•. _ PLAN&PROFILE
°�4 •40 •! •044•�4��4i:�4�i 404ip:14i�4 •: •4�: STA 26.9P END DIP ALONG BASELINE
36 .••.••4•••.••..•••••••••41.•40,•••••••4 --Exlsr sD R
.•.•.ww•.H.•.•.•.•.•Aw.•.•.4.•.•-•.•.•.•.••I• •.•.•.•AAD E ZO-45'BEND Ia o-4r BEND ... ........ .....-. 36
45 :f `tlT CEN TERPDINT 4-GAS 1-ZB-BV END NAy 750 LF RESTRAINED.ID N15 •uwSTA.P3+o110 00�0 STA 2B+00 SHEET
• BL'STA'N:00 i .. ..... .. ..-. ;..IBL'STA'27L00' \\ SDATEs w , 20 14
L _
jN 34 BEGIN DIP/MIN 330 LF'RESTRAINED JOINTS 45• BEND \\\\ \�\,-��.� ��` 34 ["Z'
S: 23.00 24i00 25.00 26•00 27 00 28.00 uo.loannIRAILPE�" Raw OF 82
'•741) .
'
//7. CONCRETE ////1 i,lrvuixll a is 4Ian TO ss0 /(♦ / J I
STOP N GO wW%EIS Or tErAS,mL^
ELEVENTH NCS REALTY COi1P T / yl• IC••1H•° 0 Al 40
ATL a 14 PG •1 HCOR / _
° / ,03-20-19B5 / / / / ,P,,, SrwCE nan -00' EAST RO/ (PROF)LEGEND
/ / •
/ /• // / BURGER MOLD KIN
s / / / / LEST ROW (PROF1
/ / .. / / 1-20"X6" TEE
RECONNECT TO .d} �. + /j _ T-GYLB EAST DITCH (PROF(
EXIST SERVICE,/ J,�,. TwEE7Y MAR EE7 ---
t-20"X6"TEE /CRITICAL LOCATION nN I-FH •'^,(,°�•I° LINE /' '' I:OVLO 1"y0�B 16.1`f'E`'"" BL STA 59•95 REST DI1CN (PROFI --
P •arMALT 1.10"CVLB /• SEE SPEC 02]ID CRITICAL LOCATION / T
�, I-H U. 40.]0' LT OP OF PAVEMENT•BASELINE
c _`°, r• IX VA 56.80 I.45• BEND /� Q1°`E YiKr SEE SPE�cN 271E �/ , -
\ �saTAt I5.70' T BC STA 56.95.00 / �, ,47. .
G O
16.30' LT n ; /'g°•• EASEMENT 7PRhP • S. TO BEM ESFERRE ICE u
Or .swar � �/ cm.rA[rt Z__ - -�. TO BE TRANSFERRED
O .. // �`. r. •c•� - - =o_ _00 Ct7NFROL BEMCMNIRRT
%+s•• - BEING A METAL ROD STAMPED"NCCSD
LD� ° ,e4ro <, �,'-+ � _•__� f BASEI INE� p 76 1906•LOCATED ON WONOL IA RD
LTY PROPZO-TWAT ER LINE !•_-: ••�•_ _ mr[aw•r[NOV �r�^�r'9i _1p
_•-•�_ a•sL cs uve Or-VA-69-+-]tiaT',,-L,- - O.2•/•MILE LEST OF INTERSECTION
"4 °/ 1-I6"BV - - --- ,a+.rta TB,/0Ax Q STATE HIGHWAY 35 ANO WGNOL II.
t- L� '(FIN Nrnl • NO-JACK CASING-
BL STA 56.95 F.4
a T urca av4 RESTRAINED STEEL OISINC/ ND 5T[FL CASING ELEV. 46.00 IN.G.C.S.O. 1987 AOJ.I
W N 2• 00' 40.6B-L 13.34' LT /57.�'>• wNs p JOINTS A NETTr_ 58.00 1• a. 59.00 • 60 W
J I.442.6Y' BASEIwE•IE%I STEFH SALVAGE r-,S" .....
• �a�l OLD ALVIN RDA, // ' "`(r c 1•AROE LOCATIONS
OF EXISTING TW7E ONLY.
UTILITIES
4,1n lN[A RANT � ,• a •',� ° X
2.SEE STREET CROSSING DETAM1S
_-LIP 01- _ RECONNECT TO = SN 39 k AI•iRAFiIC CONTROL
CJ c z-- ' •'Ir /q c[ /� rEXIST 2" U PLANS AND DETAILS.
Q -�i or�.rcN _ T _ •\; ,� ` _ � ` SERVICE LINE p t'-
c�r�f nmc..-
«�:WEN e1"41•a iffj h\' `, \ ,`'°-a-[a'e,n / \ 11 ..."muu`,°p'wc°" r s NOT:Ir.,o,N..v[¢leer
RESTAURANT c"•ET K ., T r[ � / ss 1 1[•
u [ 1w 1N n •c•u[•aa,
S[ P �' P_• y / ..•$1`N--, I I - cmvL•sONN<U I 1
I w Lot PA°r0,1r1ap,rin m..ti
CUT, PLUG cTsn 4•s infA -� • PRIMATE UTILITY LINES SHOVN
L ABANDON / �I -16-%16-TSAR �'� ! lg7c�-pc c s_
l BL STA 07.42.00 IV/ ' r_ __
o Mc�nr"u�nN`s'a.c ABANDON EXIST B•RATER /x L 16.30' R7 __-_ " Dole
® CCNf ERGO If0T E0IfRG./ELEC000IrACIL 111CS 5. aN,,,, 1UN„ J1ROP 20R SERVICES TO AL STA 57.30•L7.]5'LT rO,,,,,"';�`ir I'�.1:LtaC•�:� ABANDON EXIST LATER LINE, 1NLo•n[m[w
°/0/•stn.. scn,or[a DROP 20'WATER LINE ®BEGIN JACK L BORE/ TRANSFER SERVICES TO •o.10•r US o a.lnw, •
N00,OIl aNl _ - STEEL CASING irrtBL STA 57.35 PROP 20'LATER LINE 7 qqq
s1c Too.
K r•tw Tr tl[m 1•20-BV 17.BD' LT • AT&T UTILITY L;INCS�SIOVH COMM'KT•1,1u ON.,
mBL STA 57.10 BEGIN PPCA °•'^°'1°`°1u•'me-ux maN n
•N..T mPnNn wow uc 16.50' L7 BNw Bm4 va mill MY a<.c.e
•�° coo,OIAN�Don _ ,..,,ILL STA 50•]5 CEN`500PUI•1IcEN.aflwiawS rACILI LIES
I:wN�ii i o 0Al \s - Loma �26.50• LT
_B„9 ! To. //''// 1°01 Cal r0ENSLINTILI END PPCA Date
CLIKAST CABLE CoNRANr
it.ADDENDW 2 5/24 JH LN
•
•
e 46 TOP OF PAVEMENT A BASELINE
WEST ROW
L .. _ NG A PROP NL 4G
2
'a FL EAST DITCH _ -- -
Rth'
- • QQ N• B[scw.rmN oa[ MIN o.,
1.
Q2 0 BL STA 57.10N RI.STA 57.15 BEGIN DIP - - - •
..........._,.../..--,
-Liar �;S
z_ �E%IST B•VA. __�' •B��.\7�__ -r,`.- 012E L./Y,rts.+
40 GRATE INLET 1^ ••\\\ �� P •• •I� IB'RCP-- TOP1N 45,33• OR TE INL •• •• •• „-•", &a 5/6/2013
TOP 43031'''' .-'•• • • • TC 45.33 7 ♦39' 40
• EN
3�((61"((((WWNO0AS)41.I4 (PROP 16'RATER LINE I6' Y EH``NE 1 1{ATE INLETGRATE LE 0 44.46 • 18•(N)41.$ �CWAX.IWG CR CHARLES 0. ANCCRS NC
VO"OR('ItLCESSED, - _--' (� ,•T SE3.700 O .43.42 t0-(SW)41 BB 0000ASr trfi a[ssmnu
S �� 18 77 R TE INLET
II (
38 ... ..... .. ..._. .. .. I I.... 1.A ... , 1 T(NW) A7 113"(NW)411 16 TOP♦ C (l l 00-5001 77051
SURE A
w ... �" ... ...c E INLET IB'(SE)7966 38
♦0 3
i -- \ .4344.---_-___J 418-(W
e I6" iM LEADI ...� .2a:{SE�39 O1 t - l
24"Nl qT�
36 PROP•20^LATER•kINEI .•. 'TOPN MGM i4.fi7 I04 LF 36'STEEL CASING"' .. S EELS A9F CC? MIN540XLE RESTRAINED JOINTS/ 36• � '.
BL STA 56.40 TO STA 57.30 4 TC♦4.65 • /RESTRAINED JOINTS/ MITI CLR 1 L �� I,;
M 0 L RE TRAINED JOINT 1'� I ' 'U'4.s.BV ' " ' VITON'IFNW'TYPE GASREYS " ' �.
34 1 a Nw T[ �.�♦®♦h♦ 34 Pe .
r S•�7��� . .. ...... . . Cityof d,Texas
.. • •'10r 4!/�j�'•�%,"14:4P•/4P•44;•'��%!474re;�14•%4 44 j••%i•%0149/ir&I.4 s4+®�!�- !'s.:,'...t OLD ALVIN ROAD
fr-2o 4s• BENDS .'•/•/•/�/•/•/•�••/•/•/•/•/•/•/•/•/�/�/� ••/•/•. .i.� 6'cx L AD • 20-INCH WATER UNE
32 -... ...... ...: .. ....... .... .... .... .......... . .. ......... .. .... �•• ♦I••••.•••••.4•••I. ••♦A ♦ 32
100' DEFLECTION PLAN A.PROFILE
ALONG BASELINE
_ STA 56+00 TO STA 60.00
30 •
- . ... ..... ......;. .... .....-_......... ... ... . 30 ...... :BIB SUET
;..:z
: 56 7+00 58+00 1�a ..n,..P.E
8 A, 21
59+00 60�00 ow,wL.n.,Hw,.He or 02
ripajoksill
L _ T E. X A S +�
Meeting Notes
Pre-Bid Meeting-Old Alvin Road Water Line—John Lizer Road to McHard Road
Meeting Date: May 16,2013
Meeting Time:9:00AM
Attendees: Sign-In Sheet is attached to these Meeting Notes
Meeting was opened at 9:05 AM by Mrs.Cara Davis
Mrs. Davis led the meeting through Introduction of Participants, Introduction of Project,and the Bidding
Process. Emphasis was put on the successful bidder submitting contract documents back to the City
very quickly. The City is interested in having this project constructed during the summer when school is
out.
Charles D. Gooden,Jr. led the meeting through the Project Overview, Preliminary Cost Estimate,
Contract,and Closing Comments. As part of the Project Overview, Mr. Gooden listed and discussed
(1117,
three special circumstances related to construction of this project:
1. Along Old Alvin Road from Plum to Town Ditch are the Pearland ISD Bus Barn,Pearland Public
Works, Pearland EMS, and Pearland Fire Department. There will be extensive coordination with
these organizations to minimize disruption during construction.
2. The wrought iron fence at Salem Village Apartments is to be removed and replaced. The
temporary chain link fence is to be erected for the safety and security of the residents. Plans do
not call for the removal of the motorized gate apparatus.
3. Potentially Petroleum Contaminated Area(PPCA)—exists near the intersection of Old Alvin Road
and FM 518. Spec section 02105 details handling of contaminated soils and ground water. Mr.
Gooden also noted that all items related to the PPCA are included in Items 27 and 31 of the bid
proposal as issued with the Project Manual.
Charles D. Gooden Consulting Engineers, Inc.TBPE#4176 Page 1 of 2
Phone(713) 660-6905 j Fax(713) 660-8817
2320 Holmes Road,Suite A, Houston,TX 77051
(7- VABbfkiktil
r c x n s
Questions as Posed by the Meeting Attendees
Q1.Who will provide construction surveying and staking?
Al.The contractor shall be responsible for construction surveying and staking.
Q2. Is there an area actually found to be contaminated? Question was raised because of the title of the
spec,"Potentially Petroleum Contaminated Area"
A2.Yes,there is an area found to be contaminated. See the Phase II Environmental Site Assessment for
contaminants,contaminant levels,and other details. Phase II Environmental Site Assessment was issued
with the project manual via the City's E-Bid Website.
Q3. Who will handle construction management/inspection?
Climb\ A3. UA Engineering represented by Curtis Villarreal, P.E.
Q4.Who will be responsible for the construction materials testing?
A4. The City will retain and pay for construction materials testing.
Q5. When do you anticipate issuing a notice-to-proceed?
A5. Throughout this process the City is requesting contractors to submit all bonds, qualifications,and
contract documents on an expedited basis. No date was given for a notice-to-proceed; however,it was
made clear that this project is to be submitted to Council on June 10,2013.
Meeting Adjourned at 9:45 AM.
Meeting notes were compiled and produced by Charles D. Gooden,Jr., (713)660-6905.
Distribution date: May 21,2013
(111\ Charles D. Gooden Consulting Engineers, Inc.TBPE#4176 Page 2 of 2
Phone(713) 660-6905 I Fax(713) 660-8817
2320 Holmes Road,Suite A, Houston,TX 77051
Old Alvin Road Water Line -John Lizer Rd to McHard Rd
F ,� Sign-In Sheet
Ttzi` May 16, 2013
www.cityofpearland.com/projects
Name(Print) Company Phone Number FAX Number Email
A/7
gg6-24o- �y� 6;' G�1�n���q��� �. 6 -ter
��`�7 l �1 Gc1/c�''[c� l 7 r��• � I- v� l / GQ,,, AeXC.O,'cd, c v�2
Lhci3 -CC(S-D fi93 713- s-Lf 23 `canQ €pbr ,Q7 J S-M.. CQ,•ri
�, C7 }-tll S C__ �`A CJML 1 l�O� Ili 555 �`��� ♦C.CM").
{
Admin 1 of 2 4.Revised 7/25/08
i
Name(Print) Company Phone Number FAX Number Email
1 eA1414, Ca.r - 246,1_0f 267p •' '�7-Yr
t_4 r-10 lc.c.Arre t't- -+''`i c 13noka l,A)t'1 .713 Soc ¶-f'-( ] 4.3/ krr Ie (.4-4 6t6,#lftclZ
i1R 7 & tCM" C yr -P-5 '7 B`1`6p 13'33 c se aoo(l9t Q +G.�!5- CD 11r'
L'{ '11 'I i l� V'r ;-U 1^1 l3'02igg 4,-;l i/ .glen?!/e•(C5'.ca
1
*To be included in consultant's meeting minutes
*Consultant can add incorporate their information to bring to meetings
Admin 2 of 2 4.Revised 7/25/08
rib\
i 1L x w e
Meeting Notes
Pre-Bid Meeting-Old Alvin Road Water Line—John Lizer Road to McHard Road
Meeting Date: May 23, 2013
Meeting Time:2:00PM
Attendees: Sign-In Sheet is attached to these Meeting Notes
Meeting was opened by Mrs.Cara Davis
Mrs. Davis led the meeting through Introduction of Participants, Introduction of Project, and the Bidding
Process. Mrs. Davis then led the meeting through the rest of the agenda.
Questions as Posed by the Meeting Attendees
Q1. How will Project be awarded?
Al. Lowest Responsible Bidder.
Q2. Deadline for questions is today?
A2.The deadline for questions will be extended to Tuesday, May 28,2013 at noon.
Q3.Will paper bids be accepted?
A3. Bidders are encouraged to utilize the City's E-Bid system. All bid proposal forms must be received by
the 2PM closing deadline.
Q4.Will City require pollution insurance?
A4. Refer to the Project Manual for environmental guidance.
Q5. Question was asked about the PPCA area and handling procedures for contaminated water and soil.
A5. Refer to the Project Manual for environmental guidance.
Q6. Is there more than one PPCA area?
A6.There is only one PPCA area called out on the construction drawings. On sheet 21 of 92,an •
erroneous call-out for Viton gaskets outside of the PPCA was removed.
Q7. Do fittings require mechanical restraints as well as thrustblocks?
A7. 20-inch line designed without thrustblocks. For all other lines, please observe City's standard detail.
C17:
Charles D.Gooden Consulting Engineers, Inc.TBPE#4176 Page 1 of 2
Phone(713) 660-6905 I Fax(713) 660-8817
2320 Holmes Road,Suite A, Houston,TX 77051
igow
Q8. Who will pay for power pole bracing and relocations?
A8.CenterPoint Energy has agreed to brace and/or relocate poles.
Q9.Who pays to relocate buried fiber-optic cables?
A9. Fiber optic cable in the right-of-way is the responsibility of the owner.
Q10.General Note 1,sheet 3,states that select fill is to be used under pavement, but Detail 4/1 of sheet
47B states that cement stabilized sand is to be used.
A10. Utility Note 1,Sheet 3 refers to select fill. Utility Note 1,Sheet 3 is hereby removed from the
construction drawings.
Q11. Did Engineer use Detail 4/1 on sheet 47B to calculate quantity for pavement removal?
All. Detail 4/1 on sheet 47B was used to calculate quantity for pavement removal.
Meeting minutes developed by Leon Hoch, P.E. and Charles Gooden,Jr.
Distribution date: May 28,2013. •
Attachment:Sign In Sheet
Charles D. Gooden Consulting Engineers, Inc.TBPE#4176 Page 2 of 2
Phone(713) 660-6905 I Fax(713) 660-8817
2320 Holmes Road,Suite A, Houston,TX 77051
7-) 7-) 7-1
L Q Egli' Tr-.�44 Old Alvin Road Water Line -John Lizer Rd to McHard Rd
" , Sign-In Sheet
` VIE May 23, 2013
N7.10? www.cityofpearland.com/projects
Name(Print) Company Phone Number FAX Number Email
-=( ( C (1)-76,-,-,4... op_5\c_ -71' -MF73- OO -7(s -473 -?ci 6 erisc cP ,7)P rcon`Lc-i :(1 n e-.
11�h z t-- r; 5 A) Co15 liz t7>-3 9 7.3 I c 7/.3'-)•-7 g j1( tsic A) a t-14-ri. )7 o ce .-
Admin 1 of 2 4.Revised 7/25/08
7-1) •/-) •/)
•
Name(Print) Company Phone Number FAX Number Email
77..47�/ ;i .A e) '1/-:1-- cam 42- y 1 rD.�trn
-I Try(4, StYuic2S •3a -sa4,4 a$1- y -t3oq 4 '��c4n�(}n)0121oSZYuit 5.4s✓' r
\Lel ste. vim` �txr.3 8 32-3�°1-qe, s. eve l�-z g+e ch.gs+crl�►ct
, J
*To be included in consultant's meeting minutes
'Consultant can add incorporate their information to bring to meetings
Admin 2 o 2 4.Revised 7/25/OS
CITY OF PEARLAND SUMMARY OF WORK
05/2008 01100- 1 of 3
Section 01100
SUMMARY OF WORK
1.0 GENERAL
1.01 SECTION INCLUDES
A A summary of the Work to be performed under this Contract,work by Owner,Owner
furnished products, Work sequence, future Work, Contractor's use of Premises, and
Owner occupancy.
1.02 WORK COVERED BY CONTRACT DOCUMENTS
A Work of the Contract is for the construction of :Old Alvin Road Water Line from John
Lizer Road to McHard Road. Approximately 13,000 linear feet of new 20-inch
diameter water line and associated service transfers, water line abandonment,
pavement removal and replacement,and storm sewer removal and replacement. The
storm sewer to be up-graded is approximately 1,400 linear feet;pipe sizes are 24",36",
and 48", box size is 5' x 4'. Control of surface and ground water; preparation and
implementation of a traffic control plan and storm water pollution prevention plan,and
all associated construction related permits are included in the scope.
(b.\ B Special circumstances exist along Old Alvin Road from Plum Street to Town Ditch.
This area houses the Pearland Independent School District Bus Barn,Pearland Public
Works Department,Pearland EMS,and Pearland Fire Department. The City may see
fit to limit working times in this area in order to accommodate the heavy traffic
produced by these operations. During the day,fire trucks will be lined up behind the
fire station and will exit through the gate on Orange Street. At night,any open trench
shall be covered with plates in order to allow the fire trucks to be parked in the bays.
While work is being performed at the EMS Station,the ambulance will be parked at
Fire Station 1. Any open trench between Linwood Street and Town Ditch shall be
covered with plates when work is not actively being performed.
C Open-cut construction method shall be used for the water line and storm sewer unless
otherwise shown on the drawings or instructed by the City Engineer. Any pavement
curbs,sidewalks,driveways,fences,gates,irrigation systems,or mailboxes that have
been distrubed shall be replaced with the same quality material or better.
D All existing utility service lines may not be shown on the drawings. Contractor will
anticipate that such service lines exist,and repair them at no additoinal cost to the City
if damaged during construction.
E A service connection tap shall be provided for each existing water meter; whether or
not shown on the drawings. Wye type branches are not acceptable. The information
on existing service connections represent the best informaiton available to the City and
Engineer and is not warrented to be complete.
CITY OF PEARLAND SUMMARY OF WORK
05/2008 01100- 1 of 3
CITY OF PEARLAND SUMMARY OF WORK
05/2008 01100-2 of 3
F The Contractor shall be responsible for field locating and avoiding sprinkler systems
during construction. The contractor at no additional cost to the City or Owner shall
repair any damage done to the sprinkler system by the Contractor with equal or better
materials and workmanship.
G Services are to be transferred between existing and proposed water lines with
minimum interruption to end user.
H Salvaged fire hydrants shall be returned to the City of Pearland Public Works
Department, 3501 East Orange Street, Pearland, TX 77581. Telephone (281) 652-
1900.
1.03 WORK BY OWNER
A None
1.04 OWNER FURNISHED PRODUCTS
A None
1.05 WORK SEQUENCE
A At present,no phases exist for the project. Owner may direct Contractor to begin work
between FM 518(Broadway)and Town Ditch to take advantage of low traffic periods
during the summer. The goal of such direction would be to perform intrusive work in
the vicinity of schools in this area when school is out for the summer.
B Contractor to submit project schedule to Engineer&Owner for approval as specified
in Section 01300—Submittals.
C Contractor shall coordinate the Work with the Engineer and Owner as specified in
Section 01040 - Coordination and Meetings.
1.06 FUTURE WORK
A None
1.07 CONTRACTOR'S USE OF PREMISES
A Comply with procedures for access to the site and Contractor's use of rights-of-way as
specified in Section 01140 -Contractor's Use of Premises.
B Contractor shall be responsible for all utilities required for construction.
1.08 OWNER OCCUPANCY
A Cooperate with the Owner to minimize conflict, and to facilitate the Owner's
�` operations. Coordinate Contractor's activities with Engineer.
\ CITY OF PEARLAND SUMMARY OF WORK
05/2008 01100-2 of 3
CITY OF PEARLAND SUMMARY OF WORK
05/2008 01100-3 of3
(11.1*.\ B Schedule Work to accommodate this requirement.
2.0 PRODUCTS -NotUsed
3.0 EXECUTION-NotUsed
END OF SECTION
CITY OF PEARLAND SUMMARY OF WORK
05/2008 01100-3 of 3
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
Section 01500
TEMPORARY FACILITIES AND CONTROLS
1.0 GENERAL
1.01 SECTION INCLUDES
A Temporary facilities and the necessary controls for the Work including utilities,
telephone, sanitary facilities, field office, storage sheds and building, safety
requirements,first aid equipment,fire protection,security measures,protection of the
Work and property, access roads and parking, environmental controls, disposal of
trash,debris,and excavated material,pest and rodent control,water runoff and erosion
control.
B References to Technical Specifications:
Section 00200—Instructions to Bidders
Section 01100—Summary of Work
Section 01350—Submittals
Section 01566—Source Controls for Erosion& Sedimentation
Section 01100—Summary of Work
(411"', Section 01600—Material&Equipment
Section 01570—Trench Safety System
Section 01555—Traffic Control&Regulation
Section 01720—Field Surveying
Section 01563 —Tree&Plant Protection
Section 01564—Control of Ground Water& Surface Water
Section 13730-Computer Equipment
C Referenced Standards:
Occupational Safety and Health Administration(OSHA)
National Fire Protection Association(NFPA)
Code of Ordinances, City of Pearland,Texas
D Definitions:
Underground Structures - sewer, water, gas, and other piping, and manholes,
chambers, electrical and signal conduits, tunnels, and other existing subsurface
installations located within or adjacent to the limits of the Work.
Surface Structures- existing buildings, structures and other constructed installations
above the ground surface. Included with such structures are their foundations or any
extension below the surface. Surface structures include, but are not limited to
12/2011 01500- 1 of 10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
buildings,tanks, walls,bridges,roads, dams,channels,open drainage,piping,poles,
wires,posts, signs, markers, curbs, walks, guard cables, fencing, and other facilities
that are visible above the ground surface.
1.02 MEASUREMENT AND PAYMENT
A Unless indicated as a Bid Item,no separate payment will be made for Work performed
under this Section. Include cost in Bid Items for which this Work is a component.
1.03 SUBMITTALS
A Make Submittals required by this Section under the provisions of Section 01350 —
Submittals.
1.04 CONTRACTOR'S RESPONSIBILITY
A The facilities and controls specified in this Section are considered minimum for the
Work. The Contractor may provide additional facilities and controls for the proper
execution of the Work and to meet Contractor's responsibilities for protection of
persons and property.
B Comply with applicable requirements specified in other Technical Specifications.
Maintain and operate temporary facilities and systems to assure continuous service.
Modify and extend systems as Work progress requires.
Completely remove temporary materials and equipment when their use is no longer
required.
Restore existing facilities used for temporary services to specified or to original
condition.
1.05 TEMPORARY UTILITIES
A Temporary Service
Make arrangements with utility service companies for such temporary services as are
necessary to construct the work and manage the site.
Abide by rules and regulations of the utility service companies or authorities having
jurisdiction.
Be responsible for utility service costs until the Work is Substantially Complete.
Included are fuel,power,light,heat,and other utility services necessary for execution,
completion,testing, and initial operation of the Work.
B Water
Provide water required for and in connection with Work to be performed and for
specified tests of piping, equipment, devices, or for other use as required for proper
completion of the Work.
12/2011 01500-2of10
CITY OFPEARLAND TEMPORARY FACILITIES AND CONTROLS
For water to be drawn from public water supply, obtain special permit or license and
meter from the proper City officials. For facilities under construction, establish a
water/sewer billing account with City's Utility Billing Department.A deposit based on
rates established by latest ordinance will be required.
For water drawn from fire hydrants,apply for and receive a construction water meter
from City'Public Works Department. Identify specific location for construction water
meter installation. Once installed,water meter may not be moved without notification
of Public Works Department. Install backflow preventer on fire hydrant supply if not
included in City provided meter.
Provide and maintain an adequate supply of potable water for domestic consumption
by Contractor personnel.
C Electricity and Lighting
1 Provide temporary electric power service in Contractor's name, as required for the
prosecution of the Work, including testing of Work. Provide power for lighting,
operation of the Contractor's equipment, or for any other use by Contractor or as
necessary to maintain any of Owner's on-going operations as may continue on the site
during any scheduled shutdown. Minimum lighting level shall be 5 foot-candles for
open areas; 10 foot-candles for stairs and shops.
2 Provide permanent electric power service,in the Contractor's name,to the work or site
as and when required by the schedule of the work to achieve Substantial Completion or
Partial Substantial Completion.Contractor to establish service billing in its name and
transfer service and billing to the Owner upon acceptance of the work as Substantially
Complete and suitable for beneficial occupancy by the Owner.
D Natural Gas
Provide and pay for natural gas service to the work as and when required by the
schedule to achieve Substantial Completion. Contractor to establish service billing in
its name and transfer service and billing to the Owner upon acceptance of the work as
Substantially Complete and suitable for beneficial occupancy by the Owner.
E Temporary Heat and Ventilation
Provide temporary heat as necessary for protection or completion of the Work.
Provide temporary heat and ventilation to assure safe working conditions; maintain
enclosed areas at a minimum of 50 degrees F.
F Telephone
Provide emergency telephone service at the Project Site for use by Contractor
personnel and others performing work or furnishing services.
G Sanitary Facilities
Provide and maintain sanitary facilities for persons on the Project Site,in compliance
with federal, state, and local regulations. Locate toilets on the Project Site near the
12/2011 01500-3of10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
,°1116' work and secluded from view insofar as possible. Keep toilets clean and supplied
throughout the course of the Work.
Enforce the use of sanitary facilities by construction personnel at the Project Site.
Such facilities shall be enclosed. Pit-type toilets will not be permitted. No discharge
will be allowed from these facilities. Collect and store sewage and waste so as not to
cause a nuisance or health problem; have sewage and waste hauled off-site and
properly disposed in accordance with local regulations.
Control areas where sanitary facilities are located in conformance with Section 01566
— Source Controls for Erosion& Sedimentation.
1.06 FIELD OFFICE
A Provision of a Field Office and other specific associated amenities as required in
paragraph B below UNLESS otherwise stated in Section 00800 - Special
Conditions of the Agreement,or Section 01100—Summary of Work. Provide for
transportation,move-in,set-up,tie-down and,when project is complete,removal and
move-out. The Contractor shall confirm location of office and other temporary
facilities with Owner's Representative at Pre-Construction Meeting prior to delivery
and set up. Location of temporary facilities shall be approved by the Owner's
Representative by way of the submittal process.
B. At a minimum, the Contractor's field office shall provide for, contain or serve to:
provide a secured space for project administrative operations, periodic progress
meetings,on-site storage for project files and plans,office space for CONTRACTOR's
field supervisory personnel and provide a separate securable office space for
OWNER's Representative including: meeting table and chairs, a single two drawer
filing cabinet,a built-in drawing table and plan holders. Provide electric lighting and
HVAC to the mobile office.
1. Field Office shall provide for, at a minimum,a high speed internet connection for
use by Owner's Representative or Construction Manager as controlled by Paragraph A
above.
1.07 STORAGE OF MATERIALS
A Provide for storage of materials under the provisions of Section 01600—Material&
Equipment.
1.08 SAFETY REQUIREMENTS
A Contractor shall prepare, submit and follow a Safety Program that complies with
federal, state, and local safety codes, statutes, and practices. Include in the Safety
Program documented response to excavation, embankment, and trench safety
requirements as specified in Section 01570—Trench Safety System.
B Conduct operations in strict accord with applicable federal,state and local safety codes
and statutes and with good construction practice. The Contractor is fully responsible
and obligated to establish and maintain procedures for safety of all work,personnel
and equipment involved in the Work.
12/2011 01500-4 of 10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
C Observe and comply with Texas Occupational Safety Act (Art. 5182a, V.C.S.) and
with all safety and health standards promulgated by Secretary of Labor under Section
107 of Contract Work Hours and Standards Act,published in OSHA Standards -29
CFR, Part 1926, and adopted by Secretary of Labor under the Williams-Steiger
Occupational Safety and Health Act of 1970,and to any other legislation enacted for
safety and health of Contractor employees. Such safety and health standards apply to
subcontractors and their employees as well as to the Contractor and its employees.
D Observance of and compliance with the regulations shall be solely and without
qualification the responsibility of the Contractor without reliance or superintendence of
or direction by the Engineer or the Engineer's representative. Immediately advise the
Engineer of investigation or inspection by Federal Safety and Health inspectors of the
Contractor or subcontractor's work or place of work on the Project Site under this
Contract,and after such investigation or inspection,advise the Engineer of the results.
Submit one copy of accident reports to Engineer within ten(10) days of occurrence.
E Protect areas occupied by workmen using the best available devices for detection of
lethal and combustible gases. Test such devices frequently to assure their functional
capability. Constantly observe infiltration of liquids into the Work area for visual or
odor evidence of contamination. Take immediate and appropriate steps to seal off
entry of contaminated liquids to the Work area.
F Safety measures, including but not limited to safety personnel, first-aid equipment,
ventilating equipment and safety equipment,in the Plans and Technical Specifications
are obligations of the Contractor.
G Maintain required coordination with the local Police and Fire Departments during the
entire period covered by the Contract.
1.09 FIRST AID EQUIPMENT
A Provide a first aid kit throughout the construction period. List telephone numbers for
physicians,hospitals, and ambulance services in each first aid kit.
B Have at least one person thoroughly trained in first aid procedures present on the
Project Site whenever work is in progress.
1.10 FIRE PROTECTION
A Fire Protection Standards.
Conform to specified fire protection and prevention requirements as well as those that
may be established by Federal, State, or local governmental agencies.
B. Comply with all applicable provisions of NFPA Standard No. 241, Safeguarding
Building Construction and Demolition Operations.
Provide portable fire extinguishers, rated not less than 2A or 5B in accordance with
NFPA Standard No. 10,Portable Fire Extinguishers,for each temporary building,and
(111b. for every 3000 square feet of floor area of facilities under construction.
12/2011 01500-5 of 10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
Locate portable fire extinguishers within 50 feet maximum from any point on the
Project Site.
C. Fire Prevention and Safety Measures.
Prohibit smoking in hazardous areas. Post suitable warning signs in areas that are
continuously or intermittently hazardous.
Use metal safety containers for storage and handling of flammable and combustible
liquids.
Do not store flammable or combustible liquids in or near stairways or exits.
Maintain clear exits from all points within a structure.
1.11 SECURITY MEASURES
A Protect all materials, equipment, and property associated with the Work from loss,
theft,damage,and vandalism. Contractor's duty to protect property includes Owner's
property.
B If existing fencing or barriers are breached or removed for purposes of construction,
provide and maintain temporary security fencing equal to existing as approved by
Owner's Representative.
1.12 PROTECTION OF PUBLIC UTILITIES
A Prevent damage to existing public utilities during construction. These utilities are
shown on the Plans at their approximate locations. Give owners of these utilities at
least 48 hours notice before commencing Work in the area, for locating the utilities
during construction,and for making adjustments or relocation of the utilities when they
conflict with the proposed Work.
1.13 PROTECTION OF PEOPLE AND PROPERTY
A Preventive Actions.
Take precautions,provide programs, and take actions necessary to protect the Work
and public and private property from damage.
Take action to prevent damage, injury or loss, including, but not limited to, the
following:
a. Store apparatus,materials,supplies,and equipment in an orderly,safe
manner that will not unduly interfere with progress of the Work or the
Work of any other contractor, any utility service company, or the
Owner's operations.
b. Provide suitable storage for materials that are subject to damage by
exposure to weather,theft,breakage, or otherwise.
c. Place upon the Work or any part thereof only such loads as are
consistent with the safety of that portion of the Work.
d. Frequently clean up refuse,rubbish,scrap materials,and debris caused
, by construction operations,keeping the Work safe and orderly.
12/2011 01500-6 of 10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
e. Provide safe barricades and guard rails around openings, for
scaffolding, for temporary stairs and ramps, around excavations,
elevated walkways,and other hazardous areas.
Obtain written consent from proper parties before entering or occupying with workers,
tools,materials or equipment,privately owned land except on easements provided for
construction.
Assume full responsibility for the preservation of public and private property on or
adjacent to the site. If any direct or indirect damage is done by or on account of any
act, omission, neglect, or misconduct in execution of the Work by the Contractor, it
shall be restored by the Contractor to a condition equal to or better than that existing
before the damage was done.
B Barricades and Warning Signals.
Where Work is performed on or adjacent to any roadway, right-of-way, or public
place, furnish and erect barricades, fences, lights,warning signs,and danger signals;
provide watchmen;and take other precautionary measures for the protection of persons
or property and protection of the Work.Conform to Section 01555—Traffic Control&
Regulation.
C Preserving Control Points
Maintain permanent benchmarks,public or private elevation or property demarcation
and control monumentation, or other reference points. Unless otherwise directed in
writing,replace at no cost to the Owner,those monuments,property corners or other
permanent demarcations that are damaged or destroyed in accordance with Section
01720—Field Surveying.
D Tree and Plant Protection.
Protect trees,shrubs,lawns,outside of grading limits and within the grading limits as
designated on the Plans,and in accordance with requirements of Section 01563—Tree
&Plant Protection.
E Protection of Underground and Surface Structures
Known underground structures, including water, sewer, electric, and telephone
services are shown on the Plans in accordance with the best information available,but
is not guaranteed to be correct or complete. Contractor is responsible for making
Locate Calls.
Explore ahead of trenching and excavation work and uncover obstructing underground
structures sufficiently to determine their location, to prevent damage to them and to
prevent interruption of utility services. Restore to original condition damages to
underground structure at no additional cost to the Owner.
Immediately notify the agency or company owning any existing utility which is
damaged,broken,or disturbed. Obtain approval from the Engineer and agency for any
repairs or relocations, either temporary or permanent.
12/2011 01500-7 of 10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
Necessary changes in location of the Work may be made by the Engineer to avoid
(/111"\
unanticipated underground structures.
If permanent relocation of an underground structure or other subsurface installations is
required and not otherwise provided for in the Contract Documents,the Engineer will
direct Contractor in writing to perform the Work, which shall be paid for under the
provisions for changes in the Contract Price as described in Section 00700—General
Conditions of Agreement.
Support in place and protect from direct or indirect injury to underground and surface
structures located within or adjacent to the limits of the Work. Install such supports
carefully and as required by the party owning or controlling such structure. Before
installing structure supports,Contractor shall satisfy the Engineer that the methods and
procedures to be used have been approved by the owner of the structure.
Avoid moving or in any way changing the property of public utilities or private service
corporations without prior written consent of a responsible official of that service or
public utility. Representatives of these utilities reserve the right to enter within the
limits of this project for the purpose of maintaining their properties,or of making such
changes or repairs to their property that may be considered necessary by performance
of this Contract.
Notify the owners and/or operators of utilities and pipelines of the nature of
construction operations to be performed and the date or dates on which those
operations will be performed. When construction operations are required in the
rubh immediate vicinity of existing structures,pipelines,or utilities,give a minimum of five
(5)working days advance notice. Probe and flag the location of underground utilities
prior to commencement of excavation. Keep flags in place until construction
operations reach and uncover the utility.
Assume risks attending the presence or proximity of underground and surface
structures within or adjacent to the limits to the Work including but not limited to
damage and expense for direct or indirect injury caused by the Work to any structure.
Immediately repair damage caused, to the satisfaction of the owner of the damaged
structure.
1.14 PROTECTION OF THE WORK
Provide protection of installed products to prevent damage from subsequent
operations.
Remove protection facilities when no longer needed,prior to completion of the Work.
Control traffic to prevent damage to equipment, materials, and surfaces.
1.15 ROADS AND PARKING
A Prevent interference with traffic and Owner operations on existing roads.
B Minimize use of existing streets and driveways by construction traffic.
C Control traffic to prevent damage to equipment,materials, and surfaces.
CaRb.\
12/2011 01500-8of10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
D Construct and maintain temporary detours, ramps, and roads to provide for normal
public traffic flow when use of public roads or streets is closed by necessities of the
Work.
E Provide mats or other means to prevent overloading or damage to existing roadways
from tracked equipment or exceptionally large or heavy trucks or equipment
F Designate temporary parking areas to accommodate construction personnel. When site
space is not adequate, provide additional off-site parking. Locate as approved by
Engineer.
G Do not allow heavy vehicles or construction equipment unnecessarily in existing
parking areas.
1.16 ENVIRONMENTAL CONTROLS
A Provide and maintain methods, equipment, and temporary construction as necessary
for controls over environmental conditions at the construction site and adjacent areas.
B Comply with statutes,regulations,and ordinances which relate to the proposed Work
for the prevention of environmental pollution and preservation of natural resources,
including but not limited to the National Environmental Policy Act of 1969, PL 91-
190,Executive Order 11514.
C Provide, install and maintain storm water runoff control including but not limited to
temporary entrance, silt fencing, etc. as specified in Contract Documents.
D Recognize and adhere to the environmental requirements of the Project. Disturbed
areas shall be strictly limited to boundaries established by the Contract Documents.
Burning of rubbish,debris or waste materials is not permitted.
1.17 POLLUTION CONTROL
A Provide methods,means,and facilities required to prevent contamination of soil,water
or atmosphere by discharge of noxious substances from construction operations.
B Provide equipment and personnel to perform emergency measures required to contain
any spillage,and to remove contaminated soils or liquids. Excavate and dispose of any
contaminated earth off-site, and replace with suitable compacted fill and topsoil.
C Take special measures to prevent harmful substances from entering receiving streams
or storm water conveyance systems in conformance with TPDES requirements and
Section 01566—Source Controls for Erosion& Sedimentation.
D Provide systems for control of atmospheric pollutants.
Prevent toxic concentrations of chemicals.
Prevent harmful dispersal of pollutants into the atmosphere.
12/2011 01500-9 of 10
CITY OF PEARLAND TEMPORARY FACILITIES AND CONTROLS
(111. E Use equipment during construction that conforms to current federal, state, and local
laws and regulations.
1.18 PEST AND RODENT CONTROL
A Provide rodent and pest control as necessary to prevent infestation of Project Site.
B Employ methods and use materials which will not adversely affect conditions at the
Project Site or adjoining properties.
1.19 NOISE CONTROL
A Provide vehicles, equipment, and construction activities that minimize noise to the
greatest degree practicable. Noise levels shall conform to OSHA Standards- 29 CFR
and in no case will noise levels be permitted which create a nuisance in the
surrounding neighborhoods.
B Conduct construction operations during daylight hours from 7:30 a.m. to 6:00 p.m.
except as approved by Engineer.
C Comply with Chapter 19 NOISE,Codes of Ordinances, City of Pearland,Texas.
1.20 DUST CONTROL
A Control objectionable dust caused by operation of vehicles and equipment under the
provisions of Section 01566—Source Controls for Erosion& Sedimentation.
1.21 WATER RUNOFF AND EROSION CONTROL
A Provide methods to control surface water,runoff,subsurface water,and water pumped
from excavations and structures to prevent damage to the Work, the Project Site, or
adjoining properties in accordance with Section 01564—Control of Ground Water&
Surface Water and Section 01566—Source Controls for Erosion& Sedimentation.
B Inspect earthwork periodically to detect any evidence of the start of erosion. Apply
corrective measures as required to control erosion.
2.0 PRODUCTS - Not Used
3.0 EXECUTION - NotUsed
END OF SECTION
12/2011 01500- 10 of 10
CITY OF PEARLAND MOBILIZATION
CIPik\ Section 01505
MOBILIZATION
1.0 GENERAL
1.01 SECTION INCLUDES
A Mobilization of construction equipment and facilities onto the Work.
B Referenced Standards:
1. Texas Department of Transportation(TxDOT)
2. Texas Manual on Uniform Traffic Control Devices (Texas MUTCD)
1.02 MEASUREMENT AND PAYMENT
A. Payment for Mobilization is on a Lump Sum basis and shall not exceed three
percent(3%) of the total bid price.
B. Payment for 50% of the Mobilization lump sum bid item may be included in the
first monthly Application for Payment. Payment is subject to the receipt and
approval by Engineer of the following items, as applicable:
1. Schedule of Values (Section 01350—Submittals)
(11.6\ 2. Trench Safety Program(Section 01570—Trench Safety System)
3. Construction Schedule(Section 01350—Submittals)
4. Pre-construction Photographs (Section 01380—Construction Photographs)
5. Installation and acceptance of Project Identification Sign(s) (Section
01580—Project Identification Signs)
6. Installation and acceptance of Field Office(Section 01500—Temporary
Facilities and Controls)
7. Installation and acceptance of TPDES requirements (Section 01565 -
TPDES Requirements)
C. Payment for 25% of the Mobilization lump sum bid item may be included in the
second monthly Application for Payment. Payment is subject to the receipt and
approval by Engineer of the following items, as applicable:
1. Installation of High Speed Internet Access (Section 01500—Temporary
Facilities and Controls)
2. Laptop Computer(Section 00800—Special Conditions of Agreement)
D. Payment for 15%of the Mobilization lump sum bid item may be included in the
third monthly Application for Payment.
E. Payment for the remaining 10%of the Mobilization lump sum bid item may be
included in the fourth monthly Application for Payment.
09/2012 01505- 1 of 1
CITY OF PEARLAND MOBILIZATION
G. Mobilization payments will be subject to Retainage as stipulated in Section 00700
General Conditions of Agreement.
2.0 PRODUCTS
2.01 PROJECT IDENTIFICATION SIGNS
A. Provide specified number of project identification sign(s)per Section 01580. The
name, address and contact information of the general contractor for the project
shall be shown on the sign per Section 01580 and the attached exhibit.
3.0 EXECUTION
3.01 PLACEMENT OF PROJECT IDENTIFICATION SIGNS
A. Place a Project Identification Sign as described in Section 01580,part 1.03, D
visible to passing traffic or as directed by Engineer.
END OF SECTION
09/2012 01505 - 1 of 1
CITY OF PEARLAND TPDES REQUIREMENTS
(1111b.\ Section 01565
TPDES REQUIREMENTS
1.0 GENERAL
A DEFINITIONS
As used herein and in conjunction with TPDES General Permit No.TXR150000,the
term OPERATOR refers to the CONTRACTOR.
1.01 SECTION INCLUDES
A Description of the required documentation to be prepared signed and submitted by the
Contractor before conducting construction operations, in accordance with the terms
and conditions of the Texas Pollutant Discharge Elimination System(TPDES)General
Permit TXR150000 as issued March 5, 2003 and re-issued March 5, 2008, by the
Texas Commission on Environmental Quality under the provisions of Section 402 of
the Clean Water Act and Section 26.040 of the Texas Water Code.
B Contractor's responsibility for implementation,maintenance,and inspection of storm
water pollution prevention control measures including,but not limited to,erosion and
sediment controls,storm water management plans,waste collection and disposal,off-
site vehicle tracking,and other practices shown on the Plans or specified elsewhere in
this or other Technical Specifications.
C References to Technical Specifications:
1. Section 01350—Submittals
2. Section 01310—Coordination&Meetings
3. Section 01770—Contract Closeout
D Referenced Standards:
1. Texas Commission on Environmental Quality(TCEQ)
E Other References:
1. Storm Water Pollution Prevention Plan(SWPPP) found in Appendix A of
these Technical Specifications.
1.02 MEASUREMENT AND PAYMENT
A Unless indicated as a Bid Item,no separate payment will be made for Work performed
under this Section. Include cost in Bid Items for which this Work is a component.
1.03 SUBMITTALS
A Make Submittals required by this Section under the provisions of Section 01350 —
Submittals.
2.0 PRODUCTS - Not Used
01/2008 01565- 1 of 3
CITY OF PEARLAND TPDES REQUIREMENTS
3.0 EXECUTION
3.01 REQUIRED NOTICES
A The Contractor shall complete,sign,and date the Contractor's Notice of Intent(NOD
attached in Appendix A. The Contractor's NOI shall be submitted to the TCEQ. It is
the Contractor's responsibility to pay for any fees associated with the permit.
Submission of the NOI is required by the Contractor before construction operations
begin.
B Upon completion of construction and acceptance of the Work by the Owner, the
Contractor shall complete, sign, date and submit the Contractor's Notice of
Termination(NOT) attached in Appendix A.
3.02 CERTIFICATION REQUIREMENTS
A On the Operator's Information form attached in Appendix A, the Contractor shall
complete name, address, and telephone number for the Contractor; the names of
persons or firms responsible for maintenance and inspection of erosion and sediment
control and Subcontractors.
B The Contractormeasures and Subcontractors named in the Contractor's Information form shall
read, sign, and date the Contractor's/Subcontractor's Certification form, attached in
Appendix A.
\! C The persons or firms responsible for maintenance and inspection of erosion and
sediment control measures shall read, sign, and date the Contractor's Inspection and
Maintenance Certification form,attached in Appendix A.
D The Contractor's Information form and all certification forms shall be submitted to the
Owner before beginning construction.
E Contractor shall review implementation of the SWPPP in a meeting with the Owner
and Engineer prior to start of construction in accordance with Section 01310 —
Coordination&Meetings.
3.03 RETENTION OF RECORDS
A The Contractor shall keep a copy of the SWPPP at the Project Site or at the
Contractor's office from the date that it became effective to the date the Work is
accepted by the Owner.
B At Contract Closeout,the Contractor shall submit to the Owner all TPDES forms and
certifications, as well as a copy of the SWPPP, in accordance with Section 01770—
Contract Closeout. The SWPPP records and data will be retained by Owner for a
period of 3 years from the date the Work is accepted by the Owner.
01/2008 01565-2 of 3
CITY OF PEARLAND TPDES REQUIREMENTS
3.04 POSTING OF NOTICES
A The following notices shall be posted from the date that this SWPPP goes into effect
until the date the Work is accepted by the Owner:
1. Copies of the Notices of Intent submitted by the Contractor and a brief
Description of Construction Activity being conducted at the Project Site,as
given in Article 1 of the SWPPP, shall be posted at the Project Site or at
Contractor's office in a prominent place for public viewing.
2. Notice to drivers of equipment and vehicles, instructing them to stop,check,
and clean tires of debris and mud before driving onto traffic lanes. Post
such notices at every stabilized construction exit area.
3. In an easily visible location on Project Site,post a notice of waste disposal
procedures.
4. Notice of hazardous material handling and emergency procedures shall be
posted with the NOI on Project Site. Keep copies of Material Safety Data
Sheets at a location on Project Site that is known to all personnel.
5. Keep a copy of each signed certification at the Project Site or at Contractor's
office.
APPENDIX A(PAGE 1 —50)FOLLOWS THIS SECTION
END OF SECTION
01/2008 01565-3 of 3
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
Section 02105
SAMPLING AND ANALYSIS IN PPCA
PART1 GENERAL
1.01 SECTION INCLUDES
A. Preparatory work related to site remediation and excavation in a Potentially
Petroleum Contaminated Area(PPCA).
B. Sampling and analysis of site material.
1.02 MEASUREMENT AND PAYMENT
A. Unit Prices
1. Preparatory work is paid on a lump sum basis. Item includes hiring
environmental consultants,preparing Environmental Health and Safety Plan,
preparing Environmental Work Plan, training personnel, and obtaining permits
and additional insurance.
2. Underground Utility construction in PPCA
CIilk\
a. Underground utility construction and appurtenances in areas identified
within PPCA limits is on a linear foot basis, each basis, or lump sum basis,
as shown in Document 00300 -Bid Proposal.
b. Payment includes compensation for labor, equipment, and supervision for
mobilization, environmental monitoring and field screening,handling,
sampling, and testing of contaminated soil and ground water.
Contaminated soil may be Category I or II. Contaminated groundwater
will be that encountered during excavation for underground utilities and
flowing at a rate not greater than 20 gallons per minute. Included in this
pay item is incremental cost for upgraded piping, gaskets, and appurtenant
materials.
c. Limits of measurement under this section are noted on Drawings as
"Begin PPCA Excavation"and"End PPCA Excavation,"and other areas
determined by the Engineer during the course of the work.
d. Payment will be made upon receipt of field test reports from approved
analytical laboratory.
3. Refer to Section 01200 -Measurement and Payment for unit price procedures.
B. Stipulated Price(Lump Sum). If the Contract is a Stipulated Price Contract,payment
, ilh\ for work in this Section is included in the total Stipulated Price.
02105-1
October 2008
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
CW' 1.03 REFERENCE STANDARDS
A. ASTM D 5092 -Practice for Design and Installation of Groundwater Monitoring
Wells in Aquifers.
B. Code of Federal Regulation(CFR),Title 40, Section 261.24-Protection of the
Environment.
C. CFR,Title 29, Section 1910.120 -Occupational Safety and Health Administration,
Department of Labor
D. CFR,Title 29, Section 1926. -Occupational Safety and Health Administration,
Department of Labor
E. CFR,Title 40, Section 261,Appendix II. -Protection of the Environment.
F. Texas Administrative Code(TAC),Title 30,Chapter 335 -Industrial Solid Waste&
Municipal Hazardous Waste.
G. TAC,Title 30, Chapter 334 -Underground and Aboveground Storage Tanks
H. TAC,Title 30, Chapter 106.533 -Exemptions from Permitting, Subchapter X. Waste
Processes and Remediation.
I. U.S. Environmental Protection Agency(EPA), (SW-846)Test Methods for
Evaluating Solid Waste, Office of Solid Waste and Emergency Response,
Washington,D.C. (P1388-239223,November 1986).
J. Texas Commission on Environmental Quality(TCEQ) (formerly Texas Natural
Resource Conservation Commission(TNRCC)) Interoffice Memo, dated 4/12/94,by
Chris Chandler, RPR Section,PST Division,regarding"Revised Procedures for
Classifying and Assigning Waste Codes for Underground and Aboveground
Petroleum Storage Tank Wastes(text attached following this section).
1.04 DEFINITIONS
A. Petroleum: Crude oil,natural gas,natural gas liquids, liquified natural gas, and
synthetic gas usable for fuel, as well as distillates of crude oil including gasoline,
kerosene, diesel oil,motor oil,waste oil,jet fuels, and fuel oil.
B. Potentially Petroleum Contaminated Area(PPCA): An area within station-to-station
locations identified on Drawings where petroleum contamination has been detected in
the soil or groundwater. PPCA also includes areas where contamination is suspected
or encountered during utility installation outside areas identified on Drawings,and
such contamination has been verified by the Engineer.
C. Category I Soil: Soil containing visual or physical evidence of contamination,as
described in paragraph 3.01, and that is not Category II Soil.
02105-2
October 2008
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
(00W,
D. Category II Soil: Soil that contains petroleum contamination in excess of levels
identified in paragraph 3.04, and is consistent with a classification as Special Waste-
PST as defined by TCEQ (formerly TNRCC) in their interoffice memo dated 4/12/94,
or soil that contains visible free product or is impacted with non-petroleum
compounds detected above Risk Reduction Standard Number 2 levels as defined in
the Texas Administrative Code,Title 30, Chapter 335.
E. Potentially Contaminated Groundwater: Water recovered in a groundwater control
system located in PPCA or groundwater that contains visual or physical evidence of
contamination,as described in paragraph 3.01, and such contamination has been
verified by the Engineer.
1.05 SUBMITTALS
A. Conform to requirements of Section 01350- Submittal Procedures.
B. Submit an Environmental Work Plan within 30 days after issuance of Notice to
Proceed.
1. Environmental Work Plan to be prepared by a Corrective Action Project Manager
licensed in Texas, who has completed 40-hours of Health and Safety Training and
the required annual refresher training, and in the employment of a registered
Corrective Action Specialist firm.
2. Environmental Work Plan shall include the following items. Compile and arrange
in format acceptable to TCEQ.
a. Proposed sequence of construction through PPCA;
b. Procedures for screening soil in PPCA, identifying Category I or II Soil;
c. Procedures for handling material from PPCA;
d. Proposed location of stockpile areas;
e. Proposed reuse of Category I Soil as trench backfill below depths of 30
inches;
f. Proposed methods for disposal or recycling of Category I or II Soil;
g. Proposed carriers of Category I or II Soil or potentially contaminated
groundwater with verification each is properly licensed;
h. Proposed recycle/disposal sites for Category I or II Soil or potentially
contaminated groundwater with verification that each is properly licensed;
i. Copy of permit required for discharge of potentially contaminated
groundwater in sanitary sewer system, if to be disposed in sanitary sewer;
02105-3
October 2008
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
j. Name and qualifications of Corrective Action Project Manager and
professional environmental consultants for health, environmental, and
safety issues regarding operations within PPCA; and,
k. Proposed analytical laboratory with verification it is accredited by A2LA
or other recognized association, or it is a participant in the EPAs
Performance Evaluation Program.
3. Do not commence work in PPCA until Environmental Work Plan has been
reviewed and accepted by the Engineer.
C. Submit Environmental Health and Safety Plan within 30 days after issuance of Notice
to Proceed.
1. The Health and Safety Plan shall be prepared by a Corrective Action Project
Manager licensed in Texas,who has completed 40 hours of health and safety
training, and required annual refresher training, or a Certified Industrial
Hygienist.
2. Include methods and procedures for assuring work,which will be conducted
under conditions expected in the field, is safe.
D. As work proceeds, submit field screening,monitoring and analytical laboratory test
results on a weekly basis for soil and on a daily basis for groundwater. Summarize
test results in tables together with applicable regulatory criteria.
E. Submit copies of correspondence,reports,permits and other documents provided to,
or received from,regulatory agencies.
1.06 PERSONNEL REQUIREMENTS
A. Provide trained personnel who have completed minimum health and safety programs
specified by the Occupational Safety and Health Administration in 29 CFR 1910.120.
Before beginning work at the site, each employee that will work in PPCA is required
to have completed 40 hours health and safety training and the required annual
refresher training.
PART2 PRODUCTS
2.01 MATERIALS
A. Do not use polyvinyl chloride or other plastic material,unless approved by Engineer.
B. Water Line Pipe Material.
1. Furnish ductile-iron pipe or steel pipe material within station-to-station locations
identified as PPCA on Drawings.
2. Provide restrained joints for ductile-iron pipe or welded joints for steel pipe.
02105-4
October 2008
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
(11166\ 3. Provide pipe material conforming to Section 02634-Ductile-Iron Pipe and
Fittings or Section 02635 - Steel Pipe and Fittings.
C. Use Viton(FKM) type gaskets,or other material as recommended by the pipe
manufacturer, for water lines, sanitary and storm sewer pipe, and appurtenances
requiring gaskets.
PART3 EXECUTION
3.01 POTENTIALLY PETROLEUM CONTAMINATED AREAS
A. Conduct operations in PPCA in accordance with the accepted Environmental Work
Plan and the Environmental Health and Safety Plan and to minimize the spread of
contamination. In other areas which are either detected or suspected to be potentially
petroleum contaminated areas, immediately notify the Engineer and proceed with
work in accordance with this Section,unless otherwise directed by Engineer.
B. Immediately notify the Engineer and TCEQ's Region 12 Field Office whenever
Category I or II Soil or potentially contaminated groundwater are encountered.
1. Provide location, depth, type(soil or groundwater), source(if known),and
evidence of suspected contamination.
2. Determine if Category I Soil or potentially contaminated groundwater is present
by visual or physical evidence of contamination. Visual or physical evidence
includes:
a. Petroleum or chemical odor
b. Indication of levels of contamination by air monitoring devices employed
as part of the Environmental Health and Safety Plan.
c. Soil or groundwater discoloration.
d. Material oozing/dripping into excavation.
e. Liquid or oily sheen floating on groundwater
f. Buried containers or refuse.
g. Field screening"head-space"results in excess of a 25 ppm reading on a
photoionization detector(PID)or flame ionization detector(FID).
C. Install piping and gasket materials and appurtenances in conformance with
appropriate section, except as modified in this Section.
D. Construct trench dams within a utility trench at each boundary of PPCA and laterals
to minimize potential for contaminant transport within pipe bedding material. A
® trench dam shall consist of at least 24 inches of cement stabilized sand with 10
` 02105-5
October 2008
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
percent bentonite clay added, extending from 6 inches below bottom of trench to
within 12 inches of limits of topsoil or pavement.
3.02 ENVIRONMENTAL MONITORING
A. An environmental consultant shall monitor conditions in PPCA,as specified in the
Environmental Health and Safety Plan. Maintain safe working conditions in
accordance with OSHA requirements (29 CFR 1926).
3.03 SCREENING PPCA SOILS
A. An environmental consultant shall perform field screening of soil removed from
excavation or tunneling in PPCA.
B. Screening Procedures.
1. Place samples in a sealed plastic bag and place in a warm location for 15 minutes
prior to screening.
2. Properly calibrate the PID/FID using a calibration gas. For PID use 100 ppm
isobutylene and for FID use 100 ppm methane.
3. Open bag just enough to insert instrument probe and take maximum headspace
(� reading.
4. Screen at least twice per hour while removing soils in open cut areas or shafts.
5. During tunneling, screen once for each pipe length in pipe jacked tunnels or each
advance of tunnel shield in primary-lined tunnels. Screen at least once per shift
where excavating.
3.04 SAMPLING AND TESTING
A. Frequency.
1. Sample soil in PPCA at a rate of not less than one composite sample for every
20 cubic yards of excavation or volume corresponding to every 50 linear feet of
installed underground utility,whichever is more frequent.
2. Sample water from PPCA to be discharged to a sanitary sewer one week prior to
initiation of discharge, and at a rate of one grab sample once per day during
discharge to sanitary sewer.
B. Analyze soil samples for parameters listed in Table 02105, Soil Criteria-Petroleum
Only,and in accordance with SW-846. Handle as a Category II Soil if analytical
results indicate any one, or more,parameters exceed allowable Maximum
Concentration listed in Table 02105-1. If benzene concentration from composite
sample is greater than 5 milligrams per kilogram(mg/kg) or lead concentration is
( ik\ •
greater than 30 mg/kg,perform Toxicity Characteristic Leaching Procedure(TCLP)
02105-6
October 2008
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
(.16\ analysis of appropriate compound for that sample to determine if a more stringent
disposal classification is warranted. If contaminants other than petroleum are
suspected, immediately notify the Engineer who will determine the list of parameters
to be analyzed. Use a 4-part representative composite sample for analysis parameters,
except when inconsistent with SW-846.
C. Analyze groundwater samples for discharge to sanitary sewers. Analyze samples for
BTEX by EPA Method 602, 8020,or 8021; TPH by Method TX 1005; and LEL in
accordance with EPA Method 1010.
D. Conduct analyses by proposed analytical testing laboratory listed in Environmental
Work Plan.
3.05 EXCAVATION MONITORING REQUIREMENTS
A. Ensure health and safety of workers at the construction site. Maintain air quality
within the construction zone to conform to exposure limits specified in Code of
Federal Regulations(CFR) Title 29, Section 1910.120 enforceable by OSHA.
B. Provide adequate shoring and sufficient escape ladders in accordance with applicable
trench safety regulatory requirements.
C. In the trench, continuously operate a combustible gas indicator(CGI) with LEL/02
meter to monitor vapor and oxygen levels. Properly calibrate CGI and provide an
alarm that sounds if greater than or equal to 20 percent Lower Explosive Limit(LEL),
less than or equal to 19.5 percent oxygen, or greater than or equal to 25 percent
oxygen is reached. Record monitoring data from CGI every 15 minutes to ensure
safe working conditions.
D. Take appropriate measures during construction to keep LEL levels below 20 percent
in the trench. If vapor concentrations exceed 20 percent of LEL, stop construction
work,turn off equipment,and have workers immediately vacate the PPCA in an
upwind direction.
E. Take reading with PID/FID 50 feet downwind of an area during excavation or work
in contaminated excavation areas and until one hour after cessation of such work.
Take readings within breathing zone at approximately 4 feed above ground level.
Record readings, date, time, initials of person taking reading,PID/FID serial number
and last calibration date of PID/FID in bound field book.
(111114\ 02105-7
October 2008
CITY OF PEARLAND SAMPLING AND ANALYSIS IN PPCA
TABLE 02105-1
SOIL CRITERIA-PETROLEUM ONLY
Maximuma
Contaminant Concentration(mg/kg) Method
TPH 1500 TX 1005
Total BTEXb 150 EPA 8020/8021
Total Lead 250 EPA 6000/6010/7000
Notes:
a If any parameters exceed the maximum concentrations,then the soil shall be considered Category II Soil
and a Special Waste-PST as defined by the TCEQ in their interoffice memo dated 4/12/94.
b If benzene is greater than 5.0 mg/kg then analyze TCLP benzene which should be<0.3 mg/1.
If total lead is great than 30 mg/kg then analyze TCLP lead which should be<1.5 mg/1.
Definitions:
TCLP-toxicity characteristic leachate procedure(40 CFR 261,Appendix II)
BTEX-benzene,toluene,ethyl benzene,and total xylenes
TPH-total petroleum hydrocarbons
mg/kg-milligrams per kilogram
mg/1-milligrams per liter
TABLE 02105-2
POTENTIALLY CONTAMINATED GROUNDWATER DISCHARGE LIMITS
Discharge to Sanitary Sewer
Parameter,. Limit Method „
TPH(mg/1) 30.0 TX 1005
Total BTEX(mg/1) 1.0 EPA 602/8020/8021
Lower Explosive Limit(%) 10 EPA 1010
Notes: See definitions above.
END OF SECTION
Culh\ 02105-8
October 2008
CITY OF PEARLAND SPECIAL PROVISION TO SECTION 02220
Section 02220S
Special Provision to Section 02220-Site Demolition
All references to Technical Specification"Section 01730—Cutting and Patching"are removed.
End of Section
C '
06/2012 02220S-1 of 1
CITY OF PEARLAND SPECIAL PROVISION TO SECTION 02510
Section 02510S
Special Provision to Section 02510-Water Mains
Section 2.02 "POLYVINYL CHLORIDE (PVC)PRESSURE PIPE"is altered as follows:
Under Item A. "Pipe"add the following text:
"PVC pressure pipe of 16-inches through 20-inches for water shall conform to
AWWA C-905."
Section 3.03 "WET CONNECTIONS"is altered as follows:
Under Item D: "2-Inch Wet Connections" the word copper is replaced with the word
polyethylene.
End of Section
f 06/2012 02510S-1 of 1
CITY OF PEARLAND WATER TAP AND SERVICE LINE INSTALLATION
Section 02515
WATER TAP AND SERVICE LINE INSTALLATION
1.0 GENERAL
1.01 SECTION INCLUDES
A Tapping existing mains and furnishing and installing new service lines for water.
B References to Technical Specifications:
1. Section 01200—Measurement and Payment Procedures
2. Section 02318—Excavation and Backfill for Utilities
3. Section 02520—Valve Boxes,Meter Boxes, and Meter Vaults
C Referenced Standards:
1. American Society for Testing and Materials (ASTM)
a. ASTM D 2737 Standard Specification for Polyethylene (PE) Plastic
Tubing(Pressure Rated).
2. American Water Works Association(AWWA)
a. AWWA C800 Standard Underground Service Line Valves and Fittings
b. AWWA C900 Polyvinyl Chloride (PVC)Pressure Pipe, 4"— 12" for
Water Distribution
\111111.\ D Definitions:
1. Short Side Connection- service line connecting proposed curb stop, located
inside water meter box,to water main on same side of street.
2. Long Side Connection- service line connecting proposed curb stop, located
inside water meter box,to water main on opposite side of street or from center
of streets where supply main is located in street center such as boulevards and
streets with esplanades.
1.02 MEASUREMENT AND PAYMENT
A Measurement for installation of 1 inch water taps and service lines is on a per each
basis. Separate measurements will be made for "Short Side" and "Long Side"
connections.
B Measurement for installation of 2 inch water taps and service lines is on a per each
basis. Separate measurements will be made for "Short Side" and "Long Side"
connections.
C Payment for installation of water taps and service lines includes locating water main,
tap installation and connection to meter,restoring site,excavation,bedding,backfill,
compaction,push-unders, etc.,and all other labor and materials required to complete
•
installation as indicated on Plans.
D Refer to Section 01200—Measurement and Payment Procedures.
04/2009 02515- 1 of 6
CITY OF PEARLAND WATER TAP AND SERVICE LINE INSTALLATION
1.03 SUBMITTALS
A Make Submittals required by this Section under the provisions of Section 01350 —
Submittals.
B Submit manufacturer's product data for approval.
2.0 PRODUCTS
2.01 MATERIALS
A Copper Tubing:
1. Provide Type K annealed, seamless, copper tubing, 1-inch to 2-inch in
diameter conforming to requirements of ASTM B 88.
2. Furnish 1 inch tubing in straight stock of a minimum 20 feet in length. Furnish
2 inch tubing in coils 40 feet in length.
3. All tubing shall be manufactured in United States of America. Copper tubing
may be inspected and tested by a laboratory designated by the Owner at point
of manufacture or locally. Furnish tubing,without cost,to designated testing
laboratory with mil compliance certificates.
4. Provide pack joint type brass fittings for use with Type K annealed copper
tubing in accordance with AWWA C800.
B Polyethylene Tubing- SDR 9 CTS.
C Corporation Stops: AWWA C800 as modified herein:
1. Inlet End: AWWA standard thread.
2. Valve Body: Tapered plug type,0-ring seat ball type,or rubber seat ball type.
3. Outlet End: Pack joint type fitting for use with type-K, soft copper.
04/2009 02515-2 of6
CITY OF PEARLAND WATER TAP AND SERVICE LINE INSTALLATION
C111.6..\
D Provide taps for various water main types and sizes in accordance with following
schedule:
PIPE TAPPING SCHEDULE
WATER MAIN SERVICE SIZE
TYPE AND
DIAMETER 1" 2"
4" Cast Iron or Ductile DSS,WBSS DSS,WBSS
Iron
4" Asbestos Cement WBSS DSS,WBSS
4" PVC (AWWA DSS,WBSS DSS,WBSS
C900)
6" and 8" Cast Iron or DSS,WBSS DSS,WBSS
Ductile Iron
6" and 8" Asbestos DSS,WBSS DSS,WBSS
Cement
6" and 8" Cast Iron or DSS,WBSS DSS,WBSS
Ductile Iron
6" and 8" PVC DSS,WBSS DSS,WBSS
(AWWA C900)
12" Cast Iron or Ductile DSS,WBSS DSS, WBSS
� Iron
12"Asbestos Cement DSS,WBSS DSS, WBSS
12"PVC (AWWA DSS,WBSS DSS, WBSS
C900)
16" and Up Cast Iron or DWBSS DWBSS
Ductile Iron
16" and Up Asbestos DWBSS DWBSS
Cement
16" and Up PVC DWBSS DWBSS
(AWWA C900)
DSS—Dual Strap Saddles
WBSS—Wide Band Strap Saddles
DWBSS—Dual Wide Band Strap Saddles
*Mueller H-15092, or equal
E Dual Strap Saddles: Red brass body and straps; ductile-iron;vinyl-coated body and
straps; or ductile-iron, nylon-coated strap (Romac 101N or equivalent) body and
stainless-steel straps.
F Taps for PVC Water Mains: Use dual-strap or single,wide-band strap saddles which
provide full support around circumference of pipe and bearing area of sufficient width
along axis of pipe, 2 inches minimum, ensuring that pipe will not be distorted when
04/2009 02515-3 of 6
CITY OF PEARLAND WATER TAP AND SERVICE LINE INSTALLATION
saddle is tightened. Romac Series l O 1N wide-band,stainless-steel tapping saddle with
AWWA standard thread(Mueller thread)or equal.
G Taps for Steel Pipe: Not allowed, unless specifically approved by Engineer. Use
saddle only if tap is approved on steel pipe.
H Curb Stops and Brass Fittings: AWWA C800 as modified herein.
1. Inlet End: Pack joint type fitting.
2. Valve Body: Straight-through or angled,meter-stop design equipped with the
following:
a. 0-Ring seal straight plug type.
b. Rubber seat ball type.
3. Outlet End: Female, iron-pipe thread or swivel-nut, meter-spud thread on 1
inch stops and 2-hole flange on 2 inch sizes.
4. Fittings:Ford or approved equal;use same size open end wrenches and tapping
machines as used with respective Ford fittings.
5. Factory Testing of Brass Fittings:
a. Submerge in water for 10 seconds at 85 psi with stop in both closed
and open positions.
b. Reject any fitting that shows air leakage. Owner may confirm tests
locally. Entire lot from which samples were taken will be rejected
when random sampling discloses unsatisfactory fittings.
I Angle Stops: In accordance with AWWA C800; ground-key, stop type with bronze
lock-wing head stop cap; inlet and outlet threads conform to application tables of
AWWA C800; and inlets pack joint connection.
1. Outlet for 1-inch size: Meter swivel nut with saddle support.
2. Outlet for 2 inch size: 0-ring sealed meter flange,iron pipe threads.
J Fittings: In accordance with AWWA C800 and:
1. Castings: Smooth, free from burrs, scales, blisters, sand holes, and defects
which would make them unfit for intended use.
2. Nuts: Smooth cast and have symmetrical hexagonal wrench flats.
3. Thread fittings, of all types, shall have N.P.T. or AWWA threads, and male
threaded ends shall be protected in shipment by plastic coating or other equally
satisfactory means.
4. Pack joint tube fittings shall have beveled gasket.
5. Stamp of manufacturer's name or trademark and size on body.
3.0 EXECUTION
3.01 GENERAL
A Set service taps at right angles to proposed meter location and locate taps in upper pipe
segment within 45 degrees of pipe springline unless otherwise approved by Engineer.
B For service lines and lateral connections larger than those allowed in this Section,Part
(11.6\ 2.01C,branch connections must be used.
04/2009 02515-4 of 6
CITY OF PEARLAND WATER TAP AND SERVICE LINE INSTALLATION
(111.."` C Tapped collars of appropriate sizes: Approved in new construction only provided they
are set at right angles to proposed meter location.
D All 2-inch and smaller service taps on pressurized water mains: Use tapping machine
manufactured for pressure tapping purposes.
E Install service lines in open-cut trench in accordance with Section 02318—Excavation
and Backfill for Utilities except that service lines under all paved roadways, other
paved areas and areas indicated on Plans shall be installed in bored hole as specified in
this Section.
F Unless otherwise approved by Engineer,lay service lines with minimum of 30 inches
of cover as measured from top of curb or, in absence of curbs, from centerline
elevation of crowned streets or roads. Provide minimum of 18 inches of cover below
flow line of all ditches to service lines,unless otherwise approved by Engineer.
G Service lines across existing street(push-unders): Pull service line through prepared
hole under paving. Only full lengths of tubing will be used. Take care not to damage
copper tubing when pulling it through hole. A pack joint type union is only permitted
if Contractor cannot span underneath pavement with a full length of tubing.
Contractor is allowed one pack joint type union for each full length of tubing,provided
it is not under the pavement.
H Maintain service lines free of dirt,coupons and foreign matter at all times.
I Install service lines per City of Pearland. Standard Details.
J Locate water meters in accordance with City of Pearland Standard Details. Contact
Engineer when major landscaping or trees conflict with service line and meter box
location. No additional payment will be made for work on customer side of meter.
K Joints
1. Minimum joint spacing for 1 inch tubing shall be in multiples of 60 feet and
for 2 inch tubing shall be in multiples of 40 feet.
2. Cut copper tubing squarely by using an approved cutting tool and avoiding
excessive pressure on the cutting wheels which might bend or flatten pipe
walls.
3. For pack joint fittings, cut copper tubing squarely prior to insertion into the
fitting. Final assembly shall be in accordance with manufacturer's
recommended procedure.
L Bends
1. Bending of tubing shall be accomplished by using appropriate sized bending
tool. No kinks, dents, flats, or crimps will be permitted, and should such
occur,the damaged section shall be cut out and replaced. Bends shall have no
smaller radius than radius of coil of tubing as packaged by manufacturer.
Copper tubing shipped in straight lengths conform to following:
a. For 2-inch diameter: Maximum of one 45 degree bend per 4 foot
section.
04/2009 02515-5 of 6
CITY OFPEARLAND WATER TAP AND SERVICE LINE INSTALLATION
3.02 CURB STOP INSTALLATION
A Set curb stops or angle stops at outer end of service line inside of meter box. Secure
opening in curb stop to prevent unwanted material from entering. In close quarters,
make an "S" curve in the field. No flattening of tube. In all 1-inch services, install
meter coupling,swivel-nut,or curb stop ahead of meter. Install straight meter coupling
on outlet end of meter.
3.03 SEQUENCE OF OPERATIONS
A Open trench for proposed service line in accordance with Section 02318—Excavation
and Backfill for Utilities.
B Install curb stop on meter end of service line.
C With curb stop open and prior to connecting service line to meter in slack position,
open corporation stop and flush service line thoroughly. Close curb stop, leaving
corporation stop in full-open position.
D Check service line for apparent leaks. Repair any leaks before proceeding.
E Call to schedule inspection prior to backfilling. After inspection, backfill in
accordance with Section 02318—Excavation and Backfill for Utilities.
C.16\ F Install meter box centered over meter with top of lid 3-inches above fmished grade for
grasses or landscaped areas,and flush with finished grade for paved areas. Meter box:
Refer to Section 02520—Valve Boxes,Meter Boxes, and Meter Vaults.
END OF SECTION
0
04/2009 02515-6 of 6
CITY OF PEARLAND PVC PIPE
Section 02534
PVC PIPE
1.0 GENERAL
1.01 SECTION INCLUDES
A Polyvinyl chloride pressure pipe for water distribution in nominal diameters 4 inches
through 16 inches.
B Polyvinyl chloride sewer pipe for gravity sanitary sewers in nominal diameters 4
inches through 48 inches.
C Polyvinyl chloride pressure pipe for gravity sanitary sewers and force mains in nominal
diameters 4 inches through 36 inches.
D References to Technical Specifications:
1. Section 01350—Submittals
2. Section 02634—Ductile Iron Pipe and Fittings
3. Section 02533—Sanitary Sewage Force Mains
4. Section 02512—Polyethylene Wrap
5. Section 02510—Water Mains
6. Section 02530—Gravity Sanitary Sewers
7. Section 02731 —Sanitary Sewage Force Mains
8. Section 02630—Storm Sewers
9. Section 02318—Excavation and Backfill for Utilities
E Referenced Standards:
1. American Water Works Association(AWWA)
a. AWWA C900 Polyvinyl Chloride (PVC)Pressure Pipe, 4"— 12"for
Water Distribution
b. AWWA C905 Polyvinyl Chloride (PVC) Water Transmission Pipe,
Nominal Diameters, 14in. Through 36 in.
c. AWWA C110 Ductile-Iron and Gray Iron Fittings for Water
2. American Society for Testing and Materials (ASTM)
a. ASTM D 1784,"Standard Specification for Rigid Poly Vinyl Chloride
(PVC) Compounds and Chlorinated Poly Vinyl Chloride (CPVC)
Compounds"
b. ASTM F 477,"Standard Specification for Elastomeric Seals(Gaskets)
for Joining Plastic Pipe"
c. ASTM D 3139,"Standard Specification for Joints for Plastic Pressure
Pipes Using Flexible Elastomeric Seals"
d. ASTM D 3034, "Standard Specification for Type PSM Poly Vinyl
Chloride(PVC) Sewer Pipe and Fittings"
e. ASTM F 949,"Standard Specification for Poly Vinyl Chloride(PVC)
Corrugated Sewer Pipe with a Smooth Interior and Fittings"
02/2008 02534- 1 of 6
CITY OF PEARLAND PVC PIPE
�`\ f. ASTM D 794,"Standard Specification for Poly Vinyl Chloride(PVC)
ll Profile Gravity Sewer Pipe and Fittings Based on Controlled Inside
Diameter"
g. ASTM F 679,"Standard Specification for Poly Vinyl Chloride(PVC)
Large-Diameter Plastic Gravity Sewer Pipe and Fittings"
h. ASTM D 2241,"Standard Specification for Poly Vinyl Chloride(PVC)
Pressure-Rated Pipe(SDR Series)"
i. ASTM D 3212,"Standard Specification for Joints for Drain and Sewer
Plastic Pipes Using Flexible Elastomeric Seals"
j. ASTM D 2444, "Standard Test Method for Determination for the
Impact Resistance of Thermoplastic Pipe and Fittings by Means of a
Tup (Falling Weight)"
k. ASTM D 1248, "Standard Specification for Polyethylene Plastics
Extrusion Materials for Wire and Cable"
1. ASTM D 2321, "Standard Practice for Underground Installation of
Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications"
3. American National Standards Institute(ANSI)
a. ANSI A21.10 Cast Iron and Ductile Iron Fittings, 2 thru 48 in./Water
b. ANSI A21.11 Rubber Gasket Joints Cast and Ductile Iron Press Pipe
1.02 MEASUREMENT AND PAYMENT
A Unless indicated as a Bid Item,no separate payment will be made for PVC pipe under
this Section. Include cost in Bid Items for Water Mains,Gravity Sanitary Sewer,and
Sanitary Sewage Force Mains.
1.03 SUBMITTALS
A Make Submittals required by this Section under the provisions of Section 01350 —
Submittals. .
B Submit Shop Drawings showing design of new pipe and fittings indicating alignment
and grade, laying dimensions, fabrication, fittings, flanges, and special details.
1.04 QUALITY CONTROL
A Submit manufacturer's certifications that PVC pipe and fittings meet requirements of
this Section and AWWA C900 or AWWA C905 for pressure pipe applications,or the
appropriate ASTM standard specified for gravity sewer pipe.
B Submit manufacturer's certification that PVC pressure pipe has been hydrostatically
tested at the factory in accordance with AWWA C900 or AWWA C905 and this
Section.
C When foreign manufactured material is proposed for use, have material tested for
conformance to applicable ASTM requirements by certified independent testing
laboratory located in United States. Certification from any other source is not
acceptable. Furnish copies of test reports to the Engineer for review. Cost of testing
shall be borne by Contractor or Supplier.
02/2008 02534-2 of 6
CITY OF PEARLAND PVC PIPE
Climh\ 2.0 PRODUCTS
2.01 MATERIAL
A Use PVC compounds in the manufacture of pipe that contain no ingredient in an
amount that has been demonstrated to migrate into water in quantities considered to be
toxic.
B Furnish PVC pressure pipe manufactured from Class 12454-A or Class 12454-B virgin
PVC compounds as defined in ASTM D 1784. Use compounds qualifying for a rating
of 4000 psi for water at 73.4 degrees F per requirements of PPI TR3. Provide pipe
which is homogeneous throughout,free of voids,cracks,inclusions,and other defects,
uniform as commercially practical in color, density, and other physical properties.
Deliver pipe with surfaces free from nicks and scratches with joining surfaces of
spigots and joints free from gouges and imperfections which could cause leakage.
C For PVC pressure pipe used for water mains,provide self-extinguishing PVC pipe that
bears Underwriters'Laboratories mark of approval and is acceptable without penalty to
Texas State Fire Insurance Committee for use in fire protection lines.
D Gaskets:
1. Gaskets shall meet the requirements of ASTM F 477. Use elastomeric factory-
installed gaskets to make joints flexible and watertight.
2. Pipes to be installed in potentially contaminated areas, especially where free
'' product is found near the elevation of the proposed sewer, shall have the
following gasket materials for the noted contaminants.
CONTAMINANT GASKET MATERIAL REQUIRED
Petroleum(diesel, gasoline) Nitrile Rubber
Other contaminants As recommended by the pipe manufacturer
E Lubricant for rubber-gasketed joints: Water soluble,non-toxic,non-objectionable in
taste and odor imparted to fluid, non-supporting of bacteria growth, having no
deteriorating effect on PVC or rubber gaskets.
2.02 WATER SERVICE PIPE
A Pipe 4-inch through 12-inch: AWWAC900, Class 150, DR 18; nominal 20-foot
lengths; cast iron equivalent outside diameters.
B Pipe 16-inch: AWWA C905; Class 235; DR 18; nominal 20 foot lengths; cast iron
equivalent outside diameter.
C Joints: ASTM D 3139; push-on type joints in integral bell or separate sleeve
couplings. Do not use socket type or solvent weld type joints.
(ob.\
02/2008 02534-3 of 6
CITY OF PEARLAND PVC PIPE
Where restrained joints for buried service are required by Plans,provide one of
the following, or Approved Equal(restrained joints shall be polyethylene
wrapped):
1. UNI-FIT Series 6130, 6190, or 6190-D by United Water Products.
2. Pipe Restraint by ROMAC Industries
3. EBAA IRON MEGALUG Bell Restraint Harness for AWWA C900
and C905 PVC Pipe.
D Make curves and bends by deflecting the joints. Do not exceed maximum deflection
recommended by the pipe manufacturer. Submit details of other methods of providing
curves and bends for review by the Engineer.
E Hydrostatic Test: AWWA C900,AWWA C905, ANSI A21.10 (AWWA C110); at
point of manufacture; submit manufacturer's written certification.
2.03 BENDS AND FITTINGS FOR PVC PRESSURE PIPE
A Bends and Fittings: ANSI A21.10, ductile iron; ANSI A21.11 single rubber gasket
push-on type joint; minimum 150 psi pressure rating.
B Coatings and Linings: Conform to requirements of Section 02634—Ductile Iron Pipe
and Fittings.
2.04 GRAVITY SANITARY SEWER PIPE
A PVC gravity sanitary sewer pipe shall be in accordance with the provisions in the
following table:
WALL PRODUCT ASTM SDR(MAX.)/ DIAMETER
TYPE MANUFACTURER OPTIONS DESIGNATION STIFFNESS(MIN.) SIZE RANGE
Solid J-M Pipe Approved D3034 SDR 26/PS 115 6"to 10"
CertainTeed Approved D3034 SDR 35/PS 46 12"& 15"
Can-Tex Approved F679 SDR 35/PS 46 18"to 27"
Carlon
Diamond Approved AWWA C900 DR 18/N/A 4"to 12"
Approved AWWA C905 DR 18/N/A 14"to 36"
Profile Contech A-2000* Only when F949 N/A/50 psi 12"to 36"
included in the
ETI Ultra-Rib Bid Schedule F794 N/A/46 psi 12"to 48"
Lamson Vylon F794 N/A/46 psi 21"to 48"
*Allowed to be used to a maximum depth of 10' only.
B When solid wall PVC pipe 18 inches to 27 inches in diameter is required in SDR 26,
provide pipe conforming to ASTM F679,except provide wall thickness as required for
SDR 26 and pipe strength of 115 psi.
02/2008 02534-4 of 6
CITY OF PEARLAND PVC PIPE
C For sewers up to 12-inch-diameter crossing over waterlines, or crossing under
waterlines with less than 2 feet separation,provide minimum 150 psi pressure-rated
pipe conforming to ASTM D 2241 with suitable PVC adapter couplings.
D Joints: Spigot and integral wall section bell with solid cross section elastometric or
rubber ring gasket conforming to requirements of ASTM D 3212 and ASTM F 477.
E ASTM D 3139 and ASTM F 477 shall be provided. Gaskets shall be factory-
assembled and securely bonded in place to prevent displacement. The manufacturer
shall test a sample from each batch conforming to requirements ASTM D 2444.
F Fittings: Provide PVC gravity sewer sanitary bends, tee, or wye fittings for new
sanitary sewer construction. PVC pipe fittings shall be full-bodied, either injection
molded or factory fabricated. Saddle-type tee or wye fittings are not acceptable.
2.05 SANITARY SEWER FORCE MAIN PIPE
A Provide PVC pressure pipe conforming to the requirements for water service pipe,and
conforming to the minimum working pressure rating specified in Section 02533 —
Sanitary Sewage Force Mains.
B Acceptable pipe joints are integral bell-and-spigot,containing a bonded-in elastomeric
sealing ring meeting the requirements of ASTM F 477. In designated areas requiring
restrained joint pipe and fittings, use EBAA Iron Series 2000PV, Uniflange Series
(1111h. 1350 restrainer,or equal joint restraint device conforming to UNI-B-13,for PVC pipe
12-inch diameter and less.
C Fittings: Provide ductile iron fittings as per this Section,2.03 `Bends and Fittings for
PVC Pressure Pipe", except furnish all fittings with one of the following internal
linings:
1. Nominal 40 mils (35 mils minimum) virgin polyethylene complying with
ASTM D 1248,heat fused to the interior surface of the fitting,as manufactured
by American Cast Iron Pipe"Polybond", or U.S. Pipe "Polyline".
2. Nominal 40 mils(35 mils minimum)polyurethane,Corro-pipe II by Madison
Chemicals,Inc.
3. Nominal 40 mils(35 mils minimum)ceramic epoxy,Protecto 401 by Enduron
Protective Coatings.
D Exterior Protection: Provide polyethylene wrapping of ductile iron fittings as required
by Section 02512—Polyethylene Wrap.
E Hydrostatic Tests: Hydrostatically test pressure rated pipe in accordance with this
Section,2.02E.
F Manufacturers: Approved manufacturers of pressure rated, solid wall PVC pipe for
sanitary sewer force mains are:
1. J&M Manufacturing Company, Inc.
2. CertainTeed Corporation
(111.6'. 3. Diamond Plastics Corporation
02/2008 02534-5 of 6
CITY OF PEARLAND PVC PIPE
4. Carlon Company
5. North American Pipe Corporation(NAPCO)
3.0 EXECUTION
3.01 PROTECTION
A Store pipe under cover out of direct sunlight and protect from excessive heat.or
harmful chemicals in accordance with the manufacturer's recommendations.
3.02 INSTALLATION
A Conform to requirements of Section 02510—Water Mains, Section 02530—Gravity
Sanitary Sewers,Section 02731 —Sanitary Sewage Force Mains,and Section 02630—
Storm Sewers.
B Install PVC pipe in accordance with Section 02318 — Excavation and Backfill for
Utilities,ASTM D 2321, and manufacturer's recommendations.
C Water service pipe 12 inches in diameter and smaller: Installed to clear utility lines
and have minimum 4 feet of cover below lowest property line grade of street,unless
otherwise required by Plans.
D For water service,exclude use of PVC within 200 feet(along the public right-of-way)
(Pik\ of underground storage tanks or in undeveloped commercial acreage. Underground
storage tanks are primarily located on service stations but can exist at other
commercial establishments.
E Avoid imposing strains that will overstress or buckle the pipe when lowering pipe into
trench.
F Hand shovel pipe bedding under the pipe haunches and along the sides of the pipe
barrel and compact to eliminate voids and ensure side support.
END OF SECTION
Clia‘\
02/2008 02534-6 of 6
CITY OF PEARLAND SPECIAL PROVISION TO SECTION 02634
(111
Section 02634S
Special Provision to Section 02634—Ductile Iron Pipe and Fittings
All references to Technical Specification "Section 02676—Hydrostatic Testing of Pipelines"
are removed.
Section 2.01 "DUCTILE IRON PIPE"is altered as follows:
Item A is revised to read:
"Ductile iron pipe barrels: ANSI A21.15, ANSI A21.50 or ANSI A21.51;bear mark of
Underwriters'Laboratories approval"
Add Item C to read:
"Use minimum Pressure Class 250 for water lines or thickness Class 52 for water lines in
casing or augered hole. Provide minimum thickness Class 52 for sanitary sewers. Provide
minimum Pressure Class 350 for flanged pipe."
Climb\ Section 2.02 "JOINTS"is altered as follows:
Under Item B. add the following text:
"4. EBAA IRON MEGALUG Mechanical Joint Restraint"
Section 2.03 "GASKETS" is altered as follows:
Replace the existing table in Item B with the following table:
Contaminant Gasket Material Required
Petroleum(diesel, gasoline) Nitrile Rubber,FKM Viton Type Gasket(ASTM 1418)
Other contaminants As recommended by the pipe manufacturer
End of Section
CI11116\ 06/2012 02634S-1 of 1
CITY OF PEARLAND COMPUTER EQUIPMENT
SECTION 13731 —COMPUTER EQUIPMENT
PART 1 -GENERAL
1.1 RELATED DOCUMENTS
A. General provisions of the Contract, including General and Special Conditions and Division 01
Specification Sections, 01200 Measurement and Payment Procedures, 01350 Submittals, 01500
Temporary Facilities and Controls and 01505 Mobilization apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Portable"laptop"computer work-station.
2. One or more internet access workstations.
3. Computer operating system and application software.
1.3 DEFINITIONS
A. CPU: Central processing unit.
B. ProTrak software: a web-based project management and collaborative communications system
providing multiple project users access to all project documentation.
C. Credential: Password for the protected access to the ProTrak software providing data security
for project documentation.
D. DSL: Digital Subscriber Line. Commercial subscription for access to the internet
E. Wireless Hub: Wireless access to the DSL internet connection for use with wireless computer
modems in lap top computers.
F. PC: Personal computer. Applies to the central station, workstations, file servers and portable
lap tops.
G. PDF: Portable Document Format. The file format used by the Acrobat document-exchange-
system software from Adobe.
H. RAS: Remote access services.
I. RF: Radio frequency.
J. ROM: Read-only memory. ROM data are maintained through losses of power.
K. TCP/IP: Transport control protocol/Internet protocol incorporated into Microsoft Windows.
12,2011 13730- 1
CITY OF PEARLAND COMPUTER(11116'\
L. UPS: Uninterruptible power supply.
M. USB: Universal serial bus.
N. WAN: Wide area network.
O. WAV: The digital audio format used in Microsoft Windows.
P. WMP: Windows media player.
Q. Windows: Operating system by Microsoft Corporation.
R. Workstation: A PC with software that is configured for specific functions.
1.4 ACTION SUBMITTALS
A. Product Data: Provide manufacturer's product description as a submittal for each type of
product indicated. Include rated capacities, operating characteristics, and furnished specialties
or accessories. Reference each product to the original specification. Warranty data and any
required warranty use authorization should be provided and transferable to the City as end user.
1.5 CLOSEOUT SUBMITTALS
A. Operation and Maintenance Data: Provide all users' manuals, warranty information and any
proof of purchase type information required for warranty and information regarding imbedded
CifDIN,
. software licensing. In addition to items specified in Section 01782"Operation and Maintenance
Data,"include the following:
1. Microsoft Windows software documentation.
2. PC installation and operating documentation, manuals, and software for the PC and all
installed peripherals. Software shall include system restore, emergency boot diskettes/
cd's,and drivers for all installed hardware. Provide separately for each PC.
3. Hard copies of manufacturer's specification sheets, operating specifications, design
guides,user's guides for software and hardware, and PDF files on CD-ROM of the hard-
copy submittal.
4. System installation and setup guides with data forms to plan and record options and setup
decisions.
1.6 QUALITY ASSURANCE
A. Comply with NFPA 70,"National Electrical Code."
B. Provide "new" in the box materials and equipment complete with manufacturer's warranty as
required. Provide all documentation as supplied by OEM.
1.7 DELIVERY, STORAGE,AND HANDLING
A. Workstations,and Portable"laptop"computers:
12,2011 13730-2
CITY OF PEARLAND COMPUTER EQUIPMENT
1. Store in temperature- and humidity-controlled environment in original manufacturer's
sealed containers. Maintain ambient temperature between 50 and 85 deg F,and not more
than 80 percent relative humidity,non-condensing.
2. Open each container; verify contents against packing list; and file copy of packing-list,
complete with container identification.
3. Save original manufacturer's containers and packing materials and deliver as directed
under provisions covering extra materials.
1.8 PROJECT CONDITIONS
A. Environmental Conditions: System shall be capable of withstanding the following
environmental conditions without mechanical or electrical damage or degradation of operating
capability:
1. Indoor,Controlled Environment: System components,except installed in air-conditioned
indoor environments shall be rated for continuous operation in ambient conditions of 36
to 78 deg F dry bulb and 20 to 90 percent relative humidity,non-condensing.
2. Outdoor Environment: System components installed in locations exposed to weather
shall be rated for continuous operation in ambient conditions of 36 to plus 100 deg F dry
bulb and 20 to 90 percent relative humidity,condensing.
PART 2-PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, provide products by the following
Manufacturer to comply with existing City IT requirements and Software access:
1. Dell Computer: Latitude E6420 ATG(225-0702)
B. Basis-of-Design Product: Subject to compliance with requirements, provide Dell Latitude
E6420 (225-0702)or comparable product.
2.2 DESCRIPTION
A. System Hardware and Software:
Base Unit: Dell Latitude E6420 ATG(225-0702)
Processor: Intel Core i5-2540M,2.60GHz,3MB Cache,Dell Latitude E6X20(317-5995)
Memory: 4.0GB,DDR3-1333MHz SDRAM,2 DIMM,Dell Latitude(317-6239)
Keyboard: Internal Backlit Dual Pointing English Keyboard,Dell Latitude E(331-1201)
Keyboard: Tech Setup Guide,English,Dell Latitude E6420 ATG(331-1715)
Keyboard: Documentation(English/French),Dell Latitude E-Family/Mobile Precision(331-2169)
Video Card: Intel HD Graphics 3000,Dell Latitude E6420 ATG(318-0512)
Hard Drive: 320GB Hard Drive 7200RPM,Dell Latitude E(342-0482)
(1111.6\
12,2011 13730-3
CITY OF PEARLAND COMPUTER EQUIPMENT
Hard Drive Controller: NO Internal Fingerprint Reader and NO contactless smartcard reader,Dell Latitude
E6420 ATG(331-2714)
Floppy Disk Drive: 14.0 in HD(1366x768)Anti-Glare LED,Dell Latitude E6420 ATG(320-2141)
Floppy Disk Drive: LCD Cover,No Touchscreen,Dell Latitude E6420 ATG(318-0510)
Operating System: Genuine Windows 7 Professional,64-bit,No Media,Latitude,English(421-8067)
Modem: No Modem,Dell Latitude E(331-1221)
TBU: 90W 3-Pin,AC Adapter,Dell Latitude E(331-1719)
TBU: US-3 foot Flat Power Cord,Dell Latitude(330-4016)
CD-ROM or DVD-ROM 8X DVD+/-RW Bezel,Dell Latitude E6320/E6420/E6520/ATG(318-0466)
Drive:
Software Cyberlink Power DVD 9.5,No Media,Dell OptiPlex,Latitude and Precision Work-
station(421-4370)
Software: Roxio Creator Starter,No Media,Dell OptiPlex,Latitude and Precision Workstation
(421-4539)
Sound Card: No Camera,with single digital microphone,Dell Latitude E6420/ATG(318-0441)
Processor Cable: Intel WiFi Link 6205(802.11a/g/n 2X2) 1/2 MiniCard for VPRO Latitude E/Mobile
Precision(430-3961)
Documentation Disk- Intel vPro Technology Advanced Management Features,Dell Latitude E6X20(331-
ette: 1227)
Bundled Software: Adobe Acrobat X,includes Serial Key Card,FI,ENG/FRN(410-0560)
Bundled Software: Microsoft Office Professional 2010,English,OptiPlex,Precision and Latitude(421-
3957)
Feature 6-Cell(60WH)Primary Lithium Ion Battery for Latitude(312-1151)
Feature Carrying Handle,Latitude E6420 ATG(331-1713)
Service: Dell Limited Hardware Warranty Plus Service Extended Year(s)(934-9528)
Service: Dell Limited Hardware Warranty Plus Service Initial Year(929-3587)
Service: ProSupport:Next Business Day Limited Onsite Service After Remote Diagnosis 4
Year Extended(927-0034)
Service: ProSupport:Next Business Day Limited Onsite Service After Remote Diagnosis Ini-
tial Year(951-4140)
Service: ProSupport: 7x24 Technical Support,4 Year Extended(928-8134)
Service: ProSupport:7x24 Technical Support,Initial(956-5210)
Support: Accidental Damage Service,5 Year(927-0184)
Support: Info,Complete Care(988-7689)
(111111‘\
12,2011 13730-4
CITY OF PEARLAND COMPUTER EQUIPMENT
t Misc: Energy Star Enabled/E-PEAT/Gold,Latitude E6420/ATG(331-1931)
Misc: Intel Core i5 vPro Processor(331-1641)
Resource DVD with Drivers,Dell Latitude E6420/ATG(331-1222)
Cyberlink Power 9.5.1 AND Roxio Creator Starter Media for DVD+/-RW,Dell Opti-
Plex,Workstation and Latitude(421-5109)
Media Kit,Win 7 Professional 64bit,MUI,Dell OptiPlex,Precision and Latitude(421-
5682)
Dell Back-up and Recovery Manager for Win7,MUI,Optiplex,Precision,Latitude
(331-3300)
CFI,Integration Fee,Order Ready,Pronc(365-0530)
B. Field Office Internet Access
1. CONTRACTOR shall provide and pay for DSL internet access in the temporary Field
Office for use by OWNER'S REPRESENTATIVE,CONSTRUCTION MANAGER and
INSPECTORS as well as for CONTRACTOR'S use.
a. Service must support a minimum of two users simultaneously and be available at
all times during working ours
b. No separate pay item will be made for Internet Access. Include monthly cost in
Temporary Facilities,if a separate pay item is established,or as an incidental cost
PART 3-EXECUTION
Provide computer equipment and software submittal in initial "Critical" submittals as material
submittal#1. Upon approval by OWNER and ENGINEER;
a) deliver computer equipment to OWNER in original manufacturer's
packaging.
b) Establish wireless internet connections in CONTRACTOR'S field
office and coordinate operation of computer with internet access at
this location and request
c) Invoice Computer Equipment line item in first 50%of Mobilization.
END SECTION
(111116\
12,2011 13730-5