Loading...
R2001-0163 11-12-01 RESOLUTION NO. R2001-163 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS, APPROVING A CHANGE ORDER FOR CONSTRUCTION SERVICES ASSOCIATED WITH THE DAVID L. SMITH EAST POND REGIONAL DETENTION PROJECT. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS: Section 1. That certain change order by and between the City of Pearland and Haddock Construction Company, a copy of which is attached hereto as Exhibit "A" and made a part hereof for all purposes, is hereby authorized and approved. Section 2. That the City Manager or his designee is hereby authorized to execute and the City Secretary to attest a change order with Haddock Construction Company, for construction services associated with the David L. Smith East Pond Regional Detention Project. PASSED, APPROVED and ADOPTED this the t2 day of November ., A.D., 2001. TOM REID MAYOR ATTEST: \PPROVED AS TO FORM: DARRIN M. COKER CITY ATTORNEY CHANGE ORDER NO. 2 November 1, 2001 CITY OF PEARLAND, TEXAS David L. Smith East Pond Regional Detention Basin B2000-36 CONTRACTOR: Haddock Construction Co. PO Box 1263 Friendswood, TX 77549 ITEM NO. DESCRIPTION (CONTINUE ON ATTACHED SHEETS) 1. Original specified color was "Olive Drab Green #1448" at a net cost to us of $8.00/CY. Final color choice was "Linoleum Brown #450" at a net cost of $11.50.CY. Creating an increased cost of $3.50 per cubic yard for 516 CY. $1806.00 2. The addition of 20 each PVC wall drains with screen wire 12" tube surrounded with pea gravel filter covered with geotextile filter fabric. At a cost of $220 each X 20 = $4,400.00 3. An addition of one log stop in bottom of Manhole $2,000.00. 4. In order to complete this additional work an additional 5 days is added to the contract. 5. Increase the quantity of excavation. 5,200 CY at $2.25/CY. $11,700.00 6. Increase item #10. Embankment from 28,800 CY to 35,668 CY. Anetincreaseof6,868 CY ~ $2.25 = $15,453.00. 7. Increase item #12. Interlocking concrete blocks from 180 Sq.Yd. to 280 Sq. Yd. A net increase of 100 Sq.Yd. @ $49.00 = $4,900.00 8. Reduce Item #7. 18' Rip Rap from 700 Sq. Yd. to 480 Sq. Yd. A net of-220 Sq.Yd~ ~ $20.00 = ($- 4,400.00) CALENDAR DOLLAR TIME .AMOUNT This Change Order +5 $35,859.00 Current Contract 77/185 $1,256,745.00 Revised Contract 771190 $1,292,604.00 Page 1 of 2 CHANGE ORDER NO. 2 November 1, 2001 ' CITY OF PEARLAND, TEXAS David L. Smith East Pond Regional Detention Basin B2000-36 Approved for Owner: Approved for Contractor CITY OF PEARLAND / By: By: t~~ City Engineer Haddock Construction Comp'~y By: Bill Eisen, City Manager ATTACHMENTS: NONE Page 2 of 2 CONTRACTOR: Haddock Construction Co. ADDRESS: P.O. Box 1263 Friendswood, TX 77549 ~ PHONE: 281-489-2828 Estimate and Certification for Payment PROJECT: David L. Smith Site East Pond Regional Detention Basin (B2000-36) OWNER: CITY OF PEARLAND ADDRESS: 3519 Liberty Drive Pearland, TX 77581 A'CI'N: Mr. John W. Hargrove, P.E. Initial Contract Time 60/180 days Current Approved Extensions + or- +0/005 days Previous Approved Extensions + or- +17/0 days Estimate No: 7 Total Contract Time 77/190 days Invoice No: Billing_07 FINAL Spent Days 113/170 days Start Date: 03101/01 Days Remaining -36/20 days Current Contract Completion Date: _10/10/01 Estimate Cut Off Date: 10/10/01 Rain Days to Date 47/47 days Date of Estimate: 10/10/01 A. Contact Amount to Date: 1. Contract Price: $1,169,595.00 2. Approved Change Ordem: Number One Add $87,150.00 Number Two Add $35,859.00 Total Changesto Date: + or- __ +$123,009.00 TOTAL CONTRACT AMOUNT: $1,292,604.00 B. Eamin.qs to Date: 1. Previous Work Completed $1,254,686.75 Previous Earnings: __.$1,254,686.75 2. Work Completed This Period $ 37,917.25 Earnings this period: $ 37,917.25 3. Materials On Site $ 0.00 TOTAL EARNINGS: $1,292,604.00 C. Reductions: 1. Retainage 0% of $1,292,604.00 0.00 Total Payments Due: $1,292,604.00 Less Previous Payments: __ $1,242,139.88 Total Amount Due Contractor This Estimate: $ 50,464.t2 The undersigned Contractor certifies that to the best of his knowledge, information, and belief that the Work has been completed in accordance with the Plans and Specifications and the current payment shown on this Application for PaymenLis .now due~ ,, ~.~NTRACT~'S R~RESENTATIVE The foregoing estimate of w(~rk.cempleted is true and correct to the best of my knowledge and belief. Project Representative Approved by:. Date: Engineer Approved by:. Date: City Engineer, John W. Hargrove, P.E.