R75-13 04-01-75RESOLUTION 75-13
Whereas, the CIT7'OF PEARLAND
has made application to the Texas Water Quality Board and the
Environmental Protection Agency for a federal grant pursuant to
the Federal Water Pollution Control Act Amendments of 1972, Public
Law 92-500, and the rules and regulations thereto.
Now Therefore, Be It Resolved by the above named applicant
that the application for which federal grant assistance has been
requested pursuant to the Federal Water Pollution Control Act
Amendments of 1972, Public Law 92-500, will be constructed to
completion in accordance with the laws, rules, and regulations and
with the following project schedule.
Project Schedule Item, Date of Action
General
Availability of Financing Funds
for applicants share of the
project costs Step 1' 17 Feb. -1975
Step 2 15 Oct. 1975
Step 3 (Requires Bond 10 April 1976
Issue)
Availability of the Sites
for the project facilities Existing
Step 1
Infiltration/Inflow Analysis
Initiated
Completed
Submitted to State (TWQB)
1 May 1975
15 -July 1975.'
28 July 1975
Project Schedui^Item Date .of Action
Preliminary Infiltration/Inflow
Evaluation Survey Study Plan (if needed)
Initiated 15 July 1975
Completed 31 July 1975
Report Completed 15 Aug. 1975
Submitted to State (TWQB) 18 Aug. 1975
Infiltration/Inflow Evaluation Survey (if needed)
Initiated 15 Aug.` 1975
Completed 15 Oct. 1975
Report Completed
Submitted to State (TWQB)
14 Nov. 1975
17 Nov. 1975
Environmental Assessment
Initiated (instructions on Form CG -178) 15 July 1975
Completed (Sections 1-6) 29 Aug. 1975
Public Hearing Advertised -2 Oct. 1975
Public Hearing Conducted (Section 7; 30 day
minimum period of advertisement) -
Environmental Assessment
Finalized (Section 7, minutes of public
hearing completed)
Submitted to State (TWQB)
The Regional Planning Agency
Comments and Approvals Completed
Submitted to State (TWQB)
Facility Plan (Including Final Engineering •
Report/Feasibility Report)
Initiated
Completed
3 Nov. 1975
14 Nov. 1975
17 Nov., 19/5
20 Oct.1975
28 Oct: 1975-
15- JuTy 1975
'15 Sept. 1975
Report Completed 1 Oct.: 1975
Public Hearing (30 day minimum period of
Advertisement)
3 Nov. 1975
Submitted to State (TWQB) 17 :Nov. 1975
Step 2
Step 3
Project. Schedule
Item Date of Action
Final Plans and Specifications
Initiated
Completed
Submitted to State (TWQB)
Advertise for Construction Bids
within the days indicated after
authorization to advertise for
bids has been issued
Submit Bid Opening Documents
within the days indicated after
the bid opening date
Award Construction Contract
within the days indicated after
authorization to award the
contract has been issued
Initiation of Construction
within the days indicated after
the award of the contract
Complete Construction
within the days indicated after
initiation of construction
15 Oct. 1975
15 Mar. I976
18 Mar. 1976
15 days
15 days
10 days
10 days
`240 days»
Be it further resolved, that the above named applicant under-
stands that the above project schedule must be approved by the
Texas Water Quality Board and the Environmental Protection Agency,
and that once a project schedule has been approved, nochanges
will be authorized without first receiving approval of` the change
from the Texas Water Quality Board and the Environmental Protection
Agency.
Passed, approved and adopted this 27th day of March, 1975,
This schedule is all predicated on receiving a grant
approval within 30 -days after 1 April 1975.
Carlton McComb, Mayor