R2000-079 06-12-00RESOLUTION NO. R2000-79
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, AUTHORIZING THE CITY MANAGER OR HIS DESIGNEE TO
ENTER INTO A CONTRACT WITH BOB HOLT FOR INSPECTION
SERVICES ASSOCIATED WITH THE MAGNOLIA/HARKEY SANITARY
SEWER PROJECT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That certain contract by and between the City of Pearland and
Bob Holt, a copy of which is attached hereto as Exhibit "A" and made a part hereof for all
purposes, is hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute
and the City Secretary to attest a contract with Bob Holt for inspection services associated
with the Magnolia/Harkey Sanitary Sewer Project.
PASSED, APPROVED and ADOPTED this the 12t. h day of June
A.D., 2000.
ATTEST: /~
APPROVED AS TO FORM:
DARRIN M. COKER
CITY ATTORNEY
%M REI~DD~:~71
MAYOR
VdikuLp_
co 4,p
4 r Fa „ G
. E D
June 6, 2000 T E X A s
Fsr. I s9�
Bob Holt
3603 Millbridge
Houston, Texas 77059
Re. Engineering Inspection Contract (Magnolia/Harkey Trunk
Sewer)
Dear Mr. Holt :
This letter is the agreement between BOB HOLT (BH) , and the CITY
OF PEARLAND (COP) , and is a contract for the delivery of
construction inspection services covering the contract
construction of the above-referenced projects . Construction
efforts are estimated to begin on Magnolia/Harkey (MLH) on or
about Wednesday, July 5, 2000 and are estimated to be completed
by January 5, 2001 . The estimated duration of this contract is
expected to cover the time necessary to complete this project .
The CITY represents that it has the funds to construct the
referenced project.
Under this Agreement, BH will perform construction inspection
services that will include:
1 . Provide on-site inspection and observation of construction
activity of the above project. Includes making informal
written, personal, and telephone reports to the City Engineer
and design engineer as appropriate.
2 . Maintain Project Diaries for the Project, and submit to the
City Engineer and design engineer monthly for review and
file.
3. Coordination of geotechnical services under contract to COP,
including schedule and scope of all field and laboratory
services . Make recommendations for retention by COP of
specific geotechnical firms as needed.
4 . Receive, comment and report upon all submittals, requests for
clarification, requests for change orders, partial pay
estimates and requests for approval inspections as needed.
5 . Act as COP on-site representative in contract administration
3519 LIBERTY DRIVE • PEARLAND,TEXAS 77581 • (281)485-2411 •www.ci.pearland.tx.us
June 6, 2000
Bob Holt
3603 Millbridge
Houston, Texas
77059
Re. Engineering Inspection Contract (Magnolia/Harkey Trunk
Sewer)
Dear Mr. Holt:
This letter is the agreement between BOB HOLT (BH), and the CITY
OF PEARLAND (COP), and is a contract for the delivery of
construction inspection services covering the contract
construction of the above-referenced projects. Construction
efforts are estimated to begin on Magnolia/Harkey (MLH)on or
about Wednesday, July 5, 2000 and are estimated to be completed
by January 5, 2001. The estimated duration of this contract is
expected to cover the time necessary to complete this project.
The CITY represents that it has the funds to construct the
referenced project.
Under this Agreement, BH will perform construction inspection
services that will include:
Provide on-site inspection and observation of construction
activity of the above project. Includes making informal
written, personal, and telephone reports to the City Engineer
and design engineer as appropriate.
Maintain Project Diaries for the Project,
City Engineer and design engineer monthly
file.
and submit to the
for review and
Coordination of geotechnical services under contract to COP,
including schedule and scope of all field and laboratory
services. Make recommendations for retention by COP of
specific geotechnical firms as needed.
Receive, comment and report upon all submittals, requests for
clarification, requests for change orders, partial pay
estimates and requests for approval inspections as needed.
5. Act as COP on-site representative in contract administration
3519 LIBERTY DRIVE · PEARLAND, TEXAS 77581 · (281) 48,5-2411 · www.ci.pearland.tx.us
BH6600 (Cont.) Sheet 2 of 3
on the referenced project and assume rssponsibility for
maintaining effective communication between contractor, COP,
COP Plant Operating Department, geotechnical services, design
engineer, surveyor, utility companies, and other entities
public and private having interest in the successful com-
pletion and acceptance of the referenced'project.
In the performance of the terms of this Contract, BH will provide
and maintain an automobile, beeper, mobile phone, and various
small tools such as measuring tapes, rulers, scales, straight
edges and writing aids. COP will provide pads of Inspection
Daily Diary forms and occasional city personnel for non- .
repetitive aid,'such as transit operator and chainman. It is the
intention of this agreement that BH will not be required to be on
the job when rained out, on contractors' holidays, or other
events that do not include actual construction work; PROVIDING
that BH does not fail to meet the other terms of this Agreement.
BH will be required to attend Project meetings, and to be on the
project when the contractor is working setting pipe and manholes,
or is covering up or testing. This may include ~after-hours~ as
well as Saturdays and some government holidays. The construction
contract is written prohibiting work on Sundays.
As compensation for these required services, the COP will pa~ BH
monthly for services and scheduled expenses. Payment for
services shall be 1.0 percent (0.01) of the total monthly
estimates of payment due from the COP to the construction
contractors of the referenced projects. That is, for example, if
the monthly pay estimate totals $500,000, payment for services to
BH will be $5,000 plus agreed expenses for that month.
In addition to payment for services, the COP will pay $10.00 per
day of actual use of BH personal automobile on all projects BH
holds contracts with the COP., providing the day paid is backed
up by an Inspection Daily Diary sheet. In addition, the COP will
pay $0.25 per mile actually driven in the personal automobile.
Fuel, oil, tires, maintenance and emergency service is the
responsibility of BH. Vacation, holiday, and sick time is the
responsibility of BH.
The COP will pay billed phone services upon submittal of tele-
phone invoices. Other qualified expenses may include emergency
or other expenses beyond the control of BH that benefit the
project and are required and approved by the City Engineer.
BH shall be totally self-insured and.is not an employee of the
COP. BH shall submit monthly invoices for services and expenses
BH6600 (Cont.) Sheet 3 of 3
to the COP. BH will be provided with a statement of compensation
paid for tax and FICA purposes soon after the first of the tax
year. A copy of this will be sent to the Internal ReveNue
Service by COP.
It is anticipated that from time to time, ciJcumstances may
prevent BH from being on-site during construction activity. At
such times, BH will in advance provide for the project work to be
covered by agreement with the City Engineer. In addition, in the
event of emergency condition, BH may notify the City Engineer on
a call-in basis for relief. Actual values of all relieved
service will be subject to negotiation with the City Engineer,
and will be based on net costs to maintain level of service.
Termination of this contract may be effected by either party
unilaterally upon the submission of 30 days notice to the other.
Uncompensated eligible expenses will be paid up to the date of
termination, and unpaid compensation for current services, at 1.0
percent (0.01) of contract pay estimates for the current month of
notice,-will be paid prorated to the day of termination.
This letter constitutes the scope and terms of agreement between
BH and the COP.
Sincerely,
Glen Erwin
Interim City Manager
Accepted:
Bobby Holt Date
AGENDA REQUEST
BUSINESS OF THE CITY COUNCIL
CITY OF PEARLAND, TEXAS
AGENDA OF: June 12, 2000
DATE SUBMITTED: June 2, 2000
PREPARED BY: Michael Ross
ITEM NO. ~
DEPARTMENT OF ORIGIN: City Manager
PRESENTOR: Michael Ross
SUBJECT: Magnolia Harkey Sanitary Sewer Project
EXHIBITS: City of Pearland Contract Proposal
EXPENDITURE REQUIRED $11,552.14 plus mileage and phone reimbursements
AMOUNT BUDGETED $148,140.00
ACCOUNT NO. 064-9608-565-03.00
ADDITIONAL APPROPRIATION REQUIRED N/A
ACCOUNT NO. N/A
FUNDS AVAILABLE ~ (Finance Department Approval)
EXECUTIVE SUMMARY
Staff has prepared a contract proposal for construction inspection services for the above project.
The Texas Water Development requires the City to provide adequate inspection services for
assurance that the construction work is being performed in a satisfactory manner in accordance
with the plans and specifications.
Staff has selected Mr. Bob Holt for this project due to his extensive experience with the City on
previous sanitary sewer projects and his familiarity with Texas Water Development Board
program guidelines. The inspector for this project will be compensated based upon 1% of the
total construction contract which currently equals to $11,552.40 plus any mileage and phone
expenses. A copy of the contract proposal is attached for reference.
The funding for this contract is available in account number 064-9608-565-03.00. This project is
one of the Texas Water Development Board (TWDB) State Revolving Fund (SRF) Tier III
projects; therefore the contract is also contingent on the TWDB's approval.
RECOMMENDED ACTION
Staff recommends that Council accept and approve the contract inspection proposal with Mr.
Bob Holt in the amount of $11,552.14 plus mileage and phone reimbursement expenses for the
Magnolia Harkey Sanitary Sewer Project.