R2007-195 2007-12-17 RESOLUTION NO. R2007-195 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS, APPROVING CHANGE ORDER NO. 1 ASSOCIATED WITH THE STATE HIGI-tWAY 35 TRUNK SEWER PROJECT. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS: Section 1. That Change Order NO.1 associated with the State Highway 35 Trunk Sewer Project, a copy of which is attached hereto as Exhibit "A" and made a part hereof for all purposes, is hereby authorized and approved. Section 2. That the City Manager or his designee is hereby authorized to execute and the City Secretary to attest Change Order NO.1 associated with the State Highway 35 Trunk Sewer Project. PASSED, APPROVED and ADOPTED this the 1 ih day of December, A.D., 2007. \,\\"I~'R">lLIf""llt, ,..,. <:.,... AA:"., f~~~t~ (~/. ~ y~ \,..,..,.........................."",/ Ill/lllitH.IB"""'" ATTEST: APPROVED AS TO FORM: a~. h. a-L. DARRIN M.-COKER - CITY ATTORNEY , ~'--. 0" . 1'1-1/1 "'~..., A." ~ ...., <:; " ~1 ~ E. ... " ~ Exhibit" A" Resolution No. R2007 -195 07 -0094 W42041 CITY OF PEARLAND PROJECTS DEPARTMENT 3519 Liberty Drive Pearland, Texas 77581 f' sr. I st)l. CHANGE ORDER For SH35 Trunk Sewer Contracts 1 & 2 Construction Management and Inspection Services Change Order No: CoP Project No: PO#: 070916 1 W42041 Date of Issuance: 12/10/07 Consultant: Construction and Mana2ement Professionals Subconsultant: N/A Explanation: This change order encompasses the following: Description of Work 1. Amend the original contract amount for Construction Management and Construction Inspection services as due to service needs extension, project start delays, and other reasoning as outlined in the attached documentation letter. $ Cost 108,000.00 Time 5 Mths Please attach back-up documentation Revised Contract: Cost $ 222.200.00 $ 0 $ 222.200.00 $ 108,000.00 $ 330.200.00 Time 10 Mths N/ A Mths 10 Mths 5 Mths Cost & Time Chan2e Summary: Original Contract: Previous Change Order(s): Original Contract: Net increase (decrease) from this change order: 15 Mths Finance Approval: {\~~:~ ~L Date: );1. J[J. 01 Finance Director ACCE~ By: ' Consultan Date: (~/1 (0, APPROVED: By: ~JIj?-k Ow er ~11 Eisen Date: 1211@/07 *Contractor agrees to perform change(s) included in this Change Order for the price and time indicated. The prices for changes included all costs associated with this Change Order. No work is to be done until this change order is executed. No payment to the Contractor (or Consultant) shall be made for work included in the change order until the Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, this Change Order governs. Upon execution by all parties, the following changes identified for the contract value and/or contract time shown, are made part of the contract. Page I of I 54. Revised 7/23/07 eo G 0 Construction and Management Professionals, LLC ~":', " ' Helping Clients Achieh' Their OhjeclIFt's November 5, 2007 City of Pearland 3519 Liberty Drive Pearland, TX 75810 Attn.: Ms. Cara Nesby Reference: State Highway 35 Trunk Sewer Construction Management Services - Contracts 1 and 2 Dear Ms. Nesby As requested in your letter of October 12, 2007, I have audited the invoicing to date for the Referenced projects. I found no charges which were incorrectly invoiced. The current authorized amount is $222,200.00. Our expenditures through September are $196,416.96, leaving $25,783.04 remaining. We have averaged approximately $19,600 per month. Accordingly, our current authorization will be expended by the middle of November 2007. Please note the following: . The current authorization, per Cecil Bowery, was based on a 10 month construction period. . We had expenditures prior to the start of construction because of the continued delay in starting construction . The projected was budgeted on a 5 day work week. The contractor has worked many Saturdays . There have been 2 major contract issues causing unbudgeted expenditures. These are the multiple failures of the Cement Stabilized Sand to meet the Contract Requirements and many problems with the failure of Garver to install casings to the Contract tolerances. Since the projects appear that they will use the full construction time, I have prepared the following estimate of the additional authorization required to complete both projects. This estimate is based on the following: . Project 1 will begin the middle of December 2007 and complete not later than the middle of middle of March 2008 . Project 2 will complete on schedule, April 24, 2008 . Average monthly expenditures on the projects to date PO Box 209 Item Construction Period: Warranty Period: Previously Unbilled costs: Total: Estimated Costs $ 100,000 $ 3,000 $ 5,000 $ 108,000 Barker, Texas 774] 3 T 7]3.202.3237 F 281.492.6836 www.candmp.com e eGG Construction and Management Professionals, LLC lIe/pmg C/u:'nls Achiel't! Their Ohjectll'es These estimated costs are from the totals on the attached spreadsheet, rounded to the nearest $1,000. This estimate is based on the project data shown and will need to be adjusted if that changes. If you have any questions please call. Since,rely; ~ ,1 -.::J/}. ,'~L C{Y-L~ Georg~ D.Ng, P.E. PO Box 209 Barker, Texas 77413 T 713.202.3237 F 281.492.6836 www.candmp.com ,,'-N CCD" CU ~ C i: CD CU U) CU CD~'t"" Q.CS '0 2 u ~.... .~ ._ 10 '- oCO)Q. >- cu ~ .c .2' J: en - ~ s::: o en en Q) ~ o I-< p.. c --' .... s::: Q) -. S ;~ Q) OIl ~ s::: ~ ~ "0 s::: ~ s::: o .... u ~ I-< .... en s::: o U . e . . ..... \p- o ..... 0 LO 10 0 0 10 0 LO 10 N 0 to- ..- I"- co ''If: 10 to-ft LO 'o::t (J) CO) ~ to- O) ~ (J) ~ ..". 0 ~ ..". 't"" ..". co f-- 0 0 0 0 0 0 0 0 0 0 :::R. J! ('I') 0 0 0 ('I') 0 CD CD 0 N N LO en N N N N N ('I') ('I') ..- 0 - +-' ~ ~ ~ ~ ~ ~ ~ .... .t: u m ..- ..- S c. .~ ~ ~ 4( 0 0 tn en ~ 0 0 J: 0> a.. 0 C) en .... e: :J 0> f-- U 0 0. 0 0 0 0 0 0 0 0 ~ CD I"- 0 0 0 I"- ~ 'o::t 'o::t '- 0::: >< ..- ~ ..- ..- ..- ~ 'o::t ('I') e: tn ~ J: W t5 ~ ~ ~ ~ ~ ~ ~ E Q. .... .~ m e: S - w 0 0 +:i J! .... ~ 0 e: .... 0 w a.. 0 C .... ...J <..> cu " Q. f-- f-- .~ CD 0 0 0 0 LO 0 LO 0) ~ .... :E e: CD N 0 0 ..- ('I') N ..- C cu 0 N ..- ..- ..- ..- ..- CD N E 0 t5 en ~ .2' 0 15 ~ 0) +:i .!g ::J 'o::t C U) tn 0 0> 0 ~ l! '- w .... 0. 0 I .e en ~ '- U) e: a.. CU .... e: 3: S U) - tn 0 0 0 0 0 LO 0 LO ..- '- 0 0 15 ..- ..- ('I') ('I') ..- 0) ex) CU 0 0 ..- 'o::t CD ::J +-' en I"- >- " .... ~ U ~ +-' .~ ::J ~ CD ~ 0 en 0 C e: W 0 0 I 0 .c ~ ~ 0 <..> a.. C :J 0::: - Q. ..... LO LO 0 0 LO 0 LO 0 0 .:::. 0 0 0 ...J e: ..- N N N N LO LO 0 0 tn 0 0 0 4( 0> N ..- 0) I"- ~ 0) CD LO E ..... en l"- N 0 ~ ('I') 'o::t Z u ~ 0 .~ .~ ::J N ~ > ~ ~ 0 ~ CD .... m 0 I '- e: ~ Q. C m a.. C ~ f-- 4( e: 0 0 0 0 0 0 0 0 0 C 0 N ..- ..- ..- LO 0 N +:i ..- 0 I"- W u t5 en 0) ~ .... ::J ~ ~ .~ ::J ~ 4( ..... 0 en 0 :E e: ~ I i= 0 a.. U) <..> i-- W en ~ ""'''0''0 en en C) en m m e: Q) e: Q) 5.5 E ~ ~ ..... Q) N m ~ .r:. Q) Q) ~ 0 0 E==CJ)::J ._ en Q) ~m- ..... ..c ..c ~ I- 0 0>:.0 = m<..>..c e: 0 E E <..> m m > e ::J .r:. en ..... u.. ~ Q) Q) ::J ~ U m CJ) a.. > u e: ..c ~ .~ ..... 0 Q) m Q) m 0 Z 0 ...., u.. ~ <( I- " o o N - 0'\ N - ..... ..... 0 CITY OF PEARLAND ii % PROJECTS DEPARTMENT `',lk x 3519 Liberty Drive La �j.T E X A 5 � Pearland Texas 77581 CHANGE ORDER For SH35 Trunk Sewer Contracts 1 &2 Construction Management and Inspection Services Date of Issuance: 11/29/07 Change Order No: 1 Consultant: Construction and Management Professionals CoP Project No: W42041 Subconsultant: N/A PO#: 070916 Explanation: This change order encompasses the following: Description of Work Cost Time 1. Amend the original contract amount for Construction $ 108,000.00 5 Mths Management and Construction Inspection services as due to service needs extension,project start delays, and other reasoning as outlined in the attached documentation letter. Please attach back-up documentation Cost& Time Change Summary: Cost Time Original Contract: $ 222,200.00 10 Mths Previous Change Order(s): $ 0 N/A Mths Original Contract: $ 222,200.00 10 Mths Net increase (decrease) from this change order: $ 108,000.00 5 Mths Revised Contract: $ 330,200.00 15 Mths Finance Approval: Date: Finance Director ACCEPTED*: APPROVED: By: Date: By: Date: Consultant Owner *Contractor agrees to perform change(s)included in this Change Order for the price and time indicated.The prices for changes included all costs associated with this Change Order. No work is to be done until this change order is executed.No payment to the Contractor(or Consultant)shall be made for work included in the change order until the Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent,this Change Order governs.Upon execution by all parties,the following changes identified for the contract value and/or contract time shown,are made part of the contract. Page 1 of 1 54.Revised 7/23/07 November 5, 2007 City of Pearland 3519 Liberty Drive Pearland, TX 75810 Attn.: Ms. Cara Nesby Reference: State Highway 35 Trunk Sewer Construction Management Services—Contracts 1 and 2 Dear Ms. Nesby As requested in your letter of October 12, 2007, I have audited the invoicing to date for the Referenced projects. I found no charges which were incorrectly invoiced. The current authorized amount is $222,200.00. Our expenditures through September are $196,416.96, leaving $25,783.04 remaining. We have averaged approximately$19,600 per month. Accordingly, our current authorization will be expended by the middle of November 2007. Please note the following: • The current authorization, per Cecil Bowery, was based on a 10 month construction period. • We had expenditures prior to the start of construction because of the continued delay in starting construction • The projected was budgeted on a 5 day work week. The contractor has worked many Saturdays • There have been 2 major contract issues causing unbudgeted expenditures. These are the multiple failures of the Cement Stabilized Sand to meet the Contract Requirements and many problems with the failure of Garver to install casings to the Contract tolerances. Since the projects appear that they will use the full construction time, I have prepared the following estimate of the additional authorization required to complete both projects. This estimate is based on the following: • Project 1 will begin the middle of December 2007 and complete not later than the middle of middle of March 2008 • Project 2 will complete on schedule, April 24, 2008 • Average monthly expenditures on the projects to date Item Estimated Costs Construction Period: $ 100,000 Warranty Period: $ 3,000 Previously Unbilled costs: $ 5,000 Total: $ 108,000 These estimated costs are from the totals on the attached spreadsheet, rounded to the nearest$1,000. This estimate is based on the project data shown and will need to be adjusted if that changes. If you have any questions please call. Sincerely; George O. Puig, P.E. City of Pearland Highway 35 Trunk Sewer Projects 1 and 2 ESTIMATED ADDITIONAL PROJECT COSTS TO COMPLETE THROUGH April 2008 Month Construction Management Construction Inspection Expenses Project 1 Project 2 Project 1 Project 2 Project 1 Project 2 Hours Hours Hours Hours Dollars Dollars _ November 0 15 10 60 $70 $230 _ December 20 25 10 120 $100 $200 _ January 10 20 30 100 $100 $200 February 10 20 30 100 $100 $200 March 10 25 15 115 $70 $230 April 0 50 0 130 $0 $300 _ Totals 50 155 95 - 625 $440 $1,360 Totals Dollars, $9,000 $27,900 $7,481 $49,219 $340 $1,160 $95,100 Contingency 5% $4,755 Total $99,855 One Year Warranty $720 $2,700 $3,420 Previously Unbilled Costs for Significant Items Cement Stabilized Sand Failures $900 Various Casing Problems $3,600 $4,500 $4,500 Estimated total Project Costs $107,775 11/29/2007 1 of 1 • 50 "-N• CITY OF PEARLAND PROJECTS DEPARTMENT LOM; ‘ a. 3519 Liberty Drive Pearland,Texas 77581 CHANGE ORDER For SH35 Trunk Sewer Contracts 1 &2 Construction Management and Inspection Services Date of Issuance: '12/10/07 Change Order No: 1 Consultant: Construction andManagement Professionals CoP Project No: W42041 Subconsultant: N/A PO#: 070916 Explanation: This change order encompasses the following: Description of Work Cost Time 1. Amend the original contract amount for Construction $ 108,000.00 5 Mths Management and Construction Inspection services as due to service needs extension, project start delays, and other reasoning as outlined in the attached documentation letter. Please attach back-up documentation Cost& Time Change Summary: Cost Time Original Contract: $ 222,200.00 10 Mths Previous Change Order(s): $ 0 N/A Mths Original Contract: $ 222,200.00 10 Mths Net increase(decrease) from this change order: $ 108,000.00 5 Mths Revised Contract: $ 330,200.00 15 Mths Finance Approval: Date: - Finance Director ACCEPTED*: APPROVED: By: Date: By: Date: Consultant Owner *Contractor agrees to perform change(s)included in this Change Order for the price and time indicated.The prices for changes included all costs associated with this Change Order. - No work is to be done until this change order is executed.No payment to the Contractor(or Consultant)shall be made for work included in the change order until the Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent,this Change Order governs.Upon execution by all parties,the following changes identified for the contract value and/or contract time shown,are made part of the contract. Page 1 of 1 54.Revised 7/23/07 a4 Construction and Management Professionals, LLC Helping Clients:lcnie,r Their Ch;•;tive.r November 5, 2007 City of Pearland 3519 Liberty Drive Pearland, TX 75810 Attn.: Ms. Cara Nesby Reference: State Highway 35 Trunk Sewer Construction Management Services—Contracts 1 and 2 Dear Ms. Nesby As requested in your letter of October 12, 2007, I have audited the invoicing to date for the Referenced projects. I found no charges which were incorrectly invoiced. The current authorized amount is $222,200.00. Our expenditures through September are $196,416.96, leaving $25,783.04 remaining. We have averaged approximately $19,600 per month. Accordingly, our current authorization will be expended by the middle of November 2007. Please note the following: • The current authorization, per Cecil Bowery, was based on a 10 month construction period. • We had expenditures prior to the start of construction because of the continued delay in starting construction • The projected was budgeted on a 5 day work week. The contractor has worked many Saturdays • There have been 2 major contract issues causing unbudgeted expenditures. These are the multiple failures of the Cement Stabilized Sand to meet the Contract Requirements and many problems with the failure of Garver to install casings to the Contract tolerances. Since the projects appear that they will use the full construction time, I have prepared the following estimate of the additional authorization required to complete both projects. This estimate is based on the following: • Project 1 will begin the middle of December 2007 and complete not later than the middle of middle of March 2008 • Project 2 will complete on schedule, April 24, 2008. • Average monthly expenditures on the projects to date Item Estimated Costs Construction Period: $ 100,000 Warranty Period: $ 3,000 Previously Unbilled costs: $ 5,000 Total: $ 108,000 PO Box209 Barker,Texas 77413 T 713.202.3237 F 281.492.6836 www.candmp.com • d Construction and Management Professionals, LLC 1 le/ping Clients AchieveThew Ubjeclit,es These estimated costs are from the totals on the attached spreadsheet, rounded to the nearest $1,000. This estimate is based on the project data shown and will need to be adjusted if that changes. If you have any questions please call. Sincerely; George O. 'uig, P.E. PO Box 209 Barker,Texas 77413 T 713.202.3237 P 281.492.6836 www.candmp.com ,At City of Pearland ..-: , #& I i Pv Construction and Management Professionals Highway 35 Trunk Sewer _ Projects 1 and 2 - - ESTIMATED ADDITIONAL PROJECT COSTS TO COMPLETE THROUGH April 2008 Month Construction Management Construction Inspection Expenses _ Project 1 Project 2 Project 1 Project 2 Project 1 Project 2 Hours Hours Hours Hours Dollars Dollars November 0 15 10 60 $70 $230 December 20 25 10 120 $100 $200 January ° 10 20 30 100 $100 $200 February 10 20 30 100 $100 $200 March 10 25 15 115 $70 $230, April 0 50 0 130 $0 $300 Totals 50 155 95 625 $440 $1,360 Totals Dollars $9,000 $27,900 $7,481 $49,219 $340 $1,160 $95,100 Contingency 5% $4,755 Total $99,855 One Year Warranty $720 $2,700 $3,420 Previously Unbilled Costs for Significant Items Cement Stabilized Sand Failures $900 Various Casing Problems ' $3,600 $4,500 $4,500 Estimated total Project Costs $107,775 11/29/2007 1 of