R2003-0031 02-24-03 RESOLUTION NO. R2003-31
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, APPROVING CHANGE ORDER NO. 4 FOR THE CONSTRUCTION
OF SEWER IMPROVEMENTS ASSOCIATED WITH THE PEARLAND
PARKWAY PROJECT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That change order No. 4 for the construction of a water main
associated with the Pearland Parkway Project, a copy of which is attached hereto as
Exhibit "A" and made a part hereof for all purposes, is hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute
and the City Secretary to attest Change Order No. 4 for the construction of sewer
improvements associated with the Pearland Parkway Project.
PASSED, APPROVED and ADOPTED this the 241:h day of February ,
A.D., 2003.
ATTEST:
APPROVED AS TO FORM:
DARRIN M. COKER
CITY ATTORNEY
TOM REID
MAYOR
Freese
· ' '::' Nichol. s,
Engineers
Environmental Scientists
Exhibit "A"
R2003-31
Architects
2010 East Broadway
January 28, 2003
FNI 00-403A
Pear[and, TX 77581-5502
281/485-2404
281/485-4322 fax
www.freese.com
Mr. Jim White
W.W. Webber
3899 Wilcrest Drive
Houston, Texas 77042
Re:
Pearland Parkway - Northbound Lanes
City of Pearland
New 12" Force Main (Beazer Homes Portion)
Dear Jim:
Enclosed is a request for Change Order No. 4 plans for a 12" force main. The plans pertaining to
this change order are for a new 12" force main extending from existing manhole at about station
1214-50 to station 150+15 for the referenced project. To complete the change order price, we
need unit prices for items 1 and 2. Other items are per unit prices in the original bid. The force
main unit price includes excavation, bedding and backfill. Per our discussion, a 21 calendar day
extension is also included for this change order. This is subject to City's approval.
Please provide us with needed unit prices to complete and process this change order. Please call
me if you have any question.
Sincerely,
Mehran (Ron) Bavarian, P.E.
Associate
Houston Area Manager
Enclosure:
Cc:
A1 Hague, City of Pearland, w/encl.
Gary Mensik, LJA Engineering
T:PRL00403AWhite Itt
; V
FEBRUARY 12, 2003
W. W. WEBBER
14333 Chrismann Road
Houston, Texas 77039
CITY OF PEARLAND
PEARLAND PARKWAY
NORTHBOUND LANES
B 2001-060
FNI 00-403
CHANGE ORDER NO. 4
New 12" Force Main
Beazer Homes Portion
STA 121+50 TO 150+15
The following change order for materials and labor has been approved:
ITEM DESCRIPTION UNIT QUANTITY PRICE AMOUNT
1 Add 12" PVC Sanitary Sewer Inside
Manhole Drop Approx. 14 Ft Depth w/
MJ fittings (coated w/125 mil Coal Tar
Epoxy) and Stainless Steel Straps as
per detail in Plans. LS 1 $5,000.00 $5,000.00
2 Coat Manhole w/60 mil Novolac Epoxy LS 1 $2,500.00 $2,500.00
3 Add 12" PVC SDR 26 {ASTM D2241)
Force Main LF 2,835 $22.00 $62,370.00
4 Add Trench Safety LF 2,835 $1.00 $2,835.00
TOTAL CHANGE ORDER NO. 4 $72,705.00
Contract Time: Extra 21 calendar days added for above work.
By:
Date:
Approved for Engineer:
FREESE & NICHOLS
Approved for Owner:
By: CITY ~
Date:
/ '/
~p. wPrOved for Contractol.'~ · WEBBER
, Date: ~/~
C.O. 4-1/1
FEBRUARY 12, 2003
W. W. WEBBER
14333 Chrismann Road
Houston, Texas 77039
CITY OF PEARLAND
PEARLAND PARKWAY
NORTHBOUND LANES
B 2001-060
FNI 00-403
CHANGE ORDER NO. 4
New 12" Force Main
Beazer Homes Portion
STA 121+50 TO 150+15
The following change order for materials and labor has been approved:
UNIT
ITEM DESCRIPTION UNIT QUANTITY PRICE AMOUNT
Add 12" PVC Sanitary Sewer Inside
Manhole Drop Approx. 14 Ft Depth w/
MJ fittings (coated w/125 mil Coal Tar
Epoxy) and Stainless Steel Straps as
per detail in Plans. LS 1 $5,000.00 $5,000.00
Coat Manhole w/60 mil Novolac Epoxy LS 1 $2,500.00 $2,500.00
Add 12" PVC SDR 26 (ASTM D2241)
Force Main LF 2,835 $22.00 $62,370.00
Add Trench Safety LF 2,835 $1.00~ $2,835.00
TOTAL CHANGE ORDER NO. 4 $72,705.00
Contract Time: Extra 21 calendar days added for above work.
Approved for Engineer:
FREESE & NICHOLS
Approved for Owner:
CITY OF PEARLAND
Date: _____
W.~vo. WEBBEVed for Contractor: R
C.O. 4-1/1
02/19/2003 02:51 FAX 832 467 4383
BEAZER LAND 1002
EAZI R
February 18, 2003
City of Pearland
3519 Liberty Drive
Pearland, Texas 77581
Attn: Mr Alan Mueller:
Re: Pearland Parkwy Northbound Lanes — Change Order No. 4
Dear Mr. Mueller:
Beazer Homes hereby authorizes City of. Pearland to proceed with the work outlined in
the referenced change order (attached). Beazer Homes will reimburse the City of
Pearland for the total cost of $72,705.00 thirty (30) days after City of Pearland's payment
to W W. Webber.
Sincerely,
1
Dan Olson
SeniorVice President
GC
Enclosures
BZH Beazer I-Iames Texas, L.P.
NYSE 10235 West Little York, Suite 100 J Houston, Texas 77040
Phone (713) 819.5017 • Fax (713) 849-2252
www•.beazer.com
02119/2003 02:51 FAX 832 467 4383
BEAZER LAND
1003
•
W. W. WEBBER
14333 Christen Road
Houston Texas 77039
FERRUARY 12, 2003
OITV OF PEARLAIQD
PEA€RLAND PARKWAY
NORTHBOUND LANES
$ 2001-060
FM 00 403
CHANGE ORDER NO, 4
New 12u Force Main
6eaze: Homes Portion
STA 121 450 TO 150+15
the Wowing change coder for materials and labor has bean approved:
NO.1 ITEM DESCRIPi1Q
1( Add 127 PVC Sanitary Sewer Inside
Manhole Drop Approx. 14 Ft Depth wl
pN 1%ttings (coated w1 12.5 mil Coal Tar
Epoxy) and Stainless Steel straps as
pot email in Ptann.
2 Coat Manhole w! 60 mil Novolao Epoxy
a Add 12' Pvc sof! a6 ({45l' i D2241j.
Forts Mahn
ar Add Trench Satoiy
TOTAL CHANGE ORDER NO. 4
Contrast Tirno: Extra 21 calendar days added for above work.
•
•
AAp'rowd for Enpinaer.
FR5ES5 & NICHOLS
ay:-•
Dols! Z fir
ate:
•
Approved fotQwtle(:
CITY OF PEARLAND
By:
Crate:
C.O, 4-111
r
Apptamd ler contractor:
W. W. WESRER
•
o "d
OS:: T
2Oa 7T qa3
Lira
DOCUMENT FILING REQUEST
RP-130
Description:
Change Order #4
Resolution:
Bill Eisen
City Manager
Type:
New 12" Force Main (Beazer Homes Portion)
Search String Parameters:
Pearland Parkway — Northbound Lanes
Requested By:
Robin Pitcock
Project Management
03/04/03
Exhibit A
R2003-31
C E
MAR 5 70313
lassis
CITY OF PEARIAND
CITY SECRETARY'S OFFICE