R2007-082 2007-05-14 T70011
RESOLUTION NO. R2007 -82
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, APPROVING CHANGE ORDER NO.5 ASSOCIATED WITH THE
BAILEY ROAD EXTENSION.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That Change Order No.5 associated with the Bailey Road Extension,
a copy of which is attached hereto as Exhibit "A" and made a part hereof for all purposes,
is hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute
and the City Secretary to attest Change Order No. 5 associated with the Bailey Road
Extension.
PASSED, APPROVED and ADOPTED this the 14th day of
, A.D., 2007.
T M REID
MAYOR
ATTEST:
APPROVED AS TO FORM:
(J~ 11. (!.J-,
DARRIN M. COKER
CITY ATTORNEY
R2007-82 - - _ -- _ -
File No. 07-0036
e �
10,
a/ARA
Ofr1 - �R.
)
X A „r•
r-=es� ��
r
CHANGE ORDER
For
Bailey Road Extension Project between Veterans and S.H. 35
Project No. T70011,PO No.062826,Acct.No. 070-0000-565-03-02
Pearland,Texas
Date of Issuance: 05-06-07 Change Order No: 05
Owner: City of Pearland Owner's Project No: T70011
Contractor: Hassell Construction,Inc. Contractor's Project No:
Engineer: Freese&Nichols,Inc. Engineer's Project No:
Explanation of this Change Order:
This change order encompasses the following:
Item 1-Scope
The Owner has requested that the Contractor provide a proposal to install additional
asphaltic overlay of existing main lanes along Veterans Drive between Sta. 12+73 and
Sta. 24+31 (reference Sheets 27-30). The overlay is too match the proposed elevations
for the intersection at Bailey Road and the proposed shoulders along Veterans Drive. A
unit price and quantity will be established under Section E, Extra Work, Item 12 -
Asphalt Finish Course/Overlay. One additional Calendar Day has been requested.
12-Asphalt Finish Course/Overlay 230 Tons $120.00/Ton=$27,600.00
Justification
Since design and bid time, the existing asphalt road surface has degraded. The overlay
will extend the life of the intersection and main lane paving until the new entire concrete
intersection can be constructed during the next phase of Bailey Road construction. This
is a no cost or time change to the contract.
Contract Amount:
Original Contract Price: $ 9,914,274.85
Previous Change Order(s): $ 0.00
Contract price prior to this change order: $ 9,914,274.85
Net increase(decrease)from this change order: $ 0.00
Contract price with all change orders to date:
(Including this change order): $ 9,914,274.85
City of Pearland-Change Order No.2,Page 2
Contract Time:
One(1) additional Calendar Days. The activity is a critical path item.
RECOMMENDED• ACCEPTED:
By: By:
Construc 'on M ger Contrac
Date: */--1 d 1 Date: S -i s`0 7
APPROVED: APPROVED:
By: . /J
Engineer Own Bill Eisen, City Manager
Date: -s' 1I- 0 7 Date:May 14, 2007