HomeMy WebLinkAboutR2026-200 20261116RESOLUTION NO. R2026-200
A Resolution of the City Council of the City of Pearland, Texas, authorizing
Letter Finance Agreements associated with the Orchard at Lower Kirby
Project between the City and the Pearland Municipal Management District No.
1.and the City and the Lower Kirby Pearland Management District.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That a certain Reimbursement Agreement by and between the City of
Pearland and the Pearland Economic Development Corporation was approved on August 5, 2026.
Section 2. That certain Letter Finance Agreement with the Pearland Municipal
Management District No. 1 associated with the Orchard at Lower Kirby Project, a copy of which is
attached hereto as Exhibit “A” and made a part hereof for all purposes, is hereby approved.
Section 3. That the City Manager or his designee is hereby authorized to execute and
the City Secretary to attest a Letter Finance Agreement with the Pearland Municipal Management
District No.1.
Section 4. That certain Letter Finance Agreement with the Lower Kirby Pearland
Management District associated with the Orchard at Lower Kirby Project, a copy of which is
attached hereto as Exhibit “B” and made a part hereof for all purposes, is hereby approved.
Section 5. That the City Manager or his designee is hereby authorized to execute and
the City Secretary to attest to Letter Finance Agreement with the Lower Kirby Pearland
Management District.
PASSED, APPROVED and ADOPTED this the 16th day of November, A.D., 2026.
________________________________
QUENTIN WILTZ
MAYOR
ATTEST:
________________________________
FRANCES AGUILAR, TRMC, MMC
CITY SECRETARY
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
RESOLUTION NO. R2026-200
APPROVED AS TO FORM:
________________________________
LAWRENCE G. PROVINS
CITY ATTORNEY
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
PEARLAND MUNICIPAL MANAGEMENT DISTRICT NO. 1
c/o Allen Boone Humphries Robinson LLP
3200 Southwest Freeway, Suite 2600
Houston, Texas 77027
September 24, 2026
Mr. Trent Epperson
City Manager
City of Pearland, Texas
3519 Liberty Drive
Pearland, TX 77581
Re: Financing for design, construction and land acquisition
Dear Mr. Epperson:
Pearland Municipal Management District No. 1 (the “District”) and the City of
Pearland, Texas (the “City”) entered into a Financing Agreement (the “Agreement”) dated
February 6, 2014, to provide for the financing and construction of facilities to serve land
within the District.
The District and the City have determined to proceed with the design and
construction of those water, sanitary sewer, drainage, detention, road, and park and
recreational facilities identified on Exhibit A attached hereto (the “Facilities”). The District
and the City have also determined to proceed with the acquisition of land necessary for
regional detention identified on Exhibit B attached hereto (the “Regional Detention Land”).
The District has entered into a Development Financing Agreement with Pearland
Orchard, LLC (the “Developer”) for the design, construction and financing of a portion of
the costs of the Facilities. The City has entered into a Development Agreement with
Planned Community Developers V, Ltd., which was assigned to the Developer, regarding
the Facilities and the Regional Detention Land.
The estimated costs to be incurred by the City for the Facilities and the Regional
Detention Land are set forth in Exhibit A attached hereto.
The District agrees to reimburse the City for the costs of the Facilities and the
Regional Detention Land, to the extent such amounts were paid by the City to the
Developer. The District’s obligation to reimburse the Developer and the City for the
Facilities and the Regional Detention Land shall be subject to the Priority of
Reimbursement set forth on Exhibit C attached hereto.
[EXECUTION PAGE FOLLOWS]
4925-3927-3669 v.1
Exhibit A to R2026-200
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
11/17/2026 | 3:34 PM CST
EXHIBIT A
THE FACILITIES
Roadway and Utility Improvements ($6,620,189)
Promenade Shops Drive
Promenade Shops Drive/South Spectrum Traffic Signal
Street C – North Spectrum Drive Extension
Street E – Green Ivy Drive Extension
Street K – SH 288 Entry to North Spectrum
Regional Detention Improvements ($3,553,386)
Main Detention Pond
South Detention Pond
East Detention Pond
Central Detention Pond
North Detention Pond
Park Development and Gathering Space Improvements ($8,167,019)
Orchard Plaza
Regional Detention Land - 16.438 acres ($128,472)
East Detention Pond
Central Detention Pond
South Detention Pond
South Tract for Detention Pond
South Tract for Main Pond Expansion
4925-3927-3669 v.1
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
EXHIBIT B
Regional Detention Land
4925-3927-3669 v.1
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
EXHIBIT C
PRIORITY OF REIMBURSEMENT
BETWEEN DEVELOPER AND CITY OF PEARLAND
The District’s reimbursement of the Developer and the City for eligible costs associated
with the Roadway and Utility Improvements, Regional Detention Improvements, Park
Development and Gathering Space Improvements and Regional Detention Land shall be
subject to the following conditions:
The Developer and the City agree that the District, in its sole discretion, may reimburse
other developers, the City, Lower Kirby Pearland Management District, and Pearland
Municipal Management District No. 2 for any amounts owed by the District to such entities
as of the effective date of this Agreement prior to reimbursing the Developer and the City
for those items subject to reimbursement pursuant to this Agreement.
Provided the District has not received written notice from the City that an event of default
has occurred under the City’s development agreement with the Developer, and such event
of default has not been cured by Developer, reimbursements will occur in the following
order of priority as among the Developer and the City:
I. Water, Sewer and Drainage (WSD) Bonds for Utility Improvements, Regional
Detention Improvements and Regional Detention Land:
First, the City shall be reimbursed for costs spent on the purchase of Regional
Detention Land.
Second, the Developer shall be reimbursed for Utility Improvements and Regional
Detention Improvements that are financed 100% by the Developer.
Third, for any Utility Improvements or Regional Detention Improvements financed
jointly by the Developer and the City, the following shall apply:
a. When preparing applications to the TCEQ for approval of WSD bonds, any
project included in a bond application that is jointly financed by the Developer
and the City shall include the costs prefinanced by Developer and the City. To
the extent the District’s bonding capacity does not allow for the reimbursement
in full of the Developer and the City for any project, the City will defer its
portion of the reimbursement that cannot be funded with such series of WSD
bonds until the next series of WSD bonds issued by the District (the “City
Deferred Amount”) prior to the Developer deferring any portion of its
reimbursement for such project.
b. If after deducting the City Deferred Amount the Developer will not be
reimbursed in full for such project, such amount (the “Developer Deferred
4925-3927-3669 v.1
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
Amount”) shall be included in the next WSD bond application. If there is a City
Deferred Amount, but no Developer Deferred Amount in the next bond
application for WSD bonds, the City’s Deferred Amount shall be given priority
for reimbursement over any additional projects. If there is a City Deferred
Amount and a Developer Deferred Amount in the next WSD bond application,
such amounts shall be given priority for reimbursement over any additional
projects. If the City Deferred Amount and the Developer Deferred Amount
cannot be paid in full, the Developer Deferred Amount shall be reimbursed first,
and the City Deferred Amount shall be reimbursed second.
c. The process outlined in a. and b. above shall occur for each bond application
until the City has been reimbursed in full for Utility Improvements and Regional
Detention Improvements.
Fourth, the City shall be reimbursed for Utility Improvements and Regional
Detention Improvements that are financed 100% by the City.
II. Road Bonds for Roadway Improvements:
First, the Developer shall be reimbursed for Roadway Improvements that are
financed 100% by the Developer.
Second, for any Roadway Improvements financed jointly by the Developer and the
City, the following shall apply:
a. When preparing summaries of costs for Road bonds, any project that is
jointly financed by the Developer and the City shall include the costs
prefinanced by Developer and the City. To the extent the District’s bonding
capacity does not allow for the reimbursement in full of the Developer and the
City for any project, the City will defer its portion of the reimbursement that
cannot be funded with such series of Road bonds until the next series of Road
bonds issued by the District (the “City Deferred Amount”) prior to the
Developer deferring any portion of its reimbursement for such project.
b. If after deducting the City Deferred Amount the Developer will not be
reimbursed in full for such project, such amount (the “Developer Deferred
Amount”) shall be included in the next series of Road bonds. If there is a City
Deferred Amount, but no Developer Deferred Amount in the next series of Road
bonds, the City’s Deferred Amount shall be given priority for reimbursement
over any additional projects. If there is a City Deferred Amount and a
Developer Deferred Amount in the next series of Road bonds, such amounts
shall be given priority for reimbursement over any additional projects. If the
City Deferred Amount and the Developer Deferred Amount cannot be paid in
4925-3927-3669 v.1
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
full, the Developer Deferred Amount shall be reimbursed first, and the City
Deferred Amount shall be reimbursed second.
c. The process outlined in a. and b. above shall occur for each series of Road
bonds until the City has been reimbursed in full for Roadway Improvements.
Third, the City shall be reimbursed for Roadway Improvements that are financed
100% by the City.
III. Park Bonds for Park Development and Gathering Space Improvements:
First, the Developer shall be reimbursed for Park Development and Gathering Space
Improvements that are financed 100% by the Developer (Mews, Linear Park, and
East Detention Pond amenities).
Second, the City shall be reimbursed for Park Development and Gathering Space
Improvements that are financed 100% by the City (Orchard Plaza).
Third, the Developer shall be reimbursed for any Park Development and Gathering
Space Improvements not reimbursed under the First clause.
If, at the time of preparation of a bond application for WSD bonds or the preliminary
official statement for Road bonds or Park bonds, the District has received written notice
from the City that an event of default has occurred under the City’s development
agreement with the Developer, and such event of default has not been cured by
Developer, only the projects prefinanced by the City (or the City’s portion of projects
jointly financed with the Developer, to the extent permitted by the rules of the TCEQ)
shall be included for funding in such series of bonds.
The District, in its sole discretion, shall determine the timing of the issuance of bonds,
and which type of bonds (WSD, Road, Park) shall be issued.
4925-3927-3669 v.1
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
Exhibit B to R2026-200
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
11/17/2026 | 3:34 PM CST
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287
Docusign Envelope ID: FCA372E9-1BDB-8187-8350-41AFE0C0A287