HomeMy WebLinkAboutR2026-168 20261026RESOLUTION NO. R2026-168
A Resolution of the City Council of the City of Pearland, Texas, authorizing the
City Manager or his designee to enter into a contract with LJA, Inc., in the
amount of $893,929.00, for professional services associated with the Alice
Elevated Storage Tank and Ground Storage Tank Project (WA2601) and the
Alice Water Treatment Plant New 5 MG Ground Storage Tank Project
(WA2609).
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That certain contract by and between the City of Pearland and LJA, Inc., a
copy of which is attached hereto as Exhibit “A” and made a part hereof for all purposes, is hereby
authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute and
the City Secretary to attest a contract with LJA, Inc., for professional services associated with the
Alice Elevated Storage Tank and Ground Storage Tank Project (WA2601) and the Alice Water
Treatment Plant New 5 MG Ground Storage Tank Project (WA2609).
PASSED, APPROVED and ADOPTED this on the 26th day of October, A.D., 2026.
________________________________
QUENTIN WILTZ
MAYOR
ATTEST:
________________________________
FRANCES AGUILAR, TRMC, MMC
CITY SECRETARY
APPROVED AS TO FORM:
________________________________
LAWRENCE G. PROVINS
CITY ATTORNEY
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Professional Services Contract 1 of 5 4/2019
CONTRACT FOR PROFESSIONAL SERVICES
THIS CONTRACT is entered into upon final execution by and between the City of Pearland
("CITY") and LJA, Inc. ("CONSULTANT").
The CITY engages the CONSULTANT to perform professional services for a project known and
described as Alice Elevated & Ground Storage Tank Replacement and Alice 5MG GST
("PROJECT"). (Project # WA2601, WA2609), Contract # P121-26.
SECTION I - SERVICES OF THE CONSULTANT
The CONSULTANT shall perform the following professional services to CITY standards and in
accordance with the degree of care and skill that a professional in Texas would exercise under
the same or similar circumstances:
A. The CONSULTANT shall provide professional services. See Exhibit A, attached,
for a detailed SCOPE OF WORK and PROJECT schedule. The PROJECT
schedule shall be submitted in digital and hard copy form in the Microsoft Project
for Windows format.
B.The CONSULTANT shall prepare and submit a detailed opinion of estimated cost
of the PROJECT.
C.The CONSULTANT acknowledges that the CITY (through its employee
handbook) considers the following to be misconduct that is grounds for
termination of a CITY employee: Any fraud, forgery, misappropriation of funds,
receiving payment for services not performed or for hours not worked,
mishandling or untruthful reporting of money transactions, destruction of assets,
embezzlement, accepting materials of value from vendors, or consultants, and/or
collecting reimbursement of expenses made for the benefit of the CITY. The
CONSULTANT agrees that it will not, directly or indirectly; encourage a CITY
employee to engage in such misconduct.
D.The CONSULTANT shall submit all final construction documents in both hard
copy and electronic format. Plans shall be AutoCAD compatible and all other
documents shall be Microsoft Office compatible. The software version used shall
be compatible to current CITY standards. Other support documents, for example,
structural calculations, drainage reports and geotechnical reports, shall be
submitted in hard copy only. All Record Drawings electronic files shall be
submitted to the CITY in TIF format.
E.The CONSULTANT recognizes that all drawings, special provisions, field survey
notes, reports, estimates and any and all other documents or work product
generated by the CONSULTANT under the CONTRACT shall be delivered to the
CITY upon request, shall become subject to the Open Records Laws of this State.
EXHIBIT A Resolution No. R2026-168Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Professional Services Contract 2 of 5 4/2019
F. The CONSULTANT shall procure and maintain for the duration of this
Agreement, insurance against claims for injuries to persons, damages to property,
or any errors and omissions relating to the performance of any work by the
CONSULTANT, its agents, employees or subcontractors under this Agreement,
as follows:
(1) Workers’ Compensation as required by law.
(2) Professional Liability Insurance in an amount not less than $1,000,000 in
the aggregate.
(3) Comprehensive General Liability and Property Damage Insurance with
minimum limits of $1,000,000 for injury or death of any one person,
$1,000,000 for each occurrence, and $1,000,000 for each occurrence of
damage to or destruction of property.
(4) Comprehensive Automobile and Truck Liability Insurance covering
owned, hired, and non-owned vehicles, with minimum limits of
$1,000,000 for injury or death of any one person, $1,000,000 for each
occurrence, and $1,000,000 for property damage.
The CONSULTANT shall include the CITY as an additional insured under the
policies, with the exception of the Professional Liability Insurance and Workers’
Compensation. Certificates of Insurance and endorsements shall be furnished to
the CITY before work commences. Each insurance policy shall be endorsed to
state that coverage shall not be suspended, voided, canceled, and/or reduced in
coverage or in limits (“Change in Coverage”) except with prior written consent of
the CITY and only after the CITY has been provided with written notice of such
Change in Coverage, such notice to be sent to the CITY either by hand delivery to
the City Manager or by certified mail, return receipt requested, and received by
the City no fewer than thirty (30) days prior to the effective date of such Change
in Coverage. Prior to commencing services under this CONTRACT,
CONSULTANT shall furnish CITY with Certificates of Insurance, or formal
endorsements as required by this CONTRACT, issued by CONSULTANT’S
insurer(s), as evidence that policies providing the required coverage, conditions,
and limits required by this CONTRACT are in full force and effect.
G. The CONSULTANT shall indemnify and hold the CITY, its officers, agents, and
employees, harmless from any claim, loss, damage, suit, and liability of every
kind for which CONSULTANT is legally liable, including all expenses of
litigation, court costs, and attorney's fees, for injury to or death of any person, for
damage to any property, or errors in design, any of which are caused by the
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Professional Services Contract 3 of 5 4/2019
negligent act or omission of the CONSULTANT, his officers, employees, agents,
or subcontractors under this CONTRACT.
H. All parties intend that the CONSULTANT, in performing services pursuant to this
CONTRACT, shall act as an independent contractor and shall have control of its
own work and the manner in which it is performed. The CONSULTANT is not to
be considered an agent or employee of the CITY.
SECTION II - PERIOD OF SERVICE
This CONTRACT will be binding upon execution and end March 31, 2029.
SECTION III - CONSULTANT'S COMPENSATION
A. The total compensation for the services performed shall not exceed the total noted
in Section B.
B. The CITY shall pay the CONSULTANT in installments based upon monthly
progress reports and detailed invoices submitted by the CONSULTANT based
upon the following:
1. Basic Services (Lump Sum) $734,676.00
2. Additional Services shall require independent and specific authorization
and shall be billed as (Lump Sum): $159,253.00
3. Bid Phase Services (Hourly Not to Exceed)
4. Construction Phase Services (Hourly Not to Exceed)
5. Reimbursable Expenses (Not to Exceed)
6. Total: $893,929.00
C. The CITY shall make payments to the CONSULTANT within thirty (30) days
after receipt and approval of a detailed invoice. Invoices shall be submitted on a
monthly basis.
SECTION IV - THE CITY'S RESPONSIBILITIES
A. The CITY shall designate a project manager during the term of this CONTRACT.
The project manager has the authority to administer this CONTRACT and shall
monitor compliance with all terms and conditions stated herein. All requests for
information from or a decision by the CITY on any aspect of the work shall be
directed to the project manager.
B. The CITY shall review submittals by the CONSULTANT and provide prompt
response to questions and rendering of decisions pertaining thereto, to minimize
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Professional Services Contract 4 of 5 4/2019
delay in the progress of the CONSULTANT'S work. The CITY will keep the
CONSULTANT advised concerning the progress of the CITY'S review of the
work. The CONSULTANT agrees that the CITY'S inspection, review,
acceptance or approval of CONSULTANT'S work shall not relieve
CONSULTANT'S responsibility for errors or omissions of the CONSULTANT or
its sub-consultant(s) or in any way affect the CONSULTANT’S status as an
independent contractor of the CITY.
SECTION V - TERMINATION
A. The CITY, at its sole discretion, may terminate this CONTRACT for any reason -
- with or without cause -- by delivering written notice to CONSULTANT
personally or by certified mail at 11821 East Freeway, Suite 360 Houston, TX.
77029. Immediately after receiving such written notice, the CONSULTANT shall
discontinue providing the services under this CONTRACT.
B. If this CONTRACT is terminated, CONSULTANT shall deliver to the CITY all
drawings, special provisions, field survey notes, reports, estimates and any and all
other documents or work product generated by the CONSULTANT under the
CONTRACT, entirely or partially completed, together with all unused materials
supplied by the CITY on or before the 15th day following termination of the
CONTRACT.
C. In the event of such termination, the CONSULTANT shall be paid for services
performed prior to receipt of the written notice of termination. The CITY shall
make final payment within sixty (60) days after the CONSULTANT has delivered
to the CITY a detailed invoice for services rendered and the documents or work
product generated by the CONSULTANT under the CONTRACT.
D. If the remuneration scheduled under this contract is based upon a fixed fee or
definitely ascertainable sum, the portion of such sum payable shall be
proportionate to the percentage of services completed by the CONSULTANT
based upon the scope of work.
E. In the event this CONTRACT is terminated, the CITY shall have the option of
completing the work, or entering into a CONTRACT with another party for the
completion of the work.
F. If the CITY terminates this CONTRACT for cause and/or if the CONSULTANT
breaches any provision of this CONTRACT, then the CITY shall have all rights
and remedies in law and/or equity against CONSULTANT. Venue for any action
or dispute arising out of or relating to this CONTRACT shall be in Brazoria
County, Texas. The laws of the State of Texas shall govern the terms of this
CONTRACT. The prevailing party in the action shall be entitled to recover its
actual damages with interest, attorney’s fees, costs and expenses incurred in
connection with the dispute and/or action. CONSULTANT and CITY desire an
expeditious means to resolve any disputes that may arise between under this
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
5 of 5 4/2019
CONTRACT. To accomplish this, the parties agree to mediation as follows: If a
dispute arises out of or relates to this CONTRACT, or the breach thereof, and if
the dispute cannot be settled through negotiation, then the parties agree first to try
in good faith, and before pursuing any legal remedies, to settle the dispute by
mediation of a third party who will be selected by agreement of the parties.
SECTION VI – ENTIRE AGREEMENT
This CONTRACT represents the entire agreement between the CITY and the CONSULTANT
and supersedes all prior negotiations, representations, or contracts, either written or oral. This
CONTRACT may be amended only by written instrument signed by both parties.
SECTION VII – COVENANT AGAINST CONTINGENT FEES
The CONSULTANT affirms that he has not employed or retained any company or person, other
than a bona fide employee working for the CONSULTANT to solicit or secure this
CONTRACT, and that he has not paid or agreed to pay any company or person, other than a
bona fide employee, any fee, commission, percentage brokerage fee, gift, or any other
consideration, contingent upon or resulting from the award or making of the CONTRACT. For
breach or violation of this clause, the CITY may terminate this CONTRACT without liability,
and in its discretion, may deduct from the CONTRACT price or consideration, or otherwise
recover, the full amount of such fee, commission, percentage brokerage fee, gift, or contingent
fee that has been paid.
SECTION VIII- SUCCESSORS AND ASSIGNS
This CONTRACT shall not be assignable except upon the written consent of the parties hereto.
DATE
DATE
________________________________
ASSISTANT FINANCE DIRECTOR
CITY OF PEARLAND, TEXAS
________________________________
CITY MANAGER/DIRECTOR
CITY OF PEARLAND, TEXAS
________________________________
CONSULTANT
Professional Services Contract
DATE
09/08/26Jimmy Flowers, PE - Vice President
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
11/4/2026 | 8:47 AM CST
11/4/2026 | 8:26 AM CST
ATTEST:
________________________________
FRANCES AGUILAR, TRMC, MMC
CITY SECRETARY
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
September 8, 2026
Ms. Lori Bender
Senior Project Manager
Engineering & Public Works
City of Pearland
2016 Old Pearland Road
Pearland, Texas 77581
Re: Proposal for Design and Construction Related Services for the
WA2601 – Alice Elevated and Ground Storage Tank Rehabilitation and
WA2609 – Alice Water Treatment Plant New 5-Million-Gallon Ground Storage Tank for
the City of Pearland
LJA Proposal No. 0000022236
Dear Ms. Bender:
LJA, Inc. (LJA) is pleased to submit this proposal to provide design and construction related
services associated with the WA2601 – Alice Elevated and Ground Storage Tank Rehabilitation
and the WA2609 – Alice Water Treatment Plant New 5 MG Ground Storage Tank for the City of
Pearland.
The Alice Water Treatment Plant (WTP) was built in the 1980s, with a 500,000-gallon elevated
storage tank (EST). In 2010, the facility was expanded to add a 5-million-gallon (MG) ground
storage tank (GST), three booster pumps, and a 750-kilowatt (kW) emergency generator. The
original 2010 plan also reserved space for a second 5-MG GST and an additional booster pump
to support anticipated demand growth in Pearland’s east service area.
WA2601 – Alice Elevated and Ground Storage Tank Rehabilitation:
The Texas Commission on Environmental Quality (TCEQ) requires annual inspections of all
water storage tanks. The July 2025 inspection found that while the existing EST and GST
remain operational, their interior and exterior coatings have exceeded their typical service life.
To maintain regulatory compliance and extend asset longevity, replacement of coatings,
electrical components, venting, piping, and the City logo is recommended.
WA2609 – Alice Water Treatment Plant New 5-Million-Gallon Ground Storage Tank:
The original WTP layout was designed to accommodate a future second 5-MG GST and
booster pump. Constructing this additional tank will increase potable water storage capacity,
improve system reliability, support peak-demand conditions, and reduce dependence on
external water sources.
SCOPE OF CONTRACT/AGREEMENT
Projects WA2601 and WA2609 have been combined into a single design and construction
package. This approach streamlines coordination and minimizes operational disruptions when
the existing GST is taken offline for rehabilitation.
WA2601 – Rehabilitation Scope:
LJA will prepare construction documents for the rehabilitation of existing EST and GST. Planned
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Ms. Lori Bender
City of Pearland
September 8, 2026
Page 2 of 8
H:\Engineering\Proposals\City of Pearland\City of Pearland - Assignment Letter - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - REV 2026-09-08.docx
improvements include replacement of interior and exterior coatings, upgrades to the electrical
and vent systems, and piping repairs. Both tanks will be equipped with mixers to eliminate
thermal stratification and improve water quality. LJA will provide full design, bidding, and
construction-phase services.
WA2609 – Alice WTP New 5-MG GST Scope:
LJA will design and prepare construction documents for a new 5-MG concrete GST equipped
with a mixer. The project also includes installation of a new booster pump, replacement of three
existing pumps, and evaluation of electrical and generator capacity for potential upgrades. LJA
will provide full design, bidding, and construction-phase services.
SCOPE OF SERVICES
A. Basic Services (Design)
1. 60% Design Phase
a. Attend Preliminary Conference with the City and other interested parties regarding
the project. Provide a detailed design schedule from Notice to Proceed (NTP)
through bidding completion for the project, including submittal dates, review times,
Texas Commission on Environmental Quality (TCEQ) approvals, bidding and award.
b. Review all reports/plans regarding the existing water plant and tanks planned for
rehabilitation.
c. Establish the scope of any topographical surveys which, in the opinion of the
Engineer, may be required. Coordinate mobilization of survey crews and incorporate
detailed topographic survey into the proposed civil site plans.
d. Coordinate the geotechnical investigations to ensure adequate bores are completed
in accordance with American Concrete Institute requirements. Incorporate findings
and recommendations from the geotechnical reports into the proposed plans and
specifications.
e. Review and determine if the existing generator is sized to handle the existing
electrical load and proposed electrical load.
f. Review and determine if the existing electrical room and control room is of sufficient
size to accommodate the additional Variable Frequency Drives (VFD) and control
panel, as well as if the existing HVAC system is sufficient for the additional heat load
generated by the additional electrical equipment.
g. Coordinate with electrical engineer to provide memorandum of understanding with
findings and recommendations regarding the generator and electrical room early in
the 60% Design Phase.
h. Prepare preliminary site layout for discussions with the City and to gain their
approval early in the 60% Design Phase.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Ms. Lori Bender
City of Pearland
September 8, 2026
Page 3 of 8
H:\Engineering\Proposals\City of Pearland\City of Pearland - Assignment Letter - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - REV 2026-09-08.docx
i. Coordination with Brazoria Drainage District No. 4 (BDD4) with regards to
Drainage/Detention Requirements.
j. Prepare draft detention/drainage calculations and show on site plan.
k. Review of existing Electrical and Controls for space and capacity needs, coordination
with CenterPoint Energy (CPE) as needed.
l. Prepare detailed structural sheets required for establishing minimum standards for
the tank manufacturers to adhere to.
m. Prepare detailed electrical sheets illustrating any modifications to the electrical
equipment, conduits, and controls to ensure the tank can be placed online,
monitored, and integrated into the City’s infrastructure and SCADA systems.
n. Prepare detailed civil and mechanical sheets illustrating any site modifications
required to construct the tank, modifications to the yard piping needed to place the
tank online, removal of the existing booster pumps, and the installation of four new
booster pumps.
o. Prepare and submit 60% submittal for City review, including Construction Plans and
Opinion of Probable Construction Cost (OPCC).
p. Prepare detailed specifications, contract documents, and contract drawings.
q. Coordination with BDD4 on drainage / detention requirements as necessary.
2. 90% Design Phase
a. Address City comments from 60% submittal and review.
b. Continue the design of detailed structural sheets required for establishing minimum
standards for the tank manufacturers to adhere to.
c. Continue the design of detailed electrical sheets illustrating any modifications to the
electrical equipment, conduits, and controls to ensure the tank can be placed online,
monitored, and integrated into the City’s infrastructure and SCADA systems.
d. Continue the design of detailed civil and mechanical sheets illustrating any site
modifications required to construct the tank, modifications to the yard piping needed
to place the tank online, removal of the existing booster pumps, and the installation
of four new booster pumps.
e. Continue the preparation of detailed specifications, contract documents, and contract
drawings.
f. Prepare and submit 90% submittal for City review, including Construction Plans and
OPCC.
g. Submit final contract specifications and drawings to the required agencies for review
and approval.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Ms. Lori Bender
City of Pearland
September 8, 2026
Page 4 of 8
H:\Engineering\Proposals\City of Pearland\City of Pearland - Assignment Letter - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - REV 2026-09-08.docx
3. Final 100% Design Phase
a. Address City comments from 90% submittal and review.
b. Finalize contract drawings and prepare detailed specifications and contract
documents.
c. Submit final contract documents to corresponding regulatory agencies (such as
TCEQ) for review and approval, in order to receive approvals and permits if required.
4. Deliverables and Schedule for Each Phase
a. Provide memorandum of understanding from electrical engineer with findings and
recommendations regarding the generator requirements within 28 Calendar Days of
NTP.
b. 60% Design Phase: 60% plans, specs, project manual, OPCC, estimated
construction schedule, and updated design schedule to be submitted approximately
109 Calendar Days after kick-off meeting and NTP.
c. 90% Design Phase: 90% plans, specs, project manual, OPCC, estimated
construction schedule, updated design schedule, and comment response log to be
submitted approximately 81 Calendar Days after receipt of 60% comments.
d. Final 100% Design Phase: final plans, specs, project manual, OPCC, estimated
construction schedule, and comment response log to be submitted approximately 70
Calendar Days after receipt of 90% comments.
e. At every design phase, submit documents and coordinate with City permitting
department (City of Pearland Community Development Department) and any other
external regulatory agency (such as TCEQ), as required for the completion of this
project to ensure City permitting requirements are met.
f. Maintain an Action Tracker for the duration of the project.
B. Bidding Phase
1. Assist the City in the advertisements of the project for bids.
2. Respond to questions regarding the project during the bidding process. If required,
issue addendums to clarify any questions regarding the project.
3. Conduct a Pre-Bid Conference between the Engineer, City, prospective bidders,
suppliers, etc., to make certain that the scope of the work is fully understood.
4. Evaluate bids, check Contractor financial standing and references, and prepare a
recommendation letter for Council action.
a. Bid evaluation to include the following:
i. Check for math errors and reconcile any mathematical discrepancies.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Ms. Lori Bender
City of Pearland
September 8, 2026
Page 5 of 8
H:\Engineering\Proposals\City of Pearland\City of Pearland - Assignment Letter - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - REV 2026-09-08.docx
ii. Review for unbalanced bid items.
iii. Provide certified Bid Tabulation including Engineer’s estimate.
b. Review of contractor’s financial standing and references to include the
following:
i. Detailed summary of the client call, outlining participant roles,
questions raised, and responses provided.
c. Recommendation of award to include the following:
i. Explanation of discrepancies between the Engineer provided OPCC
and bids received.
5. Attend City Council Meeting and make recommendation for award of Contract.
6. Prepare final contract documents for execution by the Contractor and the City.
C. Construction Phase
1. Conduct a Pre-Construction Conference between the City, Engineer, and Contractor.
2. Issue a work order with dates approved by the City.
3. Make periodic visits to the project site to observe work with regard to general
compliance with the plans and specifications.
4. Review, comment, and accept Contractor’s submittals, Requests for Information
(RFIs), and Requests for Proposals (RFPs), including coordination with City Project
Manager on Change Directives and Change Orders.
5. Preparation for execution of the necessary progress documents including work order,
payment estimates (after City Inspector has reviewed and approved the quantity of
installed items), change orders, time extensions, and other correspondence required
to achieve the intended finished project.
6. Provide interpretive guidance for the Contractor and City Project Manager to assist in
resolving issues that might arise.
7. Coordinate with City Project Manager and/or Construction Inspector to (a) review
progress of work for Substantial Completion; (b) Substantial Completion walk
through and produce the punch list; (c) confirm that the punch list items are
completed at a final completion walk through; and (d) issue both Certificate of
Substantial Completion and Final Acceptance.
8. Issue letter to the City recommending acceptance, based upon City Inspector
observations, and release of final payment.
9. Upon completion of the project, the contract drawings will be revised to reflect all
field changes. The completed “record drawings” will be delivered to the Owner.
Record Drawings to be supplied to the City in PDF and AutoCAD formats.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Ms. Lori Bender
City of Pearland
September 8, 2026
Page 6 of 8
H:\Engineering\Proposals\City of Pearland\City of Pearland - Assignment Letter - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - REV 2026-09-08.docx
D. Additional Services
1. Additional Design Phase Services (New Generator) with Written Authorization:
a. Provide additional design phase services to incorporate a new generator into
the proposed design.
b. Provide additional electrical design services to incorporate a new generator
into the proposed design.
2. Additional Construction Phase Services (New Generator) if Generator Design is
Authorized:
a. Provide additional construction phase services to incorporate a new
generator into the proposed construction.
b. Provide additional electrical design assistance in construction phase to
incorporate a new generator into the proposed construction.
3. Topographical Surveys: Provide field surveys of existing structures, lines, site
conditions, and other features required for the preparation of final construction.
4. Geotechnical Investigations: Provide field investigations of the geotechnical
conditions to determine design. Determine groundwater conditions and need for
dewatering during construction.
5. Landscape Architecture Services: Upon receipt of written authorization, LJA
Landscape Architecture will provide landscape architecture and irrigation design
services for the Alice Street Water Plant, including the preparation of permit and
construction-ready documentation in accordance with City of Pearland requirements.
Services include development of planting and irrigation plans, technical details, plant
schedules, specifications, and coordination with project consultants to deliver a
cohesive and constructible design. Project deliverables will include a 90% Planting
and Irrigation Plan submittal, a 100% Construction Document package, an Issue for
Bid (IFB) package, and an Issue for Construction (IFC) package. Documents will be
prepared under the supervision of a registered Professional Landscape Architect,
with coordination and permit support provided as necessary to facilitate agency
review and project implementation.
6. Project Representative: It is our understanding the City will provide all required
on-site project inspection services, and the services of an AMPP / NACE Int.
Certified Coatings Inspector, so a project representative is not included in the
scope of this project.
7. Conditions Assessment of Existing Tanks: It is our understanding the City will
provide all required conditions assessments, so assessments of the existing
tanks are not included in the scope of this project.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Ms. Lori Bender
City of Pearland
September 8, 2026
Page 7 of 8
H:\Engineering\Proposals\City of Pearland\City of Pearland - Assignment Letter - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - REV 2026-09-08.docx
BASIS OF COMPENSATION
For the accomplishment of the above tasks and additional services, we propose that our
compensation be based on the Scope of Services for each Phase and include a combination of
Time and Materials and Lump Sum Fees.
According to the City’s published FY2025-2030 CIP, the preliminary opinion of probable
construction costs for the Alice Elevated and Ground Storage Tank Rehabilitation project and
the Alice Water Treatment Plant New 5 MG Ground Storage Tank project are approximately
$1,301,000.00 and $6,350,000.00, respectively, for a combined total of $7,651,000. With the
additional mechanical and electrical scope (booster pumps, VFDs/controls, etc.) the pre-design
OPCC is approximately $8,851,000.00 without contingencies. If it is determined a new
generator is required to support the additional electrical load, the pre-design OPCC would be
approximately $9,601,000.00 without contingencies.
CURRENT AUTHORIZATION
Basic Services
Phase Description Contract Type FEE
WA2601-903A1 60% Design Phase Lump Sum $ 45,629.00
WA2601-903B1 90% Design Phase Lump Sum $ 23,002.00
WA2601-903C1 Final 100% Design Phase Lump Sum $ 10,426.00
WA2601-904A Bidding Phase Lump Sum $ 5,752.00
WA2601-905A Construction Phase Lump Sum $ 23,310.00
WA2609-903A2 60% Design Phase Lump Sum $ 302,449.00
WA2609-903B2 90% Design Phase Lump Sum $ 152,991.00
WA2609-903C2 Final 100% Design Phase Lump Sum $ 53,634.00
WA2609-904B Bidding Phase Lump Sum $ 25,601.00
WA2609-905B Construction Phase Lump Sum $ 91,882.00
Sub-Total Basic Services $ 734,676.00
Additional Services
Phase Description Contract Type FEE
WA2609-903D2 Add’l. Design Phase (New Gen) Lump Sum $ 72,870.00
WA2609-905B1 Add’l. Constr. Phase (New
Gen)
Lump Sum $ 8,688.00
WA2609-905B2 Add’l. Elec. Asst. Constr. (New
Gen)
Lump Sum $ 2,100.00
WA2609-917 Landscape Architecture T&M $ 14,770.00
WA2609-925 Topographic Surveys T&M (Actual Cost + 5%) $ 18,900.00
WA2609-926 Geotechnical Investigations T&M (Actual Cost + 5%) $ 41,925.00
Sub-Total Additional Services $ 159,253.00
TOTAL CURRENT AUTHORIZATION $ 893,929.00
If the above Scope of Services and Basis of Compensation are satisfactory to you, your
acceptance in the space provided below and a City issued Contract for Professional Services
will be sufficient authorization to immediately commence the stated work.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Ms. Lori Bender
City of Pearland
September 8, 2026
Page 8 of 8
H:\Engineering\Proposals\City of Pearland\City of Pearland - Assignment Letter - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - REV 2026-09-08.docx
On behalf of the project team, LJA appreciates this opportunity to provide Professional
Engineering Services on this important project. Please do not hesitate to contact me should you
have any questions or need additional information at 713.657.6013 or jflowers@lja.com.
Sincerely, Proposal Accepted By:
CITY OF PEARLAND
Jimmy C. Flowers, PE By:
Vice President
Name:
JCF/msc
Date:
Enclosure(s)
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
9711 S. Mason Rd.
Suite 125 PMB 326
Richmond, Texas 77407
(281) 529-5005
TBPE Firm No. 16575
June 22, 2026
Jimmy Flowers, P.E.
LJA Engineering, Inc.
3600 W. Sam Houston Pkwy S, Suite 600
Houston, Texas, 77042
Re: Professional Engineering Services Proposal for
City of Pearland Alice Street Water Plant Expansion
Brazoria County, Texas
BGD Project No. 138-0059; Rev.1
Dear Jimmy:
We appreciate the opportunity to present this proposal for electrical engineering services in
connection with City of Pearland Alice Street Water Plant Expansion.
Project Understanding
The City of Pearland is expanding the existing Alice Street Water Plant. The scope of this project includes
the addition of a 5MG ground storage tank, one (1) 200HP booster pump with Variable Frequency Drive
(VFD), and one (1) mixer for the ground storage tank along with the associated control modifications. In
addition, the existing three pumps and motors will be replaced. The three existing pumps include two
pumps with existing VFDs which will remain, but the third pump has an existing SSRV starter and will be
replaced with another VFD. All proposed VFDs will be “clean power” rated to reduce harmonics upstream
of the VFDs.
Based on the existing record drawing, we assume there is room in the existing electrical room for one (1)
of the proposed VFDs, but it does not appear there is room for two (2) VFDs. We will look at other rooms
or locate the VFD on the exterior of the building in an outdoor rated enclosure. In addition, we will evaluate
the existing 750kW Diesel generator size and provide an alternate design and construction services fee if
it needs to be replaced with larger generator for the additional motor load.
Based on our understanding of your project, the review and approval process, we prepared the following
scope of services and fee proposal for your consideration.
Scope of Services
A. Electrical Design Phase Services
1. Initial site visit to visually inspect existing conditions.
2. The electrical construction drawings shall include the following:
a. Electrical site layout depicting location of electrical equipment and conduit routing.
b. Electrical one-line diagram of the complete facility and load analysis specifying electrical
equipment sizes.
c. Conduit schedule specifying conductor and conduit sizes .
d. Electrical control schematics for the proposed equipment.
e. Electrical details.
3. Electrical Technical Specifications
a. Division 13 & 16 specifications for electrical work and equipment required.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Jimmy Flowers, P.E.
Page 2
June 22, 2026
4. Deliverables
a. 30% review set of drawings in electronic format (PDF). Limited to electrical site layout with
major items of equipment/ductbank routing and one-line diagram.
b. 60% review set for internal and agency reviews in electronic format (PDF).
c. 100% signed and sealed construction drawings in electronic format (PDF).
d. Electrical specifications in electronic format (PDF).
5. Items provided by Client
a. AutoCAD drawings.
i. Site layout
ii. Border
b. Load information including motor horsepower and/or equipment wattage of current and ultimate
phase.
c. Mechanical and process equipment specifications.
6. Attend one (1) design review meeting at Client’s office.
B. Bidding Phase Services
1. Attend pre-bid meeting.
2. Respond to bidder questions through Client via phone and email.
3. Prepare addenda and revised plans as needed to correct errors and omissions or provide
clarification.
C. Construction Phase Services
1. Attend pre-construction meeting.
2. Review electrical shop drawings and submittals.
3. Review and comment on any Requests for Information (RFI).
4. One interim and one (1) final inspection at substantial completion and provide a punch list of
observed electrical deficiencies. Additional site visits may be requested and shall be billed as an
hourly service.
5. Interpret the intent of the plans via telephone or email.
D. Additional Design Phase Services (Generator Replacement)
1. Generator sizing calculations.
2. Additional drawing modifications to site plan, one-line diagram, and conduits schedules and
additional details.
E. Additional Construction Phase Services (Generator Replacement)
1. Additional submittal reviews for generator, test reports, and O&Ms.
Proposed Fee
A. Electrical Design Phase Services (Lump Sum) = $30,000
B. Bid Phase Services (Lump Sum) = $1,000
C. Construction Phase Services (Lump Sum) = $8,000
D. Additional Design Phase Services (Lump Sum) = $20,000
E. Additional Construction Phase Services (Lump Sum) = $2,000
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Jimmy Flowers, P.E.
Page 3
June 22, 2026
Special Considerations
This proposal is based on the following special considerations:
1. This proposal shall be subject to the Master Subconsultant Services Agreement dated December
21, 2020, between LJA Engineering, Inc. and Baird Gilroy & Dixon, LLC.
2. Civil design items including buildings, concrete slabs, drainage, and landscaping are not included.
3. Reimbursable expenses including outside services not performed by Baird Gilroy & Dixon, LLC
personnel shall be provided and reimbursed at cost plus 10%. Although we do not anticipate any
Reimbursable Expenses, these services typically include reproduction and deliveries.
4. Additional review meetings, construction site visits or other services desired by CLIENT may be
provided by SUBCONSULTANT on an hourly basis or an agreed upon lump sum as an additional
service to this contract as requested.
5. Hourly Services, if any, shall be provided in accordance with the Schedule of Hourly Rates listed
below. This rate schedule may be revised upon written notification in January of each year.
SCHEDULE OF HOURLY RATES
Effective January 2026
Subject to Annual Revision in January 2027
Engineering Personnel Programming Personnel
Electrical Engineer’s Assistant I $65 Programmer’s Assistant I $65
Electrical Engineer’s Assistant II $85 Programmer’s Assistant II $85
Electrical Staff Engineer $140 Programmer I $150
Electrical Project Engineer $160 Programmer II $170
Electrical Sr. Project Engineer $175 Programmer III $190
Electrical Project Manager $220 Programmer IV $210
Officer – Principal $265
Designer/Drafting Personnel Office Personnel
CAD Operator I $85 Project Support Administrator $85
CAD Operator II $100 Accounting Manager $95
Designer I $115
Designer II $130
6. The proposed fees shall be considered in their entirety for the scope of services . Should you wish
to contract with us for only a portion of the work, we reserve the right to negotiate individual scope
items on their own merits.
7. Cost estimates prepared by the engineer represent their best judgment as a design professional
familiar with the construction industry. It is recognized, however, that the engineer has no control
over the cost of labor, materials, or equipment; over the contractor’s methods of determining bid
prices; or over competitive bidding or market conditions. Accordingly, the engineer cannot and does
not guarantee that bids will not vary from any cost estimate prepared by them.
8. This proposal shall be valid for sixty days from this date and may be extended upon approval by
this office.
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Jimmy Flowers, P.E.
Page 4
June 22, 2026
We appreciate the opportunity to submit this proposal and look forward to working with you . An executed
copy of this proposal will serve as our notice to proceed. Please return one copy to our office. Should you
have any questions, please call.
Sincerely,
Gregory S. Baird, P.E.
Baird Gilroy & Dixon, LLC
Principal
P:\Projects\138\0059\Contracts\Proposal – City of Pearland Alice WP Expansion Rev.1.docx
APPROVED BY:
_______________________________________
Signature
_______________________________________
Name and Title (Printed)
_______________________________________
Date
_______________________________________
LJA Engineering Inc. Project Number
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Proposal No. 1140744199
December 12, 2025
Mr. Jimmy Flowers, P.E.
Vice President
LJA Engineering, Inc.
2014 Airport Road, Suite 100
Conroe, Texas 77301
Re: Proposal for Geotechnical Investigation
Proposed 5 MG Ground Storage Tank
City of Pearland – Alice Water Treatment Plant
Pearland, Texas
Dear Mr. Flowers:
As per your request, Geotest Engineering, Inc., is pleased to submit this proposal
for the above referenced project. This project consists of the design and construction of a
new 5-million gallons ground storage tank at the City of Pearland, Alice Water Treatment
Plant in Pearland, Texas. The tank will be prestressed concrete tank and will be designed
as per ACI 372R-13. Based on the information provided to us the inside diameter of the
tank is about 156 feet with a water column height of 35 feet.
Purpose and Scope
The purposes of this study are to explore the subsurface conditions at the
proposed site and develop geotechnical recommendations pertinent to the design and
construction of the ground storage tank. The scope of the geotechnical services is based
on information provided to us by email dated December 9, 2025. The scope of work
consists of the following tasks:
• Drill and sample
▪ one (1) 120-foot deep boring at the proposed tank center location and
four (4) 60-foot deep borings equally spaced on the anticipated
perimeter of the tank foundation. The exploration sampling and
testing will be in accordance with ACI372R.
The approximate boring locations are shown on Plan of Borings
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Mr. Jimmy Flowers, P.E. Proposal No. 1140744194
Page 2 December 12, 2025
presented on Figure 1.
•Perform appropriate laboratory tests including consolidation on selected
representative soil samples to determine the physical and strength
properties and consolidation characteristics of the soils.
•Perform engineering analyses to develop the geotechnical
recommendations for the proposed ground storage tank per ACI372R-13,
including foundation recommendation, over excavation, settlement
analyses and site preparation and water level control and bedding and
backfill for any pipe connections.
•Prepare a geotechnical report including field and laboratory data, and
engineering recommendations as outlined above.
It is our understanding that your surveyors will tie-in our borings after
completion of the drilling.
Project Schedule
We should be able to start the fieldwork within one week after receiving your
written authorization or one week after staking the borings, whichever is latest. The
fieldwork will be completed in about one (1) week, baring bad weather. The laboratory
tests will be completed in about five (5) weeks. The geotechnical investigation report,
which will include field and laboratory data and geotechnical recommendations, will be
submitted in about ten (10) weeks after receiving the written authorization.
Cost
Based on the scope of services outlined above, the cost of the field investigation,
laboratory testing, engineering analyses, and a final report will be a lump sum of
$39,928.00. The cost breakdown given in Attachment No. 1 is for additional information
only. The invoices will be billed on Lump Sum basis based on percent completion. This
cost is based on the assumption that the site is accessible to a truck mounted drilling rig
and no site clearance will be required.
barring
1140744199
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Mr. Jimmy Flowers, P.E. Proposal No. 1140744194
Page 3 December 12, 2025
We appreciate the opportunity to propose on this project. We hope this proposal
meets your approval. Please sign on copy of this letter in the space below and return it to
us along with your purchase order. If you have any questions, please contact us.
Sincerely,
GEOTEST ENGINEERING, INC.
Naresh Kolli, P.E.
Sr. Project Manager
NK\ego
Copies Submitted: (1-PDF)
Attachment No. 1
PC38\Geotechnical\Proposals\40744199.DOC
Figure 1 – Plan of Borings
Attachment No. 1 – Cost Breakdown
ACCEPTED BY:
PRINTED NAME:
TITLE:
DATE:
1140744199
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Project: 5 MG Ground Storage Tank Proposal No. 1140714199
Texas City, Texas
Unit
Mob and Demob of Truck Mounted Drilling Rig, Crew 1 LS $800.00 $800.00
Drilling and Continuous Sampling from 0 to 20 feet 100 ft.$25.00 $2,500.00
Drilling and Intermittent Sampling, from 20 to 50 ft.150 ft.$24.00 $3,600.00
Drilling and Intermittent Sampling, over 50 feet 110 ft.$28.00 $3,080.00
Drilling and Intermittent Sampling, over 100 feet, surcharge 20 ft.$15.00 $300.00
Field Coordination and Utility Clearance for Boring Locations 53 hrs $90.00 $4,770.00
Vehicle Charge (marking borings)18 hrs $11.00 $198.00
Cement Bentonite Grout 360 ft.$9.00 $3,240.00
Subtotal $18,488.00
Laboratory Testing
Sieve Analysis through No. 200 sieve 8 ea.$58.00 $464.00
Moisture Content 66 ea.$11.00 $726.00
Percent Passing No. 200 sieve 28 ea.$52.00 $1,456.00
Specific Gravity 1 ea.$54.00 $54.00
Triaxial Compressive Strength, per Specimen or Stage:
36 ea.$65.00 $2,340.00
Consolidation including additional increments 1 ea.$650.00 $650.00
Subtotal $8,030.00
Engineering Analyses
Sr. Engineer 15.0 hr.$210.00 $3,150.00
Staff Engineer 60.0 hr.$126.00 $7,560.00
Support Personnel (Drafting, Word Processing)15.0 hr.$80.00 $1,200.00
$13,410.00
Total Cost $39,928.00
COST BREAKDOWN
ATTACHMENT NO. 1
PC38\Geotechnical\Proposals\40744199.xls\cost
Pearland, Texas
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Geotest Engineering, Inc.
Pr
o
p
o
s
a
l
N
o
.
11
4
0
7
4
41
99
FIGURE 1
PROPOSED PLAN OF BORINGS
Legend Geotest Engineering, Inc
Proposed 5-MG Ground
Storage Tank
Alice WTP
City of Pearland
Proposed Boring
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
Geotest Engineering, Inc.
Pr
o
p
o
s
a
l
N
o
.
11
4
0
7
4
41
99
FIGURE 1
PROPOSED PLAN OF BORINGS
Legend Geotest Engineering, Inc
Proposed 5-MG Ground
Storage Tank
Alice WTP
City of Pearland
Proposed Boring
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
PROJECT FEE ESTIMATE
City of Pearland
WA2601 - Alice Elevated and Ground Storage Tank Rehabilitation and WA2609 - Alice Water Treatment Plant New 5-Million-Gallon Ground Storage Tank
E042-TBD
9/2/2026 0:00
Project
Principal / Vice
President
Project
Manager
Graduate
Engineer
Senior
Engineer Designer CAD Drafter Project Rep Project Admin
Contract
Administrator Expenses
WA2601-903A1 60% DESIGN PHASE 4 78 51 0 31 63 0 10 12 $ 0 $ 45,629
Kick-Off Meeting with City 4 4 $ 1,724
Review of Existing Reports and Record Drawings 2 4 $ 1,192
Review and incorporate tank inspection recommendations 8 6 $ 3,118
Prepare detailed structural design 6 4 $ 2,256
Prepare detailed electrical design 3 2 $ 1,128
Prepare detailed mechanical design 12 8 $ 4,512
Prepare detailed construction plans 14 11 31 63 $ 18,475
Prepare detailed specifications 5 5 4 $ 2,715
Prepare contract documents 4 5 8 $ 2,569
Prepare OPCC 5 5 3 $ 2,386
Prepare Preliminary Construction Time Estimate/Schedule 3 2 2 $ 1,282
Management, Quality Control, and Critical Coordination 4 12 $ 4,272
$ 0
WA2601-903B1 90% DESIGN PHASE 2 42 26 0 13 23 0 10 9 $ 0 $ 23,002
60% Comment Response and Resolution 4 6 3 5 3 $ 3,391
Continue detailed structural design 3 2 $ 1,128
Continue detailed electrical design 2 2 $ 862
Continue detailed mechanical design 8 4 $ 2,788
Continue detailed construction plans 6 3 10 18 $ 5,955
Continue detailed specifications 4 3 3 $ 1,979
Update contract documents 3 4 6 $ 1,946
Update OPCC 3 4 2 $ 1,612
Update Preliminary Construction Time Estimate/Schedule 3 2 1 $ 1,205
Management, Quality Control, and Critical Coordination 2 6 $ 2,136
$ 0
WA2601-903C1 FINAL 100% DESIGN PHASE 1 18 12 0 5 14 0 3 4 $ 0 $ 10,426
90% Comment Response and Resolution 1 1 1 2 $ 844
Finalize structural design 1 1 $ 431
Finalize electrical design 1 1 $ 431
Finalize mechanical design 1 1 $ 431
Finalize construction plans 2 2 4 8 $ 2,514
Finalize specifications 1 2 2 $ 876
Finalize contract documents 2 2 2 $ 966
Submit for TCEQ review 2 4 1 $ 1,141
Prepare final OPCC 2 2 $ 862
Refine Preliminary Construction Time Estimate/Schedule 2 2 $ 862
Management, Quality Control, and Critical Coordination 1 3 $ 1,068
$ 0
WA2601-904A BIDDING PHASE 0 9 10 0 0 0 0 4 10 $ 0 $ 5,752
Bidding 6 10 4 10 $ 4,954
Attend City Council Meeting for Recommendation of Award 3 $ 798
$ 0
WA2601-905A CONSTRUCTION ENGINEERING PHASE 0 26 63 0 6 7 0 18 20 $ 0 $ 23,310
Construction Administration 23 60 13 20 $ 19,819
Record Drawings - Lump Sum 3 3 6 7 5 $ 3,491
$ 0
COST PER
PHASE
MANHOURS/EMPLOYEE INITIALS
DESCRIPTIONPHASE
LOE - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - WA2609 - REV 2026-09-02 10/19/2026
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
WA2609-903A2 60% DESIGN PHASE 54 281 329 303 259 279 0 14 22 $ 18,900 $ 302,449
Kick-Off Meeting with City 4 4 4 $ 2,804
Review of Existing Reports and Record Drawings 4 4 $ 1,724
Establish scope of survey and geotechnical investigations 4 4 $ 1,724
Coordinate geotechnical investigations 4 2 $ 1,394
Coordinate with DD4 with regards to Drainage / Detention Requirements 4 $ 1,064
Prepare draft detention / drainage calculations 4 4 20 $ 5,724
Review existing electrical and controls, coordination with CPE as needed 4 4 $ 1,724
Confirmation that existing generator is sized for proposed loads (Subconsultant)$ 3,150 $ 3,150
Coordination with Electrical Subconsultant 4 2 $ 1,394
Prepare preliminary site layouts 20 20 40 40 60 $ 30,480
Prepare detailed structural design 35 65 $ 18,775
Prepare detailed electrical design (Subconsultant)$ 15,750 $ 15,750
Review electrical design and incorporate into project set 8 3 6 $ 3,823
Prepare detailed civil and mechanical design 90 112 120 $ 66,420
Coordinate with DD4 with regards to Drainage / Detention Requirements 5 5 $ 2,155
Prepare detailed construction plans 40 48 52 215 215 $ 89,160
Prepare detailed specifications (Includes additional pump scope)25 20 $ 9,950
Prepare contract documents (Includes additional pump scope)10 20 22 $ 9,040
Prepare OPCC 10 20 $ 5,960
Prepare and submit 60% submittal 20 20 4 4 14 $ 10,818
Prepare Preliminary Construction Time Estimate/Schedule 5 2 $ 1,660
Management, Quality Control, and Critical Coordination 50 16 $ 17,756
$ 0
WA2609-903B2 90% DESIGN PHASE 29 94 115 155 179 179 0 16 22 $ 15,750 $ 152,991
60% Comment Response and Resolution 4 4 4 $ 2,804
Continue detailed structural design 10 25 $ 6,650
Continue detailed electrical design (Subconsultant)$ 15,750 $ 15,750
Continue detailed civil and mechanical design 30 38 70 $ 28,250
Continue detailed construction plans 16 21 60 175 175 $ 68,721
Continue detailed specifications 12 10 $ 4,842
Update contract documents 5 10 22 $ 6,060
Update OPCC 5 10 $ 2,980
Prepare and submit 60% submittal 10 10 4 4 16 $ 6,662
Update Preliminary Construction Time Estimate/Schedule 4 2 $ 1,394
Management, Quality Control, and Critical Coordination 25 8 $ 8,878
$ 0
WA2609-903C2 FINAL 100% DESIGN PHASE 9 51 66 23 19 24 0 19 15 $ 12,600 $ 53,634
90% Comment Response and Resolution 4 4 4 $ 2,804
Finalize structural design 11 15 $ 4,815
Finalize electrical design (Subconsultant)$ 12,600 $ 12,600
Finalize civil and mechanical design 5 5 8 $ 3,755
Finalize construction plans 8 10 15 15 $ 7,978
Finalize specifications 10 8 $ 3,980
Finalize contract documents 3 4 4 15 $ 3,866
Submit for TCEQ review 5 8 5 $ 3,315
Prepare final OPCC 4 6 $ 2,054
Prepare and submit 100% submittal 5 8 4 4 15 $ 4,925
Refine Preliminary Construction Time Estimate/Schedule 3 2 $ 1,128
Management, Quality Control, and Critical Coordination 5 4 $ 2,414
$ 0
WA2609-904B BIDDING PHASE 6 20 40 0 0 0 0 43 55 $ 1,050 $ 25,601
Bidding 6 17 40 43 55 $ 23,753
Electrical assistance during bidding phase (Subconsultant)$ 1,050 $ 1,050
Attend City Council Meeting for Recommendation of Award 3 $ 798
$ 0
WA2609-905B CONSTRUCTION ENGINEERING PHASE 21 60 206 25 8 8 0 86 100 $ 8,400 $ 91,882
Construction Administration 20 56 200 25 81 100 $ 78,533
Electrical assistance during construction phase (Subconsultant)$ 8,400 $ 8,400
Record Drawings - Lump Sum 1 4 6 8 8 5 $ 4,949
$ 0
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
ADDITIONAL SERVICES 7 58 130 54 25 55 0 0 0 $ 98,695 $ 159,253
WA2609-903D2 Additional design phase services (new generator)4 50 100 50 25 55 $ 21,000 $ 72,870
WA2609-905B1 Additional construction phase services (new generator)3 8 30 4 $ 8,688
WA2609-905B2 Additional electrical assistance in construction (new generator) (Subconsultant)$ 2,100 $ 2,100
WA2609-905B2 Landscape Architecture Services $ 14,770 $ 14,770
WA2609-925 Topographic Surveys (LJA Survey) - Time & Materials (Actual Cost + 5%)$ 18,900 $ 18,900
WA2609-926 Geotechnical Investigations - Time & Materials (Actual Cost + 5%)$ 41,925 $ 41,925
$ 0
TOTAL HOURS 133 737 1048 560 545 652 0 223 269 $ 893,929
RAW SALARY $100 $76 $47 $57 $42 $38 $42 $22 $40
MULTIPLIER 2.7 3.5 3.5 3.5 3.5 3.5 3.5 3.5 3.5
RATE $ 270 $ 266 $ 165 $ 200 $ 147 $ 133 $ 147 $ 77 $ 140
TOTAL ENGINEERING FEE $ 35,910 $ 196,042 $ 172,920 $ 112,000 $ 80,115 $ 86,716 $ 0 $ 17,171 $ 37,660 $ 155,395 $ 893,929
LOE - WA2601&WA2609 Alice EST & GST Rehab - New 5MG GST - WA2609 - REV 2026-09-02 10/19/2026
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754
ID Task
Mode
Task Name Duration Start Finish Predecessors
1 60% Design Phase 120 days Mon 11/2/26 Mon 3/1/27
2 Kickoff Meeting / Site Visit w/ City 0 days Mon 11/2/26 Mon 11/2/26
3 Review Existing Reports and Record Drawings and
Establish Scope of Survey & Geotechnical
2 days Mon 11/2/26 Tue 11/3/26 2
4 Topographic Surveys & Geotechnical 29 days Wed 11/4/26 Wed 12/2/26 3
5 Review Generator Capacity & Electrical Room &
Issue Memo w/ Recommendations
16 days Thu 12/3/26 Fri 12/18/26 4
6 Preliminary Site Layouts 15 days Thu 12/3/26 Thu 12/17/26 4
7 Prepare Detailed Structural, Electrical, Mechanical,
and Civil Design
49 days Fri 12/18/26 Thu 2/4/27 6
8 60% Opinion of Probable Cost 4 days Mon 2/1/27 Thu 2/4/27
9 Prepare and Submit 60% Design Package 15 days Fri 2/5/27 Fri 2/19/27 7
10 City Review Period 10 days Sat 2/20/27 Mon 3/1/27 9
11 90% Design Phase 91 days Mon 3/1/27 Mon 5/31/27
12 Attend 60% Design Review Meeting w/ City 0 days Mon 3/1/27 Mon 3/1/27 10
13 Continue Detailed Structural, Electrical,
Mechanical, and Civil Design
31 days Tue 3/2/27 Thu 4/1/27 12
14 Continue Detailed Construction Plans and
Specifications
35 days Fri 4/2/27 Thu 5/6/27 13
15 90% Opinion of Probable Cost 4 days Mon 5/3/27 Thu 5/6/27
16 Prepare and Submit 90% Design Package 15 days Fri 5/7/27 Fri 5/21/27 14
17 City Review Period 10 days Sat 5/22/27 Mon 5/31/27 16
18 Final 100% Design Phase 70 days Mon 5/31/27 Mon 8/9/27
19 Attend 90% Design Review Meeting w/ City 0 days Mon 5/31/27 Mon 5/31/27 17
20 Finalize Structural, Electrical, Mechanical, and Civil
Design
14 days Tue 6/1/27 Mon 6/14/27 19
21 Finalize Detailed Construction Plans and
Specifications
17 days Tue 6/15/27 Thu 7/1/27 20
22 Finalize Opinion of Probable Cost 4 days Mon 6/28/27 Thu 7/1/27
23 TCEQ Review 39 days Fri 7/2/27 Mon 8/9/27 21
24 Prepare and Submit 100% Design Package 12 days Fri 7/2/27 Tue 7/13/27 21
25 City Review Period 8 days Wed 7/14/27 Wed 7/21/27 24
26 Address any Final Comments and Submit Bid
Package
19 days Thu 7/22/27 Mon 8/9/27 25
27 Submit Bid Package 0 days Mon 8/9/27 Mon 8/9/27 26
28 Bidding Phase and Contract Executions 54 days Mon 8/16/27 Fri 10/8/27
29 Construction Phase (480 CDs)480 days Mon 10/18/27 Thu 2/8/29
3/1
11/2
3/1
5/31
8/9
1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 3 10 17 24 31
November December January February March April May June July August September October November
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
City of Pearland
WA2601 - Alice Elevated and Ground Storage Tank Rehabilitation and
WA2609 - Alice Water Treatment Plant New 5-Million-Gallon Ground Storage Tank
LJA, Inc.
Project: WA2609
Date: Fri 9/4/26
Docusign Envelope ID: C28D5CF5-C29B-8338-815B-7578F282F754