HomeMy WebLinkAboutR2026-055 20260316RESOLUTION NO. R2026-55
A Resolution of the City Council of the City of Pearland, Texas, approving a
Change Order with Conrad Construction Co., LTD., in the amount of
$117,572.37 (total contract amount of $5,543,110.87), associated with the
Industrial Drive Reconstruction Project.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That certain change order associated with the Industrial Drive Reconstruction
Project, a copy of which is attached hereto as Exhibit “A” and made a part hereof for all purposes, is
hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute and
the City Secretary to attest a change order associated with the Industrial Drive Reconstruction
Project.
PASSED, APPROVED and ADOPTED this the 16th day of March, A.D., 2026.
_________________________________
J.KEVIN COLE
MAYOR
ATTEST:
________________________________
FRANCES AGUILAR, TRMC, MMC
CITY SECRETARY
APPROVED AS TO FORM:
________________________________
LAWRENCE G. PROVINS
CITY ATTORNEY
Docusign Envelope ID: 0B27859C-80D5-4438-95BE-FB1CB6D9F24A
Bid Item
By: By:
By: By:
*Contractor agrees to perform change(s) included in the Change Order for the price and time indicated. The prices for changes included all costs associated with this
Change Order.
No work is to be done until this change order is executed. No payment to the Contract (or Consultant) shall be made for work included in the change order until the
Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are
inconsistent, this Change Order governs. Upon execution by all parties, the following changes identifies for the contract value and/or contract time shown, are made part of
the contract.
Consultant Construction Manager
ACCEPTED*: APPROVED:
Date Date
276 Days
Date Date
Contractor Owner
4.4 (32,340.00)$ Days
Total Change Orders:117,572.37$
Back-up documentation attached.
Cost & Time Change Summary Cost Time
Original Contract:5,425,538.50$ 270 Days
Previous Change Order(s):-0 Days
Contract prior to this Change Order:5,425,538.50$ 270 Days
4.6 94,760.00$ Days
PP#3 2,240.00$ DaysRFI#2&316LF add of 18” RCP
Consultant:Cobb Fendley & Associates P.O. No.: 2026-661
Explanation:
This change order encompasses the following: RFI’s 1, 2, 3, 5, 7, 8 & 10.
Description of Work Cost Time
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive
Pearland, TX 77581
CHANGE ORDER
Date of Issuance:03/16/2026 Change Order No.: 1
Contractor:Conrad Construction Co. LTD CoP Project No.: EDC177
Net increase (decrease) from this Change Order:117,572.37$ 6 Days
Revised Contract:5,543,110.87$
Finance Approval: Date
RECOMMENDED: RECOMMENDED:
5.2 7,820.00$ Days
1 EA increase of 8” water line wet connection
68LF increase of 8” waterline
1 EA increase of 8” gate valve
1 EA reduction of 12” water line wet connect
5.1 (990.00)$ Days
Days
5.8 3,000.00$ Days
5.4 (38,000.00)$ Days
5.5 3,700.00$ Days
Days
2.8 (5,038.00)$ Days
PP#1 13,490.05$ Days
2.2 59,860.00$ Days
1 EA add of 12” water line tapping sleeve and valve
164 TONS increase of hydrated lime
Days
4.17 (8,000.00)$ Days
4.22 3,750.00$ Days
Days
Industrial Drive Reconstruction
184LF increase of 6’x2’ RCB RFI#1-3
-Days
-Days
9.2 (5,537.00)$ Days
1 Days
PP#2 18,796.36$ 5
-
PP#4 5,855.96$
2.6 (2,295.00)$
5.7 (3,500.00)$
1 add Cast In Place Box and relocation of an AT&T utility
974 SY deduction of 1.5” asphalt overlay for SH35
2 EA increase of access manhole tops to the 6x2 RCB RFI#8
RFI#10
RFI#3
RFI#5
RFI#5
RFI#5
255 LF reduction of sidewalk
458 SF reduction of driveway paving
1 EA reduction of sidewalk bridge
1 EA increase of armor curb slot
RFI#7
RFI#7
RFI#7
132LF deduction of triple arch pipe
9LF reduction of 12” waterline
8 EA reduction of 12” gate valves
RFI#5
RFI#5
RFI#5
RFI#5
RFI#6
RFI#7
2/27/2026
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
3/18/2026 | 9:10 AM PDT
3/20/2026 | 9:25 AM CDT
3/20/2026 | 4:40 PM CDT
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive
Pearland, Texas 77581
www.pearlandtx.gov/projects
CHANGE ORDER JUSTIFICATION
Industrial Drive Reconstruction
Paving, Drainage, & Water Line Improvements, West of SH35
Project No. EDC 177
This change order encompasses the following: RFI’s 1, 2, 3, 5, 6, 7, 8 & 10.
• RFI #1: During the production of the 6’x2’ box culverts the manufacturer
calculated a total of 3,696LF of box needed per the approved plans, however, Bid
Item 4.6 listed a quantity of 3,532LF. Engineer of Record confirmed the total
quantity needed to increase by 164LF, resulting in an increase of $84,460.
o Item 4.6: +164 LF 6x2 box x $515 = $84,460
• RFI #2: During the production of the box sections, the manufacturer noted that
the T-structure that ties into the side of the box culverts would not be possible to
fabricate due to the structural design of the proposed structure and effectively
leaving an open side in the box. They recommended using a junction box rather
than a T-structure. Engineer of Record acknowledged the structural integrity
concerns and updated the sheet 29 to remove the T-structure and replace with
18” RCP to tie into the box culvert. (PP#3)
o Item 4.6: -12 LF 6x2 box x $515 = -$6,180
o New Item: +8 LF 18” RCP x $140 = $1,120
• RFI #3: Similar issue to RFI #2, Engineer of Record acknowledged the structural
integrity concerns and updated plan sheet 28 to remove the triple arch pipe and
replace with 6x2 boxes. (PP#3)
o Item 4.4: -132 LF arch pipe x $245 = -$32,340
o Item 4.6: +32 LF 6x2 box x $515 = $16,480
o New Item: +8 LF 18” RCP x $140 = $1,120
• RFI #5: Waterline, valves and connection quantities updated per field conditions.
Originally a wet connection was planned for tying into the existing waterline,
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
however, it was determined both ends of Industrial Drive, east and west of SH35,
would be impacted from isolating the waterline to make the connection, which
could take an extended period of time. To avoid the impact to water users, a
tapping sleeve and value (TS&V) is proposed, which can be installed on an
active line, instead of the wet connection. (PP#1)
o Item 5.1: -9LF 12” waterline x $110 = -$990
o Item 5.2: +68LF 8” waterline x $115 = $7,820
o Item 5.4: -8 EA 12” gate valves x $4,750 = -$38,000
o Item 5.5: +1 EA 8” gate valve x $3,700 = $3,700
o Item 5.7: -1 EA 12” water line wet connect x $3,500 = -$3,500
o Item 5.8: +1 EA 8” water line wet connection x $3,000 = $3,000
o New Item: +1 EA 12” water line TS&V = $13,490.05
• RFI #6: The Lime Determination report provided by the construction materials
testing lab called for over double the amount of hydrated lime treatment for the
soils as was called for in the original geotechnical study performed at the
beginning of design. Upon further investigation it was determined the original
lime recommendation (6%) was based on the surficial soils below the existing
pavement, however, the samples collected during the construction were 2 feet
below existing grade and indicated higher PI values, which would require a
higher lime content. The initial assumption led to an insufficient amount of lime
planned for the project. Engineer of record acknowledged the discrepancy and
has estimated approximately 164 tons of additional lime will be needed on the
project, resulting in an increase of $59,860. Only the actual amount of lime used
will be charged against the project.
o Item 2.2: +164 TONS lime x $365 = $59,860.
• RFI #7: Adjustments were made to the sidewalk terminating at the cul-de-sac,
reducing associated quantities.
o Item 2.6: -255 LF sidewalk x $9 = -$2,295
o Item 2.8: -458 SF driveway paving x $11 = -$5,038
o Item 4.17: -1 EA sidewalk bridge x $8,000 = -$8,000
o Item 4.22: +1 EA armor curb slot x $3,750 = $3,750
• RFI #8: Approved plans did not show manhole access locations at two 6x2 box
bends as required per City specifications, resulting in an addition of two manhole
access tops to the project. (PP#4)
o New Item: 2 EA manhole access tops = $5,855.96
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
• RFI #10: Two 24” parallel storm pipes were uncovered along the east side of
SH35 where the project’s new storm pipe is proposed to cross SH35 and outfall
into Industrial’s roadside ditch. An ATT ground box was also uncovered and
found to be in conflict. Engineer of Record acknowledged the conflicts and the
need for a cast-in-place storm box to be installed to connect the pipe crossings,
and need to relocate the ATT ground box, resulting in an increase of $18,796.36.
(PP#2)
o New Item: 1 LS cast in place box = $18,796.36
• Asphalt Overlay: The project includes asphalt replacement for the crossing of the
new storm line across SH 35, both in part and in full depending on the timing of
TxDOT’s plans to overlay the asphalt on SH35. TxDOT would require the entire
intersection to be overlayed if the City’s open cut occurred after TxDOT’s overlay.
Since the contractor has completed the crossing prior to TxDOT’s overlay, the
line item for the full overlay is no longer needed, resulting in a deduction of
$5,537.
o Item 9.2: -974 SY 1.5” asphalt overlay for SH35 = -$5,537
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10
Docusign Envelope ID: B5747A86-5B14-491B-9D96-B7B91296EB10