R2002-0174 11-11-02 RESOLUTION NO. R2002-174
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, AUTHORIZING THE CITY MANAGER OR HIS DESIGNEE TO
EXECUTE A CHANGE ORDER ASSOCIATED WITH THE SWEC
DETENTION BASIN AND CONTROL STRUCTURE.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That certain change order associated with the SWEC Detention Basin
and Control Structure, a copy of which is attached hereto as Exhibit '%" and made a part
hereof for all purposes, is hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute
and the City Secretary to attest the change order associated with the SWEC Detention
Basin and Control Structure.
PASSED, APPROVED and ADOPTED thisthe llth dayof November .,
A.D., 2002.
ATTEST:
Y, NG ~/-/ ,/
APPROVED AS TO FORM:
DARRIN M. COKER
CITY ATTORNEY
TOM REID
MAYOR
Exhibit "A"
R2002-174
SWEC Detention Basin and Control Structure, B2001-063
CHANGE ORDER NO. 3
October 30, 2002
1. Fumish and operate 6" pump with hoses for 15 days at $200.00/day (Pump-down from August
16, 2002 storm). All work down time caused bY basin flooding, pumping time, and muddy work
areas will be credited as allowed rain days.
Amount of Item 1. (ADD)
Contract Time Change for Item 1. (NONE - Provided by allowed rain days)
$3,000.00
N/A
2. Furnish all material, equipment and labor to construct the SWEC 2na Outlet Outfall Structure
in accordance with the attached plans and technical specifications.
Amount of Item 2. (ADD)
Contract Time Change for Item 2. (ADD)
$13,804.00
28 Days
3. Furnish and install additional 125 CY along hard edge at $43.50/CY.
Amount of Item 3. (ADD)
Contract Time Change for Item 3. (NONE - Concurrent with Item 2 & 4)
$5,437.50
N/A
4. Install Additional 62 LF of handrail on top of box culvert beam and upper end of sidewalls of
end treatment at lake (south) end of intake structure at $150/LF.
Amount of Item 4.
Contract Time Change for Item 4. (ADD)
62 L.F. ~ $150 $ 9,300
21 Days
TOTAL AMOUNT OF CHANGE ORDER No. 3
Increase Contract $31,541.50
END OF SHEET ONE of Change Order No. 3, B2001-063
b1063co3(CO#3Cont.) Sheet 2 of 2
Contract Time is hereby increased 49 Calendar days from 246 Calendar Days (reference Change
Order No. 2) to 317 Calendar days by this Change Order No. 3. Contract Price is increased from
$2,054,857.71 to $2,086,399.21 by this Change Order No. 3.
This Change Order No.3 to Contract B2001-063 is effective upon date of signature by the City
Manager.
OWNER
City of Peadand
Bill Eisen Date
CONTRACTOR
Bean Construction Company
W. B. Bean
Date
END CHANGE ORDER NO. 3, B2001-063
Exhibit "A"
R2002-174
SWEC Detention Basin and Control Structure, B2001-063
CHANGE ORDER NO. 3
October 30, 2002
1 Furnish and operate 6 pump with hoses for 15 days at $200.00/day (Pump -down from August
16, 2002 storm). All work down time caused by basin flooding, pumping time, and muddy work
areas will be credited as allowed rain days.
Amount of Item 1. (ADD) $3,000.00
Contract Time Change for Item 1. (NONE - Provided by allowed rain days) N/A
2. Furnish all material, equipment and labor to construct the SWEC 2nd Outlet Outfall Structure
in accordance with the attached plans and technical specifications.
Amount of Item 2. (ADD)
Contract Time Change for Item 2. (ADD)
3. Furnish and install additional 125 CY along hard edge at $43.50 /CY.
Amount of Item 3. (ADD) $5,437.50
Contract Time Change for Item 3. (NONE - Concurrent with Item 2 & 4) N/A
4. Install Additional 62 LF of handrail on top of box culvert beam and upper end of sidewalls of
end treatment at lake (south) end of intake structure at $150/LF.
Amount of Item 4. 62 LF @ $150 $ 9,300
Contract Time Change for Item 4. (ADD) 21 Days
$13, 804.00
28 Days
TOTAL AMOUNT OF CHANGE ORDER No. 3 Increase Contract $31,541.50
END OF SHEET ONE of Change Order No. 3, B2001-063
b 1063 co3 (CO#3 Cont.)
Sheet 2 of 2
Contract Time is hereby increased 49 Calendar days from 246 Calendar Days (reference Change
Order No. 2) to 317 Calendar days by this Change Order No. 3. Contract Price is increased from
$2,054,857.71 to $2,086,399.21 by this Change Order No. 3.
This Change Order No.3 to Contract B2001-063 is effective upon date of signature by the City
Manager.
OWNER
City of Pearland
CONTRACTOR
Bean Construction Company
W. B. Bean
END CHANGE ORDER NO. 3, B2001-063
Date