Loading...
HomeMy WebLinkAboutR2025-016 20250113RESOLUTION NO. R2025-16 A Resolution of the City Council of the City of Pearland, Texas, amending a design contract with Lockwood, Andrews & Newnam, Inc., associated with the Mykawa Road Widening Project (BW8 to FM518), in the additional amount of $239,786.60 (total contract of $3,727,656.13). BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS: Section 1. That certain amended contract for design services associated with the Mykawa Road Widening Project, a copy of which is attached hereto as Exhibit “A” and made a part hereof for all purposes, is hereby authorized and approved. Section 2. That the City Manager or his designee is hereby authorized to execute and the City Secretary to attest an amended contract for design services associated with the Mykawa Road Widening Project. PASSED, APPROVED and ADOPTED this the 13th day of January, A.D., 2025. _________________________________ J.KEVIN COLE MAYOR ATTEST: ________________________________ FRANCES AGUILAR, TRMC, MMC CITY SECRETARY APPROVED AS TO FORM: ________________________________ DARRIN M. COKER CITY ATTORNEY Docusign Envelope ID: 5DE91000-0F0D-4540-9456-9A80D7DC4FE0 Explanation: This amendment encompasses the following: 1 Days 2 Days 3 Days 4 Days 5 Days Days Days Days Days 0 Days Finance Approval: Date: By: Date: By: Date: Consultant Owner Lockwood, Andrews & Newnam, Inc. Drainage Design (FC 161) Signing, Pavement Markings & Signalization (Permanent) (FC 162) 95,250.00$ 47,030.00$ Miscellaneous Design (FC 163) - Sanitary sewer relocation 40,805.00$ Design Survey (FC 150) 45,960.00$ Cost & Time Change Summary For Mykawa Road Widening from Beltway 8 to Farm to Market 518 No work is to be done until this change order is executed. No payment to the Contractor (or Consultant) shall be made for work included in the change order until the Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, this Change Order governs. Upon execution by all parties, the following changes identified for the Contract Value and/or Contract Time shown, are made part of the Contract. *Contractor agrees to perform change(s) included in this Change Order for the price and time indicated. The prices for changes included all costs associated with this Change Order. 4 TR0601 2018-00001241 Date of Issuance: Consultant: Professional Services Contract Amendment P.O. No.: Description of Work 12/13/2024 Mykawa Road/McHard Road;b)perform drainage analysis using ATLAS-14 criterion per BDD4's requirement; c) perform survey of additional parcels for the proposed stormwater detention and mitigation ponds adjacent to Clear Creek; d) delineate and survey possible wetland around the proposed stormwater detention & mitigation ponds adjacent to Clear Creek; and e) lowering the existing sanitary sewer force main at Scott Lane/Mykawa Road sanitary sewer lift station in conflict with proposed stormwater detention pond at northeast corner of Mykawa Road/McHard Road intersection. a) Update design plan to reconstruct the intersection of Environmental Studies (FC 120) 10,741.60$ TimeCost Amendment No.: CoP Project No.: Original Contract: Net increase (decrease) from this amendment Revised Contract: Please attach back-up documentation 2,987,697.11$ Cost Time Contract prior to this amendment: Previous Amendment(s): 500,172.42$ ACCEPTED*: APPROVED: 239,786.60$ 3,727,656.13$ 3,487,869.53$ Design 1 of 1 D4. Revised 01/15 12/17/2024 Docusign Envelope ID: 7FD5A234-8CFE-46ED-94F7-70EAC76B2FB1 1/14/2025 | 9:06 AM CST 1/14/2025 | 11:48 AM CST