R2006-166 10-09-06
RESOLUTION NO. R2006-166
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, APPROVING CHANGE ORDER NO.1 ASSOCIATED WITH THE
BAILEY ROAD WATER LINE PROJECT.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That Change Order No.1 associated with the Bailey Road Water Line
Project, a copy of which is attached hereto as Exhibit "A" and made a part hereof for all
purposes, is hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute
and the City Secretary to attest Change Order No. 1 associated with the Bailey Road
Water Line Project.
PASSED, APPROVED and ADOPTED this the 9th day of October, A.D., 2006.
,~~/ J-0
TOM REID
MAYOR
ATTEST:
APPROVED AS TO FORM:
(L.: k. ~
DARRIN M. COKER
CITY ATTORNEY
SNOWDEN ENGINEERING, INC.
/'\' t:XmDlt "An
rf}Lb Resolution 2006-166 10/9/06
od' /r PEARLA~N~D
.\-,.,.. _(U~ "-. QU
D'" 0,.v '.~,j C)'o \ck>
~ ~. V'~. 0-'0^
CHANGE OUDER ,P
for Veterans Drive Bailey Road Water Line Project
n' ,,/6
\( 0 \ r\ f'
LP'
{)
SEP.1 4 2006
City of Penrlund
Projects Dept.
Date of Issuance:
September 14, 2006
Change Order No:
1
Engineer: Snowden Engineering, Inc.
COP Project No.
W 42052
Explanation
This change order encompasses the following:
In accordance with the contractor's letter which is attached, the City of Pearl and has
requested a change from Ductile Iron Pipe Class 51 to PVC C-905 pipe because of long term
maintenance considerations.
Please attach back-up documentation
Contract Amount:
Original Contract Price
Previous Change Order(s):
Contract price prior to this change order:
Net increase (decrease) from this change order:
$
$
$
$
667.478.60
0.00
667.478.60
35.470.50
Contract price with all change orders to date
(including this change order):
$
702.949.10
Contract Time:
Authorized contract time change:
N/A
By:
A~PTED:
~ff4~
E ineer
By:
APPROVED:
Uf
~wlii Bill Eisen, City
--'
Manager
Date:
September 14. 2006
Date: Oc tober 9. 2006
REDDICO
CONSTRUCTION
COMPANY
September 7, 2006
Mr. Cecil Bowery, Project Manager
City of Pearland
3519 Liberty Drive
Pearland, Texas 77581
Re: Bailey Road / Veterans Drive Water Line
Project No. W 42052
Change Order NO.1 Request
Dear Mr. Bowery,
The City has requested that the 30-inch water pipe material
be changed from Ductile Iron Pipe Class 51 to PVC C-905
Pipe. The net increase in the cost of the pipe for the 30-inch
water line is as follows:
Increase in 30-inch PVC C-905 Pipe
Decrease in Labor Cost for PVC Pipe
Net Increase in Pipe Cost
$ 14.25/ If
$ 1.50 / If
$ 12.75 / If
The total footage of 30-inch water line is 2,782 If. The
amount requested for Change Order NO.1 is $ 35,470.50.
Very truly yours,
Stephen C. Redd
President
"....
",
,"'t..
c/ job file