R2023-051 2023-06-12RESOLUTION NO. R2023-51
A Resolution of the City Council of the City of Pearland, Texas, amending a
design contract with Lockwood, Andrews & Newnam, Inc., associated with the
Mykawa Road Project (BW8 to F.M. 518), in the additional amount of
$488,390.11 (total contract of $3,487,869.53).
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That certain amended contract for design services associated with the
Mykawa Road Project, a copy of which is attached hereto as Exhibit “A” and made a part hereof for
all purposes, is hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute and
the City Secretary to attest an amended contract for design services associated with the Mykawa
Road Project.
PASSED, APPROVED and ADOPTED this the 12th day of June, A.D., 2023.
_________________________________
J.KEVIN COLE
MAYOR
ATTEST:
________________________________
FRANCES AGUILAR, TRMC, MMC
CITY SECRETARY
APPROVED AS TO FORM:
________________________________
DARRIN M. COKER
CITY ATTORNEY
DocuSign Envelope ID: BBE0B535-ADAB-44EE-88F4-91B0A63EA115
Lockwood, Andrews & Newnam, Inc.
Explanation:
This amendment encompasses the following:
1 Days
2 Days
3 Days
4 Days
5 Days
6 Days
Days
Days
Days
Days
0 Days
Finance Approval:Date:
By: Date: By: Date:
Consultant Owner
Drainage Design (FC 161)
Miscellaneous Design (FC 163) - Retaining Wall Design
84,715.20$
50,099.94$
Bridge Design (FC 170)79,055.76$
Project Coordination (FC 164)73,460.89$
Roadway Design (FC 160)42,973.32$
Cost & Time Change Summary
For Mykawa Road Widening from Beltway 8 to Farm to Market 518
No work is to be done until this change order is executed. No payment to the Contractor (or Consultant) shall be made for work included in the change order until
the Contractor's pay estimate is updated.
Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, this Change Order governs.
Upon execution by all parties, the following changes identified for the Contract Value and/or Contract Time shown, are made part of the Contract.
*Contractor agrees to perform change(s) included in this Change Order for the price and time indicated. The prices for changes included all costs associated with
this Change Order.
3
TR0601
2018-00001241
Date of Issuance:
Consultant:
Professional Services Contract Amendment
P.O. No.:
Description of Work
4/6/2023
Slough and Clear Creek; storm sewer main crossing existing 16 - inch pipes owned by Enterprise Crude
Pipeline, LLC near Shank Road and Clear Creek and 24 & 30 - inch pipes owned by Kinder Morgan Crude &
Condensate Pipeline, LLC near Clear Creek; and retaing wall on the west side of Mykawa Road at Hickory
Slough and between McHard Road to Scott Lane and Lila Street to Isla Street.
Update design plan to install pedestrian bridge at Hickory
Design Survey (FC 150)158,085.00$
TimeCost
Amendment No.:
CoP Project No.:
Original Contract:
Net increase (decrease) from this amendment
Revised Contract:
Please attach back-up documentation
2,987,697.11$
Cost Time
Contract prior to this amendment:
Previous Amendment(s):11,782.31$
ACCEPTED*:APPROVED:
488,390.11$
3,487,869.53$
2,999,479.42$
Design 1 of 1 D4. Revised 01/15
4/7/2023
Exhibit ADocuSign Envelope ID: CD70F760-5203-408E-AE8F-445513A7319F
6/13/2023 | 9:44 AM CDT
6/13/2023 | 10:25 AM CDT