R2022-281 2022-12-12RESOLUTION NO. R2022-281
A Resolution of the City Council of the City of Pearland, Texas, amending a
Design Build contract with CDM-Smith, in the additional amount of
$2,777,925.81 (Phase 3b, Wastewater) to the Guaranteed Maximum Price
(GMP) of $7,843,525.93 (inclusive of Phase 1, 2 and 3a), for design,
programming and construction phase services associated with the
Supervisory Control and Data Acquisition (SCADA) Project.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That the City Council hereby amends a Design Build contract with CDM-
Smith, in the additional amount of $2,777,925.81 (Phase 3b, Wastewater) to the Guaranteed
Maximum Price (GMP) of $7,843,525.93 (inclusive of Phase 1, 2 and 3a), for design, programming
and construction phase services associated with the SCADA Project.
Section 2. The City Manager or his designee is hereby authorized to execute an
amended Design Build contract for the SCADA Project
PASSED, APPROVED and ADOPTED this the 12th day of December, A.D., 2022.
_____________________________
J.KEVIN COLE
MAYOR
ATTEST:
_____________________________
FRANCES AGUILAR, TRMC, MMC
CITY SECRETARY
APPROVED AS TO FORM:
________________________________
DARRIN M. COKER
CITY ATTORNEY
DocuSign Envelope ID: 99411CF0-CD66-4E92-9EAB-D0E3524061A3
DocuSign Envelope ID:C403DFCB-6B4A-42BD-8486-7A9B75BA3227
CITY OF PEA.RLAND
111)01#
PROJECTS I,EPAR IVIENT
44.01,
2016 Old Alvin
old 1, "1,14111111 i"""'
1,11 1
Penland,Texas 77581
pearlandtx.gov/projects
Pr It fessit nal Services C,IIntr 4 ct Amendill ent
SCA1111A-WP/WW/LS
Date of Issuance: 12/12/2022 Amendment No.: 2
CoP Project No.: SCADA
Consultant: CIO,M Smith P.O.No.: 2020-00001681
Exp141,nation:
This amendment encompasess the following work associated with Phase 3B -Wastewater
Description of Work Cost Time
1 Add Item No. 6 Phase 3B 2,777,925.81 467 Days
2 Days
3 Days
4 Days
5 Days
Please attach back-up documentation
Cost& Time Change Summari Cost Ti ii e
Original Contract: 319,750,00 107 Days
Previous Amendment(s): 4,745,850.12 424 Days
Contract prior to this amendment: 5,065,600.12 531 Days
Net increase(decrease) from this amendment 2,777,925.81 467 Days
Revised Contract: 7,843,525.93 998 Days
DocuSigned by:
Finance Approval: Date: 12/13/2022 I 8:44 AM CST
012013C2ILC6126,
ACCEPT:D*: APPROVED:
DocuSigned by:
By: Date: 30 By 12/14/2022 I 5:50 AM PS1
t5...3trl&7415e7'.46,023
Con taint Owner
*Contractor agrees to perform change(s)included in this Change Order for the price and time indicated, The prices for changes included all costs associated with
this Change Order.
No work is to be done until this change order is executed No payment to the Contractor(or Consultant)shall be made for work included in the change order until the
Contractor's pay estimate is updated.
Revise the project plans and specifications as referenced and insofar as the onginal project drawings and specifications are inconsistent,this Change Order governs.
Upon execution by all parties,the following changes identified for the Contract Value and/or Contract Time shown,are made part of the Contract.
Desi. 1 of I 11)4,Revised 01/15