R2022-207 2022-09-26RESOLUTION NO. R2022-207 A Resolution of the City Council of the City of Pearland, Texas, amending a Construction Manager at Risk contract with Durotech to include the Guaranteed Maximum Price (GMP) of $4,780,850.00 (inclusive of General Conditions and Pre-Construction Services) for Construction Phase Services associated with the Public Safety Training & Education Building and $1,263,087.00 (inclusive of General Conditions and Pre-Construction Services) for Construction Phase Services associated with Public Safety Building Renovations. BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS: Section 1. That the City Council hereby amends a Construction Manager at Risk contract with Durotech to include the Guaranteed Maximum Price (GMP) of $4,780,850.00 (inclusive of General Conditions and Pre-Construction Services) for Construction Phase Services associated with the Public Safety Training & Education Building and $1,263,087.00 (inclusive of General Conditions and Pre-Construction Services) for Construction Phase Services associated with Public Safety Building Renovations. Section 2. The City Manager or his designee is hereby authorized to execute an amended Construction Manager at Risk contract for the Public Safety Training and Education Building; and Public Safety Building Renovation Project. PASSED, APPROVED and ADOPTED this the 26th day of September, A.D., 2022. _____________________________ J.KEVIN COLE MAYOR ATTEST: _____________________________ FRANCES AGUILAR, TRMC, MMC CITY SECRETARY APPROVED AS TO FORM: ________________________________ DARRIN M. COKER CITY ATTORNEY DocuSign Envelope ID: A833DC9B-EADD-4AE8-A74B-B0156E41FC5A Jameson Appel Digitally signed by Jameson Appel DN: C=US, E=jappel@pearlandtx.gov, O=City of Pearland, OU=Projects, CN=Jameson Appel Date: 2022.10.03 17:13:07-05'00' DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A 10/4/2022 | 9:28 AM CDT ^•z-^By,Date:ContractorOwner*Contractor agrees to perform cliange(s) included in this Change Order for the price and time indicated. The prices for changes included all costs associated with tliis ChangeOrder.No work is to be done until this change order is executed. No payment to the Contractor (or Consultant) sliall be made for work included in the change order until the Contractor'spay estimate is updated.Revise tlie project plans and specifications as referenced and insofar as tlie original project drawings and specificattons are inconsistent, tliis Cliange Order govems. Uponexecution by alt parties, tlie following ciianges identified for tlie contract value and/or contract time shown, are made part of (lie contract.DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A10/4/2022 | 9:38 AM CDT 1 11931 Wickchester Lane ● Suite 205 ● Houston, Texas 77043-4501 Phone: 281.558.6892 ● Fax: 281.496.5637 Date: August 26, 2022 Mr. Jameson Appel Assistant Director of Capital Projects Engineering & Public Works City of Pearland 2016 Old Alvin Rd. Pearland, Texas 77581 Re: Guaranteed Maximum Price for Public Safety Building Renovations & Training and Education Building Projects (aka Pearland Public Safety Projects) Dear Mr. Appel: We wish to inform you that after working together with Joiner Architects on these facilities, we have formally advertised and solicited proposals for the development of the GMP for the Pearland Public Safety Projects. Subcontractor & vendor proposals were received on July 22, 2022. After careful review and compilation of these proposals, Durotech, Inc. is pleased to present the following: Public Safety Training & Education Building $ 4,780,850 Public Safety Building Renovations $ 1,263,087 Total GMP (Training & Education Building + PSB Renovations) $ 6,043,937 It is our recommendation that we ask the City Council of The City of Pearland approve the Guaranteed Maximum Price of $6,043,937 and execute GMP Amendment No. 1 between The City of Pearland and Durotech, Inc. We are excited about the potential of entering into the construction phase of these projects and want to thank you and your team, Joiner Architects and their consultants for a very successful pre-construction phase. Durotech is committed to the citizens of Pearland, Texas in the successful delivery of the Pearland Public Safety Projects. Thank you and The City of Pearland for selecting Durotech as its building partner. It is our goal to meet and exceed your expectations. Should you have any questions please do not hesitate to contact me. Sincerely, David Rowe CEO 'David Rowe CEO DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A 2 11931 Wickchester Lane ● Suite 205 ● Houston, Texas 77043-4501 Phone: 281.558.6892 ● Fax: 281.496.5637 GMP SUMMARY Project: Pearland Public Safety Projects Consisting of: 1. Public Safety Building Renovations 2. Public Safety Training & Education Building Location: 2555 Cullen Blvd., Pearland, TX 77581 8333 Freedom Dr., Pearland, TX 77581 Owner: The City of Pearland, Texas Scope of work: THE PROJECT: The Work of Project is defined by the Contract Documents and consists of the following: 1. Major renovations to convert the existing Fire Station No. 4 into the Public Safety Training and Education Building. The Public Safety Training and Education Building includes a large conference room, break room area, fitness area to be shared by Police and Fire, office area, and associated restroom/shower facilities . The work also includes new electrical, mechanical, plumbing, communications, and security systems. Exterior renovations include metal roof replacement and painted brick. 2. Select interior renovations to both levels of the existing Public Safety Building including security upgrades, office revisions, building partitioning, and department modifications. 3. All work or portions of work necessary to provide complete facilities as represented in the Drawings and Specifications, including, but not limited to, architectural and structural building components, architectural finishes, mechanical equipment and ducting, plumbing piping and fixtures, electrical equipment and fixtures, fire alarm, security, and communications. GMP Proposal Package: The GMP proposal package consists of the following items: 1. Exhibit A – GMP Top Sheet – dated 26 August 2022 2. Exhibit B – Project Manual – dated 06 July 2022 3. Exhibit C – List of Drawings – dated 06 July 2022 4. Exhibit D – List of Addendums 5. Exhibit E – Qualifications & Assumptions 6. Exhibit F – Allowance Schedule 7. Exhibit G – Self Performed Work Items 8. Exhibit I – Cost Saving Items DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT 'A' PROJECT: LOCATION: OWNER: ARCHITECT: DATE: SECTION DESCRIPTION REMARKS TRAINING & EDUCATION PSB RENOVATIONS TOTAL 01 21 00 SIGNAGE ALLOWANCE 40,000 0 40,000 01 21 00 STATION ALTERTING SYSTEM ALLOWANCE 50,000 0 50,000 01 21 00 PLANTING BEDS ALLOWANCE 0 0 0 Deleted - In 32 80 00 & 32 90 00 01 21 00 CM CONTINGENCY ALLOWANCE 180,000 20,000 200,000 01 21 00 DOOR HARDWARE ALLOWANCE 70,000 20,000 90,000 01 43 39 MOCKUP PANEL 1,500 0 1,500 01 51 19 EQUIPMENT FUEL & FUEL TANK 3,580 0 3,580 01 54 16 MATERIAL HANDLING & HOISTING 14,320 1,500 15,820 01 54 23 TEMPORARY SCAFFOLDING / SHORING 13,919 0 13,919 01 55 26 TRAFFIC CONTROL 1,568 0 1,568 01 56 26 TEMPORARY FENCING 7,613 0 7,613 01 57 00 EROSION & SEDIMENT CONTROL 15,309 0 15,309 01 64 00 OWNER FURNISHED ITEMS 6,062 2,552 8,614 01 71 23 FIELD ENGINEERING & LAYOUT 0 0 0 01 74 13 PROGRESS CLEANING 11,258 6,928 18,186 01 74 16 SITE MAINTENANCE/CLEAN STREETS 8,243 0 8,243 01 74 19 CONSTRUCTION WASTE MANAGEMENT 7,176 3,626 10,802 01 74 23 FINAL CLEANING 4,550 4,220 8,770 DIV 02 EXISTING CONDITIONS 02 21 00 SURVEYS 3,150 0 3,150 02 41 13 SITE DEMOLITION 29,865 0 29,865 02 41 19 BUILDING DEMOLITION 85,761 35,055 120,816 02 70 00 PUMP & DEWATER 1,500 0 1,500 DIV 03 CONCRETE 03 20 00 CONCRETE REINFORCING 0 0 0 In 03 30 00 - Cast-in-Place Concrete 03 30 00 CAST-IN-PLACE CONCRETE 202,700 5,000 207,700 DIV 04 MASONRY 04 05 19 MASONRY REBAR 0 0 0 In 04 20 00 - Masonry 04 20 00 MASONRY 42,000 0 42,000 DIV 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING 35,825 0 35,825 05 12 50 STRUCTURAL STEEL ERECTION 46,708 0 46,708 05 37 00 PREPARE EXPOSED STRUCTURE 4,159 0 4,159 05 50 00 MISCELLANEOUS STEEL 5,980 2,480 8,460 05 50 10 TIMBER MATS 4,583 0 4,583 DIV 06 WOOD, PLASTICS, AND COMPOSITES 06 10 00 ROUGH CARPENTRY 14,071 6,137 20,208 06 22 00 MILLWORK 57,000 40,000 97,000 06 60 00 PLASTIC FABRICATIONS 1,026 0 1,026 DIV 07 THERMAL AND MOISTURE PROTECTION 07 11 00 DAMPPROOFING 34,771 0 34,771 07 21 00 THERMAL INSULATION 2,567 0 2,567 07 41 00 METAL ROOF PANELS 0 0 0 In 07 52 00 - Modified Bit Roofing 07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING 134,337 0 134,337 07 54 00 THERMOPLASTIC MEMBRANE ROOFING 0 12,357 12,357 OWNER'S TOPSHEET - CITY OF PEARLAND PUBLIC SAFETY GMP TOPSHEET City of Pearland Public Safety Projects 8333 Freedom Dr. / 2555 Cullen Pkwy - Pearland, TX 77581 City of Pearland, Texas Joiner Architects 8/26/2022 3 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT 'A' SECTION DESCRIPTION REMARKS TRAINING & EDUCATION PSB RENOVATIONS TOTAL GMP TOPSHEET 07 84 00 FIRESTOPPING 1,547 453 2,000 07 92 00 JOINT SEALANTS 9,940 2,356 12,296 DIV 08 OPENINGS 08 08 00 DOOR & HARDWARE INSTALLATION 5,100 3,577 8,677 08 11 00 METAL DOORS & FRAMES 30,970 27,997 58,967 08 12 00 INTERIOR ALUMINUM FRAMES 1,539 0 1,539 08 14 23 PLASTIC LAMINATE FACED WOOD DOORS 1,462 1,462 2,924 08 31 00 ACCESS DOORS AND PANELS 1,807 981 2,788 08 33 00 COILING DOORS & GRILLES 16,431 0 16,431 08 71 00 DOOR HARDWARE 3,741 1,621 5,362 08 80 00 GLAZING 205,425 34,858 240,283 08 80 10 TEMPORARY ENCLOSURES 5,792 0 5,792 08 80 15 CLEAN GLASS 683 190 873 08 91 00 LOUVERS 1,714 0 1,714 DIV 09 FINISHES 09 24 00 CEMENT PLASTERING 15,500 0 15,500 09 29 00 GYPSUM BOARD 171,075 118,268 289,343 09 30 00 TILING 68,909 14,974 83,883 09 51 00 ACOUSTICAL CEILINGS 82,075 13,925 96,000 09 60 00 FLOOR PREPARATION 6,016 4,110 10,126 09 60 10 FLOOR PROTECTION 5,486 6,341 11,827 09 62 00 RESILIENT ATHLETIC FLOORING 20,327 0 20,327 09 62 05 MOISTURE CONTROL ALLOWANCE 22,750 0 22,750 09 65 00 RESILIENT FLOORING 40,287 56,351 96,638 09 67 00 FLUID-APPLIED FLOORING 784 0 784 09 84 00 ACOUSTIC WALL PANELS 0 0 0 In 09 51 00 - Acoustical Ceilings 09 90 00 PAINTING & COATING 48,845 50,950 99,795 DIV 10 SPECIALTIES 10 11 00 VISUAL DISPLAY UNITS 0 5,700 5,700 10 14 00 SIGNAGE 0 0 0 In 01 21 00 - Signage Allowance 10 21 13 TOILET COMPARTMENTS 8,518 0 8,518 10 21 16 SHOWER & DRESSING COMPARTMENTS 0 0 0 In 08 80 00 - Glazing 10 21 23 CUBICLE CURTAINS & TRACK 0 0 0 None 10 26 13 CORNER GUARDS 5,596 882 6,478 10 28 13 TOILET ACCESSORIES 4,887 350 5,237 10 44 00 FIRE PROTECTION SPECIALTIES 750 0 750 10 44 15 KNOX BOX 902 0 902 10 51 13 METAL LOCKERS 6,780 0 6,780 10 51 23 PLASTIC LAMINATE CLAD LOCKERS 0 0 0 In 06 22 00 - Millwork 10 51 53 LOCKER ROOM BENCHES 1,115 0 1,115 10 71 13 EXTERIOR SUN CONTROL DEVICES 0 0 0 In 10 73 00 - Protective Covers 10 73 00 PROTECTIVE COVERS 82,980 0 82,980 10 75 00 FLAGPOLES 13,825 0 13,825 DIV 11 EQUIPMENT 11 31 00 RESIDENTIAL APPLIANCES 23,461 8,291 31,752 11 40 00 FOODSERVICE EQUIPMENT 0 134,231 134,231 11 66 23 GYMNASIUM EQUIPMENT 17,062 0 17,062 DIV 12 FURNISHINGS 12 21 00 WINDOW BLINDS 0 2,370 2,370 12 24 00 WINDOW SHADES 19,865 0 19,865 DIV 13 SPECIAL CONSTRUCTION DIV 14 CONVEYING EQUIPMENT DIV 21 FIRE SUPPRESSION 21 10 00 FIRE SUPPRESSION SYSTEMS 65,465 13,989 79,454 DIV 22 PLUMBING 22 00 00 PLUMBING 212,500 25,000 237,500 DIV 23 HVAC 23 00 00 HVAC 515,384 133,523 648,907 4 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT 'A' SECTION DESCRIPTION REMARKS TRAINING & EDUCATION PSB RENOVATIONS TOTAL GMP TOPSHEET 23 00 10 HVAC FILTER CHANGES 2,750 1,500 4,250 23 05 00 MEP COORDINATION 4,240 2,120 6,360 DIV 25 INTEGRATED AUTOMATION DIV 26 ELECTRICAL 26 00 00 ELECTRICAL 795,375 242,100 1,037,475 26 00 05 ROUGH IN/BACK BOXES - LOW VOLTAGE 9,100 4,400 13,500 26 41 00 LIGHTNING PROTECTION 0 0 0 In 26 00 00 - Electrical DIV 27 COMMUNICATIONS 27 10 00 STRUCTURED CABLING 26,525 24,554 51,079 27 41 16 INTEGRATED AUDIO-VIDEO SYSTEMS & EQUIPMENT 0 0 0 A/V By Owner DIV 28 ELECTRONIC SAFETY & SECURITY 28 13 00 ACCESS CONTROL SYSTEM 76,240 19,250 95,490 28 23 00 VIDEO SURVEILLANCE SYSTEM 0 0 0 In 28 13 00 - Access Control 28 31 00 FIRE DETECTION & ALARM SYSTEM 36,374 12,028 48,402 DIV 31 EARTHWORK 31 20 00 EARTHWORK 58,650 0 58,650 31 22 16 FINAL GRADING 4,301 0 4,301 31 23 10 HAUL OFF SPOILS 12,860 0 12,860 31 63 29 DRILLED CONCRETE PIERS & SHAFTS 0 0 0 In 03 30 00 - Cast-in-Place Concrete DIV 32 EXTERIOR IMPROVEMENTS 32 01 11 CLEAN PAVING & SIDEWALKS 3,258 0 3,258 32 13 75 REMOVE STRIP/CLEAN PAVING JOINTS 1,335 0 1,335 32 16 15 BACKFILL CURBS 1,857 0 1,857 32 17 23 PAVEMENT MARKINGS 4,900 0 4,900 32 18 13 SYNTHETIC GRASS SURFACING 146,454 0 146,454 32 31 00 FENCES & GATES 25,860 0 25,860 32 80 00 IRRIGATION 15,661 0 15,661 32 80 10 IRRIGATION SLEEVES 642 0 642 32 90 00 LANDSCAPING 49,537 0 49,537 DIV 33 UTILITIES 33 00 00 SITE UTILITIES 89,300 0 89,300 35 00 00 PUNCH LIST 10,393 - 10,393 ACCEPTED COST SAVINGS (162,979) (17,094) (180,073) SUB TOTAL - COST OF WORK ITEMS 4,101,029 1,111,463 5,212,492 GENERAL CONDITIONS PER RFP 237,055 - 237,055 ADDITIONAL GENERAL CONDITIONS (BR / GL / BONDS)99,039 60,843 159,882 PERMIT - CITY OF PEARLAND - - - AGC FEES 7,921 2,645 10,566 QMS/SAFETY 14,224 3,760 17,984 MATERIAL ESCALATION CONTINGENCY 82,021 22,229 104,250 SUBTOTAL - COST OF WORK 4,541,289 1,200,939 5,742,228 FEE 229,335 60,647 289,983 PRECONSTRUCTION FEE 10,226 1,500 11,726 TOTAL GMP 4,780,850 1,263,087 6,043,937 5 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 6 PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS Document 00 00 01 - Title Page Document 00 00 02 - Table of Contents Document 00 10 00 - Notice for Subcontractor Proposals Document 00 12 00 - Sub Proposal Form Document 00 21 10 - Instructions to Subcontractor-Vendor Proposers Document 00 21 11 - Sample Insurance Certificate Document 00 45 23 - Affidavit of Non-Asbestos, Lead, and PCB Use in Project (Project Close-Out) Document 00 45 25 - Statutory Lien Waiver Forms Document 00 61 00 - Insurance and Bonds Document 00 61 10 - Contract Documents Document 00 72 00 - General Conditions Document 00 73 00 - Supplementary Conditions Document 00 73 43 - Prevailing Wage Rates SPECIFICATIONS DIVISION 01 - GENERAL REQUIREMENTS Section 01 11 00 - Summary of Work Section 01 12 00 - Owner Provided Supplementary Documents Geotechnical Report No. AHA 19-105-00 Section 01 13 00 - Mechanical and Electrical Coordination Section 01 14 00 - Contractor’s Use of Premises Section 01 19 00 - Codes, Regulations and Standards Section 01 21 00 - Allowances Section 01 25 00 - Applications for Payment Section 01 26 00 - Contract Modification Procedures Section 01 26 13 - Request for Interpretation Section 01 29 10 - Change Order Procedures Section 01 31 00 - Project Management and Coordination Section 01 31 06 - Coordination Drawings Section 01 31 10 - Coordination and Meetings Section 01 32 00 - Construction Progress Documentation Section 01 33 00 - Submittal Procedures Section 01 33 10 - BIM Coordination Section 01 33 10.2 - Technical Submittal Procedures Section 01 38 00 - Construction Photographs Section 01 39 00 - Contractor’s Quality Control Section 01 40 00 - Quality Requirements DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 7 Section 01 42 00 - Definitions and Abbreviations Section 01 42 10 - References Section 01 44 00 - Observation Services Section 01 45 29 - Testing Laboratory Services Section 01 50 00 - Temporary Facilities and Controls Section 01 50 50 - Mobilization Section 01 53 20 - Temporary Tree and Plant Protection Section 01 55 00 - Stabilized Construction Exit Section 01 55 40 - Street Signs Section 01 55 50 - Traffic Control Section 01 56 20 - Waste Material Disposal Section 01 56 40 - Control of Ground Water and Surface Water Section 01 56 50 - TDPS Requirements Section 01 56 66 - Source Controls for Erosion and Sedimentation Section 01 57 13 - Fabric Filter Fence Section 01 57 20 - Reinforced Filter Fabric Barrier Section 01 58 00 - Project Signs Section 01 60 00 - Product Options and Substitutions Section 01 60 10 - Material and Equipment Section 01 63 10 - Substitution Request Form Section 01 71 23 - Field Engineering Section 01 73 00 - Execution Section 01 73 29 - Cutting & Patching Section 01 74 00 - Warranties Section 01 74 19 - Waste Water Disposal Section 01 75 00 - Starting Systems Section 01 76 00 - Project Record Document Section 01 77 00 - Closeout Procedures DIVISION 02 - EXISTING CONDITIONS Section 02 41 19 - Selective Demolition DIVISION 03 - CONCRETE Section 03 30 00 - Concrete Construction for Structures Section 03 30 10 - Cast-In-Place Concrete Section 03 45 00 - Architectural Precast Concrete DIVISION 04 - MASONRY Section 04 20 00 - Unit Masonry Assemblies DIVISION 05 - METALS Section 05 12 00 - Structural Steel Section 05 50 00 - Miscellaneous Metals DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 8 DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES Section 06 10 00 - Rough Carpentry DIVISION 07 - THERMAL AND MOISTURE PROTECTION Section 07 10 50 - Under-Slab Vapor Retarder Section 07 13 10 - Shower Stall Waterproofing Section 07 21 00 - Building Insulation Section 07 41 13 - Standing Seam Metal Roof Panels Section 07 62 00 - Sheet Metal Flashing, Gutters, Downspouts, and Trim Section 07 72 00 -Roof Accessories Section 07 84 13 - Penetration Firestopping Section 07 92 00 - Joint Sealants DIVISION 08 - OPENINGS Section 08 11 13 - Hollow Metal Doors and Frames Section 08 12 16 - Interior Aluminum Frames Section 08 14 16 - Flush Wood Doors Section 08 31 00 - Access Doors Section 08 33 10 - Overhead Coiling Insulated Doors Section 08 41 10 - Aluminum Storefronts Section 08 42 13 - Aluminum Entrances Section 08 71 00 - Door Hardware Section 08 80 00 - Glazing Section 08 83 00 - Mirrors Section 08 91 00 - Metal Louvers Section 08 91 10 - Aluminum Curtain Wall DIVISION 09 - FINISHES Section 09 24 00 - Lath and Plaster Section 09 25 00 - Gypsum Board Assemblies Section 09 30 13 - Ceramic Tiling Section 09 51 13 - Acoustical Panel Ceilings Section 09 54 26 - Wood Panel Ceiling Section 09 62 05 - Moisture Control Section 09 65 13 - Resilient Base & Accessories Section 09 65 19 - Resilient Tile Flooring Section 09 65 66 - Resilient Athletic Flooring Section 09 68 16 - Carpeting Section 09 72 00 - Wall Covering Section 09 77 00 - Dry Erase Wall Covering Section 09 79 50 - Concrete Floor Sealer Section 09 84 13 - Acoustical Wall Panels DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 9 Section 09 91 00 – Painting DIVISIONS 10 - SPECIALTIES Section 10 11 00 - Visual Display Surfaces Section 10 21 13.21 - Solid Color Reinforced Composite Toilet Partitions Section 10 26 00 - Wall Protection and Recessed Corner Guards Section 10 28 13 - Toilet Accessories Section 10 28 80 - Glass Shower Enclosures Section 10 41 00 - Knox Box Section 10 43 00 - Exterior Signage Section 10 44 00 - Interior Signage Section 10 51 30 - Metal Lockers Section 10 52 00 - Fire Protection Specialties Section 10 71 13 - Exterior Sun Control Devices Section 10 73 16 - Aluminum Canopies Section 10 99 00 - Miscellaneous Specialties DIVISIONS 11 THROUGH - EQUIPMENT Section 11 30 00 - Residential Appliances Section 11 48 10 - Protection Padding DIVISION 12 - FURNISHINGS Section 12 21 24 - Electric Roller Shade System Section 12 21 24.1 - Manual Roller Shade System Section 12 30 00 - Manufactured Casework Section 12 36 61 - Quartz Countertops DIVISION 13 - SPECIAL CONSTRUCTION - (Not Used) DIVISION 14 - CONVEYING EQUIPMENT - (Not Used) DIVISION 21 - FIRE SUPPRESSION Section 21 00 00 - Fire Protection Section 21 02 01 - Coordination Drawings Section 21 05 29 - Hangers and Supports for Fire Suppression Piping and Equipment Section 21 13 13 - Wet Pipe Sprinkler System DIVISION 22 - PLUMBING Section 22 02 00 - Basic Materials and Methods Section 22 02 01 - Coordination Drawings Section 22 03 00 - Plumbing Demolition for Remodeling Section 22 05 13 - Common Motor Requirements for Plumbing Equipment Section 22 05 16 - Expansion Fittings and Loops for Plumbing Piping DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 10 Section 22 05 29 - Hangers and Supports for Plumbing Piping and Equipment Section 22 05 48 - Vibration and Seismic Controls for Plumbing Piping Section 22 05 53 - Identification for Plumbing Piping Equipment Section 22 07 19 - Plumbing Piping Insulation Section 22 08 00 - Commissioning of Plumbing Systems Section 22 10 00 - Plumbing Piping Section 22 11 19 - Plumbing Specialties Section 22 11 21 - Natural Gas Piping Systems Section 22 30 00 - Plumbing Equipment Section 22 40 00 - Plumbing Fixtures DIVISION 23 - HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) Section 23 02 00 - Basic Materials and Methods Section 23 02 01 - Coordination Drawings Section 23 05 13 - Common Motor Requirements for HVAC Equipment Section 23 05 16 - Expansion Fittings and Loops for HVAC Piping Section 23 05 29 - Hangers and Supports for Piping and Equipment for HVAC Section 23 05 48 - Vibration and Seismic Controls for HVAC Piping and Equipment Section 23 05 53 - Identification for HVAC Piping and Equipment Section 23 05 93 - Testing, Adjusting, and Balancing Section 23 07 13 - Duct Insulation Section 23 07 16 - HVAC Equipment Insulation Section 23 07 19 - HVAC Piping Insulation Section 23 08 00 - Commissioning of HVAC Systems Section 23 09 00 - Building Control System for HVAC Section 23 21 13 - Above Ground Hydronic Piping Section 23 23 00 - Refrigerant Piping Section 23 31 13 - Metal Ductwork Section 23 33 00 - Ductwork Accessories Section 23 34 00 - HVAC Fans Section 23 37 13 - Air Distribution Devices Section 23 37 23 - HVAC Gravity Ventilators Section 23 41 00 - Air Filters Section 23 62 13 - Air Cooled Condensing Units Section 23 81 26 - Split System Air Conditioners - Wall Mounted Section 23 82 19 - Fan Coil Unit Section 23 82 39 - Electric Unit Heaters DIVISIONS 24 AND 25 - Not Used DIVISION 26 - ELECTRICAL Section 26 02 00 - Basic Materials and Methods Section 26 02 01 - Coordination Drawings DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 11 Section 26 03 00 - Demolition Work Section 26 03 13 - Electrical Demolition for Remodeling Section 26 05 19 - Wire, Cable, and Related Materials Section 26 05 26 - Grounding Section 26 05 33 - Raceways Section 26 05 73 - Short Circuit, Coordination Study, ARC Flashing Hazard Analysis Section 26 08 00 - Commissioning of Electrical Systems Section 26 21 13 - Electrical Service Entrance Section 26 24 16 - Panelboards Section 26 27 26 - Wiring Devices Section 26 28 13 - Fuses Section 26 28 16 - Safety and Disconnect Switches Section 26 29 26 - Miscellaneous Electrical Controls and Wiring Section 26 32 13 16 - (250kW) Natural Gas Engine-Driven Standby Generator Section 26 33 53 - Uninterruptible Power Supply Section 26 43 13 - Surge Protective Device -Service Entrance Section 26 43 13 13 - Surge Protective Device- Standard Interrupting Section 26 51 00 13 - Lighting Fixtures (LED) DIVISIONS 27 - COMMUNICATIONS Section 27 02 00 - Basic Materials and Methods Section 27 05 26 - Grounding and Bonding for Communications Systems Section 27 05 28 - Pathways for Communications Systems Section 27 05 43 - Underground Ducts and Raceways for Communications Systems Section 27 11 00 - Communications Room Fittings Section 27 13 00 - Communications Backbone Cabling Section 27 15 00 - Communications Horizontal Cabling DIVISIONS 28 - ELECTRONIC SAFETY AND SECURITY Section 28 02 00 - Basic Materials and Methods Section 28 03 00 - Life Safety and Security Demolition for Remodeling Section 28 13 00 - Access Control System Section 28 20 00 - Video Surveillance System Section 28 46 00.21 - Fire Alarm System DIVISION 31 - EARTHWORK Section 31 11 00 - Clearing and Grubbing Section 31 22 00 - Earthwork Section 31 23 00 - Excavation Filling and Backfilling for Site Utilities Section 31 23 13- Subgrade Preparation Section 31 23 23.15 - Cement Sand Backfilling Section 31 23 43 - Trench Safety System DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 12 Section 31 31 16 - Termite Control DIVISION 32 - EXTERIOR IMPROVEMENTS Section 32 11 13.13 - Lime Stabilization of Subgrade Section 32 13 13 - Portland Cement Concrete Pavement Section 32 16 13 - Concrete Curbs Section 32 17 13 - Concrete Pavement Joints Section 32 17 16 - Concrete Wheel Stops Section 32 17 23 - Pavement Markings Materials Section 32 18 13 - Synthetic Grass Surfacing Section 32 20 10 - Concrete Sidewalks Section 32 31 19 - Metal Panel Gates Section 32 31 20 - Ornamental Metal Fence and Gates Section 32 84 00 - Irrigation System Section 32 90 00 - Landscape Planting Section 32 92 00 - Turf and Grasses DIVISION 33 - UTILITIES Section 33 05 13 - Manholes Section 33 05 23 - Jacking, Boring, or Tunneling Pipe Section 33 11 00 - Water Distribution Mains Section 33 31 00 - Sanitary Sewers Section 33 40 00 - Storm Drainage DIVISIONS 34 THROUGH 48 - (Not Used) END OF TABLE OF CONTENTS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 13 SAFETY TRAINING & EDUCATION BUILDING: CIVIL C001 GENERAL NOTES C002 DEMOLITION PLAN C003 DIMENSION CONTROL C100 GRADING & DRAINAGE C101 FLOODPLAIN ANALYSIS C200 UNDERGROUND UTILITIES C300 PAVING & JOINT LAYOUT C400 SWPPP C401 SWPPP DETAILS C500 CONSTRUCTION DETAILS C501 CONSTRUCTION DETAILS C502 CONSTRUCTION DETAILS C503 CONSTRUCTION DETAILS C504 CONSTRUCTION DETAILS C505 CONSTRUCTION DETAILS C506 CONSTRUCTION DETAILS C507 CONSTRUCTION DETAILS C508 CONSTRUCTION DETAILS C509 CONSTRUCTION DETAILS LANDSCAPE L001 LANDSCAPE NOTES & DETAILS L101 LANDSCAPE PLAN IR100 IRRIGATION PLAN ARCHITECTURAL A001 CODE ANALYSIS A002 TYPICAL SITE DETAILS A003 TYPICAL MOUNTING HTS A004 FENCE & GATE DETAILS A005 GENERAL NOTES A100 DEMOLITION SITE PLAN A101 ARCHITECTURAL SITE PLAN A200 DEMOLITION FLOOR PLAN A201 ARCHITECTURAL FLOOR PLAN A301 ROOF PLAN A401 EXTERIOR ELEVATIONS A501 WALL SECTIONS A601 ENLARGED PLANS & INTERIOR ELEVATIONS A701 COMPOSITE REFLECTED CEILING PLAN A801 MILLWORK DETAILS A802 MISCELLANEOUS DETAILS A901 FINISH SCHEDULE DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 14 A902 DOOR & FRAME TYPES & SCHEDULE A903 PARTITION TYPES STRUCTURAL S001 ABBREVIATIONS, SYMBOLS & SHEET INDEX S101 GENERAL NOTES S201 FOUNDATION PLAN S202 ROOF FRAMING PLAN S301 FOUNDATION DETAILS S401 FRAMING DETAILS MEP MEPD101 MEP DEMOLITION SITE PLAN MEP 101 MEP SITE PLAN MECHANICAL M001 MECHANICAL SYMBOL & LEGEND MD211 MECHANICAL DEMOLITION PLAN M211 MECHANICAL PLAN M501 MECHANICAL SCHEDULES M601 MECHANICAL DETAILS M701 MECHANICAL CONTROLS ELECTRICAL E001 ELECTRICAL SYMBOL & LEGEND ED211 ELECTRICAL DEMOLITION PLAN E401 ELECTRICAL ONE-LINE DIAGRAMS E501 ELECTRICAL SCHEDULES E502 ELECTRICAL SCHEDULES E601 ELECTRICAL DETAILS E602 ELECTRICAL DETAILS ED211 ELECTRICAL DEMOLITION PLAN EL211 ELECTRICAL LIGHTING PLAN EP211 ELECTRICAL POWER PLAN PLUMBING P001 PLUMBING SYMBOL & LEGEND P200 PLUMBING DEMOLITION PLAN P211 PLUMBING PLAN P212 PLUMBING PLAN - DOMESTIC WATER & GAS P401 PLUMBING RISER & NATURAL GAS P402 PLUMBING RISER SANITARY WASTE & VENT P501 PLUMBING SCHEDULES P502 PLUMBING SCHEDULES P601 PLUMBING DETAILS P602 PLUMBING DETAILS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 15 TECHNOLOGY T001 TECHNOLOGY GENERAL NOTES T100 TECHNOLOGY SITE PLAN T211 TECHNOLOGY DEMOLITION PLAN T212 TECHNOLOGY PLAN T301 TECHNOLOGY ENLARGED PLANS T601 TECHNOLOGY DETAILS T602 TECHNOLOGY DETAILS T603 TECHNOLOGY DETAILS PUBLIC SAFETY BUILDING RENOVATIONS: ARCHITECTURAL A001 CODE ANALYSIS A002 TYPICAL MOUNTING HEIGHTS A200 COMPOSITE DEMOLITION PLAN A200.1 DEMOLITION IMAGES A201 COMPOSITE FLOOR PLAN A202 ENLARGED FLOOR PLANS A601 INTERIOR ELEVATIONS/MILLWORK DTL A701 ENLARGED REFLECTED CEILING PLAN A901 FINISH SCHEDULE/DOOR & FRAME TYPES & SCHEDULE A902 PARTITION TYPES FOOD SERVICES K0 DEMOLITION PLAN K1 FS EQUIPMENT PLAN K1.1 FS FACILITY MODEL K1.2 FS EQUIPMENT MODEL K1.3 FS PLUMBING PLAN K1.4 FS ELECTRICAL PLAN K1.5 EXHUAST HOOD DRAWING K1.6 FS ELEVATIONS DETAILS MECHANICAL M001 MECHANICAL SYMBOL & LEGEND MD212 LEVEL 1 MECHANICAL DEMO PLAN – AREA B MD221 LEVEL 2 MECHANICAL DEMOLITION PLAN – AREA A MF222 LEVEL 2 MECHANICAL DEMOLITION PLAN – AREA B MD232 ROOF MECHANICAL DEMOLITION PLAN – AREA B M212 LEVEL 1 MECHANICAL PLAN – AREA B M221 LEVEL 2 MECHANICAL PLAN – AREA A M222 LEVEL 2 MECHANICAL PLAN – AREA B M232 ROOF MECHANICAL PLAN – AREA B M501 MECHANICAL SCHEDULES DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 16 M601 MECHANICAL DETAILS M701 MECHANICAL CONTROLS ELECTRICAL E001 ELECTRICAL SYMBOL & LEGEND E301 FOOD SERVICE ELECTRICAL PLAN E401 ELECTRICAL ONE-LINE DIAGRAMS E501 ELECTRICAL SCHEDULES E502 ELECTRICAL SCHEDULES E601 ELECTRICAL DETAILS EL212 LEVEL 1 LIGHTING PLAN – AREA B EL221 LEVEL 2 LIGHTING PLAN – AREA A EL222 LEVEL 2 LIGHTING PLAN – AREA B ELD212 LEVEL 1 LIGHTING DEMOLITION PLAN – AREA B ELD221 LEVEL 2 LIGHTING DEMOLITION PLAN – AREA A ELD222 LEVEL 2 LIGHTING DEMOLITION PLAN – AREA B EP212 LEVEL 1 POWER PLAN – AREA B EP221 LEVEL 2 POWER PLAN – AREA A EP222 LEVEL 2 POWER PLAN – AREA B EPD212 LEVEL 1 POWER DEMOLITION PLAN – AREA B EPD221M LEVEL 2 POWER DEMOLITION PLAN – AREA A EPD222M LEVEL 2 POWER DEMOLITION PLAN – AREA B PLUMBING P001 PLUMBING SYMBOL & LEGEND P301 ENLARGED FOOD SERVICE PLUMBING PLAN P302 LEVEL 2 PLUMBING PLAN – AREA B P501 PLUMBING SCHEDULES TECHNOLOGY T001 TECHNOLOGY GENERAL NOTES TD212 LEVEL 2 TECHNOLOGY DEMO PLAN – AREA A TD213 LEVEL 2 TECHNOLOGY DEMO PLAN – AREA B T211 LEVEL 1 TECHNOLOGY PLAN – AREA B T212 LEVEL 2 TECHNOLOGY PLAN – AREA A T213 LEVEL 2 TECHNOLOGY PLAN – AREA B T601 TECHNOLOGY DETAILS T602 TECHNOLOGY DETAILS T603 TECHNOLOGY DETAILS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘D’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF ADDENDA 17 1. Addendum No. 1 Issued on July 13, 2022 2. Addendum No. 2 Issued on July 15, 2022 3. Addendum No. 3 Issued on July 18, 2022 4. Addendum No. 4 Issued on July 22, 2022 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 18 DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS 1. Excluded is Material Testing. 2. Excluded are City/MUD Fees, City/MUD Inspection Fees, and City/Mud Tap fees. 3. Excluded are Utility Assessment & Impact Fees. 4. Utility Company agreements (terms & conditions and costs), easements and coordination which will serve as the termination point for Durotech to make connections for building service shall be the responsibility of the Owner. 5. Off-site Utility Fees and Utility District Connection Fees (if any) to on-site utilities shall be the responsibility of the Owner. 6. Excluded are all building permit fees. Building permit fees, if any, are to be paid by the Owner. 7. Excluded are unforeseen underground conditions or obstructions not indicated in contract documents. 8. Without regard to any other provision of this Agreement, Owner shall be liable to Contractor for additional costs incurred by Contractor as the result of any governmental payroll tax or healthcare tax if the tax is applicable to the Project, the Project is not tax exempt from the specific tax and the tax became effective after the date of execution of the Contract. 9. Electronic Files and CAD Files will be provided by the Architect/Engineer of re cord for the purpose of preparing shop drawings and 3D models at no cost to the General Contractor and/or Subcontractors. A signed release will be required before electronic files are released by the Architect/Engineer. 10. Owner and Contractor agree that design and specification of systems, operating parameters, and materials is by Owner’s Architectural and Engineering consultants and that enforcement of warranties is contingent upon systems being maintained and operated in accordance with manufacturer recommendations. 11. Owner and Contractor agree that all manufacturer’s warranties, and subcontractor’s warranties which extend beyond Contractor’s warranty period, are hereby assigned to and run directly from the manufacturer to the Owner and from the subcontractor to the Owner, respectively. Owner accepts these assignments and warranties, and releases and discharges Contractor from any and all claims, liabilities, damages, costs and expenses arising out of such manufacturer’s warranties and any subcontractor’s extended warranties. 12. The Contractor’s warranty excludes remedy for damage or defect caused by abuse, material alteration to the work not executed by the Contractor, insufficient DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 19 maintenance, or maintenance not in compliance with manufacturer’s written recommendations. 13. Payment and Performance Bonds will be charged to the Owner based on the State of Texas regulated rate. 14. The Guaranteed Maximum Price provided is a not to exceed amount for the entire project scope. Individual line items within the project budget are not indi vidual Guaranteed Maximum Price amounts. 15. The GMP package is valid until September 13, 2022, with the assumption that the Owner will issue a Notice to Proceed and sign the GMP Amendment on or before the stated date. 16. Excluded is any Security Personnel/Watchman. Included are security cameras as required for the General Contractor’s jobsite office. 17. Architect will provide an “Issue for Construction” set of plans and specifications which will include the bid set, addenda, permit changes and accepted cost savings to Contractor within 14 days of NTP. All individual changes from the bid set will be clouded with a reference to the origin of the change (addendum number, permit changes, cost saving, etc.). 18. The proposed cost saving recommendations by Durotech, Inc. shall be subject to the review and approval of the Architect, Owner and the Owner’s Professional Consultants. Durotech, Inc. is not required to ascertain that the cost savings are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities. The Contractors review of the proposed cost savings is in the capacity as a Construction Manager and not as a Design Professional. 19. All accepted Value Engineering/Voluntary Alternates is pending General Contractor’s review of revised contract documents. 20. For any delays caused by events outside of Contractor’s control, including but not limited to Acts of God, pandemics, epidemics, acts of governmental authorities, acts of civil authorities, acts of war or terrorism, unanticipated material shortages and price escalations, labor disputes and utilities delays, Owner shall grant additional time extensions and price increases to Contractor when properly documented, substantiated and approved by Owner, subject to Contractor’s right to dispute. 21. Section 00 73 00 – Supplementary Conditions: Excluded is the requirement of achieving substantial completion within 240 days after receipt of notice to proceed as referenced in paragraph 8.4. Due to unanticipated lead times for critical electrical and HVAC equipment, Durotech proposes to be substantially complete within 365 days after notice to proceed and receipt of building permits from the Owner except for DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 20 installation of the Uninterruptible Power Supplies (UPS) due to lead time constraints. All parties agree that installation of the UPS will not be a requirement for establishing Substantial Completion. The owner shall release all retainage for the entire value of work complete once Substantial Completion is established. Retainage may be held only for the value of work remaining after the substantial completion date. This qualification is based on the following equipment delivery lead times, and further unforeseen increase in lead times will require adjustment to the timeline previously stated: a. HVAC Equipment: 34-36 Weeks b. Main Distribution Panel: 36-38 Weeks c. Generator: 42-44 Weeks d. UPS: 85-100 Weeks 22. Section 00 73 00 – Supplementary Conditions: Excluded in its entirety is paragraph 11.2 regarding Owner’s Protective Liability Insurance. 23. Compensation for General Conditions costs, as defined by the contract, are included as part of the Guaranteed Maximum Price to the date of Substantial Completion. All General Conditions costs incurred after the date of Substantial Completion shall be considered Cost of Work. 24. Stipulated Billing Rates: No. Description Rate 1 General Liability/Umbrella Insurance Contract amount per thousand x $6.00 2 Builder’s Risk Insurance Contract amount/hundred x $0.012 x # of months 3 Project Executive $124.00 per hour 3 Project Manager $71.00 per hour 5 Estimator $98.00 per hour 4 Safety/Field Operation Manager $110.00 per hour 5 Superintendent $57.00 per hour 6 Asst. Superintendent $49.00 per hour 7 Project Engineer $44.00 per hour 8 Quality Control Inspector $80.00 per hour DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 21 9 Contract Administrator $61.00 per hour 10 BIM Coordinator $55.00 per hour 11 IT Coordinator $100.00 per hour 12 Intern $22.00 per hour 13 Labor Burden 42.5% 25. Billable rates will be subject to audit for hours worked only. 26. All labor burden rates from a subcontractor that are 42% or less are considered to be acceptable and not auditable. 27. The approval of any change requests that results in change orders or AEA is considered as final approval and are not subject to any audit mo dification. 28. Included are the following sub-limits and deductibles for Builder’s Risk Insurance: a. Training and Education Building: i. Sub Limit: Named Windstorm $4,925,000 ii. Sub Limit: Flood $1,000,000 iii. Sub Limit: Earth Movement $2,500,000 iv. Sub Limit: Soft Costs $25,000 v. Deductible: All Other Peril: $5,000 vi. Deductible: Earth Movement $25,000 vii. Deductible: Flood $25,000 viii. Deductible: Wind/Hail 5%/$25,000 ix. Deductible: Windstorm 5%/$25,000 x. Deductible: Water Damage $5,000 b. Public Safety Building Renovations: i. Sub Limit: Named Windstorm $1,225,000 ii. Sub Limit: Flood $1,000,000 iii. Sub Limit: Earth Movement $1,225,000 iv. Sub Limit: Soft Costs $25,000 v. Deductible: All Other Peril: $5,000 vi. Deductible: Earth Movement: $25,000 vii. Deductible: Flood $25,000 viii. Deductible: Wind/Hail 5%/$25,000 ix. Deductible: Windstorm 5%/$25,000 x. Deductible: Water Damage $5,000 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 22 c. Builder’s Risk Insurance Premium will be paid by Durotech. Owner will be responsible for any deductibles if they should occur. DIVISION 01 – GENERAL REQUIREMENTS- 29. Excluded are any building windstorm inspections and/or certification. 30. Excluded is any cost for third-party Building Commissioning. Included is Building Commissioning coordination. 31. Excluded are any costs for generator rental and fuel for temporary power. We assume that we can tie into the existing electrical service for temporary power needs during construction. 32. All cost for use of utilities (power, water, sanitary) during construction will be paid for by Owner. 33. Excluded is any ground water control systems, well-point systems, eductor and ejector-type systems, deep wells, and piezometers or monitoring wells. 34. Excluded is any weekend or overnight work. All work will take place during normal business hours (7am – 5pm Monday through Friday). Durotech will have unhindered access to all areas where work is required during these hours for the entire project duration. Durotech will notify and coordinate with the owner when loud / noisy work will be necessary. 35. It is assumed that the Project Manual (Exhibit B) and the Drawings (Exhibit C) include the latest Design and Building Standards provided by the owner and have been reviewed by the Architect and their Consultants for compliance. 36. Section 01 40 00 – Quality Requirements: Excluded in its entirety is paragraph 1.6 J regarding 10’ x 10’ mockup. The majority of all exterior finishes are exiting to remain. Mock-ups, if needed, will be done on the building itself as construction progresses. DIVISION 02 – EXISTING CONDITIONS 37. Excluded is the removal and/or encapsulation of any and all asbestos, lead and other hazardous materials. The removal and/or encapsulation of all asbestos, lead and other hazardous materials will be the responsibility of the Owner and all costs of testing will be paid by the Owner. 38. Durotech recognizes the Owner’s first right of salvage. All items that the Owner intends to salvage must be removed before demolition is scheduled to start per the project schedule. Excluded is any cost and labor for the Owner’s salvage , transportation, and relocation/reinstallation operations. Included is salvaging of existing generator and relocation for storage to 2559 Hillhouse Rd., Pearland, TX 77584. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 23 39. All existing Fire Suppression, HVAC, Electrical, Communications, and Security equipment scheduled to remain or be reused is assumed to be in acceptable working condition. Durotech shall be entitled to additional cost and time for any required repairs or replacements of existing equipment in order to complete the work. 40. Owner will provide Durotech a clean and safe working environment, free from any environmental contamination and/or contaminates. Prior to and during construction, Owner shall maintain in the existing building(s) normal HVAC operations and habitable climatic conditions to prevent mold growth and/or other potential humidity related damages. If, during construction, Durotech encounters any known hazardous materials or mold, Durotech will notify the Owner immediately and cease all work in the potentially contaminated area. Owner agrees to indemnify Durotech from all damages, costs and expenses stemming from Owner’s failure to maintain normal HVAC operations and habitable climatic conditions. DIVISION 03 – CONCRETE 41. Included is approximately 5,122 SF of 2” fiberglass reinforced topping slab in the apparatus bay area to level the slab and meet ADA requirements for the use of the building. Any cost associated with additional floor leveling requirements discovered after demolition operations are complete will be paid for by the Owner. DIVISION 04 – MASONRY 42. Excluded are cast stone exterior window sills per detail 12/A802. Brick exterior window sills are existing and shall remain. DIVISION 05 – METALS 43. Excluded is any galvanizing of structural steel members in enclosed unconditioned space areas of the building. DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES DIVISION 07 – THERMAL AND MOISTURE PROTECTION 44. Included are the following Dampproofing materials: a. Henry Air Bloc 17 MR Fluid Applied Air Barrier b. Henry Blueskin SA Self Adhered Flexible Flashings DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 24 45. Section 07 21 00 – Building Insulation: Excluded is injected foam insulation for concrete masonry per paragraph 2.2.B. 46. Included is the following roofing scope and modified bituminous roofing materials at the Training & Education Building per consultation with Garland Company representative Mr. Blake Dieste: a. Remove existing roof in the area indicated on sheet A301. b. Install new Garland HPR Tri-base modified base sheet over existing concrete deck. c. Adhere new 1.5” flat stock and 1/8” per foot tapered sumps at roof drain assemblies, polyiso rigid insulation over the base sheet in Garland Insulock low rise foam adhesive. d. Adhere new ½” coverboard in Garland Insulock low rise foam adhesive. e. Install new Harland two ply modified bitumen roof system over coverboard. f. Shop fabricate and install new IMETCO 24-gauge galvalume parapet coping. g. Roof work operations will not void existing roof warranty. No new roof warranty is considered. 47. Section 07 41 13 – Prefinished Metal Roofing: Prefinished Metal Roofing scope of work shall include only the following: a. Remove existing roofing to existing wood deck at tower and to framing at mansard roofs. b. Install new ¾” CDX plywood over framing at mansard roofs and secure to existing framing. Excluded is any new framing; existing framing is assumed to be in acceptable condition. c. Install new IMETCO Aquablock 60 HT underlayment over new and existing plywood per manufacturer’s recommendations. d. Install new 24-gauge IMETCO galvalume standing seam roof system per manufacturer’s recommendations, including rakes, ridges, drip edges, hips, counter flashings, and receivers. e. Included is a 30-year No-Dollar-Limit warranty. 48. Included is the following TPO roofing scope of work and roofing materials for the Public Safety Building Renovations: a. Remove (1 EA) 2’ x 2’ roof curb, infill, and patch to match existing roof area as shown on sheet MED 2.32. b. Flash (4 EA) new 2’ x 2’ curbs as indicated on sheet ME 2.32. c. Roof work operations will not void existing roof warranty. No new roof warranty is considered. 49. Excluded is any cementitious sprayed fireproofing for steel columns, floor beams, roof beams, metal floor decks, and metal roof decks. 50. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 25 DIVISION 08 – OPENINGS 51. Section 08 71 00 – Door Hardware: Door hardware for all doors (PLAM, Hollow Metal, and Aluminum) will be included in Door Hardware Allowance as specified in Section 01 21 00 – Allowances. 52. Section 08 11 13 – Hollow Metal Doors and Frames: Included are hollow metal doors and frames as manufactured by Pearland Industries. 53. Section 08 33 00 – Rolling Shutters: Included is one (1 EA) Overhead Door Corporation Model 653 Allura Shutter with the following options: a. Solid aluminum curtain slat with powder coat finish b. Aluminum hood with finish to match curtain c. Aluminum guides for face of wall mount d. Tube motor with constant contact to close rocker switch 54. Section 08 41 10 – Aluminum Storefronts & Section 08 42 13 – Aluminum-Framed Entrances: Included are aluminum storefronts and aluminum-framed entrances as manufactured by Kawneer. 55. Section 08 80 00 – Glazing: Included is a single aluminum door and frame with 2’-0” side lights on each side at Public Safety Building opening 2112 as shown on enlarged floor plan detail 6/A202. 56. Excluded is field testing, of any kind, for aluminum framed storefronts and entrances. DIVISION 09 – FINISHES 57. Excluded are aluminum wrapped interior window sills per detail 12/A802. Included are drywall interior window sills. 58. Section 09 30 13 – Ceramic Tiling at Public Safety Building Renovations: Wall tile is included at Kitchen 2111 only. All other wall tile at Public Safety Building Renovations is excluded. Included are painted walls and/or vinyl wall covering (as applicable) at these areas. 59. Section 09 30 13 – Ceramic Tiling: Included are the following qualifications: a. F2 Floor Tiling – Included is 12”x24” Daltile Porcelain Tile Volume 1.0 b. F2A Floor Tiling – Included is 6”x6” Daltile Porcelain Tile Volume 1.0 c. W2 Wall Tiling at Drinking Fountains – Included is $5.00/SF material allowance. 60. Section 09 54 26 – Wood Panel Ceiling: Included is Armstrong Woodworks 6487 2’-0” x 6’-0” tegular in Natural Variations Beech finish ceiling tile in CertainTeed Black HD 9/16” grid system. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 26 61. Section 09 65 00 – Resilient Athletic Flooring: Included is 10% speckling intensity in lieu of 30% intensity as the specified Regupol ActivLok resilient athletic floor tile is only offered with 10% speckling intensity. DIVISION 10 – SPECIALTIES 62. Section 10 35 00 – Aluminum Flagpole: Included is one (1) 5’ x 8’ US flag, one (1) 5’ x 8’ Texas flag, and one (1) 5’ x 8’ City of Pearland flag. 63. Section 10 43 00 – Exterior Signage & Section 10 44 00 – Interior Signage: All exterior building signage or graphics, accessibility parking signs, interior room identification plaques, and other interior signage or graphics will be included in Signage Allowance as specified in Section 01 21 00 – Allowances. 64. Section 10 50 00 – Phenolic Lockers: This section is excluded in its entirety. Included are custom casework lockers at Lobby 100. 65. Section 10 51 30 – Metal Lockers: Included are six (6) 18” x 18” x 72” 2-tier lockers as manufactured by ASI to be located in Women Shower 113 and Men Shower 116. 66. 10 71 13 – Exterior Sun Control Devices: Included are Clear Anodized Sunscreen Canopies as manufactured by AVAdek with 8” tube rafters in lieu of 7” tube rafters and 8” airfoils in lieu of 9” airfoils. 67. 10 73 16 – Aluminum Canopies: Included is one (1) 62’ x 20’ Clear Anodized Aluminum Patio Canopy as manufactured by AVAdek. Excluded is any canopy soffit, color anodized finish, and painted finish. 68. Section 10 99 00 – Miscellaneous Specialties: Excluded are any Vaultek Smart Modular Storage Units. DIVISION 11 – EQUIPMENT 69. Section 11 30 00 – Residential Appliances: If the specified residential appliance models become unavailable or discontinued, an equal model will be provided in its place. Any additional cost due to this change will be paid for by the Owner. 70. Section 11 40 00 – Food Service Equipment: Included are the following due specification and drawing conflicts: a. Item #622 – Included is an AccuTemp electric griddle as specified and indicated on the electrical drawings. Excluded is any Dormont gas hose. b. Item #167 – Included are 16-gauge under shelves c. Item #196 – Included are 16-gauge under shelves d. Item # 249 – Included is sink with left and right drain boards as shown on the floor plan in lieu of specified right only drain board. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 27 71. Section 11 48 10 – Protection Padding: Included is 2’ x 5’ x 2” Class A Fire Rated Wall Padding as manufactured by Draper. DIVISION 12 – FURNISHINGS 72. Window Blinds for the Public Safety Building Renovation: Included are 1” Bali Classics .008” aluminum horizontal louver blinds. 73. Section 12 21 24 – Manual Roller Shade System: Manual Roller Shades will be surface mounted below ceiling with fascia to conceal roller tubes and brackets. Excluded are side and sill channels. 74. Section 12 21 24 – Electronic Intelligent Roller Shade System: Electronic Roller Shades will be surface mounted with fascia to conceal rollers and bracket. Included are MechoSystems IQ wall switch controls. Excluded are side channels, sill channels, and network controls. 75. Section 12 30 00 – Manufactured Casework: Included is casework as manufactured by Jericho Woodworks. 76. Section 12 30 00 – Manufactured Casework: Included are Wilsonart & Formica basic laminate colors. Excluded are any “Premium” laminate colors and finishes. 77. Section 12 36 61 – Quartz Countertops: Excluded are quartz countertops as manufactured by Vicostone. Included are 2cm thick Silestone quartz countertops in color levels 1 or 2. 78. Excluded is any transportation, loading, storage, unloading, assembly, or installation of furniture, appliances, or equipment labeled “by owner” or N.I.C. DIVISION 21 – FIRE SUPPRESSION 79. We assume that there will be adequate water supply with sufficient pressure available for the proper functioning of fire sprinkler systems and other systems. 80. Excluded is any exterior sprinkler system coverage such as canopy or porch areas. DIVISION 22 – PLUMBING DIVISION 23 – HVAC 81. Excluded is TAB - Testing, Air & Balancing. 82. Section 23 31 13 Metal Ductwork: Excluded is any duct cleaning per paragraph 3.8. Duct ends will be covered during construction. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 28 DIVISION 26 – ELECTRICAL DIVISION 27 – COMMUNICATIONS 83. Excluded are all IDF/MDF network switches, PoE switches, servers, routers, wireless access points (WAPs) and associated ancillary hardware and power supplies. 84. Excluded are all flat panel displays (TV). Included are Flat Panel Display Mounts per Section 10 99 00 – Miscellaneous Specialties and installation of the same. Installation of Flat Panel Displays to TV Mounts are by Owner. 85. Division 27 – Communications: Per City of Pearland standards, all communications cabling, associated hardware, and ancillary accessories shall be manufactured by Belden Solutions. 86. Excluded is all Integrated Audio-Visual Systems & Equipment, including, but not limited to, flat panel displays (TV), projectors, projector screens, smart boards, interactive displays, local sound systems, and intercommunication systems and devices. DIVISION 28 – ELECTRONIC SAFETY AND SECURITY 87. Excluded is any Intrusion Detection System; none specified. DIVISION 31 – EARTHWORK 88. Excluded is any casing or slurry drilling of piers. DIVISION 32 – EXTERIOR IMPROVEMENTS 89. Areas that receive Hydromulch will not be warranted for developing full turf grass. Owner understands that Hydro-mulch is a 2-season maintenance program requiring continuous maintenance including watering and fertilizer by the Owner. Areas that are not irrigated will not be warranted for grass or plant development and sustainability. Any temporary irrigation requirement by the contract will only be warranted to such date the temporary irrigation is removed. DIVISION 33 – UTILITIES 90. All required utility providers (Water, Sewer, Storm Discharge Point, Electric, Gas, Fiber, Phone Lines) are the responsibility of the Owner to coordinate and execute necessary agreements so that the utilities are installed per the contractor’s schedule for construction usage and systems startup. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 29 91. Domestic water meter, irrigation water meter and any wet connections/taps to be by City and paid directly by owner. 92. Excluded are any unforeseen subsurface conditions or obstructions as it relates to the utility installation. Any additional cost, including materials, labor, or equipment, required to mitigate hindrances to the installation of these system caused by unforeseen subsurface conditions or obstructions will be substantiated for which Durotech, Inc. will be entitled to an equitable adjustment of the contract sum. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘F’ City of Pearland Public Safety Building Renovations & Training and Education Building ALLOWANCE SCHEDULE 30 Allowances per Specifications: 1. Signage Allowance $ 40,000 2. Station Alerting System Allowance $ 50,000 3. CM Contingency Allowance $200,000 4. Door Hardware Allowance $ 90,000 Other Allowances: 1. Planting beds allowance has been deleted and is excluded. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘G’ City of Pearland Public Safety Building Renovations & Training and Education Building SELF PERFORMED WORK ITEMS 31 The following scope items will be self-performed by Durotech, Inc. and will be billed against the contract based upon the proposal submitted to and accepted by the owner and will be treated as a lump sum sub-contract amount. Labor Rates: Per Hour Semi-skilled Labor $27.00 Skilled Labor $30.00 Foreman/Operator $34.00 No.Description of Scope Total 1 Owner Furnished Items 6,062$ 2 Miscellaneuos Steel (L)5,980$ 3 Rough Carpentry (L & M)14,071$ 4 Plastic Fabrications (L & M)1,026$ 5 Firestopping (L&M)1,547$ 6 Unload & distribute Metal Doors & Frames (L)1,402$ 7 Unload & distribute Interior Aluminum Frames (L)1,539$ 8 Unload & distribute Plastic Laminate Faced Wood Doors (L)1,462$ 9 Install Access Doors (L & M)1,807$ 10 Unload & distribute Door Hardware (L)3,741$ 11 Install Louvers (L)214$ 12 Floor Preparation (L & M)6,016$ 13 Floor Protection (L & M)5,486$ 14 Install Corner Guards (L)898$ 15 Install Knox Box (L & M)902$ 16 Install Residential Appliances (L)1,411$ 17 Final Grading (L & M)4,301$ 18 Haul Off Spoils 12,860$ 19 Remove strip/clean paving joints (L)1,335$ 20 Backfill curbs (L)1,855$ 21 Install Irrigation Sleeves (L & M)642$ TOTAL 74,555$ TRAINING & EDUCATION BUILDING SELF PERFORMED WORK ITEMS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘G’ City of Pearland Public Safety Building Renovations & Training and Education Building SELF PERFORMED WORK ITEMS 32 Labor Rates: Per Hour Semi-skilled Labor $27.00 Skilled Labor $30.00 Foreman/Operator $34.00 No.Description of Scope Total 1 Owner Furnished Items 2,552$ 2 Miscellaneuos Steel (L)2,480$ 3 Rough Carpentry (L & M)6,137$ 4 Firestopping (L&M)453$ 5 Unload & distribute Metal Doors & Frames (L)1,402$ 6 Unload & distribute Plastic Laminate Faced Wood Doors (L)1,462$ 7 Install Access Doors (L & M)981$ 8 Unload & distribute Door Hardware (L)1,621$ 9 Floor Preparation (L & M)4,110$ 10 Floor Protection (L & M)6,341$ 11 Install Corner Guards (L)513$ 12 Install Residential Appliances (L)321$ TOTAL 28,374$ PUBLIC SAFETY BUILDING SELF PERFORMED WORK ITEMS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘I’ City of Pearland Public Safety Building Renovations & Training and Education Building COST SAVING ITEMS 33 The following cost saving items for the Training & Education Building project have been accepted by the Owner and the Design Team and are included in the GMP pricing. DEDUCT ACCEPTED 8 (5,195)$ 8.4 Delete Break in Curtain Wall Frames FM9 and FM10 at Training & Education Building. Frames Shall be One Unit Measuring 14'w x 14'h (5,195) (5,195)$ 9 (29,989)$ 9.1 16' Markerboards (1 EA) in Lieu of Dry Erase Wall Covering at South Conference Room Wall (5,475) (5,475)$ 9.2 2" Thick Fabric Wrapped (Guildford of Maine FR-701) Acoustical Wall Panels in Lieu of Copolymer Panels (17,125) (17,125)$ 9.5 Ceramic Wall Tile at Restrooms to only 5' (4' Field Wall Tile w/ 1' Accent Band) with Paint Above in Lieu of Full Height Wall Tile (7,389) (7,389)$ 22 (22,154)$ 22.2 Delete Insulation of All Cold Water Piping. Insulat first 8' Insude Exterior Walls Only (3,000)$ (3,000)$ 22.3 Provide Two-Band Anaco No-Hub Couplings in Lieu of Four-Band (500)$ (500)$ 22.4 Remove One Wall Hydrant at North Side of Building on One Wall Hydrant at South Side of Building (2 Total)(1,500)$ (1,500)$ 22.5 Provide KITZ Domestic Water and Gas Valves in Lieu of NIBCO (1,500)$ (1,500)$ 22.6 Alternate Shower Fixture Manufacturer for SH-1 and SH-2 (Manufacturer: Leonard 7600 Series)(2,654)$ (2,654)$ 22.7 Non-ASME Gas Water Heater (GWH-1) in Lieu of ASME Gas Water Heater (GWH-1)(2,500)$ (2,500)$ 22.8 Non-ASME Gas Water Heater Expansion Tank in Lieu of ASME Gas Water Heater Expansion Tank (500)$ (500)$ 22.9 Delete CAD As-Builts and BIM for Plumbing (4,000)$ (4,000)$ 22.11 Use Schedule 80 CPVC Pipe above Ceiling for Hot and Cold Water, Copper in Walls.(6,000)$ (6,000)$ 23 (8,619)$ 23.1 Delete 3D Shop Drawings and BIM from HVAC Scope (3,800)$ (3,800)$ 23.5 Delete CAD As-Builts for HVAC (1,000)$ (1,000)$ 23.8 Deduct for Adjustable Elbows in Lieu of Stamped Elbows for Duct at Training & Education Building (346)$ (346)$ 23.9 Deduct for 1m in Lieu of Atco Flexible Duct (473)$ (473)$ 23.15 JCI Split Systems: FCU-1 through FCU-7 - Galvanized Drain Pan in Lieu of Stainless Steel at Training & Education Building (3,000)$ (3,000)$ 26 (24,200)$ 26.2 Base Bid Generator: Standard ATS in Lieu of Bypass ATS (9,000)$ (9,000)$ 26.8 Metal Clad Cable in Lieu of EMT Rough-In at Interior Drywall Walls and Daisey Chain MC for Fixtures at Training & Education Building (8,000)$ (8,000)$ 26.10 Device Ring and Pull String for Voice/Data Cabling in Lieu of Conduit at Training & Education Building (6,000)$ (6,000)$ 26.12 Code Compliant Fittings and Elbows (Rigid 90 w/ Insulating PVC Tape or Rigid Schedule 80 PVC Elbow) in Lieu of PVC Coated Rigid Steel 90 (1,200)$ (1,200)$ 32 (72,822)$ 32.2 Solid Sod and Topsoil with Irrigation in Lieu of 2,241 SF of Synthetic Turf at East-North of Building (32,122) (32,122)$ 32.3 Solid Sod and Topsoil with Irrigation in Lieu of 2,771 SF of Synthetic Turf at East-South of Building (40,700) (40,700)$ SUB TOTAL (162,979)$ (162,979)$ #DESCRIPTION - Training & Education Building COST SAVINGS ITEMS PLUMBING OPENINGS FINISHES Total Accepted - Cost Saving Items HVAC ELECTRICAL EXTERIOR IMPROVEMENTS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘I’ City of Pearland Public Safety Building Renovations & Training and Education Building COST SAVING ITEMS 34 The following cost saving items for the Public Safety Building Renovations project have been accepted by the Owner and the Design Team and are included in the GMP pricing. DEDUCT ACCEPTED 8 (7,784)$ 8.3 Delete all Interior Door Transoms and Associated Glazing (2,281) (2,281)$ 8.5 Delete EOC Sliding Aluminum Door System (FM5 @ Opening 2085B) and Replace with 3'w Storefront Door and Frame (5,503) (5,503)$ 9 (4,810)$ 9.3 Delete Pony Wall and Solid Surface Wall Cap at Court 1201 (3,048) (3,048)$ 9.6 Acoustical Lay-In Ceiling in Lieu of Drywall Furdown Accent in Training Room 2131 (1,762) (1,762)$ 26.9 Metal Clad Cable in Lieu of EMT Rough-In at Interior Drywall Walls and Daisey Chain MC for Fixtures at Public Safety Building (2,000)$ (2,000)$ 26.11 Device Ring and Pull String for Voice/Data Cabling in Lieu of Conduit at Public Safety Building Renovations (2,500)$ (2,500)$ SUB TOTAL (17,094)$ (17,094)$ #DESCRIPTION - Public Safety Building Renovations COST SAVINGS ITEMS OPENINGS FINISHES Total Accepted- Cost Saving Items DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘I’ City of Pearland Public Safety Building Renovations & Training and Education Building COST SAVING ITEMS 35 The following cost saving items have not been accepted by the Owner and the Design Team and are not included in the GMP pricing. These items are pending Owner approval and may be accepted before issuance of Notice to Proceed. Durotech will assume these cost saving items are rejected by the Owner, and therefore void, if not notified by the Owner in writing of their acceptance before issuance of Notice to Proceed. DEDUCT COULD BE ACCEPTED 1 (184,369)$ 1.1a Builder's Risk Insurance by Owner (114,768) (114,768)$ Not availible if 1.1b is accepted 1.1b Builder's Risk Insurance by Durotech Excluding Wind and Flood Coverage (69,601) (69,601)$ Not availible if 1.1a is accepted 3 (12,160)$ 3.1 Delete South Parking Stall Row (12,160) (12,160)$ 9 (39,904)$ 9.4 Delete All Work Associated with Build-Out of IT Office Rooms 2082, 2082A, 2082B, 2082C, 2082D (39,904) (39,904)$ 22 (9,000)$ 22.11 Use Schedule 80 CPVC Pipe above Ceiling, Copper in Walls. and Fittings with 3-Piece George Fisher Ball Valves in Lieu of Nibco Valves (9,000)$ (9,000)$ 23 (473)$ 23.9 Deduct for 1m in Lieu of Atco Flexible Duct (473)$ (473)$ 26 (26,000)$ 26.14 Delete UPS at Training & Education Building - Rack Mounted UPS by Owner (26,000)$ (26,000)$ SUB TOTAL (271,906)$ (271,906)$ Total "Could-Be Accepted" - Cost Saving Items HVAC ELECTRICAL PLUMBING FINISHES GENERAL REQUIREMENTS CONCRETE #DESCRIPTION - Could Be Accepted Before Issuance of Notice to Proceed COST SAVINGS ITEMS REMARKS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A Jameson Appel Digitally signed by Jameson Appel DN: C=US, E=jappel@pearlandtx.gov, O=City of Pearland, OU=Projects, CN=Jameson Appel Date: 2022.10.03 17:07:45-05'00' DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A 10/4/2022 | 9:28 AM CDT Date:ct-^22By,Date:ContractorOwner*Contractor agrees to perform change(s) included in this Change Order for the price and time indicated. The prices for changes included all costs associated with tliis ChangeOrder.No work is to be done until tliis change order is executed. No payment to tlie Contractor (or Consultant) shall be made for work included in tlie ctiange order until the Contractor'spay estimate is updated.Revise tlie project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, tliis Change Order governs. Uponexecution by all parties, tlie following cliaiigcs identified for tlie contract value and/or contract time shown, are made part of flie contract.DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A10/4/2022 | 9:38 AM CDT 1 11931 Wickchester Lane ● Suite 205 ● Houston, Texas 77043-4501 Phone: 281.558.6892 ● Fax: 281.496.5637 Date: August 26, 2022 Mr. Jameson Appel Assistant Director of Capital Projects Engineering & Public Works City of Pearland 2016 Old Alvin Rd. Pearland, Texas 77581 Re: Guaranteed Maximum Price for Public Safety Building Renovations & Training and Education Building Projects (aka Pearland Public Safety Projects) Dear Mr. Appel: We wish to inform you that after working together with Joiner Architects on these facilities, we have formally advertised and solicited proposals for the development of the GMP for the Pearland Public Safety Projects. Subcontractor & vendor proposals were received on July 22, 2022. After careful review and compilation of these proposals, Durotech, Inc. is pleased to present the following: Public Safety Training & Education Building $ 4,780,850 Public Safety Building Renovations $ 1,263,087 Total GMP (Training & Education Building + PSB Renovations) $ 6,043,937 It is our recommendation that we ask the City Council of The City of Pearland approve the Guaranteed Maximum Price of $6,043,937 and execute GMP Amendment No. 1 between The City of Pearland and Durotech, Inc. We are excited about the potential of entering into the construction phase of these projects and want to thank you and your team, Joiner Architects and their consultants for a very successful pre-construction phase. Durotech is committed to the citizens of Pearland, Texas in the successful delivery of the Pearland Public Safety Projects. Thank you and The City of Pearland for selecting Durotech as its building partner. It is our goal to meet and exceed your expectations. Should you have any questions please do not hesitate to contact me. Sincerely, David Rowe CEO 'David Rowe CEO DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A 2 11931 Wickchester Lane ● Suite 205 ● Houston, Texas 77043-4501 Phone: 281.558.6892 ● Fax: 281.496.5637 GMP SUMMARY Project: Pearland Public Safety Projects Consisting of: 1. Public Safety Building Renovations 2. Public Safety Training & Education Building Location: 2555 Cullen Blvd., Pearland, TX 77581 8333 Freedom Dr., Pearland, TX 77581 Owner: The City of Pearland, Texas Scope of work: THE PROJECT: The Work of Project is defined by the Contract Documents and consists of the following: 1. Major renovations to convert the existing Fire Station No. 4 into the Public Safety Training and Education Building. The Public Safety Training and Education Building includes a large conference room, break room area, fitness area to be shared by Police and Fire, office area, and associated restroom/shower facilities . The work also includes new electrical, mechanical, plumbing, communications, and security systems. Exterior renovations include metal roof replacement and painted brick. 2. Select interior renovations to both levels of the existing Public Safety Building including security upgrades, office revisions, building partitioning, and department modifications. 3. All work or portions of work necessary to provide complete facilities as represented in the Drawings and Specifications, including, but not limited to, architectural and structural building components, architectural finishes, mechanical equipment and ducting, plumbing piping and fixtures, electrical equipment and fixtures, fire alarm, security, and communications. GMP Proposal Package: The GMP proposal package consists of the following items: 1. Exhibit A – GMP Top Sheet – dated 26 August 2022 2. Exhibit B – Project Manual – dated 06 July 2022 3. Exhibit C – List of Drawings – dated 06 July 2022 4. Exhibit D – List of Addendums 5. Exhibit E – Qualifications & Assumptions 6. Exhibit F – Allowance Schedule 7. Exhibit G – Self Performed Work Items 8. Exhibit I – Cost Saving Items DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT 'A' PROJECT: LOCATION: OWNER: ARCHITECT: DATE: SECTION DESCRIPTION REMARKS TRAINING & EDUCATION PSB RENOVATIONS TOTAL 01 21 00 SIGNAGE ALLOWANCE 40,000 0 40,000 01 21 00 STATION ALTERTING SYSTEM ALLOWANCE 50,000 0 50,000 01 21 00 PLANTING BEDS ALLOWANCE 0 0 0 Deleted - In 32 80 00 & 32 90 00 01 21 00 CM CONTINGENCY ALLOWANCE 180,000 20,000 200,000 01 21 00 DOOR HARDWARE ALLOWANCE 70,000 20,000 90,000 01 43 39 MOCKUP PANEL 1,500 0 1,500 01 51 19 EQUIPMENT FUEL & FUEL TANK 3,580 0 3,580 01 54 16 MATERIAL HANDLING & HOISTING 14,320 1,500 15,820 01 54 23 TEMPORARY SCAFFOLDING / SHORING 13,919 0 13,919 01 55 26 TRAFFIC CONTROL 1,568 0 1,568 01 56 26 TEMPORARY FENCING 7,613 0 7,613 01 57 00 EROSION & SEDIMENT CONTROL 15,309 0 15,309 01 64 00 OWNER FURNISHED ITEMS 6,062 2,552 8,614 01 71 23 FIELD ENGINEERING & LAYOUT 0 0 0 01 74 13 PROGRESS CLEANING 11,258 6,928 18,186 01 74 16 SITE MAINTENANCE/CLEAN STREETS 8,243 0 8,243 01 74 19 CONSTRUCTION WASTE MANAGEMENT 7,176 3,626 10,802 01 74 23 FINAL CLEANING 4,550 4,220 8,770 DIV 02 EXISTING CONDITIONS 02 21 00 SURVEYS 3,150 0 3,150 02 41 13 SITE DEMOLITION 29,865 0 29,865 02 41 19 BUILDING DEMOLITION 85,761 35,055 120,816 02 70 00 PUMP & DEWATER 1,500 0 1,500 DIV 03 CONCRETE 03 20 00 CONCRETE REINFORCING 0 0 0 In 03 30 00 - Cast-in-Place Concrete 03 30 00 CAST-IN-PLACE CONCRETE 202,700 5,000 207,700 DIV 04 MASONRY 04 05 19 MASONRY REBAR 0 0 0 In 04 20 00 - Masonry 04 20 00 MASONRY 42,000 0 42,000 DIV 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING 35,825 0 35,825 05 12 50 STRUCTURAL STEEL ERECTION 46,708 0 46,708 05 37 00 PREPARE EXPOSED STRUCTURE 4,159 0 4,159 05 50 00 MISCELLANEOUS STEEL 5,980 2,480 8,460 05 50 10 TIMBER MATS 4,583 0 4,583 DIV 06 WOOD, PLASTICS, AND COMPOSITES 06 10 00 ROUGH CARPENTRY 14,071 6,137 20,208 06 22 00 MILLWORK 57,000 40,000 97,000 06 60 00 PLASTIC FABRICATIONS 1,026 0 1,026 DIV 07 THERMAL AND MOISTURE PROTECTION 07 11 00 DAMPPROOFING 34,771 0 34,771 07 21 00 THERMAL INSULATION 2,567 0 2,567 07 41 00 METAL ROOF PANELS 0 0 0 In 07 52 00 - Modified Bit Roofing 07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING 134,337 0 134,337 07 54 00 THERMOPLASTIC MEMBRANE ROOFING 0 12,357 12,357 OWNER'S TOPSHEET - CITY OF PEARLAND PUBLIC SAFETY GMP TOPSHEET City of Pearland Public Safety Projects 8333 Freedom Dr. / 2555 Cullen Pkwy - Pearland, TX 77581 City of Pearland, Texas Joiner Architects 8/26/2022 3 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT 'A' SECTION DESCRIPTION REMARKS TRAINING & EDUCATION PSB RENOVATIONS TOTAL GMP TOPSHEET 07 84 00 FIRESTOPPING 1,547 453 2,000 07 92 00 JOINT SEALANTS 9,940 2,356 12,296 DIV 08 OPENINGS 08 08 00 DOOR & HARDWARE INSTALLATION 5,100 3,577 8,677 08 11 00 METAL DOORS & FRAMES 30,970 27,997 58,967 08 12 00 INTERIOR ALUMINUM FRAMES 1,539 0 1,539 08 14 23 PLASTIC LAMINATE FACED WOOD DOORS 1,462 1,462 2,924 08 31 00 ACCESS DOORS AND PANELS 1,807 981 2,788 08 33 00 COILING DOORS & GRILLES 16,431 0 16,431 08 71 00 DOOR HARDWARE 3,741 1,621 5,362 08 80 00 GLAZING 205,425 34,858 240,283 08 80 10 TEMPORARY ENCLOSURES 5,792 0 5,792 08 80 15 CLEAN GLASS 683 190 873 08 91 00 LOUVERS 1,714 0 1,714 DIV 09 FINISHES 09 24 00 CEMENT PLASTERING 15,500 0 15,500 09 29 00 GYPSUM BOARD 171,075 118,268 289,343 09 30 00 TILING 68,909 14,974 83,883 09 51 00 ACOUSTICAL CEILINGS 82,075 13,925 96,000 09 60 00 FLOOR PREPARATION 6,016 4,110 10,126 09 60 10 FLOOR PROTECTION 5,486 6,341 11,827 09 62 00 RESILIENT ATHLETIC FLOORING 20,327 0 20,327 09 62 05 MOISTURE CONTROL ALLOWANCE 22,750 0 22,750 09 65 00 RESILIENT FLOORING 40,287 56,351 96,638 09 67 00 FLUID-APPLIED FLOORING 784 0 784 09 84 00 ACOUSTIC WALL PANELS 0 0 0 In 09 51 00 - Acoustical Ceilings 09 90 00 PAINTING & COATING 48,845 50,950 99,795 DIV 10 SPECIALTIES 10 11 00 VISUAL DISPLAY UNITS 0 5,700 5,700 10 14 00 SIGNAGE 0 0 0 In 01 21 00 - Signage Allowance 10 21 13 TOILET COMPARTMENTS 8,518 0 8,518 10 21 16 SHOWER & DRESSING COMPARTMENTS 0 0 0 In 08 80 00 - Glazing 10 21 23 CUBICLE CURTAINS & TRACK 0 0 0 None 10 26 13 CORNER GUARDS 5,596 882 6,478 10 28 13 TOILET ACCESSORIES 4,887 350 5,237 10 44 00 FIRE PROTECTION SPECIALTIES 750 0 750 10 44 15 KNOX BOX 902 0 902 10 51 13 METAL LOCKERS 6,780 0 6,780 10 51 23 PLASTIC LAMINATE CLAD LOCKERS 0 0 0 In 06 22 00 - Millwork 10 51 53 LOCKER ROOM BENCHES 1,115 0 1,115 10 71 13 EXTERIOR SUN CONTROL DEVICES 0 0 0 In 10 73 00 - Protective Covers 10 73 00 PROTECTIVE COVERS 82,980 0 82,980 10 75 00 FLAGPOLES 13,825 0 13,825 DIV 11 EQUIPMENT 11 31 00 RESIDENTIAL APPLIANCES 23,461 8,291 31,752 11 40 00 FOODSERVICE EQUIPMENT 0 134,231 134,231 11 66 23 GYMNASIUM EQUIPMENT 17,062 0 17,062 DIV 12 FURNISHINGS 12 21 00 WINDOW BLINDS 0 2,370 2,370 12 24 00 WINDOW SHADES 19,865 0 19,865 DIV 13 SPECIAL CONSTRUCTION DIV 14 CONVEYING EQUIPMENT DIV 21 FIRE SUPPRESSION 21 10 00 FIRE SUPPRESSION SYSTEMS 65,465 13,989 79,454 DIV 22 PLUMBING 22 00 00 PLUMBING 212,500 25,000 237,500 DIV 23 HVAC 23 00 00 HVAC 515,384 133,523 648,907 4 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT 'A' SECTION DESCRIPTION REMARKS TRAINING & EDUCATION PSB RENOVATIONS TOTAL GMP TOPSHEET 23 00 10 HVAC FILTER CHANGES 2,750 1,500 4,250 23 05 00 MEP COORDINATION 4,240 2,120 6,360 DIV 25 INTEGRATED AUTOMATION DIV 26 ELECTRICAL 26 00 00 ELECTRICAL 795,375 242,100 1,037,475 26 00 05 ROUGH IN/BACK BOXES - LOW VOLTAGE 9,100 4,400 13,500 26 41 00 LIGHTNING PROTECTION 0 0 0 In 26 00 00 - Electrical DIV 27 COMMUNICATIONS 27 10 00 STRUCTURED CABLING 26,525 24,554 51,079 27 41 16 INTEGRATED AUDIO-VIDEO SYSTEMS & EQUIPMENT 0 0 0 A/V By Owner DIV 28 ELECTRONIC SAFETY & SECURITY 28 13 00 ACCESS CONTROL SYSTEM 76,240 19,250 95,490 28 23 00 VIDEO SURVEILLANCE SYSTEM 0 0 0 In 28 13 00 - Access Control 28 31 00 FIRE DETECTION & ALARM SYSTEM 36,374 12,028 48,402 DIV 31 EARTHWORK 31 20 00 EARTHWORK 58,650 0 58,650 31 22 16 FINAL GRADING 4,301 0 4,301 31 23 10 HAUL OFF SPOILS 12,860 0 12,860 31 63 29 DRILLED CONCRETE PIERS & SHAFTS 0 0 0 In 03 30 00 - Cast-in-Place Concrete DIV 32 EXTERIOR IMPROVEMENTS 32 01 11 CLEAN PAVING & SIDEWALKS 3,258 0 3,258 32 13 75 REMOVE STRIP/CLEAN PAVING JOINTS 1,335 0 1,335 32 16 15 BACKFILL CURBS 1,857 0 1,857 32 17 23 PAVEMENT MARKINGS 4,900 0 4,900 32 18 13 SYNTHETIC GRASS SURFACING 146,454 0 146,454 32 31 00 FENCES & GATES 25,860 0 25,860 32 80 00 IRRIGATION 15,661 0 15,661 32 80 10 IRRIGATION SLEEVES 642 0 642 32 90 00 LANDSCAPING 49,537 0 49,537 DIV 33 UTILITIES 33 00 00 SITE UTILITIES 89,300 0 89,300 35 00 00 PUNCH LIST 10,393 - 10,393 ACCEPTED COST SAVINGS (162,979) (17,094) (180,073) SUB TOTAL - COST OF WORK ITEMS 4,101,029 1,111,463 5,212,492 GENERAL CONDITIONS PER RFP 237,055 - 237,055 ADDITIONAL GENERAL CONDITIONS (BR / GL / BONDS)99,039 60,843 159,882 PERMIT - CITY OF PEARLAND - - - AGC FEES 7,921 2,645 10,566 QMS/SAFETY 14,224 3,760 17,984 MATERIAL ESCALATION CONTINGENCY 82,021 22,229 104,250 SUBTOTAL - COST OF WORK 4,541,289 1,200,939 5,742,228 FEE 229,335 60,647 289,983 PRECONSTRUCTION FEE 10,226 1,500 11,726 TOTAL GMP 4,780,850 1,263,087 6,043,937 5 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 6 PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS Document 00 00 01 - Title Page Document 00 00 02 - Table of Contents Document 00 10 00 - Notice for Subcontractor Proposals Document 00 12 00 - Sub Proposal Form Document 00 21 10 - Instructions to Subcontractor-Vendor Proposers Document 00 21 11 - Sample Insurance Certificate Document 00 45 23 - Affidavit of Non-Asbestos, Lead, and PCB Use in Project (Project Close-Out) Document 00 45 25 - Statutory Lien Waiver Forms Document 00 61 00 - Insurance and Bonds Document 00 61 10 - Contract Documents Document 00 72 00 - General Conditions Document 00 73 00 - Supplementary Conditions Document 00 73 43 - Prevailing Wage Rates SPECIFICATIONS DIVISION 01 - GENERAL REQUIREMENTS Section 01 11 00 - Summary of Work Section 01 12 00 - Owner Provided Supplementary Documents Geotechnical Report No. AHA 19-105-00 Section 01 13 00 - Mechanical and Electrical Coordination Section 01 14 00 - Contractor’s Use of Premises Section 01 19 00 - Codes, Regulations and Standards Section 01 21 00 - Allowances Section 01 25 00 - Applications for Payment Section 01 26 00 - Contract Modification Procedures Section 01 26 13 - Request for Interpretation Section 01 29 10 - Change Order Procedures Section 01 31 00 - Project Management and Coordination Section 01 31 06 - Coordination Drawings Section 01 31 10 - Coordination and Meetings Section 01 32 00 - Construction Progress Documentation Section 01 33 00 - Submittal Procedures Section 01 33 10 - BIM Coordination Section 01 33 10.2 - Technical Submittal Procedures Section 01 38 00 - Construction Photographs Section 01 39 00 - Contractor’s Quality Control Section 01 40 00 - Quality Requirements DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 7 Section 01 42 00 - Definitions and Abbreviations Section 01 42 10 - References Section 01 44 00 - Observation Services Section 01 45 29 - Testing Laboratory Services Section 01 50 00 - Temporary Facilities and Controls Section 01 50 50 - Mobilization Section 01 53 20 - Temporary Tree and Plant Protection Section 01 55 00 - Stabilized Construction Exit Section 01 55 40 - Street Signs Section 01 55 50 - Traffic Control Section 01 56 20 - Waste Material Disposal Section 01 56 40 - Control of Ground Water and Surface Water Section 01 56 50 - TDPS Requirements Section 01 56 66 - Source Controls for Erosion and Sedimentation Section 01 57 13 - Fabric Filter Fence Section 01 57 20 - Reinforced Filter Fabric Barrier Section 01 58 00 - Project Signs Section 01 60 00 - Product Options and Substitutions Section 01 60 10 - Material and Equipment Section 01 63 10 - Substitution Request Form Section 01 71 23 - Field Engineering Section 01 73 00 - Execution Section 01 73 29 - Cutting & Patching Section 01 74 00 - Warranties Section 01 74 19 - Waste Water Disposal Section 01 75 00 - Starting Systems Section 01 76 00 - Project Record Document Section 01 77 00 - Closeout Procedures DIVISION 02 - EXISTING CONDITIONS Section 02 41 19 - Selective Demolition DIVISION 03 - CONCRETE Section 03 30 00 - Concrete Construction for Structures Section 03 30 10 - Cast-In-Place Concrete Section 03 45 00 - Architectural Precast Concrete DIVISION 04 - MASONRY Section 04 20 00 - Unit Masonry Assemblies DIVISION 05 - METALS Section 05 12 00 - Structural Steel Section 05 50 00 - Miscellaneous Metals DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 8 DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES Section 06 10 00 - Rough Carpentry DIVISION 07 - THERMAL AND MOISTURE PROTECTION Section 07 10 50 - Under-Slab Vapor Retarder Section 07 13 10 - Shower Stall Waterproofing Section 07 21 00 - Building Insulation Section 07 41 13 - Standing Seam Metal Roof Panels Section 07 62 00 - Sheet Metal Flashing, Gutters, Downspouts, and Trim Section 07 72 00 -Roof Accessories Section 07 84 13 - Penetration Firestopping Section 07 92 00 - Joint Sealants DIVISION 08 - OPENINGS Section 08 11 13 - Hollow Metal Doors and Frames Section 08 12 16 - Interior Aluminum Frames Section 08 14 16 - Flush Wood Doors Section 08 31 00 - Access Doors Section 08 33 10 - Overhead Coiling Insulated Doors Section 08 41 10 - Aluminum Storefronts Section 08 42 13 - Aluminum Entrances Section 08 71 00 - Door Hardware Section 08 80 00 - Glazing Section 08 83 00 - Mirrors Section 08 91 00 - Metal Louvers Section 08 91 10 - Aluminum Curtain Wall DIVISION 09 - FINISHES Section 09 24 00 - Lath and Plaster Section 09 25 00 - Gypsum Board Assemblies Section 09 30 13 - Ceramic Tiling Section 09 51 13 - Acoustical Panel Ceilings Section 09 54 26 - Wood Panel Ceiling Section 09 62 05 - Moisture Control Section 09 65 13 - Resilient Base & Accessories Section 09 65 19 - Resilient Tile Flooring Section 09 65 66 - Resilient Athletic Flooring Section 09 68 16 - Carpeting Section 09 72 00 - Wall Covering Section 09 77 00 - Dry Erase Wall Covering Section 09 79 50 - Concrete Floor Sealer Section 09 84 13 - Acoustical Wall Panels DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 9 Section 09 91 00 – Painting DIVISIONS 10 - SPECIALTIES Section 10 11 00 - Visual Display Surfaces Section 10 21 13.21 - Solid Color Reinforced Composite Toilet Partitions Section 10 26 00 - Wall Protection and Recessed Corner Guards Section 10 28 13 - Toilet Accessories Section 10 28 80 - Glass Shower Enclosures Section 10 41 00 - Knox Box Section 10 43 00 - Exterior Signage Section 10 44 00 - Interior Signage Section 10 51 30 - Metal Lockers Section 10 52 00 - Fire Protection Specialties Section 10 71 13 - Exterior Sun Control Devices Section 10 73 16 - Aluminum Canopies Section 10 99 00 - Miscellaneous Specialties DIVISIONS 11 THROUGH - EQUIPMENT Section 11 30 00 - Residential Appliances Section 11 48 10 - Protection Padding DIVISION 12 - FURNISHINGS Section 12 21 24 - Electric Roller Shade System Section 12 21 24.1 - Manual Roller Shade System Section 12 30 00 - Manufactured Casework Section 12 36 61 - Quartz Countertops DIVISION 13 - SPECIAL CONSTRUCTION - (Not Used) DIVISION 14 - CONVEYING EQUIPMENT - (Not Used) DIVISION 21 - FIRE SUPPRESSION Section 21 00 00 - Fire Protection Section 21 02 01 - Coordination Drawings Section 21 05 29 - Hangers and Supports for Fire Suppression Piping and Equipment Section 21 13 13 - Wet Pipe Sprinkler System DIVISION 22 - PLUMBING Section 22 02 00 - Basic Materials and Methods Section 22 02 01 - Coordination Drawings Section 22 03 00 - Plumbing Demolition for Remodeling Section 22 05 13 - Common Motor Requirements for Plumbing Equipment Section 22 05 16 - Expansion Fittings and Loops for Plumbing Piping DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 10 Section 22 05 29 - Hangers and Supports for Plumbing Piping and Equipment Section 22 05 48 - Vibration and Seismic Controls for Plumbing Piping Section 22 05 53 - Identification for Plumbing Piping Equipment Section 22 07 19 - Plumbing Piping Insulation Section 22 08 00 - Commissioning of Plumbing Systems Section 22 10 00 - Plumbing Piping Section 22 11 19 - Plumbing Specialties Section 22 11 21 - Natural Gas Piping Systems Section 22 30 00 - Plumbing Equipment Section 22 40 00 - Plumbing Fixtures DIVISION 23 - HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) Section 23 02 00 - Basic Materials and Methods Section 23 02 01 - Coordination Drawings Section 23 05 13 - Common Motor Requirements for HVAC Equipment Section 23 05 16 - Expansion Fittings and Loops for HVAC Piping Section 23 05 29 - Hangers and Supports for Piping and Equipment for HVAC Section 23 05 48 - Vibration and Seismic Controls for HVAC Piping and Equipment Section 23 05 53 - Identification for HVAC Piping and Equipment Section 23 05 93 - Testing, Adjusting, and Balancing Section 23 07 13 - Duct Insulation Section 23 07 16 - HVAC Equipment Insulation Section 23 07 19 - HVAC Piping Insulation Section 23 08 00 - Commissioning of HVAC Systems Section 23 09 00 - Building Control System for HVAC Section 23 21 13 - Above Ground Hydronic Piping Section 23 23 00 - Refrigerant Piping Section 23 31 13 - Metal Ductwork Section 23 33 00 - Ductwork Accessories Section 23 34 00 - HVAC Fans Section 23 37 13 - Air Distribution Devices Section 23 37 23 - HVAC Gravity Ventilators Section 23 41 00 - Air Filters Section 23 62 13 - Air Cooled Condensing Units Section 23 81 26 - Split System Air Conditioners - Wall Mounted Section 23 82 19 - Fan Coil Unit Section 23 82 39 - Electric Unit Heaters DIVISIONS 24 AND 25 - Not Used DIVISION 26 - ELECTRICAL Section 26 02 00 - Basic Materials and Methods Section 26 02 01 - Coordination Drawings DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 11 Section 26 03 00 - Demolition Work Section 26 03 13 - Electrical Demolition for Remodeling Section 26 05 19 - Wire, Cable, and Related Materials Section 26 05 26 - Grounding Section 26 05 33 - Raceways Section 26 05 73 - Short Circuit, Coordination Study, ARC Flashing Hazard Analysis Section 26 08 00 - Commissioning of Electrical Systems Section 26 21 13 - Electrical Service Entrance Section 26 24 16 - Panelboards Section 26 27 26 - Wiring Devices Section 26 28 13 - Fuses Section 26 28 16 - Safety and Disconnect Switches Section 26 29 26 - Miscellaneous Electrical Controls and Wiring Section 26 32 13 16 - (250kW) Natural Gas Engine-Driven Standby Generator Section 26 33 53 - Uninterruptible Power Supply Section 26 43 13 - Surge Protective Device -Service Entrance Section 26 43 13 13 - Surge Protective Device- Standard Interrupting Section 26 51 00 13 - Lighting Fixtures (LED) DIVISIONS 27 - COMMUNICATIONS Section 27 02 00 - Basic Materials and Methods Section 27 05 26 - Grounding and Bonding for Communications Systems Section 27 05 28 - Pathways for Communications Systems Section 27 05 43 - Underground Ducts and Raceways for Communications Systems Section 27 11 00 - Communications Room Fittings Section 27 13 00 - Communications Backbone Cabling Section 27 15 00 - Communications Horizontal Cabling DIVISIONS 28 - ELECTRONIC SAFETY AND SECURITY Section 28 02 00 - Basic Materials and Methods Section 28 03 00 - Life Safety and Security Demolition for Remodeling Section 28 13 00 - Access Control System Section 28 20 00 - Video Surveillance System Section 28 46 00.21 - Fire Alarm System DIVISION 31 - EARTHWORK Section 31 11 00 - Clearing and Grubbing Section 31 22 00 - Earthwork Section 31 23 00 - Excavation Filling and Backfilling for Site Utilities Section 31 23 13- Subgrade Preparation Section 31 23 23.15 - Cement Sand Backfilling Section 31 23 43 - Trench Safety System DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘B’ City of Pearland Public Safety Building Renovations & Training and Education Building PROJECT MANUAL DATED JULY 6, 2022 12 Section 31 31 16 - Termite Control DIVISION 32 - EXTERIOR IMPROVEMENTS Section 32 11 13.13 - Lime Stabilization of Subgrade Section 32 13 13 - Portland Cement Concrete Pavement Section 32 16 13 - Concrete Curbs Section 32 17 13 - Concrete Pavement Joints Section 32 17 16 - Concrete Wheel Stops Section 32 17 23 - Pavement Markings Materials Section 32 18 13 - Synthetic Grass Surfacing Section 32 20 10 - Concrete Sidewalks Section 32 31 19 - Metal Panel Gates Section 32 31 20 - Ornamental Metal Fence and Gates Section 32 84 00 - Irrigation System Section 32 90 00 - Landscape Planting Section 32 92 00 - Turf and Grasses DIVISION 33 - UTILITIES Section 33 05 13 - Manholes Section 33 05 23 - Jacking, Boring, or Tunneling Pipe Section 33 11 00 - Water Distribution Mains Section 33 31 00 - Sanitary Sewers Section 33 40 00 - Storm Drainage DIVISIONS 34 THROUGH 48 - (Not Used) END OF TABLE OF CONTENTS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 13 SAFETY TRAINING & EDUCATION BUILDING: CIVIL C001 GENERAL NOTES C002 DEMOLITION PLAN C003 DIMENSION CONTROL C100 GRADING & DRAINAGE C101 FLOODPLAIN ANALYSIS C200 UNDERGROUND UTILITIES C300 PAVING & JOINT LAYOUT C400 SWPPP C401 SWPPP DETAILS C500 CONSTRUCTION DETAILS C501 CONSTRUCTION DETAILS C502 CONSTRUCTION DETAILS C503 CONSTRUCTION DETAILS C504 CONSTRUCTION DETAILS C505 CONSTRUCTION DETAILS C506 CONSTRUCTION DETAILS C507 CONSTRUCTION DETAILS C508 CONSTRUCTION DETAILS C509 CONSTRUCTION DETAILS LANDSCAPE L001 LANDSCAPE NOTES & DETAILS L101 LANDSCAPE PLAN IR100 IRRIGATION PLAN ARCHITECTURAL A001 CODE ANALYSIS A002 TYPICAL SITE DETAILS A003 TYPICAL MOUNTING HTS A004 FENCE & GATE DETAILS A005 GENERAL NOTES A100 DEMOLITION SITE PLAN A101 ARCHITECTURAL SITE PLAN A200 DEMOLITION FLOOR PLAN A201 ARCHITECTURAL FLOOR PLAN A301 ROOF PLAN A401 EXTERIOR ELEVATIONS A501 WALL SECTIONS A601 ENLARGED PLANS & INTERIOR ELEVATIONS A701 COMPOSITE REFLECTED CEILING PLAN A801 MILLWORK DETAILS A802 MISCELLANEOUS DETAILS A901 FINISH SCHEDULE DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 14 A902 DOOR & FRAME TYPES & SCHEDULE A903 PARTITION TYPES STRUCTURAL S001 ABBREVIATIONS, SYMBOLS & SHEET INDEX S101 GENERAL NOTES S201 FOUNDATION PLAN S202 ROOF FRAMING PLAN S301 FOUNDATION DETAILS S401 FRAMING DETAILS MEP MEPD101 MEP DEMOLITION SITE PLAN MEP 101 MEP SITE PLAN MECHANICAL M001 MECHANICAL SYMBOL & LEGEND MD211 MECHANICAL DEMOLITION PLAN M211 MECHANICAL PLAN M501 MECHANICAL SCHEDULES M601 MECHANICAL DETAILS M701 MECHANICAL CONTROLS ELECTRICAL E001 ELECTRICAL SYMBOL & LEGEND ED211 ELECTRICAL DEMOLITION PLAN E401 ELECTRICAL ONE-LINE DIAGRAMS E501 ELECTRICAL SCHEDULES E502 ELECTRICAL SCHEDULES E601 ELECTRICAL DETAILS E602 ELECTRICAL DETAILS ED211 ELECTRICAL DEMOLITION PLAN EL211 ELECTRICAL LIGHTING PLAN EP211 ELECTRICAL POWER PLAN PLUMBING P001 PLUMBING SYMBOL & LEGEND P200 PLUMBING DEMOLITION PLAN P211 PLUMBING PLAN P212 PLUMBING PLAN - DOMESTIC WATER & GAS P401 PLUMBING RISER & NATURAL GAS P402 PLUMBING RISER SANITARY WASTE & VENT P501 PLUMBING SCHEDULES P502 PLUMBING SCHEDULES P601 PLUMBING DETAILS P602 PLUMBING DETAILS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 15 TECHNOLOGY T001 TECHNOLOGY GENERAL NOTES T100 TECHNOLOGY SITE PLAN T211 TECHNOLOGY DEMOLITION PLAN T212 TECHNOLOGY PLAN T301 TECHNOLOGY ENLARGED PLANS T601 TECHNOLOGY DETAILS T602 TECHNOLOGY DETAILS T603 TECHNOLOGY DETAILS PUBLIC SAFETY BUILDING RENOVATIONS: ARCHITECTURAL A001 CODE ANALYSIS A002 TYPICAL MOUNTING HEIGHTS A200 COMPOSITE DEMOLITION PLAN A200.1 DEMOLITION IMAGES A201 COMPOSITE FLOOR PLAN A202 ENLARGED FLOOR PLANS A601 INTERIOR ELEVATIONS/MILLWORK DTL A701 ENLARGED REFLECTED CEILING PLAN A901 FINISH SCHEDULE/DOOR & FRAME TYPES & SCHEDULE A902 PARTITION TYPES FOOD SERVICES K0 DEMOLITION PLAN K1 FS EQUIPMENT PLAN K1.1 FS FACILITY MODEL K1.2 FS EQUIPMENT MODEL K1.3 FS PLUMBING PLAN K1.4 FS ELECTRICAL PLAN K1.5 EXHUAST HOOD DRAWING K1.6 FS ELEVATIONS DETAILS MECHANICAL M001 MECHANICAL SYMBOL & LEGEND MD212 LEVEL 1 MECHANICAL DEMO PLAN – AREA B MD221 LEVEL 2 MECHANICAL DEMOLITION PLAN – AREA A MF222 LEVEL 2 MECHANICAL DEMOLITION PLAN – AREA B MD232 ROOF MECHANICAL DEMOLITION PLAN – AREA B M212 LEVEL 1 MECHANICAL PLAN – AREA B M221 LEVEL 2 MECHANICAL PLAN – AREA A M222 LEVEL 2 MECHANICAL PLAN – AREA B M232 ROOF MECHANICAL PLAN – AREA B M501 MECHANICAL SCHEDULES DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘C’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF DRAWINGS DATED JULY 6, 2022 16 M601 MECHANICAL DETAILS M701 MECHANICAL CONTROLS ELECTRICAL E001 ELECTRICAL SYMBOL & LEGEND E301 FOOD SERVICE ELECTRICAL PLAN E401 ELECTRICAL ONE-LINE DIAGRAMS E501 ELECTRICAL SCHEDULES E502 ELECTRICAL SCHEDULES E601 ELECTRICAL DETAILS EL212 LEVEL 1 LIGHTING PLAN – AREA B EL221 LEVEL 2 LIGHTING PLAN – AREA A EL222 LEVEL 2 LIGHTING PLAN – AREA B ELD212 LEVEL 1 LIGHTING DEMOLITION PLAN – AREA B ELD221 LEVEL 2 LIGHTING DEMOLITION PLAN – AREA A ELD222 LEVEL 2 LIGHTING DEMOLITION PLAN – AREA B EP212 LEVEL 1 POWER PLAN – AREA B EP221 LEVEL 2 POWER PLAN – AREA A EP222 LEVEL 2 POWER PLAN – AREA B EPD212 LEVEL 1 POWER DEMOLITION PLAN – AREA B EPD221M LEVEL 2 POWER DEMOLITION PLAN – AREA A EPD222M LEVEL 2 POWER DEMOLITION PLAN – AREA B PLUMBING P001 PLUMBING SYMBOL & LEGEND P301 ENLARGED FOOD SERVICE PLUMBING PLAN P302 LEVEL 2 PLUMBING PLAN – AREA B P501 PLUMBING SCHEDULES TECHNOLOGY T001 TECHNOLOGY GENERAL NOTES TD212 LEVEL 2 TECHNOLOGY DEMO PLAN – AREA A TD213 LEVEL 2 TECHNOLOGY DEMO PLAN – AREA B T211 LEVEL 1 TECHNOLOGY PLAN – AREA B T212 LEVEL 2 TECHNOLOGY PLAN – AREA A T213 LEVEL 2 TECHNOLOGY PLAN – AREA B T601 TECHNOLOGY DETAILS T602 TECHNOLOGY DETAILS T603 TECHNOLOGY DETAILS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘D’ City of Pearland Public Safety Building Renovations & Training and Education Building LIST OF ADDENDA 17 1. Addendum No. 1 Issued on July 13, 2022 2. Addendum No. 2 Issued on July 15, 2022 3. Addendum No. 3 Issued on July 18, 2022 4. Addendum No. 4 Issued on July 22, 2022 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 18 DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS 1. Excluded is Material Testing. 2. Excluded are City/MUD Fees, City/MUD Inspection Fees, and City/Mud Tap fees. 3. Excluded are Utility Assessment & Impact Fees. 4. Utility Company agreements (terms & conditions and costs), easements and coordination which will serve as the termination point for Durotech to make connections for building service shall be the responsibility of the Owner. 5. Off-site Utility Fees and Utility District Connection Fees (if any) to on-site utilities shall be the responsibility of the Owner. 6. Excluded are all building permit fees. Building permit fees, if any, are to be paid by the Owner. 7. Excluded are unforeseen underground conditions or obstructions not indicated in contract documents. 8. Without regard to any other provision of this Agreement, Owner shall be liable to Contractor for additional costs incurred by Contractor as the result of any governmental payroll tax or healthcare tax if the tax is applicable to the Project, the Project is not tax exempt from the specific tax and the tax became effective after the date of execution of the Contract. 9. Electronic Files and CAD Files will be provided by the Architect/Engineer of re cord for the purpose of preparing shop drawings and 3D models at no cost to the General Contractor and/or Subcontractors. A signed release will be required before electronic files are released by the Architect/Engineer. 10. Owner and Contractor agree that design and specification of systems, operating parameters, and materials is by Owner’s Architectural and Engineering consultants and that enforcement of warranties is contingent upon systems being maintained and operated in accordance with manufacturer recommendations. 11. Owner and Contractor agree that all manufacturer’s warranties, and subcontractor’s warranties which extend beyond Contractor’s warranty period, are hereby assigned to and run directly from the manufacturer to the Owner and from the subcontractor to the Owner, respectively. Owner accepts these assignments and warranties, and releases and discharges Contractor from any and all claims, liabilities, damages, costs and expenses arising out of such manufacturer’s warranties and any subcontractor’s extended warranties. 12. The Contractor’s warranty excludes remedy for damage or defect caused by abuse, material alteration to the work not executed by the Contractor, insufficient DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 19 maintenance, or maintenance not in compliance with manufacturer’s written recommendations. 13. Payment and Performance Bonds will be charged to the Owner based on the State of Texas regulated rate. 14. The Guaranteed Maximum Price provided is a not to exceed amount for the entire project scope. Individual line items within the project budget are not indi vidual Guaranteed Maximum Price amounts. 15. The GMP package is valid until September 13, 2022, with the assumption that the Owner will issue a Notice to Proceed and sign the GMP Amendment on or before the stated date. 16. Excluded is any Security Personnel/Watchman. Included are security cameras as required for the General Contractor’s jobsite office. 17. Architect will provide an “Issue for Construction” set of plans and specifications which will include the bid set, addenda, permit changes and accepted cost savings to Contractor within 14 days of NTP. All individual changes from the bid set will be clouded with a reference to the origin of the change (addendum number, permit changes, cost saving, etc.). 18. The proposed cost saving recommendations by Durotech, Inc. shall be subject to the review and approval of the Architect, Owner and the Owner’s Professional Consultants. Durotech, Inc. is not required to ascertain that the cost savings are in accordance with applicable laws, statutes, ordinances, codes, rules and regulations, or lawful orders of public authorities. The Contractors review of the proposed cost savings is in the capacity as a Construction Manager and not as a Design Professional. 19. All accepted Value Engineering/Voluntary Alternates is pending General Contractor’s review of revised contract documents. 20. For any delays caused by events outside of Contractor’s control, including but not limited to Acts of God, pandemics, epidemics, acts of governmental authorities, acts of civil authorities, acts of war or terrorism, unanticipated material shortages and price escalations, labor disputes and utilities delays, Owner shall grant additional time extensions and price increases to Contractor when properly documented, substantiated and approved by Owner, subject to Contractor’s right to dispute. 21. Section 00 73 00 – Supplementary Conditions: Excluded is the requirement of achieving substantial completion within 240 days after receipt of notice to proceed as referenced in paragraph 8.4. Due to unanticipated lead times for critical electrical and HVAC equipment, Durotech proposes to be substantially complete within 365 days after notice to proceed and receipt of building permits from the Owner except for DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 20 installation of the Uninterruptible Power Supplies (UPS) due to lead time constraints. All parties agree that installation of the UPS will not be a requirement for establishing Substantial Completion. The owner shall release all retainage for the entire value of work complete once Substantial Completion is established. Retainage may be held only for the value of work remaining after the substantial completion date. This qualification is based on the following equipment delivery lead times, and further unforeseen increase in lead times will require adjustment to the timeline previously stated: a. HVAC Equipment: 34-36 Weeks b. Main Distribution Panel: 36-38 Weeks c. Generator: 42-44 Weeks d. UPS: 85-100 Weeks 22. Section 00 73 00 – Supplementary Conditions: Excluded in its entirety is paragraph 11.2 regarding Owner’s Protective Liability Insurance. 23. Compensation for General Conditions costs, as defined by the contract, are included as part of the Guaranteed Maximum Price to the date of Substantial Completion. All General Conditions costs incurred after the date of Substantial Completion shall be considered Cost of Work. 24. Stipulated Billing Rates: No. Description Rate 1 General Liability/Umbrella Insurance Contract amount per thousand x $6.00 2 Builder’s Risk Insurance Contract amount/hundred x $0.012 x # of months 3 Project Executive $124.00 per hour 3 Project Manager $71.00 per hour 5 Estimator $98.00 per hour 4 Safety/Field Operation Manager $110.00 per hour 5 Superintendent $57.00 per hour 6 Asst. Superintendent $49.00 per hour 7 Project Engineer $44.00 per hour 8 Quality Control Inspector $80.00 per hour DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 21 9 Contract Administrator $61.00 per hour 10 BIM Coordinator $55.00 per hour 11 IT Coordinator $100.00 per hour 12 Intern $22.00 per hour 13 Labor Burden 42.5% 25. Billable rates will be subject to audit for hours worked only. 26. All labor burden rates from a subcontractor that are 42% or less are considered to be acceptable and not auditable. 27. The approval of any change requests that results in change orders or AEA is considered as final approval and are not subject to any audit mo dification. 28. Included are the following sub-limits and deductibles for Builder’s Risk Insurance: a. Training and Education Building: i. Sub Limit: Named Windstorm $4,925,000 ii. Sub Limit: Flood $1,000,000 iii. Sub Limit: Earth Movement $2,500,000 iv. Sub Limit: Soft Costs $25,000 v. Deductible: All Other Peril: $5,000 vi. Deductible: Earth Movement $25,000 vii. Deductible: Flood $25,000 viii. Deductible: Wind/Hail 5%/$25,000 ix. Deductible: Windstorm 5%/$25,000 x. Deductible: Water Damage $5,000 b. Public Safety Building Renovations: i. Sub Limit: Named Windstorm $1,225,000 ii. Sub Limit: Flood $1,000,000 iii. Sub Limit: Earth Movement $1,225,000 iv. Sub Limit: Soft Costs $25,000 v. Deductible: All Other Peril: $5,000 vi. Deductible: Earth Movement: $25,000 vii. Deductible: Flood $25,000 viii. Deductible: Wind/Hail 5%/$25,000 ix. Deductible: Windstorm 5%/$25,000 x. Deductible: Water Damage $5,000 DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 22 c. Builder’s Risk Insurance Premium will be paid by Durotech. Owner will be responsible for any deductibles if they should occur. DIVISION 01 – GENERAL REQUIREMENTS- 29. Excluded are any building windstorm inspections and/or certification. 30. Excluded is any cost for third-party Building Commissioning. Included is Building Commissioning coordination. 31. Excluded are any costs for generator rental and fuel for temporary power. We assume that we can tie into the existing electrical service for temporary power needs during construction. 32. All cost for use of utilities (power, water, sanitary) during construction will be paid for by Owner. 33. Excluded is any ground water control systems, well-point systems, eductor and ejector-type systems, deep wells, and piezometers or monitoring wells. 34. Excluded is any weekend or overnight work. All work will take place during normal business hours (7am – 5pm Monday through Friday). Durotech will have unhindered access to all areas where work is required during these hours for the entire project duration. Durotech will notify and coordinate with the owner when loud / noisy work will be necessary. 35. It is assumed that the Project Manual (Exhibit B) and the Drawings (Exhibit C) include the latest Design and Building Standards provided by the owner and have been reviewed by the Architect and their Consultants for compliance. 36. Section 01 40 00 – Quality Requirements: Excluded in its entirety is paragraph 1.6 J regarding 10’ x 10’ mockup. The majority of all exterior finishes are exiting to remain. Mock-ups, if needed, will be done on the building itself as construction progresses. DIVISION 02 – EXISTING CONDITIONS 37. Excluded is the removal and/or encapsulation of any and all asbestos, lead and other hazardous materials. The removal and/or encapsulation of all asbestos, lead and other hazardous materials will be the responsibility of the Owner and all costs of testing will be paid by the Owner. 38. Durotech recognizes the Owner’s first right of salvage. All items that the Owner intends to salvage must be removed before demolition is scheduled to start per the project schedule. Excluded is any cost and labor for the Owner’s salvage , transportation, and relocation/reinstallation operations. Included is salvaging of existing generator and relocation for storage to 2559 Hillhouse Rd., Pearland, TX 77584. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 23 39. All existing Fire Suppression, HVAC, Electrical, Communications, and Security equipment scheduled to remain or be reused is assumed to be in acceptable working condition. Durotech shall be entitled to additional cost and time for any required repairs or replacements of existing equipment in order to complete the work. 40. Owner will provide Durotech a clean and safe working environment, free from any environmental contamination and/or contaminates. Prior to and during construction, Owner shall maintain in the existing building(s) normal HVAC operations and habitable climatic conditions to prevent mold growth and/or other potential humidity related damages. If, during construction, Durotech encounters any known hazardous materials or mold, Durotech will notify the Owner immediately and cease all work in the potentially contaminated area. Owner agrees to indemnify Durotech from all damages, costs and expenses stemming from Owner’s failure to maintain normal HVAC operations and habitable climatic conditions. DIVISION 03 – CONCRETE 41. Included is approximately 5,122 SF of 2” fiberglass reinforced topping slab in the apparatus bay area to level the slab and meet ADA requirements for the use of the building. Any cost associated with additional floor leveling requirements discovered after demolition operations are complete will be paid for by the Owner. DIVISION 04 – MASONRY 42. Excluded are cast stone exterior window sills per detail 12/A802. Brick exterior window sills are existing and shall remain. DIVISION 05 – METALS 43. Excluded is any galvanizing of structural steel members in enclosed unconditioned space areas of the building. DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES DIVISION 07 – THERMAL AND MOISTURE PROTECTION 44. Included are the following Dampproofing materials: a. Henry Air Bloc 17 MR Fluid Applied Air Barrier b. Henry Blueskin SA Self Adhered Flexible Flashings DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 24 45. Section 07 21 00 – Building Insulation: Excluded is injected foam insulation for concrete masonry per paragraph 2.2.B. 46. Included is the following roofing scope and modified bituminous roofing materials at the Training & Education Building per consultation with Garland Company representative Mr. Blake Dieste: a. Remove existing roof in the area indicated on sheet A301. b. Install new Garland HPR Tri-base modified base sheet over existing concrete deck. c. Adhere new 1.5” flat stock and 1/8” per foot tapered sumps at roof drain assemblies, polyiso rigid insulation over the base sheet in Garland Insulock low rise foam adhesive. d. Adhere new ½” coverboard in Garland Insulock low rise foam adhesive. e. Install new Harland two ply modified bitumen roof system over coverboard. f. Shop fabricate and install new IMETCO 24-gauge galvalume parapet coping. g. Roof work operations will not void existing roof warranty. No new roof warranty is considered. 47. Section 07 41 13 – Prefinished Metal Roofing: Prefinished Metal Roofing scope of work shall include only the following: a. Remove existing roofing to existing wood deck at tower and to framing at mansard roofs. b. Install new ¾” CDX plywood over framing at mansard roofs and secure to existing framing. Excluded is any new framing; existing framing is assumed to be in acceptable condition. c. Install new IMETCO Aquablock 60 HT underlayment over new and existing plywood per manufacturer’s recommendations. d. Install new 24-gauge IMETCO galvalume standing seam roof system per manufacturer’s recommendations, including rakes, ridges, drip edges, hips, counter flashings, and receivers. e. Included is a 30-year No-Dollar-Limit warranty. 48. Included is the following TPO roofing scope of work and roofing materials for the Public Safety Building Renovations: a. Remove (1 EA) 2’ x 2’ roof curb, infill, and patch to match existing roof area as shown on sheet MED 2.32. b. Flash (4 EA) new 2’ x 2’ curbs as indicated on sheet ME 2.32. c. Roof work operations will not void existing roof warranty. No new roof warranty is considered. 49. Excluded is any cementitious sprayed fireproofing for steel columns, floor beams, roof beams, metal floor decks, and metal roof decks. 50. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 25 DIVISION 08 – OPENINGS 51. Section 08 71 00 – Door Hardware: Door hardware for all doors (PLAM, Hollow Metal, and Aluminum) will be included in Door Hardware Allowance as specified in Section 01 21 00 – Allowances. 52. Section 08 11 13 – Hollow Metal Doors and Frames: Included are hollow metal doors and frames as manufactured by Pearland Industries. 53. Section 08 33 00 – Rolling Shutters: Included is one (1 EA) Overhead Door Corporation Model 653 Allura Shutter with the following options: a. Solid aluminum curtain slat with powder coat finish b. Aluminum hood with finish to match curtain c. Aluminum guides for face of wall mount d. Tube motor with constant contact to close rocker switch 54. Section 08 41 10 – Aluminum Storefronts & Section 08 42 13 – Aluminum-Framed Entrances: Included are aluminum storefronts and aluminum-framed entrances as manufactured by Kawneer. 55. Section 08 80 00 – Glazing: Included is a single aluminum door and frame with 2’-0” side lights on each side at Public Safety Building opening 2112 as shown on enlarged floor plan detail 6/A202. 56. Excluded is field testing, of any kind, for aluminum framed storefronts and entrances. DIVISION 09 – FINISHES 57. Excluded are aluminum wrapped interior window sills per detail 12/A802. Included are drywall interior window sills. 58. Section 09 30 13 – Ceramic Tiling at Public Safety Building Renovations: Wall tile is included at Kitchen 2111 only. All other wall tile at Public Safety Building Renovations is excluded. Included are painted walls and/or vinyl wall covering (as applicable) at these areas. 59. Section 09 30 13 – Ceramic Tiling: Included are the following qualifications: a. F2 Floor Tiling – Included is 12”x24” Daltile Porcelain Tile Volume 1.0 b. F2A Floor Tiling – Included is 6”x6” Daltile Porcelain Tile Volume 1.0 c. W2 Wall Tiling at Drinking Fountains – Included is $5.00/SF material allowance. 60. Section 09 54 26 – Wood Panel Ceiling: Included is Armstrong Woodworks 6487 2’-0” x 6’-0” tegular in Natural Variations Beech finish ceiling tile in CertainTeed Black HD 9/16” grid system. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 26 61. Section 09 65 00 – Resilient Athletic Flooring: Included is 10% speckling intensity in lieu of 30% intensity as the specified Regupol ActivLok resilient athletic floor tile is only offered with 10% speckling intensity. DIVISION 10 – SPECIALTIES 62. Section 10 35 00 – Aluminum Flagpole: Included is one (1) 5’ x 8’ US flag, one (1) 5’ x 8’ Texas flag, and one (1) 5’ x 8’ City of Pearland flag. 63. Section 10 43 00 – Exterior Signage & Section 10 44 00 – Interior Signage: All exterior building signage or graphics, accessibility parking signs, interior room identification plaques, and other interior signage or graphics will be included in Signage Allowance as specified in Section 01 21 00 – Allowances. 64. Section 10 50 00 – Phenolic Lockers: This section is excluded in its entirety. Included are custom casework lockers at Lobby 100. 65. Section 10 51 30 – Metal Lockers: Included are six (6) 18” x 18” x 72” 2-tier lockers as manufactured by ASI to be located in Women Shower 113 and Men Shower 116. 66. 10 71 13 – Exterior Sun Control Devices: Included are Clear Anodized Sunscreen Canopies as manufactured by AVAdek with 8” tube rafters in lieu of 7” tube rafters and 8” airfoils in lieu of 9” airfoils. 67. 10 73 16 – Aluminum Canopies: Included is one (1) 62’ x 20’ Clear Anodized Aluminum Patio Canopy as manufactured by AVAdek. Excluded is any canopy soffit, color anodized finish, and painted finish. 68. Section 10 99 00 – Miscellaneous Specialties: Excluded are any Vaultek Smart Modular Storage Units. DIVISION 11 – EQUIPMENT 69. Section 11 30 00 – Residential Appliances: If the specified residential appliance models become unavailable or discontinued, an equal model will be provided in its place. Any additional cost due to this change will be paid for by the Owner. 70. Section 11 40 00 – Food Service Equipment: Included are the following due specification and drawing conflicts: a. Item #622 – Included is an AccuTemp electric griddle as specified and indicated on the electrical drawings. Excluded is any Dormont gas hose. b. Item #167 – Included are 16-gauge under shelves c. Item #196 – Included are 16-gauge under shelves d. Item # 249 – Included is sink with left and right drain boards as shown on the floor plan in lieu of specified right only drain board. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 27 71. Section 11 48 10 – Protection Padding: Included is 2’ x 5’ x 2” Class A Fire Rated Wall Padding as manufactured by Draper. DIVISION 12 – FURNISHINGS 72. Window Blinds for the Public Safety Building Renovation: Included are 1” Bali Classics .008” aluminum horizontal louver blinds. 73. Section 12 21 24 – Manual Roller Shade System: Manual Roller Shades will be surface mounted below ceiling with fascia to conceal roller tubes and brackets. Excluded are side and sill channels. 74. Section 12 21 24 – Electronic Intelligent Roller Shade System: Electronic Roller Shades will be surface mounted with fascia to conceal rollers and bracket. Included are MechoSystems IQ wall switch controls. Excluded are side channels, sill channels, and network controls. 75. Section 12 30 00 – Manufactured Casework: Included is casework as manufactured by Jericho Woodworks. 76. Section 12 30 00 – Manufactured Casework: Included are Wilsonart & Formica basic laminate colors. Excluded are any “Premium” laminate colors and finishes. 77. Section 12 36 61 – Quartz Countertops: Excluded are quartz countertops as manufactured by Vicostone. Included are 2cm thick Silestone quartz countertops in color levels 1 or 2. 78. Excluded is any transportation, loading, storage, unloading, assembly, or installation of furniture, appliances, or equipment labeled “by owner” or N.I.C. DIVISION 21 – FIRE SUPPRESSION 79. We assume that there will be adequate water supply with sufficient pressure available for the proper functioning of fire sprinkler systems and other systems. 80. Excluded is any exterior sprinkler system coverage such as canopy or porch areas. DIVISION 22 – PLUMBING DIVISION 23 – HVAC 81. Excluded is TAB - Testing, Air & Balancing. 82. Section 23 31 13 Metal Ductwork: Excluded is any duct cleaning per paragraph 3.8. Duct ends will be covered during construction. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 28 DIVISION 26 – ELECTRICAL DIVISION 27 – COMMUNICATIONS 83. Excluded are all IDF/MDF network switches, PoE switches, servers, routers, wireless access points (WAPs) and associated ancillary hardware and power supplies. 84. Excluded are all flat panel displays (TV). Included are Flat Panel Display Mounts per Section 10 99 00 – Miscellaneous Specialties and installation of the same. Installation of Flat Panel Displays to TV Mounts are by Owner. 85. Division 27 – Communications: Per City of Pearland standards, all communications cabling, associated hardware, and ancillary accessories shall be manufactured by Belden Solutions. 86. Excluded is all Integrated Audio-Visual Systems & Equipment, including, but not limited to, flat panel displays (TV), projectors, projector screens, smart boards, interactive displays, local sound systems, and intercommunication systems and devices. DIVISION 28 – ELECTRONIC SAFETY AND SECURITY 87. Excluded is any Intrusion Detection System; none specified. DIVISION 31 – EARTHWORK 88. Excluded is any casing or slurry drilling of piers. DIVISION 32 – EXTERIOR IMPROVEMENTS 89. Areas that receive Hydromulch will not be warranted for developing full turf grass. Owner understands that Hydro-mulch is a 2-season maintenance program requiring continuous maintenance including watering and fertilizer by the Owner. Areas that are not irrigated will not be warranted for grass or plant development and sustainability. Any temporary irrigation requirement by the contract will only be warranted to such date the temporary irrigation is removed. DIVISION 33 – UTILITIES 90. All required utility providers (Water, Sewer, Storm Discharge Point, Electric, Gas, Fiber, Phone Lines) are the responsibility of the Owner to coordinate and execute necessary agreements so that the utilities are installed per the contractor’s schedule for construction usage and systems startup. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘E’ City of Pearland Public Safety Building Renovations & Training and Education Building QUALIFICATIONS & ASSUMPTIONS 29 91. Domestic water meter, irrigation water meter and any wet connections/taps to be by City and paid directly by owner. 92. Excluded are any unforeseen subsurface conditions or obstructions as it relates to the utility installation. Any additional cost, including materials, labor, or equipment, required to mitigate hindrances to the installation of these system caused by unforeseen subsurface conditions or obstructions will be substantiated for which Durotech, Inc. will be entitled to an equitable adjustment of the contract sum. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘F’ City of Pearland Public Safety Building Renovations & Training and Education Building ALLOWANCE SCHEDULE 30 Allowances per Specifications: 1. Signage Allowance $ 40,000 2. Station Alerting System Allowance $ 50,000 3. CM Contingency Allowance $200,000 4. Door Hardware Allowance $ 90,000 Other Allowances: 1. Planting beds allowance has been deleted and is excluded. DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘G’ City of Pearland Public Safety Building Renovations & Training and Education Building SELF PERFORMED WORK ITEMS 31 The following scope items will be self-performed by Durotech, Inc. and will be billed against the contract based upon the proposal submitted to and accepted by the owner and will be treated as a lump sum sub-contract amount. Labor Rates: Per Hour Semi-skilled Labor $27.00 Skilled Labor $30.00 Foreman/Operator $34.00 No.Description of Scope Total 1 Owner Furnished Items 6,062$ 2 Miscellaneuos Steel (L)5,980$ 3 Rough Carpentry (L & M)14,071$ 4 Plastic Fabrications (L & M)1,026$ 5 Firestopping (L&M)1,547$ 6 Unload & distribute Metal Doors & Frames (L)1,402$ 7 Unload & distribute Interior Aluminum Frames (L)1,539$ 8 Unload & distribute Plastic Laminate Faced Wood Doors (L)1,462$ 9 Install Access Doors (L & M)1,807$ 10 Unload & distribute Door Hardware (L)3,741$ 11 Install Louvers (L)214$ 12 Floor Preparation (L & M)6,016$ 13 Floor Protection (L & M)5,486$ 14 Install Corner Guards (L)898$ 15 Install Knox Box (L & M)902$ 16 Install Residential Appliances (L)1,411$ 17 Final Grading (L & M)4,301$ 18 Haul Off Spoils 12,860$ 19 Remove strip/clean paving joints (L)1,335$ 20 Backfill curbs (L)1,855$ 21 Install Irrigation Sleeves (L & M)642$ TOTAL 74,555$ TRAINING & EDUCATION BUILDING SELF PERFORMED WORK ITEMS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘G’ City of Pearland Public Safety Building Renovations & Training and Education Building SELF PERFORMED WORK ITEMS 32 Labor Rates: Per Hour Semi-skilled Labor $27.00 Skilled Labor $30.00 Foreman/Operator $34.00 No.Description of Scope Total 1 Owner Furnished Items 2,552$ 2 Miscellaneuos Steel (L)2,480$ 3 Rough Carpentry (L & M)6,137$ 4 Firestopping (L&M)453$ 5 Unload & distribute Metal Doors & Frames (L)1,402$ 6 Unload & distribute Plastic Laminate Faced Wood Doors (L)1,462$ 7 Install Access Doors (L & M)981$ 8 Unload & distribute Door Hardware (L)1,621$ 9 Floor Preparation (L & M)4,110$ 10 Floor Protection (L & M)6,341$ 11 Install Corner Guards (L)513$ 12 Install Residential Appliances (L)321$ TOTAL 28,374$ PUBLIC SAFETY BUILDING SELF PERFORMED WORK ITEMS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘I’ City of Pearland Public Safety Building Renovations & Training and Education Building COST SAVING ITEMS 33 The following cost saving items for the Training & Education Building project have been accepted by the Owner and the Design Team and are included in the GMP pricing. DEDUCT ACCEPTED 8 (5,195)$ 8.4 Delete Break in Curtain Wall Frames FM9 and FM10 at Training & Education Building. Frames Shall be One Unit Measuring 14'w x 14'h (5,195) (5,195)$ 9 (29,989)$ 9.1 16' Markerboards (1 EA) in Lieu of Dry Erase Wall Covering at South Conference Room Wall (5,475) (5,475)$ 9.2 2" Thick Fabric Wrapped (Guildford of Maine FR-701) Acoustical Wall Panels in Lieu of Copolymer Panels (17,125) (17,125)$ 9.5 Ceramic Wall Tile at Restrooms to only 5' (4' Field Wall Tile w/ 1' Accent Band) with Paint Above in Lieu of Full Height Wall Tile (7,389) (7,389)$ 22 (22,154)$ 22.2 Delete Insulation of All Cold Water Piping. Insulat first 8' Insude Exterior Walls Only (3,000)$ (3,000)$ 22.3 Provide Two-Band Anaco No-Hub Couplings in Lieu of Four-Band (500)$ (500)$ 22.4 Remove One Wall Hydrant at North Side of Building on One Wall Hydrant at South Side of Building (2 Total)(1,500)$ (1,500)$ 22.5 Provide KITZ Domestic Water and Gas Valves in Lieu of NIBCO (1,500)$ (1,500)$ 22.6 Alternate Shower Fixture Manufacturer for SH-1 and SH-2 (Manufacturer: Leonard 7600 Series)(2,654)$ (2,654)$ 22.7 Non-ASME Gas Water Heater (GWH-1) in Lieu of ASME Gas Water Heater (GWH-1)(2,500)$ (2,500)$ 22.8 Non-ASME Gas Water Heater Expansion Tank in Lieu of ASME Gas Water Heater Expansion Tank (500)$ (500)$ 22.9 Delete CAD As-Builts and BIM for Plumbing (4,000)$ (4,000)$ 22.11 Use Schedule 80 CPVC Pipe above Ceiling for Hot and Cold Water, Copper in Walls.(6,000)$ (6,000)$ 23 (8,619)$ 23.1 Delete 3D Shop Drawings and BIM from HVAC Scope (3,800)$ (3,800)$ 23.5 Delete CAD As-Builts for HVAC (1,000)$ (1,000)$ 23.8 Deduct for Adjustable Elbows in Lieu of Stamped Elbows for Duct at Training & Education Building (346)$ (346)$ 23.9 Deduct for 1m in Lieu of Atco Flexible Duct (473)$ (473)$ 23.15 JCI Split Systems: FCU-1 through FCU-7 - Galvanized Drain Pan in Lieu of Stainless Steel at Training & Education Building (3,000)$ (3,000)$ 26 (24,200)$ 26.2 Base Bid Generator: Standard ATS in Lieu of Bypass ATS (9,000)$ (9,000)$ 26.8 Metal Clad Cable in Lieu of EMT Rough-In at Interior Drywall Walls and Daisey Chain MC for Fixtures at Training & Education Building (8,000)$ (8,000)$ 26.10 Device Ring and Pull String for Voice/Data Cabling in Lieu of Conduit at Training & Education Building (6,000)$ (6,000)$ 26.12 Code Compliant Fittings and Elbows (Rigid 90 w/ Insulating PVC Tape or Rigid Schedule 80 PVC Elbow) in Lieu of PVC Coated Rigid Steel 90 (1,200)$ (1,200)$ 32 (72,822)$ 32.2 Solid Sod and Topsoil with Irrigation in Lieu of 2,241 SF of Synthetic Turf at East-North of Building (32,122) (32,122)$ 32.3 Solid Sod and Topsoil with Irrigation in Lieu of 2,771 SF of Synthetic Turf at East-South of Building (40,700) (40,700)$ SUB TOTAL (162,979)$ (162,979)$ #DESCRIPTION - Training & Education Building COST SAVINGS ITEMS PLUMBING OPENINGS FINISHES Total Accepted - Cost Saving Items HVAC ELECTRICAL EXTERIOR IMPROVEMENTS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘I’ City of Pearland Public Safety Building Renovations & Training and Education Building COST SAVING ITEMS 34 The following cost saving items for the Public Safety Building Renovations project have been accepted by the Owner and the Design Team and are included in the GMP pricing. DEDUCT ACCEPTED 8 (7,784)$ 8.3 Delete all Interior Door Transoms and Associated Glazing (2,281) (2,281)$ 8.5 Delete EOC Sliding Aluminum Door System (FM5 @ Opening 2085B) and Replace with 3'w Storefront Door and Frame (5,503) (5,503)$ 9 (4,810)$ 9.3 Delete Pony Wall and Solid Surface Wall Cap at Court 1201 (3,048) (3,048)$ 9.6 Acoustical Lay-In Ceiling in Lieu of Drywall Furdown Accent in Training Room 2131 (1,762) (1,762)$ 26.9 Metal Clad Cable in Lieu of EMT Rough-In at Interior Drywall Walls and Daisey Chain MC for Fixtures at Public Safety Building (2,000)$ (2,000)$ 26.11 Device Ring and Pull String for Voice/Data Cabling in Lieu of Conduit at Public Safety Building Renovations (2,500)$ (2,500)$ SUB TOTAL (17,094)$ (17,094)$ #DESCRIPTION - Public Safety Building Renovations COST SAVINGS ITEMS OPENINGS FINISHES Total Accepted- Cost Saving Items DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A EXHIBIT ‘I’ City of Pearland Public Safety Building Renovations & Training and Education Building COST SAVING ITEMS 35 The following cost saving items have not been accepted by the Owner and the Design Team and are not included in the GMP pricing. These items are pending Owner approval and may be accepted before issuance of Notice to Proceed. Durotech will assume these cost saving items are rejected by the Owner, and therefore void, if not notified by the Owner in writing of their acceptance before issuance of Notice to Proceed. DEDUCT COULD BE ACCEPTED 1 (184,369)$ 1.1a Builder's Risk Insurance by Owner (114,768) (114,768)$ Not availible if 1.1b is accepted 1.1b Builder's Risk Insurance by Durotech Excluding Wind and Flood Coverage (69,601) (69,601)$ Not availible if 1.1a is accepted 3 (12,160)$ 3.1 Delete South Parking Stall Row (12,160) (12,160)$ 9 (39,904)$ 9.4 Delete All Work Associated with Build-Out of IT Office Rooms 2082, 2082A, 2082B, 2082C, 2082D (39,904) (39,904)$ 22 (9,000)$ 22.11 Use Schedule 80 CPVC Pipe above Ceiling, Copper in Walls. and Fittings with 3-Piece George Fisher Ball Valves in Lieu of Nibco Valves (9,000)$ (9,000)$ 23 (473)$ 23.9 Deduct for 1m in Lieu of Atco Flexible Duct (473)$ (473)$ 26 (26,000)$ 26.14 Delete UPS at Training & Education Building - Rack Mounted UPS by Owner (26,000)$ (26,000)$ SUB TOTAL (271,906)$ (271,906)$ Total "Could-Be Accepted" - Cost Saving Items HVAC ELECTRICAL PLUMBING FINISHES GENERAL REQUIREMENTS CONCRETE #DESCRIPTION - Could Be Accepted Before Issuance of Notice to Proceed COST SAVINGS ITEMS REMARKS DocuSign Envelope ID: F913E924-0F23-48D1-A00D-20DAF575171A