R2006-053 04-04-06
RESOLUTION NO. R2006-53
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, AUTHORIZING THE CITY MANAGER OR HIS DESIGNEE TO
ENTER INTO AN ADVANCED FUNDING AGREEMENT WITH THE STATE
OF TEXAS FOR IMPROVEMENTS TO THE OLD ALVIN BRIDGE.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That certain Advance Funding Agreement by and between the City of
Pearland and the State of Texas, a copy of which is attached hereto as Exhibit "A" and
made a part hereof for all purposes, is hereby authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute
and the City Secretary to attest an Advance Funding Agreement with the State of Texas,
for improvements to the Old Alvin Bridge
PASSED, APPROVED and ADOPTED this the 24th day o~ A.D., 2006
c= ~i ~
TOM REID
MAYOR
ATTEST:
APPROVED AS TO FORM:
UJ~ Ii . ~
DARRIN M. COKER
CITY ATTORNEY
Resolution 2006-53
4/24/06
CSJ: 0912-31-129
District: Houston
Code Chart 64: 32150
Project: BR 2001(692)
NBI Structure No. 120200MO 1825003
ORe<<;~NAL
STATE OF TEXAS ~
COUNTY OF TRAVIS ~
CONSTRUCTION AND MAINTENANCE AGREEMENT
For Bridee Replacement or Rehabilitation
Off the State System
AMENDMENT NO. 1
THIS Advance Funding Agreement Amendment (the Amendment) is made by and between
the State of Texas, acting by and through the Texas Department of Transportation, hereinafter
called the "State", and the City of Pearland, acting by and through its duly authorized officials,
hereinafter called the "Local Government."
THIS Amendment relates to the local match fund participation requirement being based solely
on the estimate of project direct cost included in this Amendment.
WITNESSETH
WHEREAS, the State and the Local Government executed an agreement on the 16th day of May
2002 to effectuate the project to replace or rehabilitate the deficient 2 lane wide bridge located on
a public road or street on Old Alvin Road at Drainage Ditch, hereinafter called the Project; and
WHEREAS, the previously executed agreement provides for the Local Government match fund
participation requirement to be based on the actual project cost; and
WHEREAS, Texas Administrative Code, Title 43, Section 15.52 (3)(C) provides for the Local
Government match fund participation requirement to be based solely on the estimated project
direct cost; and
WHEREAS, if the local match fund participation percentage requirement has been adjusted for
Economically Disadvantaged County CEDC) consideration under the provisions of Texas
Transportation Code Section 222.053, the required local match fund participation for this project
has been adjusted to N/A percent as authorized by Texas Transportation
Commission Minute Order number N/ A , dated N/ A ; and
Bridge- Bridge_AS
Rev 01/09/06
Page 1 - 4
Bridge Division
6-2001-A.2
CSJ: 0912-31-129
District: Houston
Code Chart 64: 32150
Project: BR 2001(692)
NBI Structure No. 120200MO 1825003
WHEREAS, if under the previously executed agreement the required local match fund
participation included payment by the Local Government of a portion of the State's indirect costs
for the project items that are eligible for State or Federal participation, such payment(s) for
indirect costs not already received by the State, may be waived under the provisions of Texas
Government Code Section 2106.08; and
WHEREAS, the Local Government has requested that the State expand the scope of the Project
to include widening of the Old Alvin Road Bridge at Drainage Ditch and the roadway
approaches to the bridge to 4 lanes, to match the Local Government's plans to widen Old Alvin
Road to 4 lanes both north and south of the bridge; and
WHEREAS, the Local Government agrees that the execution of this amendment affirms that the
widening of Old Alvin Road to 4 lanes has been approved in their current capital improvement
plan, as described in the resolution or ordinance, which is attached hereto and made a part hereof
as Attachment E; and
WHEREAS, the State will provide a proportional share of the bridge replacement widening
costs as described in Attachment D; and
WHEREAS, if one or more advance funding payments have already been received by the State
from the Local Government in accordance with the previously executed agreement, including
payment for any of the State's indirect costs for the project items that are eligible for State or
Federal participation, and, while no portion of these payments can be reimbursed to the Local
Government, such payments should be credited against the Local Government's match fund
participation requirement as provided for under this agreement amendment.
NOW THEREFORE, in consideration of the premises and of the mutual covenants and
agreements of the parties hereto, the State and the Local Government do agree as follows.
AGREEMENT
Article 1. Description of Amendment Items
Amendment Item A. - Agreement Article 13, Local Project Sources and Uses of Funds is
amended to add the following sub-articles relating to the funding responsibilities of the Local
Government regarding the additional widening of the Old Alvin Road Bridge.
m. The Local Government shall be responsible for completing the widening of Old Alvin
Road from McHard Road to East Orange Street to 4 lanes within five (5) calendar years
of completion of the Old Alvin Road Bridge construction project. A notice of
completion of work shall be delivered to the State's District Engineer no later than
thirty (30) calendar days after the widening of Old Alvin Road to 4 lanes is completed.
Bridge- Bridge_AS
Rev 01/09/06
Page 2 - 4
Bridge Division
6-2001-A.2
CSJ: 0912-31-129
District: Houston
Code Chart 64: 32150
Project: BR 2001(692)
NBI Structure No. 120200M01825003
n. Failure by the Local Government to complete the widening of Old Alvin Road to 4
lanes within the stated five-year period shall result in the Local Government being
responsible for one hundred percent (100%) of the cost difference associated with the
constructing a 2 lane bridge versus a 4 lane bridge on Old Alvin Road at the Drainage
Ditch. The cost difference is depicted in Attachment D to this agreement.
Article 2.
The state auditor may conduct an audit or investigation of any entity receiving funds from the
state directly under the contract or indirectly through a subcontract under the contract.
Acceptance of funds directly under the contract or indirectly through a subcontract under this
contract acts as acceptance of the authority of the state auditor, under the direction of the
legislative audit committee, to conduct an audit or investigation in connection with those funds.
An entity that is the subject of an audit or investigation must provide the state auditor with access
to any information the state auditor considers relevant to the investigation or audit.
Article3.
All other provisions of the original agreement are unchanged and remain in full force and effect.
Article 4. Signatory Warranty
The signatories to this amendment warrant that each has the authority to enter into this
agreement on behalf of the organization they represent.
IN TESTIMONY HEREOF, the parties hereto have caused these presents to be executed in
duplicate counterparts.
THE LOCAL GOVERNMENT
By:
~~
Signature
Bill Eisen
Printed Name of Signatory
Title: Ci ty Manager
Date: Apri 1 24. 2006
Bridge- Bridge_AS
Rev 01/09/06
Page 3 - 4
Bridge Division
6-2001-A.2
CSJ: 0912-31-129
District: Houston
Code Chart 64: 32150
Project: BR 2001(692)
NBI Structure No. 120200M01825003
THE STATE OF TEXAS
Executed for the Executive Director and approved for the Texas Transportation Commission for
the purpose and effect of activating and/or carrying out the orders, established policies or work
programs heretofore approved and authorized by the Texas Transportation Commission.
By:
~~R.
William R. Cox, P.E.
Director, Bridge Division
~
Date:
r;;-1-CJ(p
Bridge- Bridge_AS
Rev 01/09/06
Page 4 - 4
Bridge Division
6-2001-A.2
CSJ: 0912-31-129
District: Houston
Code Chart 64: 32150
Project: BR 2001(692)
NBI Structure No. 120200M01825003
EXHIBIT D
ESTIMATE OF DIRECT COSTS
(NOTE: This estimate supersedes any and all those that may have been provided previously for this project.)
Estimated Cost
Local Government
Participation
Preliminary Engineering (PE)
(1) $88,301
Ten (10) Percent or EDC Adjusted Percent
of PE for Local Government Participation
(3)
$8,830
Construction Cost to Widen Old Alvin Bridge
(F our Lane Bridge)
$883,011
$97,131
(2) $980,142
Engineering and Contingency (E&C)
The Sum of Construction and E&C
Ten (10) Percent or EDC Adjusted Percent
of the Sum of Construction and E&C for
Local Government Participation
(4)
$98,014
Amount of Advance Funds Paid by Local
Government *
(5)
($7,760)
Balance of Local Government Participation
to be Paid
(3+4-5) $99,084
Total Project Direct Cost (1+2) $1,068,443
Cost for a two lane bridge in Original Agreement (6) $627,375
Difference in cost for 2 lane vs. 4 lane
Bridge ** (1+2-6) $441,068
* Credited Against Local Government Participation
** Failure by the Local Government to complete the widening of Old Alvin Road within the five-
year period shall result in the Local Government being responsible for one hundred percent (100%)
of the cost difference associated with the constructing a 2 lane bridge versus a 4 lane bridge on Old
Alvin Road at the Drainage Ditch.