R2004-135 05-23-06 TABLED
TABLED
5/23/06
RESOLUTION NO. R2004-135
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF PEARLAND,
TEXAS, APPROVING CHANGE ORDER NO.4 ASSOCIATED WITH THE
CONSTRUCTION OF TRAFFIC IMPROVEMENTS AT THE INTERSECTION
OF PEARLAND PARKWAY AND FM 518.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That change order No. 4 associated with the construction of traffic
improvements at the intersection of Pearland Parkway and FM 518, a copy of which is
attached hereto as Exhibit "A" and made a part hereof for all purposes, is hereby
authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute
and the City Secretary to attest Change Order NO.4 associated with the construction of
traffic improvements at the intersection of Pearland Parkway and FM518.
PASSED, APPROVED and ADOPTED this the 23rd day of
A.D., 2004.
August
TOM REID
MAYOR
ATTEST:
YOUNG LORFING, TRMC
CITY SECRETARY
APPROVED AS TO FORM:
DARRIN M. COKER
CITY ATTORNEY
TurnerCollie@'Braden Inc.
EXHIBIT
Engineers. Planners. Project Managers
'c
D
D
5
'A"
Change Order
Owner:
August 11, 2004
City of Pearl and
Date:
Change Order No.4
Contractor: Windsor Contracting LLC
Amount:
$33,643.00
Engineer:
Turner Collie & Braden Inc.
Job Name:
Mobility and Drainage Bond Program - Misc.
Road Improvements Projects Group 3
052.511256.0005
Bid No. B2004-040
Job No.:
Contract:
Amount Time
Days Comp Date
Original Contract $270,119.25 10/1/2004
Previous Change Orders No. 1,2& 3 $13,450.00 8 N/A
Current Change Order # 4 $33,643.00 21 N/A
Current Contract $317,212.25 29 10/30/2004
The terms of the Agreement, dated 4/12/04, between Owner and Contractor are amended as follows:
Description of Changes
I) Extend the southbound left turn Jans on Pearland Parkway at the Broadway Intersection. The left turn lane will be
extended approximately 250 ft. to the median cut for the Lowe's Site.
APPROVED BY: OWNER
ACCEPTED BY : CONTRACTOR
By:
By:
Company:
Company:
Title:
Title:
Date:
Date:
Fonn Date: 9i11/200 1
TurnerCollie0Braden Inc.
Engineers. Planners. Project Managers
Construction Change Order
Date:
August 11, 2004
Job Name:
Mobility and Drainage Bond Program - Misc.
Road Improvements Projects Group 3
052.511256.0005
Bid No. B2004-040
Change Order No. 4
Job No.:
Contract:
Description of Changes
CHANGE ORDER TABULATION
ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE NET CHANGE
4 Traffic Control 1 LS $2,500.00 $2,500.00
9 Roadway Excavation 265 CY $7.00 $1,855.00
25 12" Cement Stablized Sub grade 349 SY $12.00 $4,188.00
30 6" Concrete Curb 300 LF $4.00 $1,200.00
CO # 4-1 Remove Concrete Pavement 1 LS $700.00 $700.00
CO # 4-2 Full Depth Saw Cut 280 LF $7.00 $1,960.00
CO # 4-3 9" Concrete Pavement 320 SY $50.00 $16,000.00
CO # 4-4 Relocate Trees 20 EA $150.00 $3,000.00
CO # 4-5 Irrigation Line I 1/2" 50 LF $10.00 $500.00
CO # 4-6 Irrigation Linc I" 80 LF $10.00 $800.00
CO # 4-2 Irrigation Line 1/2" 90 LF $10.00 $900.00
CO # 4-2 Sprinkler Heads 8 EA $5.00 $40.00
TOTAL $33,643.00
Fonll Date: 9/1112001