HomeMy WebLinkAboutR2021-161 2021-08-23RESOLUTION NO. R2021-161 A Resolution of the City Council of the City of Pearland, Texas, approving a change order with SpawGlass Corp., in the amount of $271,204 46, associated with the West Pearland Library (Shadow Creek Parkway). BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS Section 1 That certain change order associated with the West Pearland Library Project, a copy of which is attached hereto as Exhibit "A" and made a part hereof for all purposes, is hereby authorized and approved Section 2. That the City Manager or his designee is hereby authorized to execute and the City Secretary to attest the change order associated with the West Pearland Library Project. PASSED, APPROVED and ADOPTED this the 23rd day of August, A.D , 2021 EVIN COLE MAYOR AT CR • TAL ' OAN, TRMC, CMC CITY SECRETARY APPROVED AS TO FORM DARRIN M COKER R CITY ATTORNEY \v Date of Issuance: 07/30/2021 Contractor: SpawGlass Consultant: PGAL CITY OF PEARLAND PROJECTS DEPARTMENT 3519 Liberty Drive, Suite 300 Pearland, TX 77581 www.cityofpearland.com/projects CHANGE ORDER Shadow Creek Library CMAR Change Order No.: CoP Project No.: P.O. No.: 2 FA1805-CMAR 2020-00000893 Explanation: This change order encompasses the following: Change order for the new library facility includes upgrading facility fixtures to hands free units per the City's Covid-19 pandemic response plan, adding additional interior security cameras to the first floor multi -purpose rooms in use afterhours, changes trellis roofing material from fiberglass to a perforated metal material for the exterior amphitheater, upgrading shrub species to meet and exceed Shadow Creek Ranch Management Association height requirements and increase sidewalk width from 6 feet to a 10 -foot shared path to match the forthcoming sidewalk improvement project along Shadow Creek Parkway. This change order also extends the contract completion time to December 31, 2021. Description of Work 1 Add Item No. 0.00, "" 2 Add Item No. 58.00, "Hands Free Fixtures" 3 Add Item No. 59.00, "Perforated Metal Roof" 4 Add Item No. 60.00, "Multi -Purpose Security Cameras" 5 Add Item No. 61.00, "Perimeter Site Landscaping" 6 Add Item No. 62.00, "Sidewalk Width Expansion" Please attach back-up documentation. Cost & Time Change Summary Original Contract: Previous Change Order(s): Contract prior to this Change Order: Net increase (decrease) from this Change Order: Revised Contract: Finance Approval: RECOMMENDED: By: Cost Time $- $ 92,280.00 $ 79,490.02 $ 10,134.44 $ 30,300.00 $ 36,250.00 Cost $ 859,833.00 $ 15,141,618.00 $ 16,001,451.00 $ 248,454.46 $ 16,249,905.46 Date 09/02/2021 RECOMMENDED: By: - Consultant Construction Manager ACCEPTED*: APPROVED: By: Date 09/02/2021 By: Contractor Owner Date 0 Days 0 Days 0 Days 0 Days 0 Days 0 Days Time 0 Days 0 Days 0 Days 0 Days 0 Days 09/15/2021 Date 09/02/2021 Date 09/15/2021 Admin 1 of 3 6. Revised 7/25/08 Date of Issuance: 07/30/2021 Contractor: SpawGlass Consultant: PGAL CITY OF PEARLAND PROJECTS DEPARTMENT 3519 Liberty Drive, Suite 300 Pearland, TX 77581 www.cityofpearland.com/projects CHANGE ORDER Shadow Creek Library CMAR Change Order No.: CoP Project No.: P.O. No.: 2 FA1805-CMAR 2020-00000893 *Contractor agrees to perform change(s) included in the Change Order for the price and time indicated. The prices for changes included all costs associated with this Change Order. No work is to be done until this change order is executed. No payment to the Contract (or Consultant) shall be made for work included in the change order until the Contractor's pay estimate is updated. Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, this Change Order governs. Upon execution by all parties, the following changes identifies for the contract value and/or contract time shown, are made part of the contract. Admin 2 of 3 6. Revised 7/25/08 CHANGE ORDER NO. 2 ATTACHMENT "A" PROJECT: Shadow Creek Library CMAR PROJECT NO.: July 30, 2021 FA1805-CMAR ORIGINAL CONTRACT REVISED CONTRACT ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL QTY UNIT COST TOTAL NET CHANGE ADD ITEM(S) TO CONTRACT: Concrete 62.00 Sidewalk Width Expansion LS Electronic Safety & Security 60.00 Multi -Purpose Security LS Cameras Exterior Improvements 61.00 Perimeter Site LS Landscaping Fixtures 58.00 Hands Free Fixtures LS Metals 59.00 Perforated Metal Roof LS 0.00 AC 1 $36,250.00 $36,250.00 $36,250.00 1 $10,134.44 $10,134.44 $10,134.44 1 $30,300.00 $30,300.00 $30,300.00 1 $92,280.00 $92,280.00 $92,280.00 1 $79,490.02 $79,490.02 $79,490.02 0 $0.00 $0.00 $0.00 NET TOTAL CHANGE ORDER #2: ORIGINAL CONTRACT AMOUNT: CHANGE ORDER #2: REVISED CONTRACT AMOUNT: $248,454.46 $16,001,451.00 $248,454.46 $16,249,905.46 Admin 3 of 3 6. Revised 7/25/08