R2020-206 2020-10-12RESOLUTION NO. R2020-206
A Resolution of the City Council of the City of Pearland, Texas, amending a
Construction Manager at Risk contract with Durotech, to include the
Guaranteed Maximum Price (GMP) of $7,379,161.00 (inclusive of General
Conditions and Pre -Construction Services), for construction services
associated with the Fire Station No. 4 Project.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That the City Council hereby amends a Construction Manager at Risk
contract with Durotech, to include the Guaranteed Maximum Price (GMP) of $7,379,161.00, for
construction services associated with the Fire Station No. 4 Project.
Section 2. The City Manager or his designee is hereby authorized to execute an
amended Construction Manager at Risk contract for the Fire Station No. 4 Project.
PASSED, APPROVED and ADOPTED this the 12th day of October, A.D., 2020.
TOM REID
MAYOR
0
�- �,�r1NrINrRrgq
CR TAL ROAN, TRMC, CMC
CITY SECRETARY
APPROVED AS TO FORM:
DARRIN M. COKER
CITY ATTORNEY
Date of Issuance: 09/30/2020
Contractor: Durotech, Inc.
Consultant: Joiner Architects
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive, Suite 300
Pearland, TX 77581
www.cityofpearland.com/projects
CHANGE ORDER
Fire Station #4
Change Order No.:
CoP Project No.:
P.O. No.:
1
FA2001
2020-00001478
Explanation:
This change order encompasses the following: Durotech, Inc. the Construction Manager at Risk (CMAR) for Fire Station #
4, has established the Guaranteed Maximum Price (GMP) of $7,379,161. This GMP includes pre -construction fees of $420,231
already encumbered. The remaining construction phase fees total $6,958,930. After review, staff has approved the proposed
GMP. This amendment will increase the CMAR contract with Durotech to add the GMP.
Description of Work Cost Time
CHANGE ORDER
Fire Station #4
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive, Suite 300
Pearland, TX 77581
www.cityofpeariand.com/projects
Date of Issuance: 09/30/2020
Change Order No.:
1
Contractor:
Durotech, Inc.
CoP Project No.:
FA2001
Consultant:
Joiner Architects
P.O. No.:
2020-00001478
1
Add Item No. 3.00, "CM FEE"
$ 240,667.00
0
Days
2
Add Item No. 4.00, "BUILDER'S RISK INSURANCE"
$ 115,115.00
0
Days
3
Add Item No. 5.00, "ADDITIONAL GENERAL CONDITIONS"
$ 15,676.00
0
Days
4
Add Item No. 6.00, "GENERAL REQUIREMENTS"
$ 34,000.00
0
Days
5
Add Item No. 7.00, "MOCK UP PANEL"
$ 2,500.00
0
Days
6
Add Item No. 8.00, "WINDSTORM INSPECTIONS"
$ 5,400.00
0
Days
7
Add Item No. 9.00, "TEMPORARY POWER"
$ 9,600.00
0
Days
8
Add Item No. 10.00, "EQUIPMENT FUEL/FUEL TANK"
$ 4,510.00
0
Days
9
Add Item No. 11.00, "MATERIAL HANDLING & HOISITNG"
$ 12,758.00
0
Days
10
Add Item No. 12.00, "TEMPORARY SCAFFOLDING"
$ 12,216.00
0
Days
11
Add Item No. 13.00, "TEMPORARY ROADS"
$ 7,500.00
0
Days
12
Add Item No. 14.00, "TRAFFIC CONTROL"
$ 3,970.00
0
Days
13
Add Item No. 15.00, "TEMPORARY FENCING"
$ 2,548.00
0
Days
14
Add Item No. 16.00, "TEMP TREE PROTECTION"
$ 500.00
0
Days
15
Add Item No. 17.00, "EROSION & SEDIMENT CONTROL"
$ 23,293.00
0
Days
16
Add Item No. 18.00, "FIELD ENGINEERING & LAYOUT"
$ 49,070.00
0
Days
17
Add Item No. 19.00, "PROGRESS CLEANING"
$ 18,200.00
0
Days
18
Add Item No. 20.00, "SITE MAINT/CLEAN STREETS"
$ 23,815.00
0
Days
19
Add Item No. 21.00, "CONST. WASTE MANAGEMENT"
$ 17,537.00
0
Days
20
Add Item No. 22.00, "FINAL CLEANING"
$ 3,543.00
0
Days
21
Add Item No. 23.00, "SURVEY"
$ 5,000.00
0
Days
22
Add Item No. 24.00, "PUMP & DEWATER"
$ 3,000.00
0
Days
CHANGE ORDER
Fire Station #4
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive, Suite 300
Pearland, TX 77581
www.cityofpearland.com/projects
Date of Issuance: 09/30/2020
Change Order No.:
1
Contractor:
Durotech, Inc.
CoP Project No.:
FA2001
Consultant:
Joiner Architects
P.O. No.:
2020-00001478
25
Add Item No. 30.00,
"SITE & BLDG CONCRETE"
$ 452,563.00
0
Days
26
Add Item No. 50.00,
"EARTHWORK"
$ 139,027.00
0
Days
27
Add Item No. 70.00,
"POLISHED & SEALED CONC"
$ 25,006.00
0
Days
28
Add Item No. 71.00,
"SKUDO FLOOR PROTECTION"
$ 18,156.00
0
Days
29
Add Item No. 72.00,
"MASONRY"
$ 300,000.00
0
Days
30
Add Item No. 86.00,
"STRUCT STEEL FABRICATION"
$ 315,204.00
0
Days
31
Add Item No. 91.00,
"MISCELLANEOUS STEEL"
$ 21,093.00
0
Days
32
Add Item No. 93.00,
"STEEL ERECTION"
$ 206,200.00
0
Days
33
Add Item No. 95.00,
"MATTS"
$ 13,868.00
0
Days
34
Add Item No. 96.00,
"Cl DOWNSPOUT BOOTS"
$ 3,823.00
0
Days
35
Add Item No. 100.00,
"ROUGH CARPENTRY LABOR"
$ 29,045.00
0
Days
36
Add Item No. 101.00,
'ROUGH CARPENTRY MATERIAL"
$ 40,021.00
0
Days
37
Add Item No. 102.00,
"FRP PANELS"
$ 931.00
0
Days
38
Add Item No. 103.00,
"MILLWORK"
$ 144,200.00
0
Days
39
Add Item No. 110.00,
"DAMP/WATERPROOFING"
$ 79,326.00
0
Days
40
Add Item No. 125.00,
'BUILDING THERMAL INSULATION"
$ 18,600.00
0
Days
41
Add Item No. 136.00,
"METAL ROOFING'
$ 209,025.00
0
Days
42
Add Item No. 146.00,
"MODIFIED BITUMEN ROOFING'
$ 120,190.00
0
Days
43
Add Item No. 156.00,
"COMPOSITE WALL PANELS"
$ 90,685.00
0
Days
44
Add Item No. 166.00,
"DOOR/HARDWARE INSTALL"
$ 9,592.00
0
Days
45
Add Item No. 167.00,
"UNLOAD/DIST FR/DR/HDWR"
$ 10,573.00
0
Days
46
Add Item No. 168.00,
"FRAMES/DOORS/HARDWARE"
$ 113,630.00
0
Days
d7
AAA If— K1- 17F nn
--ArrGcc nnnoc'-
4Z q did 00
n
n-,,-
aot rfR'�e
u o
f E i A S
e5r. ta4a
CHANGE ORDER
Fire Station #4
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive, Suite 300
Pearland, TX 77581
www.cityofpearland.com/projects
Date of Issuance: 09/30/2020
Change Order No.:
1
Contractor: Durotech,
Inc.
CoP Project No.:
FA2001
Consultant:
Joiner Architects
P.O. No.:
2020-00001478
50
Add Item No. 196.00,
"GLASS/GLAZING"
$ 157,800.00
0
Days
51
Add Item No. 211.00,
"TEMPORARY ENCLOSURES"
$ 2,249.00
0
Days
52
Add Item No. 212.00,
'PLASTERING"
$ 2,500.00
0
Days
53
Add Item No. 213.00,
"DRYWALL"
$ 156,676.00
0
Days
54
Add Item No. 225.00,
"HARD TILE"
$ 74,737.00
0
Days
55
Add Item No. 235.00,
"RESILIENT FLOORING'
$ 38,254.00
0
Days
56
Add Item No. 245.00,
"ACOUSTICAL CEILING'
$ 139,853.00
0
Days
57
Add Item No. 250.00,
"FLOOR PREP"
$ 2,786.00
0
Days
58
Add Item No. 251.00,
"FLOOR PROTECTION"
$ 1,806.00
0
Days
59
Add Item No. 255.00,
"PAINT"
$ 43,835.00
0
Days
60
Add Item No. 270.00,
"TOILET ACCESSORIES"
$ 3,090.00
0
Days
61
Add Item No. 271.00,
"FIRE EXTINGUISHERS/CABINETS"
$ 1,404.00
0
Days
62
Add Item No. 272.00,
"METAL STORAGES SHELVING"
$ 1,100.00
0
Days
63
Add Item No. 273.00,
"GEAR GRID LOCKERS"
$ 4,450.00
0
Days
64
Add Item No. 274.00,
"KNOX BOX"
$ 2,285.00
0
Days
65
Add Item No. 275.00,
"CORNER GUARDS"
$ 3,565.00
0
Days
66
Add Item No. 281.00,
"SIGNAGE"
$ 20,618.00
0
Days
67
Add Item No. 290.00,
"FLAGPOLES"
$ 9,289.00
0
Days
68
Add Item No. 291.00,
"ALUMINUM CANOPIES"
$ 72,286.00
0
Days
69
Add Item No. 292.00,
"CERAMIC INFRARED SAUNA"
$ 4,000.00
0
Days
70
Add Item No. 293.00,
"GEAR EXTRACTOR"
$ 9,450.00
0
Days
71
Add Item No. 294.00,
"PPE GEAR DRYING CABINET"
$ 6,705.00
0
Days
CHANGE ORDER
Fire Station #4
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive, Suite 300
Pearland, TX 77581
www.cityofpeariand.com/projects
Date of Issuance: 09/30/2020
Change Order No.:
1
Contractor:
Durotech,
Inc.
CoP Project No.:
FA2001
Consultant:
Joiner Architects
P.O. No.:
2020-00001478
74
Add Item No. 310.00,
"FIRE SPRINKLER"
$ 48,400.00
0
Days
75
Add Item No. 321.00,
"PLUMBING"
$ 445,000.00
0
Days
76
Add Item No. 350.00,
"HVAC"
$ 602,985.00
0
Days
77
Add Item No. 370.00,
"HVAC FILTER CHANGES"
$ 2,500.00
0
Days
78
Add Item No. 371.00,
"BIM COORDINATION"
$ 10,000.00
0
Days
79
Add Item No. 372.00,
"ENERGY INSPECTIONS"
$ 600.00
0
Days
80
Add Item No. 380.00,
"ELECTRICAL"
$ 817,308.00
0
Days
81
Add Item No. 400.00,
"LOW VOLTAGE BOXES/CONDUIT"
$ 8,500.00
0
Days
82
Add Item No. 401.00,
"PERMANENT POWER START UP"
$ 6,859.00
0
Days
83
Add Item No. 402.00,
"FIBER EXTENSION FROM PD"
$ 27,369.00
0
Days
84
Add Item No. 403.00,
"INTEGRATED A-V SYSTEMS"
$ 1,500.00
0
Days
85
Add Item No. 404.00,
"ACCESS CONTROL"
$ 70,947.00
0
Days
86
Add Item No. 410.00,
"VIDEO SURVEILLANCE SYSTEM"
$ 3,000.00
0
.Days
87
Add Item No. 415.00,
"FIRE ALARM"
$ 14,976.00
0
Days
88
Add Item No. 420.00,
"TERMITE TREATMENT"
$ 1,080.00
0
Days
89
Add Item No. 421.00,
"FINAL GRADING"
$ 3,130.00
0
Days
90
Add Item No. 422.00,
"HAUL OFF SITE & UTILITY SPOILS"
$ 45,358.00
0
Days
91
Add Item No. 423.00,
"CLEAN PARKING LOT/SIDEWALKS"
$ 1,061.00
0
Days
92
Add Item No. 424.00,
"CONC PVMT JOINT SEALANTS"
$ 12,681.00
0
Days
93
Add Item No. 425.00,
"REMOVE TOP STRIP/CLEAN EJs"
$ 2,811.00
0
Days
94
Add Item No. 426.00,
"BACKFILL CURBS"
$ 2,505.00
0
Days
95
Add Item No. 427.00,
"PAVEMENT MARKINGS"
$ 11,090.00
0
Days
of
AAA 11-- A1- AOr 00
"CCAI! CC 0 f ATCC"
(Z rill 51FA nn
n
n-,,..
CHANGE ORDER
Fire Station #4
Date of Issuance: 09/30/2020
Contractor: Durotech, Inc.
Consultant: Joiner Architects
99 Add Item No. 470.00, "SITE UTILITIES"
100 Add Item No. 485.00, "PUNCHLIST"
101
Add Item No. 490.00,
"SIGNAGE ALLOWANCE"
102
Add Item No. 500.00,
"STATION ALERTING ALLOWA NCE"
103
Add Item No. 510.00,
"IRRIGATION ALLOWANCE"
104
Add Item No. 520.00,
"SCBA DECON WASHER ALLOW"
105
Add Item No. 525.00,
"CASCADE SYSTEM ALLOW"
106
Add Item No. 530.00.
"CM CONTINGENCY ALLOWANCE"
Please attach back -un documentation.
Cost & Time Change Summary
Original Contract:
Previous Change Order(s):
Contract prior to this Change Order:
Net increase (decrease) from this Change Order
Revised Contract:
Finance Approval: ' ` . `
RECOMMENDED:
By: ---- `1 �'Y ` — Date
Consultant
ACCEPTED*:
By:Date
Contractor
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive, Suite 300
Pearland, TX 77581
www.cityofpearland.com/projects
Change Order No.:
1
CoP Project No.:
FA2001
P.O. No.:
2020-00001478
$ 169,100.00
0
Days
$ 13,156.00
0
Days
$ 25,000.00
0
Days
$ 125,000.00
0
Days
$ 50,000.00
0
Days
$ 20,000.00
0
Days
$ 5,000.00
0
Days
$ 200,000.00
0
Days
Cost
Time
$ 420,231.00
Days
$ -
0
Days
$ 420,231.00
Days
$ 6,958,930.00
395
Days
$ 7,379,161.00
Days
Date 10/23/2020
RECOMMENDED:
10/22/2020 By: ���/— Date 10/22/2020
Construction Manager
APPROVED:
10/22/2020 By:� Date 10/22/2020
Owner
*Contractor agrees to perform change(s) included in the Change Order for the price and time indicated. The prices for changes included all costs
associated with this Change Order.
No work is to be done until this change order is executed. No payment to the Contract (or Consultant) shall be made for work included in the change order
until the Contractor's pay estimate is updated.
Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, this Change
CHANGE ORDER NO. 1
ATTACHMENT "A"
PROJECT: Fire Station #4
September 30, 2020
PROJECT NO.: FA2001
ORIGINAL CONTRACT REVISED CONTRACT
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL QTY UNIT COST TOTAL NET CHANGE
ADD ITEM(S) TO CONTRACT:
3.00
CM FEE
LS
1
240,667.00
$240,667.00
$240,667.00
4.00
BUILDER'S RISK
LS
1
115,115.00
$115,115.00
$115,115.00
INSURANCE
5.00
ADDITIONAL GENERAL
LS
1
$15,676.00
$15,676.00
$15,676.00
CONDITIONS
6.00
GENERAL
LS
1
$34,000.00
$34,000.00
$34,006.00
REQUIREMENTS
7,00
MOCK UP PANEL
LS
1
$2,500.00
$2,500.00
$2,500.00
8.00
WINDSTORM
LS
1
$5,400.00
$5,400.00
$5,400.00
INSPECTIONS
9.00
TEMPORARY POWER
LS
1
$9,600.00
$9,600.00
$9,600.00
10.00
EQUIPMENT FUEUFUEL
LS
1
$4,510.00
$4,510.00
$4,510.00
TANK
11.00
MATERIAL HANDLING &
LS
1
$12,758.00
$12,758.00
$12,758.00
HOISITNG
12.00
TEMPORARY
LS
1
$12,216.00
$12,216.00
$12,216.00
SCAFFOLDING
13.00
TEMPORARY ROADS
LS
1
$7,500.00
$7,500.00
$7,500.00
14.00
TRAFFIC CONTROL
LS
1
$3,970.00
$3,970.00
$3,970.00
15.00
TEMPORARY FENCING
LS
1
$2,548.00
$2,548.00
$2,548.00
16.00
TEMP TREE PROTECTION
LS
1
$500.00
$500.00
$500.00
17.00
EROSION & SEDIMENT
LS
1
$23,293.00
$23,293.00
$23,293.00
CONTROL
18.00
FIELD ENGINEERING &
LS
1
$49,070.00
$49,070.00
$49,070.00
LAYOUT
19.00
PROGRESS CLEANING
LS
1
$18,200.00
$18,200.00
$18,200.00
20.00
SITE MAINT/CLEAN
LS
1
$23,815.00
$23,815.00
$23,815.00
STREETS
21.00
CONST. WASTE
LS
1
$17,537.00
$17,537.00
$17,537.00
MANAGEMENT
22.00
FINAL CLEANING
LS
1
$3,543.00
$3,543.00
$3,543.00
23,00
SURVEY
LS
1
$5,000.00
$5,000.00
$5,000.00
24.00
PUMP & DEWATER
LS
1
$3,000.00
$3,000.00
$3,000.00
25.00
DEMOLITION
LS
1
$42,381.00
$42,381.00
$42,381.00
26.00
EXISTING LIGHTING
LS
1
$30,000.00
$30,000.00
$30,000.00
REWORK
30.00
SITE & BLDG CONCRETE
LS
1
452,563.00
$452,563.00
$452,563.00
50.00
EARTHWORK
LS
1
139,027.00
$139,027.00
$139,027.00
70.00
POLISHED & SEALED
LS
1
$25,006.00
$25,006.00
$25,006.00
CONC
71.00
SKUDO FLOOR
LS
1
$18,156.00
$18,156.00
$18,156.00
PROTECTION
72.00
MASONRY
LS
1
300,000.00
$300,000.00
$300,000.00
86.00
STRUCT STEEL
LS
1
315,204.00
$315,204.00
$315,204.00
FABRICATION
91.00
MISCELLANEOUS STEEL
LS
1
$21,093.00
$21,093.00
$21,093.00
93.00
STEEL ERECTION
LS
1
206,200.00
$206,200.00
$206,200.00
95.00
MATTS
LS
1
$13,868.00
$13,868.00
$13,868.00
96.00
Cl DOWNSPOUT BOOTS
LS
1
$3,823.00
$3,823.00
$3,823.00
100.00
ROUGH CARPENTRY
LS
1
$29,045.00
$29,045.00
$29,045.00
LABOR
CHANGE ORDER NO. 1
ATTACHMENT"A"
PROJECT: Fire Station #4
September 30, 2020
PROJECT NO.: FA2001
ORIGINAL CONTRACT REVISED CONTRACT
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL QTY UNIT COST TOTAL NET CHANGE
125.00
BUILDING THERMAL
LS
1
$18,600.00
$18,600.00
$18,600.00
INSULATION
136.00
METAL ROOFING
LS
1
209,025.00
$209,025.00
$209,025.00
146.00
MODIFIED BITUMEN
LS
1
120,190.00
$120,190.00
$120,190.00
ROOFING
156.00
COMPOSITE WALL
LS
1
$90,685.00
$90,685.00
$90,685.00
PANELS
166.00
DOOR/HARDWARE
LS
1
$9,592.00
$9,592.00
$9,592.00
INSTALL
167.00
UNLOAD/DIST
LS
1
$10,573.00
$10,573.00
$10,573.00
FR/DR/HDWR
168.00
FRAMES/DOORS/HARDW
LS
1
113,630.00
$113,630.00
$113,630.00
ARE
175.00
ACCESS DOORS
LS
1
$3,454.00
$3,454.00
$3,454.00
176.00
APPARATUS BAY
LS
1
239,180.00
$239,180.00
$239,180.00
DOORS
191.00
LOUVERS
LS
1
$28,389.00
$28,389.00
$28,389.00
196.00
GLASS/GLAZING
LS
1
157,800.00
$157,800.00
$157,800.00
211.00
TEMPORARY
LS
1
$2,249.00
$2,249.00
$2,249.00
ENCLOSURES
212.00
PLASTERING
LS
1
$2,500.00
$2,500.00
$2,500.00
213.00
DRYWALL
LS
1
156,676.00
$156,676.00
$156,676.00
225,00
HARD TILE
LS
1
$74,737.00
$74,737.00
$74,737.00
235.00
RESILIENT FLOORING
LS
1
$38,254.00
$38,254.00
$38,254.00
245.00
ACOUSTICAL CEILING
LS
1
139,853.00
$139,853.00
$139,853.00
250.00
FLOOR PREP
LS
1
$2,786.00
$2,786.00
$2,786.00
251.00
FLOOR PROTECTION
LS
1
$1,806.00
$1,806.00
$1,806.00
255.00
PAINT
LS
1
$43,835.00
$43,835.00
$43,835.00
270.00
TOILET ACCESSORIES
LS
1
$3,090.00
$3,090.00
$3,090.00
271.00
FIRE
LS
1
$1,404.00
$1,404.00
$1,404.00
EXTINGUISHERS/CABI NET
S
272.00
METALSTORAGES
LS
1
$1,100.00
$1,100.00
$1,100.00
SHELVING
273.00
GEAR GRID LOCKERS
LS
1
$4,450.00
$4,450.00
$4,450.00
274.00
KNOX BOX
LS
1
$2,285.00
$2,285.00
$2,285.00
275.00
CORNER GUARDS
LS
1
$3,565.00
$3,565.00
$3,565.00
281.00
SIGNAGE
LS
1
$20,618.00
$20,618.00
$20,618.00
290.00
FLAGPOLES
LS
1
$9,289.00
$9,289.00
$9,289.00
291.00
ALUMINUM CANOPIES
LS
1
$72,286.00
$72,286.00
$72,286.00
292.00
CERAMIC INFRARED
LS
1
$4,000.00
$4,000.00
$4,000.00
SAUNA
293.00
GEAR EXTRACTOR
LS
1
$9,450.00
$9,450.00
$9,450.00
294.00
PPE GEAR DRYING
LS
1
$6,705.00
$6,705.00
$6,705.00
CABINET
295.00
RESIDENTIAL
LS
1
$38,829.00
$38,829.00
$38,829.00
APPLIANCES
301.00
WINDOW SHADES
LS
1
$4,885.00
$4,885.00
$4,885.00
310.00
FIRE SPRINKLER
LS
1
$48,400.00
$48,400.00
$48,400.00
321.00
PLUMBING
LS
1
445,000.00
$445,000.00
$445,000.00
350.00
HVAC
LS
1
602,985.00
$602,985.00
$602,985.00
370.00
HVAC FILTER CHANGES
LS
1
$2,500.00
$2,500.00
$2,500.00
371.00
BIM COORDINATION
LS
1
$10,000.00
$10,000.00
$10,000.00
372.00
ENERGY INSPECTIONS
LS
1
$600.00
$600.00
$600.00
380.00
ELECTRICAL
LS
1
817,308.00
$817,308.00
$817,308.00
CHANGE ORDER NO. 1
ATTACHMENT"A"
September 30, 2020
PROJECT: Fire Station #4 PROJECT NO.: FA2001
NET TOTAL CHANGE ORDER #1: $6,958,930.00
ORIGINAL CONTRACT AMOUNT: $420,231.00
CHANGE ORDER #1: $6,958,930.00
REVISED CONTRACT AMOUNT: $7,379,161.00
ORIGINAL CONTRACT
REVISED CONTRACT
ITEM
DESCRIPTION
UNIT QTY UNIT COST TOTAL
QTY
UNIT COST
TOTAL
NET CHANGE
402.00
FIBER EXTENSION FROM
LS
1
$27,369.00
$27,369.00
$27,369.00
PD
403.00
INTEGRATED A-V
LS
1
$1,500.00
$1,500.00
$1,500.00
SYSTEMS
404.00
ACCESS CONTROL
LS
1
$70,947.00
$70,947.00
$70,947.00
410.00
VIDEO SURVEILLANCE
LS
1
$3,000.00
$3,000.00
$3,000.00
SYSTEM
415.00
FIRE ALARM
LS
1
$14,976.00
$14,976.00
$14,976.00
420.00
TERMITE TREATMENT
LS
1
$1,080.00
$1,080.00
$1,080.00
421.00
FINAL GRADING
LS
1
$3,130.00
$3,130.00
$3,130.00
422.00
HAUL OFF SITE & UTILITY
LS
1
$45,358.00
$45,358.00
$45,358.00
SPOILS
423.00
CLEAN PARKING
LS
1
$1,061.00
$1,061.00
$1,061.00
LOT/SIDEWALKS
424.00
CONC PVMT JOINT
LS
1
$12,681.00
$12,681.00
$12,681.00
SEALANTS
425.00
REMOVE TOP
LS
1
$2,811.00
$2,811.00
$2,811.00
STRIP/CLEAN EJs
426.00
BACKFILL CURBS
LS
1
$2,505.00
$2,505.00
$2,505.00
427.00
PAVEMENT MARKINGS
LS
1
$11,090.00
$11,090.00
$11,090.00
435.00
FENCES & GATES
LS
1
$54,854.00
$54,854.00
$54,854.00
440.00
LANDSCAPING
LS
1
$32,766.00
$32,766.00
$32,766.00
465.00
IRRIGATION SLEEVES
LS
1
$7,362.00
$7,362.00
$7,362.00
470.00
SITE UTILITIES
LS
1
169,100.00
$169,100.00
$169,100.00
485.00
PUNCHLIST
LS
1
$13,156.00
$13,156.00
$13,156.00
490.00
SIGNAGE ALLOWANCE
LS
1
$25,000.00
$25,000.00
$25,000.00
500.00
STATION ALERTING
LS
1
125,000.00
$125,000.00
$125,000.00
ALLOWA NCE
510.00
IRRIGATION ALLOWANCE
LS
1
$50,000.00
$50,000.00
$50,000.00
520.00
SCBA DECON WASHER
LS
1
$20,000.00
$20,000.00
$20,000.00
ALLOW
525.00
CASCADE SYSTEM
LS
1
$5,000.00
$5,000.00
$5,000.00
ALLOW
530.00
CM CONTINGENCY
LS
1
200,000.00
$200,000.00
$200,000.00
ALLOWANCE
NET TOTAL CHANGE ORDER #1: $6,958,930.00
ORIGINAL CONTRACT AMOUNT: $420,231.00
CHANGE ORDER #1: $6,958,930.00
REVISED CONTRACT AMOUNT: $7,379,161.00
Purpose
Memo
To: Clay Pearson, City Manager
From: Jameson S. Appel, Project anager
CC: Jon Branson, Deputy
Trent Epperson, Ass'
Robert Upton, Dire c
Vance Riley, Fire Chi
1 October 2020
To: Mayor and City
Council members
Information for forthcoming award to
finish the CMAR to complete
replacement Fire Station #4 and
Animal Shelter and Adoption Center
adjacent to each other on our Freedom
Drive property. Very positive and
competitive pricing, great
improvements and advances for public
CKy Manager Iservice provision. Clay
Rant City Manager
r Engineering and Capital Projects
Johnny Spires, olice Chief
Chad Randa , Assistant Chief of Police
Skipper Jo s, Assistant Director of Capital Projects
Date: Octobef1, 2020
Re: Fire"Station #4 and Shari D. Coleman Animal Shelter and
Adoption Center. Contract Award — Guaranteed Maximum Price
This memo provides information about the progress on two projects: Fire Station #4 and Shari D.
Coleman Animal Shelter and Adoption Center and the proposed award of an amendment to the
existing Construction Manager at Risk (CMAR) Pre -Construction Services contract, approving the
Guaranteed Maximum Price (GMP) for Construction Phase of the project.
Background
The Fire Station # 4 project consists of the construction of a new 14,343 SF fire station with operational
support and living quarters for one 4 -person fire crew and battalion chief and one 2 -person ambulance
and supervisor. The facility will be constructed to operate on a full-time 24/7 basis and contain four 80 -
foot -deep drive through apparatus bays for Fire apparatus as well as space to house the Police
Department's Mobile Command Post vehicle.
The Animal Shelter was approved in the May 2019 Bond Election and consists of constructing a new
modern facility focused on the increased capacity to match the current population of the City, increased
public contact and adoption rates, providing improved medical capabilities and lowering euthanasia
numbers. This project will provide a 21,520 SF facility that is intended to house 16 staff members and
kennels to house 103 canines and 98 felines. The facility includes exterior dog runs, fenced play yards
designed to give dogs space to exercise and meet their future family.
It was determined that Fire Station # 4 and the Animal Shelter would both be located north of Freedom
Drive within the Public Safety Building site, staff evaluated the best options for delivering both projects,
on similar schedules due to the close proximity to each other. To avoid risk with site and contractor
conflicts, promote coordination, and to gain economy of scale it was determined that a single CMAR
for Fire Station # 4 and Animal Shelter would provide the best benefit and value to the City. A single
CMAR will be able to schedule site work for the entire site without coordination or impact to another
general contractor and have the ability to move subcontractors from one building to the next.
Eliminating the coordination and reducing the risk of having two general contractors, and potentially
multiple sub -contractors of the same trade, will lead to better costs and scheduling efficiencies. To
ensure internal accounting allocates funding properly to each project, the costs will be tracked, specific
to each building, with clear delineations for each building's share of the site work.
The Request for Proposal (RFP) was advertised February 2020, the City selected Durotech as the
CMAR representing the best qualified to assist with final design and provide competitive sub -contractor
bidding and vendor pricing for the construction of Fire Station # 4 and Animal Shelter and Adoption
Center and to assist in the development of the most cost-effective plans and specifications for the
project. Durotech was awarded a contract for Preconstruction Services in June 2020 with the future
intent to amend that contract to include Construction Phase Services upon receipt of an acceptable
GMP.
Current Status
On September 9, 2020 Durotech received sub -contractor bids for all sub -contractor work packages
drawn from a list of pre -approved sub -contractors and vendors. Durotech provided transparent access
to all bids and carried expectation of awarding packages to the lowest responsible bidder. After all
scope clarifications and final cost/scope negotiations with each sub -contractor were completed,
Durotech provided the City with a statement of cost for the CMAR's Guaranteed Maximum Price
(GMP). Durotech's final submitted GMP for Fire Station # 4 totaled $7,379,161. The CMAR's final
submitted GMP for Animal Shelter and Adoption Center totaled $8,475,561 which is approximately 8%
lower than the advertised estimate included with the Request for Proposal issued in February 2020.
Costs include all sub -contracts, material and equipment purchases (excluding FF&E), general
conditions, bonds and insurance, and the CMAR's construction management fee (3.38% for Fire
Station 4 and 2.46% for Animal Shelter). Both general conditions and construction management fees
were approved at the initial award. The GMP represents the benefit of the CMAR process which has
gained increasing popularity as a project delivery model in both public and private industry within the
past decade. CMAR's early involvement improves the design through its insights on constructability,
value engineering, cost estimating, and schedule. The CMAR process also reduces the risk for change
orders outside of owner driven scope changes. Specific to this project, trades were able to develop
bids with the expectation of being awarded both facilities, which ultimately lowered cost.
The project was developed with the use of one CMAR for the very reason to control costs by having
one general contractor managing both project sites. The facilities are literally next to each other and
were designed to be built together maximizing the use of the area and the driveway reconfigurations.
The facilities will be presented to Council in two resolutions for the purpose of cost tracking and
transparency. The GMPs are based on both projects being awarded together. Should the facilities not
be awarded together there are cost consequences because the site work for driveways and traffic
patterns will need to be re -designed and we will lose economy of scale savings as a result of multiple
sub -contractors being awarded both contracts. The implications for awarding one and not the other
will be about a 4-6% cost increase, depending on the facility, for construction costs and additional
engineering/architectural costs to redesign the site civil. The cost savings are a result of the CMAR
process and the economy of scale for sub -contractors due to multiple buildings.
The FF&E for Fire Station # 4 and Animal Shelter is $264,000 and $600,000 respectively. The
budgeted costs will cover technology associated City's internal IT department, furniture, and
equipment specific to the Fire Station and Animal Shelter. The FF&E will be brought back to Council
for approval at the appropriate time for installation as construction progresses.
The City conducted due diligence analysis of cost of Animal Shelters in Texas as well as out of state
facilities to confirm that the GMP construction cost is in an acceptable range. The information is broken
down below. Included is the recently the recently bid Baytown Animal Shelter (see associated article
attached).
*Amounts included in Soft Cost versus Construction cost varies between entities and is difficult to distinguish.
Some entities also include Soft Costs in operational funds in lieu of project costs.
League City project note: Project was bid in December 2018. A two-year inflation factor of 5% estimates that
facility would bid at approximately $392/SF today.
Next Steps
Staff has reviewed the results of the bidding process and the complete GMP package submitted by
the CMAR and on October 12, 2020 staff will recommend that Council amend the CMAR contract to
include Construction Services. The Total GMP for the each of the facilities is the following not to
exceed amount of $7,379,161 for the Fire Station 4 and $8,475,561 for the Animal Shelter. The
amendment to the existing contracts for constriction services will be $6,958,930 for the Fire Station 4
and $8,014,795 for the Animal Shelter. Upon approval, staff will issue an immediate Notice to Proceed
(NTP) commencing applicable services for both projects.
Budget Info
Animal Shelter:
Funding Sources
Public/ Square
Soft Costs*
Construction
Construction
12,000
Total
12,000
Project Name
Private footage
(Design/FFE)
Cost*
Cost/SF
Total Cost
Cost/SF
Bid Status
Loudoun County, VA Animal Services
Public
22,500
$2,800,000
$18,500,000
$822.22
$21,300,000
$946.67
Bid Early 2019
Sugar Land Animal Shelter (estimated)
Public
17,208
$500,000
$9,000,000
$523.01
$9,500,000
$552.07
Scheduled for 2022
Midland, Tx
Public
18,000
$476,200
$8,958,000
$497.67
$9,434,200
$524.12
Bid 12/2019
Baytown, Tx
Public
14,034
$828,545
$6,523,984
$464.87
$7,352,529
$523.91
Bid 9/2020
Animal Rescue League of Western PA
Private
34,500
$1,779,000
$15,180,365
$440.01
$16,959,365
$491.58
2017
Shari D Colman Animal Shelter
Public
21,520
$1,369,565
$8,475,561
$393.85
$9,845,126
$457.49
Bids 912020
Harris County Pets Adoption Center and Clinic
Public
55,000
$2,150,000
$21,500,000
$390.91
$23,650,000
$430.00
Bid fourth quarter 2018
League City, Tx
Public
13,000
$1,320,767
$4,632,955
$356.38
$5,953,722
$457.98
Bid 12/2018
*Amounts included in Soft Cost versus Construction cost varies between entities and is difficult to distinguish.
Some entities also include Soft Costs in operational funds in lieu of project costs.
League City project note: Project was bid in December 2018. A two-year inflation factor of 5% estimates that
facility would bid at approximately $392/SF today.
Next Steps
Staff has reviewed the results of the bidding process and the complete GMP package submitted by
the CMAR and on October 12, 2020 staff will recommend that Council amend the CMAR contract to
include Construction Services. The Total GMP for the each of the facilities is the following not to
exceed amount of $7,379,161 for the Fire Station 4 and $8,475,561 for the Animal Shelter. The
amendment to the existing contracts for constriction services will be $6,958,930 for the Fire Station 4
and $8,014,795 for the Animal Shelter. Upon approval, staff will issue an immediate Notice to Proceed
(NTP) commencing applicable services for both projects.
Budget Info
Animal Shelter:
Funding Sources
Series To Date
Future
Total Budget
General Revenue - Cash
12,000
12,000
Certificates of Obligation
150,000
150,000
Certificates of Obligation
-
General Obligation Bonds
2020 1,534,000
11,341,000
12,875,000
General Obligation Bonds
-
W/S Revenue Bonds
-
Impact Fee - Debt
-
Other Funding Sources
-
Total Funding Sources
1,696,000
11,341,000
13,037,000
Fxnenditures Tn Date Future I Tntal
PER
20,240
General Revenue - Cash
20,240
Land
1,435,000
Certificates of Obligation 7,184,000
-
Design
769,565
General Obligation Bonds
769,565
Construction
460,766
8,014,795
8,475,561
Construction Management/Inspection
-
Total Funding Sources 1,435,000 7,184,000
-
Construction Materials Testing
45,835
45,835
FF&E
600,000
600,000
Total Expenditures
1.250.571
8.660.630
9.911.201
Project Balance/Contingency (24% of Project Budget) 3,125,799
Giro c+�+i. A -
Funding Sources Series To Date Future
Total Budget
General Revenue - Cash
-
Certificates of Obligation 2020A 1,435,000
1,435,000
Certificates of Obligation 7,184,000
7,184,000
General Obligation Bonds
-
General Obligation Bonds
-
W/S Revenue Bonds
-
Impact Fee - Debt
-
Other Funding Sources
-
Total Funding Sources 1,435,000 7,184,000
8,619,000
Expenditures
To Date
Future
Total
PER
-
Land
-
Design
616,525
616,525
Construction
420,231
6,958,930
7,379,161
Construction Management/Inspection
-
Construction Materials Testing
36,382
36,382
FF&E
264,000
264,000
Total Expenditures
1,036,756
7,259,312
8,296,068
Project Balance/Contingency 1 322,932
Schedule Info
Construction time for the project, which consist of both facilities, from Notice to Proceed to substantial
completion is 13 months with an additional 60 days for final completion & Owner move -in. An assumed
NTP of October 2020 would place owner move -in December 2021.
Design Start
Bid Start
Base Line Current
July -19 August -19
October -19 November -19
February -20 February -20
Proposed Construction Completion December -21
This project is being procured through the Construction Manager at Risk (CMAR) process. The
original base line schedule was projected using the design -bid -build process.
Previous Memo: 6.20.2019 (2019 Bond Projects), 9.12.2019, 5.28.2020, 8.20.2020
Project Map (Site Layout):
Fire Station # 4:
11 li! !i i
7V i
r vvow�,-
lie
#I, 1
Company selected to build animal shelter
baytownsun.com
After considering eight proposals from companies interested in building the city's new animal shelter,
the city has selected Construction Masters, Inc. for the $6.5 million project.
Andrea Brinkley, the city's assistant director of capital projects, said it selected the company based on
the best value consideration, not necessarily the best price.
Using evaluation criteria and the answers provided to the department by the bidding contractors,
Brinkley said this assisted in choosing Construction Masters as the one to build the shelter.
The criteria were based on cost, the ability to meet schedule, their experience and qualifications,
experience with subcontractor and similar projects, past reputation, ability to deliver the project on
schedule, and the quality
assurance and safety programs. The prices proposed were between $6.2 and $6.6 million.
"It was a tightly packed consideration," Brinkley said.
Brinkley added Construction Masters received 90 out of 100 points.
"Based on that, we looked at the consideration of cost and found advantageous pricing," she said. "They
were able to add back certain things into the project that were important, such as shade canopies and
'get to know you' areas. And we looked at the pricing for concrete paving, lighting, and drainage, and we
were able to successfully negotiate a post -bid amendment with a $302,000 value."
Brinkley said the value would hold until the end of construction.
Brinkley said the project's construction duration is 494 days, about 16 -and -a -half months. A small
groundbreaking is planned for Oct. 9.
The new shelter will measure 12,066 -square -feet and include a 62 -dog and 78 -cat capacity.
The new shelter will incorporate veterinary surgery space, room for pre-operation, recovery and medical
check-in area, offices, a lobby, a two -vehicle garage, and drop-off space with pet adoption areas for both
cats and dogs. An education room for pet owners is also included.
Mayor Brandon Capetillo said he was happy for the city to be able to provide a first-class facility with
many amenities that are presentable to the taxpayers.
"We have outgrown our current facility, and now we can have one to be proud of," Capetillo said.
Capetillo said he applauded Brinkley's work and everyone that took part in the project.
"It is a nice facility, and we look forward to our Animal Service and Adoption Center and what it will do
for our animal population in Baytown and our new programs," Capetillo said. "We really turned the
corner on how we approached things."
Capetillo said the city had made a lot of headway with the shelter and its programs, such as the 2025 no -
kill shelter plan.
"And we've done it a lot faster than I thought we would as a city," he said. "With programming and the
right partnerships, plus this facility, it will get us there even quicker."
4906 Morning Glory Way
McKinney TX 75072
USA
Unsubscribe I Change Subscriber Options
DUROTECH
BUILDERS OF INTEGRITY
Date: September 30, 2020
Mr. Robert Upton
Director of Engineering
Engineering & Capital Projects
3519 Liberty Drive
Pearland, TX 77581
Re: Guaranteed Maximum Price for the City of Pearland Fire Station #4
Dear Mr. Upton:
We wish to inform you that after several months of working together with the City
of Pearland and Joiner Architects on this important project, we have formally advertised
and solicited proposals for the development of the GMP for the Fire Station #4.
Subcontractor & vendor proposals were received on September 9t", 2020. After careful
review and compilation of these proposals, Durotech, Inc. is pleased to present a
Guaranteed Maximum Price of $7,379,161.00 for the construction of the new Fire
Station #4.
It is our recommendation that we ask the City Council of the City of Pearland to
approve the Guaranteed Maximum Price of $7,379,161.00 and to execute the GMP
Amendment between the City of Pearland and Durotech, Inc.
We are excited about the potential of entering into the construction phase of this
project and want to thank you and your team, Joiner Architects and their consultants for
a very successful pre -construction phase. Durotech is committed to the citizens of
Pearland, Texas in the successful delivery of the New Fire Station #4 project.
Thank you and the City of Pearland for selecting Durotech as its building partner.
It is our goal to meet and exceed your expectations. Should you have any questions
please do not hesitate to contact me.
Sincerely,
David Rowe
CEO
Durotech, Inc.
DUROTECH
BUILDERS OF INTEGRITY
GMP SUMMARY
Project: City of Pearland Fire Station #4
Location: 8325 Freedom Drive, Pearland, TX 77584
Owner: City of Pearland
Scope of work:
THE PROJECT:
The project includes of the construction of a fire station building with kitchen, dorms,
and apparatus bay. The project consists of site preparation, earthwork, site utilities,
concrete paving & drives, sidewalks, and curbs, landscaping, drilled piers and grade
beam foundation, concrete slab on grade, masonry, structural steel, steel joists, deck,
and framing, miscellaneous metal fabrications, rough carpentry, damp proofing, building
enclosure system, insulation, metal roof system and accessories, modified bitumen roof
system and accessories, fire -stopping, sealants, steel and plastic laminate doors, bi-fold
doors, sectional overhead doors, aluminum storefront, windows, building hardware,
glazing, architectural exterior and interior finishes, toilet accessories, fire protection
specialties, relocated lockers, residential appliances, window treatments, fire detection
and suppression systems, mechanical, plumbing, and electrical systems.
THE WORK:
1. All work or portions of work necessary to provide a complete in-place, weather
tight, structural sound facility as represented in the Drawings and Specifications,
including, but not limited to, architectural and structural building components,
architectural finishes, mechanical equipment and ducting, plumbing piping and
fixtures, electrical equipment and fixtures, and fire alarm.
GMP Proposal Package:
The GMP proposal package consists of the following items:
1.
Exhibit A
— GMP Top Sheet — dated 30 September 2020
2.
Exhibit B
— Project Manual — dated 13 August 2020
3.
Exhibit C
— List of Drawings — dated 13 August 2020
4.
Exhibit D
— List of Addenda
5.
Exhibit E
— Qualifications & Assumptions
6.
Exhibit F —
Allowance Schedule
7. Exhibit G — Self Performed Work Items
8. Exhibit H — Unit Prices
I
EXHIBIT'A'
D U ROT E C H
BUILDERS OF INTEGRITY
PROJECT:
LOCATION:
FIRE STATION #4
8325 Freedom Drive, Pearland, TX 77584
City of Pearland
OWNER:
ARCHITECT.
Joiner Architects
9130/2020
DATE:
FIRE STATION #4
SECTION
DESCRIPTION
BASE BID
REMARKS_
LABOR
MATERIAL
SUB -BIDS
TOTAL
01 1000
GENERAL REQUIREMENTS
34,000
-
34,000
01 21 00
SIGNAGE ALLOWANCE
-
25,000
25,000
ALLOWANCE
01 21 10
STATION ALERTING ALLOWANCE
125,000
125,000
ALLOWANCE
01 21 20 1
IRRIGATION/PLANTING BEDS ALLOWANCE
50,000
50,000
ALLOWANCE
01 21 30
CM CONTINGENCY ALLOWANCE
200,000
200,000
ALLOWANCE
01 21 40
SCBA DECON WASHER
20,000
20,000
ALLOWANCE
01 4339
MOCKUP PANEL
2,500
2,500
01 4533
WINDSTORM INSPECTIONS
-
5,400
5,400
01 51 13
TEMPORARY POWER
9,600
-
9,600
01 51 19
EQUIPMENT FUEL & FUEL TANK
4,510
4,510
01 5416
MATERIAL HANDLING & HOISTING
12,758
12,758
01 5423
TEMPORARY SCAFFOLDING
12,216
12,216
01 5523
TEMPORARY ROADS
-
7,500
7,500
01 5526
TRAFFIC CONTROL
2,052
1,918
3,970
01 5626
TEMPORARY CONSTRUCTION FENCE
-
2,548
2,548
01 5639
TEMPORARY TREE AND PLANT PROTECTION
-
500
500
01 5700
EROSION & SEDIMENT CONTROL
14,393
8,900
23,293
01 64 00
OWNER FURNISHED ITEMS
-
-
0
0
NONE
01 71 23
FIELD ENGINEERING & LAYOUT
42,640
6,430
49,070
01 7413
PROGRESS CLEANING
18,200
-
18,200
01 7416
SITE MAINTENANCE/CLEAN STREETS
7,713
16,102
-
23,815
01 74 19
CONSTRUCTION WASTE MANAGEMENT
-
-
17,537
17,537
01 7423
FINAL CLEANING
3,144
3,144
DIV 02
EXISTING CONDITIONS
0221 00
SURVEYS
5,000
5,000
0241 13
SITE DEMOLITION
-
-
42,381
42,381
02 70 00
PUMP & DEWATER
1,800
1,200
-
3,000
02 70 01
EXISTING SITE LIGHTING REWORK
-
30,000
-
30,000
ALLOWANCE
DIV 03
CONCRETE
03 20 00
ONCRETE REINFORCING
-
0
0
IN 03 30 00
03 30 00
AST -IN-PLACE CONCRETE
452,563
452,563
03 35 10
ONCRETE FLOOR SEALER
185
185
03 35 43
POLISHED CONCRETE
-
-
24,821
24,821
03 66 10
SKUDO FLOOR PROTECTION
5,253
12,903
-
18,156
DIV 04
MASONRY
04 05 19
MASONRY REBAR
-
0
0
IN 04 20 00
04 20 00
MASONRY
300,000
300,000
DIV 05
METALS
05 12 00
STRUCTURAL STEEL FRAMING
315,204
315,204
05 12 50
STRUCTURAL STEEL ERECTION
-
206,200
206,200
05 37 00
PREPARE EXPOSED STEEL STRUCTURE
-
5,135
-
5,135
055000
MISCELLANEOUS STEEL
19,993
1,100
21,093
055010
TIMBERMATS
11,756
2,112
13,868
05 56 01
CAST IRON DOWNSPOUT BOOTS
1,781
2,042
3,823
DIV 06
WOOD, PLASTICS, AND COMPOSITES
06 10 00
ROUGH CARPENTRY
29,045
40,021
-
69,066
06 20 00
FINISH CARPENTRY
-
-
0
0
IN 06 22 00
06 22 00
MILLWORK
144,200
144,200
0661 00
SIMULATED STONE FABRICATIONS
-
-
0
0
IN 06 22 00
06 83 16
FRP PANELS
611
320
-
931
DIV 07
THERMAL AND MOISTURE PROTECTION
071100
DAMPPROOFING
-
-
56,700
56,700
0721 00
HERMAL INSULATION
18,600
18,600
07 22 00
jROOF & DECK INSULATION
0
0
07 52 00
EXHIBIT'A'
SECTION
DESCRIPTION
LABOR
BASE BID
MATERIAL SUB -BIDS
TOTAL
REMARKS
07 42 00
METAL WALL PANELS
90,685
90,685
07 52 00
MODIFIED BITUMINOUS MEMBRANE ROOFING
120,190
120,190
07 84 00
FIRESTOPPING
-
-
4,800
4,800
07 92 00
OINT SEALANTS
5,553
12,273
-
17,826
DlV 08OPENINGS
08 08 00
DOOR & HARDWARE INSTALLATION
-
-
9,592
9,592
08 11 00
METAL DOORS & FRAMES
5,134
113,630
-
118,764
MATERIAL IN 08 11 00
08 12 00
LUMINUM DOORS & FRAMES
439
-
439
MATERIAL IN 08 11 00
081423
PLASTIC LAMINATE FACED WOOD DOORS
1,959
1,959
MATERIAL IN OS 11 00
0831 00
CCESS DOORS AND PANELS
1,254
2,200
3,454
08 33 00
COILING DOORS & GRILLES
-
-
0
0
IN 08 35 00
08 34 00
SPECIAL FUNCTION DOORS
314
-
314
MATERIAL IN 08 11 00
08 35 00
FOLDING DOORS & GRILLES
-
239,180
239,180
0871 00
DOOR HARDWARE
2,727
-
2,727
MATERIAL IN 08 11 00
08 80 00
GLAZING
-
-
157,800
157,800
08 80 10
TEMPORARY ENCLOSURES
1,321
928
-
2,249
08 80 15
CLEAN GLASS
295
104
399
08 83 00
MIRRORS
-
-
0
0
IN 08 80 00
0891 00
LOUVERS
7,439
20,950
-
28,389
DIV 09
FINISHES
09 24 00
CEMENT PLASTERING
-
-
2,500
2,500
09 29 00
DRYWALL
156,676
156,676
09 30 00
TILING
74,737
74,737
0951 00
0,COUSTICAL CEILINGS
139,853
139,853
09 54 23
LINEAR METAL CEILINGS
0
0
IN 09 51 00
09 60 00
FLOOR PREPARATION
1,439
1,347
-
2,786
09 60 10
FLOOR PROTECTION
880
926
-
1,806
09 65 00
RESILIENT FLOORING
-
-
38,254
38,254
09 84 00
ACOUSTIC WALL PANELS
0
0
IN 09 51 00
09 90 00
PAINTING & COATING
38,700
38,700
DIV 10
SPECIALTIES
10 14 00
SIGNAGE
20,618
20,618
10 26 13
CORNER GUARDS
3,565
3,565
10 28 13
TOILET ACCESSORIES
3,090
3,090
10 44 00
FIRE PROTECTION SPECIALTIES
-
-
1,404
1,404
10 44 15
KNOX BOX
470
1,815
-
2,285
1051 13
GEAR GRID LOCKERS
-
-
4,450
4,450
10 56 13
METAL STORAGE SHELVING
1,100
1,100
10 73 00
PROTECTIVE COVERS
72,286
72,286
10 75 00
FLAGPOLES
9,289
9,289
DIV 11
EQUIPMENT
11 2300
COMMERCIAL LAUNDRY EQUIPMENT
0
0
NONE
11 2305
SCBA DECON WASHER
0
0
IN 01 21 40
11 23 10
CASCADE SYSTEM
5,000
5,000
ALLOWANCE
11 23 15
ICE MACHINE
0
0
IN 11 31 00
11 23 20
CERAMIC INFRARED SAUNA
4,000
4,000
11 2321
GEAR EXTRACTOR
9,450
9,450
11 2325
PPE GEAR DRYING CABINET
6,705
6,705
1131 00
RESIDENTIAL APPLIANCES
1,568
37,261
-
38,829
11 41 00
COMMERCIAL KITCHEN HOODS
-
-
13,500
13,500
DIV 12
FURNISHINGS
12 24 00
WINDOW SHADES
4,885
4,885
DIV 13
SPECIAL CONSTRUCTION
DIV 14
CONVEYING EQUIPMENT
DIV 21
FIRE SUPPRESSION
21 1000
FIRE SUPPRESSION SYSTEMS
48,400
48,400
DIV 22
PLUMBING
22 00 00
PLUMBING
445,000
445,000
DIV 23
HVAC
23 00 00
HVAC
589,485
589,485
23 00 10
HVAC FILTER CHANGES
2,500
2,500
23 05 00
MEP COORDINATION
10,000
10,000
23 05 93
ENERGY INSPECTIONS
600
600
23 08 00
BUILDING COMMISSIONING
0
0BY
OWNER
23 09 00
JINSTRUMENTATION & CONTROL FOR HVAC
0
0
IN 23 00 00
DIV 26
ELECTRICAL
EXHIBIT'A'
-SECTION
DESCRIPTION
LABOR
BASE BID
MATERIAL SUB -BIDS
TOTAL
REMARKS
26 00 05
ROUGH IN/BACK BOXES - LOW VOLTAGE
8,500
8,500
26 00 10
PERMANENT POWER START UP
6,859
6,859
27 00 15
FIBER EXTENSION FROM POLICE STATION
27,369
27,369
2641 00
LIGHTNING PROTECTION
0
0
IN 26 00 00
DIV 27
COMMUNICATIONS
27 10 00
STRUCTURED CABLING
0
0
BY OWNER
2741 16
INTEGRATED AUDIO -VIDEO SYSTEMS & EQUIPMENT
1,500
1,500
DIV 28
ELECTRONIC SAFETY & SECURITY
28 13 00
ACCESS CONTROL SYSTEM
70,947
70,947
28 16 00
INTRUSION DETECTION SYSTEM
0
0
NONE
28 23 00
VIDEO SURVEILLANCE SYSTEM
3,000
3,000
2831 00
FIRE DETECTION & ALARM SYSTEM
14,976
14,976
DIV 31
EARTHWORK
31 2000
EARTHWORK
-
-
139,027
139,027
31 2216
FINAL GRADING
1,525
1,605
-
3,130
31 2310
HAUL OFF SPOILS
26,654
18,704
-
45,358
31 31 00
SOIL TREATMENT
-
-
1,080
1,080
31 6329
DRILLED CONCRETE PIERS & SHAFTS
-
0
0
IN 03 30 00
DIV 32
EXTERIOR IMPROVEMENTS
3201 11
LEAN PAVING & SIDEWALKS
-
1,061
-
1,061
32 13 73
ONCRETE PAVING JOINT SEALANTS
5,276
7,405
12,681
32 13 75
REMOVE STRIP/CLEAN PAVING JOINTS
2,811
-
2,811
32 16 15
BACKFILL CURBS
2,505
2,505
32 17 23
PAVEMENT MARKINGS
-
11,090
11,090
3231 00
FENCES & GATES
54,854
54,854
32 80 00
IRRIGATION
-
0
0
IN ALLOWANCE
32 80 10
IRRIGATION SLEEVES
3,135
4,227
-
7,362
32 90 00
LANDSCAPING
-
-
31,366
31,366
32 92 00
HYDROMULCH & SOD
0
0
IN 32 90 00
32 95 00
LANDSCAPE MAINTENANCE
1,400
1,400
DIV 33
UTILITIES
33 00 00
SITE UTILITIES
-
-
169,100
169,100
35 00 00
PUNCH LIST
11,431
1,725
-
13,156
UB TOTAL - COST OF WORK ITEMS
239,366
437,976
5,910,130
6,587,472
PERMIT - CITY OF PEARLAND
0
BY OWNER
GENERAL CONDITIONS - LUMP SUM
402,058
ADDITIONAL GENERAL CONDITIONS
15,676
BUILDER'S RISK INSURANCE W/ FLOOD & NAMED WIND
115,115
FEE
240,667
PRECONSTRUCTION FEE
18,173
TOTAL -BASE BID
7,379,161
OTAL - GMP (BASE BID + ACCEPTED ALTERNATES)
7,379,161
EXHIBIT `B'
� pill Mel 1 C41 WE �
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
PROJECT MANUAL
PROJECT MANUAL DATED August 13, 2020
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
Document 00 00 01 - Title Page
Document 00 00 02 - Table of Contents
Document 00 10 00 - Notice for Subcontractor Proposals
Document 00 12 00 - Sub Proposal Form
Document 00 21 10 - Instructions to Subcontractor -Vendor Proposers
Document 00 21 11 - Sample Insurance Certificate
Document 00 45 23 - Affidavit of Non -Asbestos, Lead, and PCB Use in Project
(Project Close -Out)
Document 00 45 25 - Statutory Lien Waiver Forms
Document 00 61 00 - Insurance and Bonds
Document 00 61 10 -Contract Documents
Document 00 72 00 - General Conditions
Document 00 73 00 - Supplementary Conditions
Document 00 73 43 - Prevailing Wage Rates
SPECIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 11 00
Summary of Work
Section 01 1200
Owner Provided Supplementary Documents Geotechnical Report No.
AHA 19-105-00
Section 01 1300
Mechanical and Electrical Coordination
Section 01 1400
Contractor's Use of Premises
Section 01 1900
Codes, Regulations and Standards
Section 01 5620
Waste Material Disposal
Section 01 5640
Control of Ground Water and Surface Water
Section 01 5650
TDPS Requirements
Section 01 5666
Source Controls for Erosion and Sedimentation
Section 01 57 13
Fabric Filter Fence
Section 01 5720
Reinforced Filter Fabric Barrier
Section 01 5800
Project Signs
Section 01 6000
Product Options and Substitutions
Section 01 60 10
Material and Equipment
Section 01 63 10
Substitution Request Form
Section 01 71 23
Field Engineering
Section 01 7300
Execution
Section 01 7329
Cutting & Patching
Section 01 7400
Warranties
.qartinn n1 7d 'IQ
IAia¢tP XA/atPr nignrlCal
EXHIBIT'B'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
PROJECT MANUAL
Section 01 75 00
Starting Systems
Section 01 76 00
Project Record Document
Section 01 77 00
Closeout Procedures
DIVISION 02 - EXISTING CONDITIONS
Section 02 41 19
Selective Demolition
DIVISION 03 - CONCRETE
Section 03 30 00 Concrete Construction for Structures
Section 03 30 10 Cast -In -Place Concrete
Section 03 45 00 Architectural Precast Concrete
Section 03 66 00 Special Concrete Floor Finishes
DIVISION 04 - MASONRY
Section 04 20 00 Unit Masonry Assemblies
Section 04 23 13 Thin Brick
Section 04 85 30 Stone Masonry
DIVISION 05 - METALS
Section 05 12 00
Structural Steel
Section 05 21 00
Steel Joist Framing
Section 05 30 00
Metal Decking
Section 05 41 00
Cold -Formed Metal Framing
Section 05 50 00
Miscellaneous Metals
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
Section 06 10 00 Rough Carpentry
Section 06 16 00 Sheathing
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
Section 07 10 50
Under -Slab Vapor Retarder
Section 07 13 10
Shower Stall Waterproofing
Section 07 21 00
Building Insulation
Section 07 22 16
Roof Board Insulation
Section 07 27 20
Self -Adhering Flexible Flashing
Section 07 27 26
Fluid -Applied Weather Barriers
Section 07 41 13
Standing Seam Metal Roof Panels
Section 07 42 16.1
Metal Soffit Panels
Section 07 42 18
Metal Wall Panels
Section 07 46 16
Metal Ceilings and Soffits
Section 07 52 16
SBS Modified Bitumen Roofing
Section 07 62 00
Sheet Metal Flashing, Gutters, Downspouts, and Trim
Section 07 72 00
Roof Accessories
SPrfinn n7 Rd 1 R
Panatrnfinn Firactnnninn
EXHIBIT `B'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
PROJECT MANUAL
Section 07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
Section 08 11 13
Hollow Metal Doors and Frames
Section 08 12 16
Interior Aluminum Frames
Section 08 14 16
Flush Wood Doors
Section 08 31 00
Access Doors
Section 08 33 10
Overhead Coiling Insulated Doors
Section 08 34 00
Special Function Doors
Section 08 36 00
Sectional Overhead Doors
Section 08 36 13
Bi -Fold Doors
Section 08 41 10
Aluminum Storefronts
Section 08 42 13
Aluminum Entrances
Section 08 71 00
Door Hardware
Section 08 80 00
Glazing
Section 08 83 00
Mirrors
DIVISION 09 - FINISHES
Section 09 24 00
Lath and Plaster
Section 09 25 00
Gypsum Board Assemblies
Section 09 30 13
Ceramic Tiling
Section 09 51 13
Acoustical Panel Ceilings
Section 09 65 13
Resilient Base & Accessories
Section 09 65 19
Resilient Tile Flooring
Section 09 68 17
Carpeted Walk -Off Mats
Section 09 79 50
Concrete Floor Sealer
Section 09 84 13
Acoustical Wall Panels
Section 09 91 00
Painting
DIVISIONS 10 - SPECIALTIES
Section 10 11 00
Visual Display Surfaces
Section 10 26 00
Wall Protection and Recessed Corner Guards
Section 10 28 13
Toilet Accessories
Section 10 28 80
Glass Shower Enclosures
Section 10 35 00
Aluminum Flagpole
Section 1041 00
Knox Box
Section 10 43 00
Exterior Signage
Section 10 44 00
Interior Signage
Section 10 52 00
Fire Protection Specialties
Section 10 56 13
Metal Storage Shelving
Section 1071 13
Exterior Sun Control Devices
Section 10 73 16
Aluminum Canopies
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
PROJECT MANUAL
DIVISIONS 11 THROUGH -EQUIPMENT
Section 11 23 26 Commercial Equipment
Section 11 30 00 Residential Appliances
Section 11 41 00 Commercial Kitchen Hoods
DIVISION 12 - FURNISHINGS
Section 12 21 24
Manual Roller Shade System
Section 12 30 00
Manufactured Casework
Section 12 36 61
Quartz Countertops
DIVISION 13 - SPECIAL
CONSTRUCTION - (Not Used)
DIVISION 14 - CONVEYING EQUIPMENT - (Not Used)
DIVISION 21 - FIRE SUPPRESSION
Section 21 00 00
Fire Protection
Section 21 02 01
Coordination Drawings
Section 21 05 29
Hangers and Supports for Fire Suppression Piping and Equipment
Section 21 13 13
Wet Pipe Sprinkler System
DIVISION 22 - PLUMBING
Section 22 02 00
Basic Materials and Methods
Section 22 02 01
Coordination Drawings
Section 22 05 16
Expansion Fittings and Loops for Plumbing Piping
Section 22 05 29
Hangers and Supports for Plumbing Piping and Equipment
Section 22 05 53
Identification for Plumbing Piping Equipment
Section 22 07 19
Plumbing Piping Insulation
Section 22 08 00
Commissioning of Plumbing Systems
Section 22 10 00
Plumbing Piping
Section 22 11 19
Plumbing Specialties
Section 22 11 21
Natural Gas Piping Systems
Section 22 30 00
Plumbing Equipment
Section 22 40 00
Plumbing Fixtures
Section 22 61 00
Compressed Air Systems
DIVISION 23 - HEATING, VENTILATION, AND AIR CONDITIONING (HVAC)
Section 23 02 00
Basic Materials and Methods
Section 23 02 01
Coordination Drawings
Section 23 05 13
Common Motor Requirements for HVAC Equipment
Section 23 05 26
Variable Frequency Motor Requirements for HVAC Equipment
Section 23 05 29
Hangers and Supports for Piping and Equipment for HVAC
Section 23 05 48
Vibration and Seismic Controls for HVAC Piping and Equipment
Section 23 05 53
Identification for HVAC Piping and Equipment
C--+;__ 00 !1C 00
1 I\/r` C:-;4+-, 1 11+-,;-1-+ f. IA/l LJ\/Af- RA -1,4 /"'....++ 1
Section 23 05 93
Section 23 07 13
Section 23 07 19
Section 23 21 13
Section 23 23 00
Section 23 31 13
Section 23 33 00
Section 23 34 00
Section 23 34 03
Section 23 37 13
Section 23 41 00
Section 23 51 26
Section 23 55 00
Section 23 55 03
Section 23 62 13
Section 23 62 16
Section 23 81 26
Section 23 82 19
EXHIBIT'B'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
PROJECT MANUAL
Testing, Adjusting, and Balancing
Duct Insulation
HVAC Piping Insulation
Above Ground Hydronic Piping
Refrigerant Piping
Metal Ductwork
Ductwork Accessories
HVAC Fans
Big Ass Fans
Air Distribution Devices
Air Filters
Flue Pipe Systems
Fuel Fired Unit Heaters
Electric Unit Heaters
Air Cooled Condensing Units
Air Cooled Condensing Units for Dedicated Outside Air Handling Units
Split System Air Conditioners - Wall Mounted
Fan Coil Unit
DIVISIONS 24 AND 25 - Not Used
DIVISION 26 - ELECTRICAL
Section 26 02 00
Basic Materials and Methods
Section 26 02 01
Coordination Drawings
Section 26 05 19
Wire, Cable, and Related Materials
Section 26 05 26
Grounding
Section 26 05 33
Raceways
Section 26 05 73
Short Circuit, Coordination Study, ARC Flashing Hazard Analysis
Section 26 08 00
Commissioning of Electrical Systems
Section 26 24 16
Panelboards
Section 26 27 26
Wiring Devices
Section 26 28 10
Class J Fuses
Section 26 28 16
Safety and Disconnect Switches
Section 26 29 01
Motors and Starters
Section 26 29 26
Miscellaneous Electrical Controls and Wiring
Section 26 32 13 16
(250kW) Natural Gas Engine -Driven Standby Generator
Section 26 41 13 13
Lightning Protection System for Low Rise
Section 26 43 13
Surge Protective Device -Service Entrance
Section 26 43 13 13
Surge Protective Device- Standard Interrupting
Section 26 51 00 13
Lighting Fixtures (LED)
DIVISIONS 27 - COMMUNICATIONS
Section 27 00 00 Basic Materials and Methods
EXHIBIT `B'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
PROJECT MANUAL
Section 27 40 00 Cable Television Distribution
Section 27 41 16 Integrated AV Systems
DIVISIONS 28 - ELECTRONIC SAFETY AND SECURITY
Section 28 01 00 Basic Materials and Methods
Section 28 13 00 Access Control System
Section 28 46 00.21 Fire Alarm System
DIVISION 31 - EARTHWORK
Section 31 11 00
Clearing and Grubbing
Section 31 2200
Earthwork
Section 31 2300
Excavation Filling and Backfilling for Site Utilities
Section 31 2313
Subgrade Preparation
Section 31 2323.15
Cement Sand Backfilling
Section 31 2343
Trench Safety System
Section 31 31 16
Termite Control
DIVISION 32 - EXTERIOR IMPROVEMENTS
Section 32 11 13.13
Lime Stabilization of Subgrade
Section 32 1313
Portland Cement Concrete Pavement
Section 32 1613
Concrete Curbs
Section 32 1713
Concrete Pavement Joints
Section 32 1716
Concrete Wheel Stops
Section 32 1723
Pavement Markings Materials
Section 32 20 10
Concrete Sidewalks
Section 32 31 19
Metal Panel Gates
Section 32 31 20
Ornamental Metal Fence and Gates
Section 32 84 00
Irrigation System
Section 32 90 00
Landscape Planting
Section 32 92 00
Turf and Grasses
DIVISION 33 - UTILITIES
Section 33 05 13 Manholes
Section 33 05 23 Jacking, Boring, or Tunneling Pipe
Section 33 11 00 Water Distribution Mains
Section 33 31 00 Sanitary Sewers
Section 33 40 00 Storm Drainage
DIVISIONS 34 THROUGH 48 - (Not Used)
END OF TABLE OF CONTENTS
EXHIBIT `C'
pill Kell I
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
LIST OF DRAWINGS
(Dated 8-17-2020)
C001 GENERAL NOTES
C002 TOPOGRAPHIC SURVEY
C003 DEMOLITION PLAN
C004 DIMENSIONED SITE PLAN
C100 GRADING AND DRAINAGE PLAN
C200 WATER LINE AND SANITARY SEWER PLAN
C300 OVERALL STORM SEWER LAYOUT
C301 STORM SEWER CALCULATIONS
C400 PAVING AND JOINT LAYOUT
C500 SWPPP
C501 SWPPP DETAILS
C502 STORMWATER POLLUTION
C600 WATER DETAILS 1
C601 WATER DETAILS 2
C602 WATER DETAILS 3
C603 SANITARY DETAILS 1
C604 SANITARY DETAILS 2
C605 SANITARY DETAILS 3
C606 STORM SEWER DETAILS
C700 PAVING DETAILS
C701 DRIVEWAY AND RAMP DETAILS
L001 LANDSCAPE NOTES & DETAILS
L101 LANDSCAPE PLAN
A001 TYPICAL MOUNTING HTS
A002 TYPICAL SITE DETAILS
A003 CODE ANALYSIS
A004 GENERAL NOTES
A005 UL DESIGN
A101 ARCHITECTURAL SITE PLAN
A201 ARCHITECTURAL FLOOR PLAN
A202 CLERESTORY PLANS
A301 COMPOSITE ROOF PLAN
A302 ROOF DETAILS
A401 EXTERIOR ELEVATIONS
A402 EXTERIOR ELEVATIONS
A403 EXTERIOR PERSPECTIVES
A501 WALL SECTIONS
A502 WALL SECTIONS
A503 WALL SECTIONS
A504 WALL SECTIONS
Arnr, 1A/AI I QP:(`TI()NIC
EXHIBIT'C'
� •t
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
LIST OF DRAWINGS
(Dated 8-17-2020)
A506 WALL SECTIONS
A507 WALL SECTIONS
A508 WALL SECTIONS
A509 WALL SECTIONS
A601 ENLARGED PLANS
A602 INTERIOR ELEVATIONS
A603 INTERIOR ELEVATIONS
A701 COMPOSITE REFLECTED CEILING PLAN
A702 CLERESTORY REFLECTED CEILING PLAN
A801 MILLWORK DETAILS
A802 MISCELLANEOUS DETAILS
A803 MISCELLANEOUS DETAILS
A901 FINISH SCHEDULE
A902 DOOR & FRAME SCHEDULE
A903 DOOR & FRAME TYPES
A904 PARTITION TYPES
S000 COVER SHEET
S101 GENERAL NOTES
S102 GENERAL NOTES
S201 FOUNDATION PLAN
S202 LOW ROOF FRAMING PLAN
S203 HIGH ROOF FRAMING PLAN
S301 FOUNDATION DETAILS
S302 FOUNDATION DETAILS
S303 FOUNDATION DETAILS
S304 FOUNDATION DETAILS
S305 FOUNDATION DETAILS
S401 CONNECTION DETAILS
S402 CONNECTION DETAILS
S501 TYPICAL FRAMING DETAILS
S502 TYPICAL FRAMING DETAILS
S503 ROOF FRAMING DETAILS
S504 ROOF FRAMING DETAILS
S505 ROOF FRAMING DETAILS
S601 CMU DETAILS
S602 CMU DETAILS
S701 BRACE DETAILS
MEP100 MEP SITE DEMO PLAN
MEP101 MEP SITE PLAN
M001 MECHANICAL SYMBOLS & LEGEND
nn7ni I r -\/pi 9 RAP:( InnIIrel DI 4nl
EXHIBIT `C'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
LIST OF DRAWINGS
(Dated 8-17-2020)
M202 LEVEL 1 AIRHAWK FLOOR PLAN
M203 MECHANICAL ROOF PLAN
M501 MECHANICAL SCHEDULES
M502 MECHANICAL SCHEDULES
M601 MECHANICAL DETAILS
M602 MECHANICAL DETAILS
E001 ELECTRICAL SYMBOL LEGENDS
EL201 LEVEL 1 LIGHTING PLAN
EL202 DAYROOM/LOBBY LIGHTING PLAN
EP201 LEVEL 1 POWER PLAN
EP202 EQUIPMENT POWER PLAN
E401 ELECTRICAL SCHEDULES
E402 ELECTRICAL SCHEDULES
E501 ELECTRICAL SCHEDULES
E601 ELECTRICAL DETAILS
E602 ELECTRICAL DETAILS
E603 ELECTRICAL DETAILS
E604 PURVIS SYSTEM DRAWING
E605 PURVIS SYSTEM DRAWING
P001 PLUMBING SYMBOLS & ABBREVIATIONS
P201 LEVEL 1 PLUMBING PLAN-WASTE/VENT
P202 LEVEL 1 PLUMBINGPLAN-WATER/GAS/FIRE
P301 ROOF PLUMBING PLAN
P401 RISER - WASTE/VENT
P402 RISER - DOMESTIC WATER
P403 RISER - GAS
P501 PLUMBING NOTES & SCHEDULES
P502 PLUMBING NOTES
P601 PLUMBING DETAILS
P602 PLUMBING DETAILS
P603 PLUMBING DETAILS
T001 TECHNOLOGY SYMBOLS & LEGEND
T201 LEVEL 1 TECHNOLOGY PLAN
T301 TECHNOLOGY ENLARGED PLAN
T501 SECURITY DETAILS
EXHIBIT `D'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
LIST OF ADDENDA
1. Addendum No. 1
Issued on August 21, 2020
2. Addendum No. 2
Issued on September 1, 2020
3. Addendum No. 2 (Revised to include Structural Sheets)
Issued on September 8, 2020
4. Addendum No. 3
Issued on September 4, 2020
5. Addendum No. 4
Issued on September 8, 2020
6. Addendum No. 5 (Post -Bid)
Issued on September 30, 2020
EXHIBIT 'E'
216, 1
aim
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
DIVISION 00 — CONDITIONS OF THE CONTRACT
Excluded is Material Testing. Material Testing will be provided by the owner.
2. Excluded are MUD Fees, MUD Inspection Fees and Tap fees.
3. Excluded are Utility Assessment & Impact Fees.
4. Utility Company agreements (terms and conditions), easements and
coordination which will serve as the termination point for Durotech to make
connections for building service shall be the responsibility of the Owner and
Design Team (Architect/MEP Engineer).
5. Offsite Utility Extension Fees, Utility District Connection Fees to on-site
utilities shall be the responsibility of the Owner.
6. Excluded are unforeseen underground conditions or obstructions not
indicated in contract documents.
7. Excluded are any Building Permit fees. Permit Fee costs to be by Owner.
8. We assume that there will be adequate water supply with sufficient pressure
available for the proper functioning of Fire Sprinkler system and other
systems.
9. Without regard to any other provision of this Agreement, Owner shall be
liable to Contractor for additional costs incurred by Contractor as the result
of any governmental payroll tax or healthcare tax, if the tax is applicable to
the Project, the Project is not tax exempt from the specific tax and the tax
became effective after the date of execution of the Contract.
10. Electronic Files and CAD Files will be provided by the Architect/Engineer of
record for the purpose of preparing shop drawings and 3D models at no
cost to the General Contractor and/or Subcontractors. A signed release will
be required before electronic files are released by the Architect/Engineer.
11. Owner and Contractor agree that all manufacturer's warranties, and
subcontractor's warranties which extend beyond Contractor's warranty
period, are hereby assigned to and run directly from the manufacturer to the
Owner and from the subcontractor to the Owner, respectively. Owner
EXHIBIT 'E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
arising out of such manufacturer's warranties and any subcontractor's
extended warranties.
12. Owner and Contractor agree that design and specification of building
systems, operating parameters, and materials is by Owner's Architectural
and Engineering consultants and the enforcement of warranties is
contingent upon building systems being maintained and operated in
accordance with manufacturer recommendations.
13. The Contractor's warranty excludes remedy for damage or defect caused
by abuse, material alteration to the work not executed by the Contractor,
insufficient maintenance or maintenance not in compliance with
manufacturer's written recommendations.
14. This proposal does not consider any potential escalation costs due to
government actions, policies, or tariffs. Any additional cost increase
accrued would be substantiated for additional cost.
15. The Guaranteed Maximum Price provided is a not to exceed amount for the
entire project scope. Individual line items within the project budget are not
individual Guaranteed Maximum Price amounts.
16. Due to the nature of the Civil Utilities design, the Guaranteed Maximum
Price for the Fire Station #4 and Shari D. Coleman Animal Shelter in this
proposal is contingent on both projects being approved and constructed at
the same time. The design of the utilities involves both buildings; a change
to that assumption will require a redesign from the Civil Engineer and
necessitate a revised Guaranteed Maximum Price.
17. The sum of all amendments to the contract between the City of Pearland
and Durotech, Inc shall constitute the Guaranteed Maximum Price.
18. Included are the following sub -limits and deductibles for Builder's Risk
Insurance:
a) Sub -Limits
Named Windstorm $15,900,000
Flood $10,000,000
Earth Movement $15,900,000
EXHIBIT `E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
Earth Movement
Flood
Windstorm/Hail (other than named)
Named Windstorm
Water Damage
$50,000
$25,000
$100,000
$25,000
$100,000
Builder's Risk Insurance Premium will be paid by the Contractor. Owner
will be responsible for the Deductibles. The Builder's Risk policy shall be a
single policy covering the Fire Station #4 and Animal Shelter; the above
Sub -Limits and Deductibles are shared between the two projects.
19. The proposed cost saving recommendations by Durotech, Inc. shall be
subject to the review and approval of the Architect, Owner and the Owner's
Professional Consultants. Durotech is not required to ascertain that the cost
savings are in accordance with applicable laws, statutes, ordinances,
codes, rules and regulations, or lawful orders of public authorities. The
Contractors review of the proposed cost savings is in the capacity as a
Construction Manager and not as a Design Professional.
20. Compensation for General Conditions costs, as defined by the contract, are
included as part of the Guaranteed Maximum Price to the date of substantial
completion. All General Conditions costs incurred after the date of
substantial completion shall be considered Cost of Work.
21. Any audit of the project financials must be initiated no more than ninety (90)
days after the project completion date as established in the Certificate of
Substantial Completion
22. Payment and Performance Bonds will be charged to the Owner based on
the State of Texas regulated rate.
23. Excluded are any requirements that are not shown on the 100% CD GMP
contract documents.
24. Stipulated Billing Rates:
No. I Description
Rate
General Liability/Umbrella Contract amount per thousand x
EXHIBIT 'E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
3
Project Manager
$76.00 per hour
4
Estimator
$75.00 per hour
5
Safety/Field Operation
Manager
$96.00 per hour
6
Superintendent
$79.00 per hour
7
Asst. Superintendent
$48.00 per hour
8
Project Engineer
$41.00 per hour
9
Quality Control Inspector
$69.00 per hour
10
Contract Administrator
$33.00 per hour
11
BIM Coordinator
$55.00 per hour
12
IT Coordinator
$95.00 per hour
13
Intern
$25.00 per hour
14
Labor Burden
42.5%
DIVISION 01— GENERAL REQUIREMENTS
25. It is assumed that the Project Manual (Exhibit B) and the Drawings (Exhibit
C) include the latest Design and Building Standards provided by the owner
and have been reviewed by the Architect and their Consultants for
compliance.
26. All required utility providers (Water, Sewer, Storm Discharge Point, Electric,
Gas, Fiber, Phone Lines) are the responsibility of the Owner to coordinate
and execute necessary agreements so that the utilities are installed per the
contractor's schedule for construction usage and systems startup.
27. Excluded are any costs for the following:
a) Generator rental and fuel for temporary power.
b) Temporary water line
c) Temporary onsite drainage due to lack of discharge point.
28. Section 01 55 50 —Traffic Control:
EXHIBIT `E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
29. Section 01 21 00 — Allowances:
a) Included is an allowance of $50,000 for Irrigation/Planting Beds. This
allowance shall cover all costs associated with the irrigation system.
DIVISION 02 — EXISTING CONDITIONS
30. Included is an allowance of $30,000 for rewiring the existing pole lights so
that they are operational after demolition of the pole lights in the limits of
construction.
31. Excluded is any ground water control systems, well -point systems, eductor
and ejector -type systems, deep wells, and piezometers or monitoring wells.
32. Durotech excludes the removal and/or encapsulation of any and all
asbestos, lead, and other hazardous materials. The removal and/or
encapsulation of all asbestos, lead, and other hazardous materials will be
the responsibility of the Owner and all costs of testing will be paid by the
Owner.
DIVISION 03 — CONCRETE
33. Section 03 66 00 — Special Concrete Floor Finishes:
a) The applicator will be Concrete Color Systems in lieu of specified
TRCPS certified applicator requirement.
34. Structural Sheets:
a) Excluded is any full forming of grade beams.
b) Excluded is any wet curing.
c) Excluded is any casing or slurry method for piers.
DIVISION 04 — MASONRY
35. Section 04 20 00 — Unit Masonry Assemblies:
a) Excluded is any foam filled CMU at any Site Walls including the
Generator Enclosure.
DIVISION 05 — METALS
36. Section 05 12 00 — Structural Steel
a) Included is a 5 -ton allowance of steel per note #18 on S101 in the
amounts of $13,750 for material and $10,000 for labor. Additional
detailing allowance mentioned in note #19 on S101 has been excluded.
37. Section 05 50 00 — Miscellaneous Steel:
EXHIBIT `E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
38. Excluded is any galvanizing of structural steel in non -air-conditioned areas.
DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES
39. Excluded is any exterior plywood sheathing behind metal panels at the fascia
wall panels as none is shown at these locations (reference details 1 and
2/A505, 1 and 2/A506, 1 and 2/A507
DIVISION 07 — THERMAL AND MOISTURE PROTECTION
40. Section 07 27 20 — Self Adhering Flexible Flashing
a) Excluded is copper laminated base flashing as seen in multiple wall
section details. Included is self -adhering membrane flashing as required
per specifications.
41. Section 07 41 13 — Standing Seam Metal Roof Panels
a) Included is the revised Garland standing seam roofing system per the
specifications in Addendum #5 that was issued Post Bid on September
30th, 2020.
b) Excluded is any jointly held warranty for roofing with a bonding
company as mentioned in paragraph 1.9 A 3.
42. Section 07 42 18 — Metal Wall Panels
a) The metal wall panels specified cannot be installed as shown. The
layout on the exterior elevations is for a composite panel. The height
of the metal panel shall be 12".
43. Section 07 52 16 — SBS Modified Bitumen Roofing
a) Excluded are any walk pads as none are shown on the roofing plans
and none are required per Garland, the roofing manufacturer.
b) Included is the revised Garland modified bitumen roofing system per
the specifications in Addendum #5 that was issued Post Bid on
September 30th, 2020.
c) Excluded is any jointly held warranty for roofing with a bonding
company as mentioned in paragraph 1.9 A 3.
DIVISION 08 — OPENINGS
44. Section 08 11 13 — Hollow Metal Doors and Frames:
a) Frame type 11 above the Bi -Fold doors shall be Hollow Metal per
A902 Door & Window Schedule. Frame details are for storefront, but
EXHIBIT 'E'
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
45. Section 08 71 00 — Door Hardware:
a) Keying and lock information was not specified. Hardware is based on
Schlage Standard 6 -Pin Interchangeable Core Type Keying.
b) Hardware is bid as specified in 08 71 00 and may not be in
accordance with TDI.
c) Gate Hardware and Bi -Fold Hardware is included only as shown in 08
71 00.
46. Section 08 83 00 — Mirrors:
a) Frameless mirrors have been included at Restrooms 103, 124, 125,
126, 127, and Decon room 114. Restrooms 116 and 137 shall have
framed mirrors provided by Division 10.
DIVISION 09 — FINISHES
47. Excluded are any hospital grade and anti -microbial finishes.
48. Included tile is Crossville "Nest" 6x36 with corresponding base.
DIVISION 10 — SPECIALTIES
49. Gear Grid Lockers — It is assumed that the existing Gear Grid Lockers in
the existing Fire Station are in acceptable quality and layout to be relocated.
Excluded are any modifications to the lockers to change the layout from the
original configuration to the new Fire Station configuration.
50. Section 10 11 00 — Visual Display Surfaces:
a) Excluded are any Visual Display Boards as none are shown on the
drawings.
DIVISION 11— EQUIPMENT
51. Section 11 31 00 — Residential Appliances:
a) Included are two sets of residential style washing machines and
dryers. Excluded are any commercial washer and dryers except for
the Gear Extractor and PPE Gear Drying Cabinets.
52. Included is an allowance of $20,000 for the SCBA Decon Washer.
53. Included is an allowance of $5,000 for relocating the existing Cascade
System from the existing Fire Station #4. A new Cascade System has been
excluded from this proposal.
EXHIBIT 'E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
DIVISION 13 — SPECIAL CONSTRUCTION
DIVISION 14 — CONVEYING EQUIPMENT
DIVISION 21— FIRE SUPPRESSION
54. Section 21 13 13 — Wet Pipe Sprinkler System:
a) Excluded is any Dry Pipe Sprinkler System at exterior canopies or
soffits.
DIVISION 22 — PLUMBING
DIVISION 23 — HVAC
55. Section 23 31 13 — Metal Ductwork:
a) Excluded is Duct System Cleaning per paragraph 3.7 of Section 23 31
13. Ductwork will be wrapped and protected by plastic during
construction.
56. Excluded are any costs associated with Testing and Balancing or
Commissioning of Mechanical Systems. All such costs shall be covered by
the Owner.
DIVISION 26 — ELECTRICAL
DIVISION 27 — COMMUNICATIONS & DIVISION 28 — ELECTRONIC SAFETY &
SECURITY
57. Section 27 00 00 — Structured Cabling
a) Excluded is any structured cabling, cabling trays, cabling hooks,
network equipment, wireless access points, cabling to cameras,
network racks, testing of cabling, patch panels, patch cords, or trim
out. The entirety of this section to be provided by the owner. Included
only is the wall rough ins and sleeves for the structured cabling.
58. Sections 27 41 16 — Integrated AV Systems & 27 40 00 — Cable Television
Distribution:
a) Excluded are any flat panel monitors, monitor mounts, AV equipment,
or any audio-visual cabling. In wall rough ins will be required for the
owner furnished and owner installed equipment and cabling as it is
shown in the contract documents.
EXHIBIT 'E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
a) Included are 2 Axis multi -sensor cameras at the corner of the building
and 1 Axis single -sensor camera viewing the gate. All cabling to these
cameras to be provided by owner and are excluded from this proposal.
60. Section 28 13 00 — Access Control System:
a) Included are card readers to match the door hardware schedule, not
the technology drawings. Technology drawings call for a total of 19
building card readers, but the hardware schedule shows a total of 22
card readers. Technology drawings show card readers on doors 104A
and 132A, but the door hardware schedule does not call for an
integrated card reader lock at those doors. Card readers and access
control have not been provided to these doors as part of this proposal.
b) Doors 110, 112B, 115B, 118B, and 142B require card readers per the
door hardware schedule but not per the technology drawings. Card
readers have been priced for these doors.
c) Doors 112A and 136A call for a card reader only at these doors per
the door hardware schedule, but technology drawings show
combination keypad and card reader. Combination keypads and card
readers have been excluded for these doors in this proposal.
d) Included are 100 windshield tags for the gate access control.
e) Keyed note #33 on A101 calls for a 3'-0" man gate with access -
controlled hardware. This gate will be provided in the Animal Shelter
scope of work and is excluded from this proposal.
DIVISION 31— EARTHWORK
61. Section 31 00 00 — Earthwork:
a) Included is 36" of imported select fill for the building pad per the
Geotechnical Report.
DIVISION 32 — EXTERIOR IMPROVEMENTS
62. Landscaping Sheets:
a) Landscaping is priced as shown on L101. Excluded are any additional
requirements from the City of Pearland and/or the Urban Forester per
General Note #6 and Keyed Note #3 on L101. Additional requirements
will be covered by the Irrigation and Planting Beds Allowance.
EXHIBIT 'E'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland — Fire Station #4
100% CD GMP
QUALIFICATIONS & ASSUMPTIONS
DIVISION 33 — UTILITIES
EXHIBIT `F'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
ALLOWANCE SCHEDULE
1.
Signage Allowance
$25,000
2.
Station Alerting System Allowance
$125,000
3.
Irrigation/Planting Beds Allowance
$50,000
4.
CM Contingency Allowance
$200,000
5.
SCBA Decon Washer
$20,000
EXHIBIT `G'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
SELF PERFORMED WORK ITEMS
The following scope items will be self -performed by Durotech, Inc. and will be billed
against the contract based upon the proposal submitted to and accepted by the owner
and will be treated as a lump sum sub -contract amount.
No.
Description of Scope
Semi -skilled
Total
A
BASE BID
Foreman/Operator
$34/hr
1
Miscellaneous Steel (L)
$
21,093
2
Rough Carpentry (L & M)
$
69,066
3
Install FRP Panels (L & M)
$
931
4
Unload & distribute Steel Doors & Frames (L)
$
5,134
5
Unload & distribute Aluminum Doors & Frames (L)
$
439
6
Unload & distribute Plastic Laminate Faced Wood Doors (L)
$
1,959
7
Install Access Doors (L& M)
$
3,454
8
Unload & distribute Special Function Doors (L)
$
314
9
Unload & distribute Door Hardware (L)
$
2,727
10
Install Louvers (L)
$
7,439
11
Floor Preparation (L & M)
$
2,786
12
Floor Protection (L & M)
$
1,806
13
Install Knox Box (L & M)
$
2,285
14
Install Residential Appliances (L)
$
1,568
15
Final grading (L & M)
$
3,130
16
Remove strip/Clean paving joints (L)
$
2,811
17
Backfill curbs (L)
$
2,505
18
Install Irrigation Sleeves (L & M)
$
7,362
19
Haul off Spoils (L & M)
$
45,358
TOTAL
$
182,167
Labor Rates:
Semi -skilled
$27/hr
Skilled
$30/hr
Foreman/Operator
$34/hr
EXHIBIT `H'
DUROTECH
BUILDERS OF INTEGRITY
City of Pearland Fire Station No. 4
UNIT PRICES
No Unit Prices were Requested per the Contract Documents
Date of Issuance: 09/30/2020
Contractor: Durotech, Inc.
Consultant: Joiner Architects
CITY OF PEARLAND
PROJECTS DEPARTMENT
3519 Liberty Drive, Suite 300
Pearland, TX 77581
www.cityofpearland.com/projects
CHANGE ORDER
Fire Station #4
Change Order No.:
CoP Project No.:
P.O. No.:
1
FA2001
2020-00001478
Explanation:
This change order encompasses the following: Durotech, Inc. the Construction Manager at Risk (CMAR) for Fire Station #
4, has established the Guaranteed Maximum Price (GMP) of $7,379,161. This GMP includes pre -construction fees of $420,231
already encumbered. The remaining construction phase fees total $6,958,930. After review, staff has approved the proposed
GMP. This amendment will increase the CMAR contract with Durotech to add the GMP.
Description of Work
1 Add Item No. 3.00, "Negotiated Construction Cost"
Please attach back-up documentation.
Cost & Time Change Summary
Original Contract:
Previous Change Order(s):
Contract prior to this Change Order:
Net increase (decrease) from this Change Order:
Revised Contract:
Finance Approval:
RECOMMENDED:
By: Date
Consultant
ACCEPTED*:
By: � ` l-, Date 10/02/2020
Contractor
Cost Time
$ 6,958,930.00
Cost
$ 420,231.00
$-
$ 420,231.00
$ 6,958,930.00
$ 7,379,161.00
Date
RECOMMENDED:
By: Date
Construction Manager
APPROVED:
By:
Owner
Date
*Contractor agrees to perform change(s) included in the Change Order for the price and time indicated. The prices for changes included all costs
associated with this Change Order.
Time
No work is to be done until this change order is executed. No payment to the Contract (or Consultant) shall be made for work included in the change order
until the Contractor's pay estimate is updated.
Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent, this Change
Order governs. Upon execution by all parties, the following changes identifies for the contract value and/or contract time shown, are made part of the
contract.
0 Days
Days
0 Days
Days
0 Days
Days
CHANGE ORDER NO. 1
ATTACHMENT "A"
PROJECT: Fire Station #4
September 30, 2020
PROJECT NO.: FA2001
ORIGINAL CONTRACT REVISED CONTRACT
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL QTY UNIT COST TOTAL NET CHANGE
ADD ITEM(S) TO CONTRACT:
3.00 Negotiated Construction LS
Cost
958,930.00 $6,958,930.00 $6,958,930.00
NET TOTAL CHANGE ORDER #1: $6,958,930.00
ORIGINAL CONTRACT AMOUNT: $420,231.00
CHANGE ORDER #1: $6,958,930.00
REVISED CONTRACT AMOUNT: $7,379,161.00