R2018-145 2018-08-13 RESOLUTION NO. R2018-145
A Resolution of the City Council of the City of Pearland, Texas, approving a
final change order with Construction Masters of Houston, Inc., in the amount
of$152,885.09, associated with the City Hall Renovation Project.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That certain change order associated with the City Hall Renovation Project,a
copy of which is attached hereto as Exhibit"A" and made a part hereof for all purposes, is hereby
authorized and approved.
Section 2. That the City Manager or his designee is hereby authorized to execute and
the City Secretary to attest the change order associated with the City Hall Renovation Project.
PASSED, APPROVED and ADOPTED this the 13 day of August, . 2018.
c=;)G)
TOM REID
MAYOR
ATTEST:
Le �' 4.•••••
Y NG L• �G,�IC _t.'.
Y SEC' r TARY 1\
APPROVED AS TO FORM: """o`‘‘````
DARRIN M. COKER
CITY ATTORNEY
CITY OF PEARLAND
of rr�Qi
PROJECTS DEPARTMENT
altRuNki 3519 Liberty Drive, Suite 300
Pearland, TX 77581
fsr �q4, www.cityofpearland.com/projects
CHANGE ORDER
City Hall Complex Renovation
Date of Issuance: 06/29/2018 Change Order No.: 5
Contractor: Construction Masters of Houston, Inc. CoP Project No.: FA0904
Consultant: Ziegler Cooper+ HBL Architects P.O. No.: 2017-00000807
Explanation:
This change order encompasses the following: Final Change Order
Description of Work Cost Time
1 Add Item No. 51.000,"Additional MEP Items" $50,169.08 0 Days
2 Add Item No. 52.000, "Additional Architectural Items" $22,061.67 0 Days
3 Add Item No. 53.000, "Unforeseen Condition Items" $ 15,021.21 0 Days
4 Add Item No. 54.000, "Staff Initiated Change Items" $65,633.13 0 Days
Please attach back-up documentation.
Cost&Time Change Summary Cost Time
Original Contract: $6,124,000.00 300 Days
Previous Change Order(s): $59,105.46 90 Days
Contract prior to this Change Order: $6,183,105.46 390 Days
Net increase(decrease)from this Change Order: $ 152,885.09 0 Days
Revised Contract: $6,335,990.55 390 Days
Finance Approval: '&`, 3 Date 09/07/2018
RECOMMENDED: RECOMMENDED:
By: AM �/[� 1>✓'l� Date 09/05/2018 By: 1 -- Date 08/30/2018
Consultant Construction Manager
ACCEPTED*: APPROVED:
By: Date 08/07/2018 By: ��"� - Date 09/07/2018
Contractor Owner
`Contractor agrees to perform change(s)included in the Change Order for the price and time indicated. The prices for changes included all costs
associated with this Change Order.
No work is to be done until this change order is executed. No payment to the Contract(or Consultant)shall be made for work included in the change order
until the Contractor's pay estimate is updated.
Revise the project plans and specifications as referenced and insofar as the original project drawings and specifications are inconsistent,this Change
Order governs. Upon execution by all parties,the following changes identifies for the contract value and/or contract time shown,are made part of the
contract.
Admin 1 of 2 6.Revised 7/25/08
•
CHANGE ORDER NO.5
•
ATTACHMENT"A"
June 29,2018
PROJECT: City Hall Complex Renovation PROJECT NO.: FA0904
ORIGINAL CONTRACT REVISED CONTRACT
ITEM DESCRIPTION UNIT QTY UNIT COST TOTAL QTY UNIT COST TOTAL NET CHANGE
ADD ITEM(S)TO CONTRACT:
51.000 Additional MEP Items LS 1 $50,169.08 $50,169.08 $50,169.08
52.000 Additional Architectural LS 1 $22,061.67 $22,061.67 $22,061.67
Items
53.000 Unforeseen Condition LS 1 $15,021.21 $15,021.21 $15,021.21
Items
54.000 Staff Initiated Change LS 1 $65,633.13 $65,633.13 $65,633.13
Items
NET TOTAL CHANGE ORDER#5: $152,885.09
ORIGINAL CONTRACT AMOUNT: $6,183,105.46
CHANGE ORDER#5: $152,885.09
REVISED CONTRACT AMOUNT: $6,335,990.55
•
•
•
•
•
Admin 2 of 2 6.Revised 7/25/08