R2018-077 2018-04-23 RESOLUTION NO. R2018-77
A Resolution of the City Council of the City of Pearland,Texas,awarding a unit
supply contract for Stabilized Base Road Material to Cherry Crushed Concrete
Companies, in an amount not to exceed $55,000.00 for the period of May 11,
2018 through May 10, 2019.
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF PEARLAND, TEXAS:
Section 1. That the City opened supply bids for stabilized base road material, and such
bids have been reviewed and tabulated.
Section 2. That the City Council hereby awards a bid to Cherry Crushed Concrete
Companies, in the unit price amounts reflected in Exhibit "A" attached hereto.
Section 3. The City Manager or his designee is hereby authorized to execute a unit
supply contract for stabilized base road material.
PASSED, APPROVED and ADOPTED this the 23rd day of April, A.D., 2018.
C
.,)GW/ 7 `9
TOM REID
MAYOR
ATTEST:
y „,`w i i i►,,,�
Z)Z1” s , --,' -- 4
.. ...:„....:.
.. ..
NG 11' FING, T;.c%C ,) =�`: �� _
Y S. ETARY
APPROVED AS TO FORM:
Qc3.----- /1 - CYr------
DARRIN M. COKER
CITY ATTORNEY
Resolution No. R2018-77
Exhibit "A"
Bid# 0218-22
Title Purchase of Stabilized Base Road Material
Cherry Crushed Concrete
Companies (Cherry
Line Items Crushed Concrete Inc)
Line Description UOM QTY Unit Extended
1 Cement Stabilized Reclaimed Base-Crushed Concrete, 7% cement Ton 123 $28.00 $3,444.00
2 Hauling - 1st Mile for Crushed Concrete, 7% Mile 1 $1.40 $1.40
3 Hauling- Each Additional Mile for Crushed Concrete, 7% Mile 1 $0.25 $0.25
4 Cement Stabilized Reclaimed Base- Crushed Concrete, 5% Cement Ton 202 $25.00 $5,050.00
5 Hauling- 1st Mile for Crushed Concrete, 5% Cement Mile 1 $1.40 $1.40
6 Hauling- Each Additional Mile for Crushed Concrete, 5% Cement Mile 1 $0.25 $0.25
7 Cement Stabilized Sand, 2 Sack, 9.4% Cement Ton 128 $18.50 $2,368.00
8 Hauling - 1st Mile for Cement Stabilized Sand Mile 1 $1.40 $1.40
9 Hauling - Each Additional Mile for Cement Stabilized Sand Mile 1 $0.25 $0.25
10 Cement Stabilized Base- Limestone, 1.5 Sack, 7% Cement Ton 10 $35.75 $357.50
11 Hauling - 1st Mile for Cement Stabilized Base- Limestone Mile 1 $1.40 $1.40
12 Hauling- Each Additional Mile for Cement Stabilized Base- Limestone Mile 1 $0.25 $0.25
13 Bank Sand Ton 100
14 Hauling- 1st Mile for Bank Sand Mile 1
15 Hauling - Each Additional Mile for Bank Sand Mile 1
16 Limestone Base Ton 50
17 Hauling - 1st Mile for Limestone Base Mile 1
18 Hauling - Each Additional Mile for Limestone Base Mile 1
19 Concrete Sand Ton 100 $28.50 $2,850.00
20 Hauling - 1st Mile for Concrete Sand Mile 1 $1.40 $1.40
21 Hauling - Each Additional Mile for Concrete Sand Mile 1 $0.25 $0.25
22 Crushed Concrete Ton 628 $18.50 $11,618.00
23 Hauling- 1st Mile for Crushed Concrete Mile 1 $1.40 $1.40
24 Hauling- Each Additional Mile for Crushed Concrete Mile 1 $0.25 $0.25
25 Bullrock, 3"x 5" Ton 50 $25.00 $1,250.00
26 Hauling - 1st Mile for Bullrock, 3"x 5" Mile 1 $1.40 $1.40
27 Hauling - Each Additional Mile for Bullrock, 3"x 5" Mile 1 $0.25 $0.25
Total $26,949.05