R2017-209 2017-10-23 Resolution No. R2017-209
Exhibit "A"
° 't r`'4 City of Pearland
3519 Liberty Drive
PEARLAND Pearland, TX 77581
'3T. 1xq°
General Services Contract
This Contract(Contract)is made between the City of Pearland,Texas(City),and Contractor.
The City and Contractor agree to the terms and conditions of this Contract, which consists of the
following parts:
I. Summary of Contract Terms
II. Signatures
III. Standard Contractual Provisions
IV. Special Terms and Conditions
V. Additional Contract Attachments
I. Summary of Contract Terms.
Contractor: Lone Star Pavement Services, Inc.
27045 Hanna Road
Conroe, TX 77385
Description of Services: Contractor will provide Road Striping Services, as needed per
the specifications of City of Pearland Bid#0716-47; City
Council Resolution#R2017-209.
Contract Type: Unit price contract.
Effective Date: November 1, 2017
Termination Date: October 31, 2018
Renewal: One (1) one-year renewal option remaining upon mutual
agreement of both parties.
II. Signatures. By signing below, the parties agree to the terms of this Contract:
CITY OF PEARLAND: CON_TRACTOR:
/
.._.S(''S D,— ic,/,,,/,
Purchasing Officer Date Title: "E.si pEv Y
Date: 2 -o ge,< 24�1�7
.0 o,vE �i-._ /�i'v�l7r�it-S'eQvICc-5
*(Sig by: Date: VA✓ ity Manager
Assistant City Manager
Director
Program Manager
*Contract Signature Authority: Program Manager-$5,999 or less
Director- $6,000 to $30,000
City Manager/Assistant City Managers -$30,001 to
$50,000
City Council Resolution -$50,000+
III. Standard Contractual Provisions.
A. Definitions.
Contract means this Standard Services Contract.
Services means the services for which the City solicited bids or received proposals as
described in Exhibit A, attached hereto.
B. Services and Payment. Contractor will furnish Services to the City in accordance with the
terms and conditions specified in this Contract. Contractor will bill the City for the Services
provided at intervals of at least 30 days, except for the final billing. The City shall pay
Contractor for the Services in accordance with the terms of this Contract,but all payments to
be made by the City to Contractor,including the time of payment and the payment of interest
on overdue amounts, are subject to the applicable provisions of Chapter 2251 of the
Government Code.
C. Termination Provisions.
(1) City Termination for Convenience. Under this paragraph,the City may terminate
this Contract during its term at any time for the City's own convenience where the
Contractor is not in default by giving written notice to Contractor. If the City
terminates this Contract under this paragraph,the City will pay the Contractor for all
services rendered in accordance with this Contract to the date of termination.
(2) Termination for Default. Either party to this Contract may terminate this Contract
as provided in this paragraph if the other party fails to comply with its terms. The
party alleging the default will give the other party notice of the default in writing citing
the terms of the Contract that have been breached and what action the defaulting
party must take to cure the default. If the party in default fails to cure the default as
specified in the notice, the party giving the notice of default may terminate this
Contract by written notice to the other party, specifying the date of termination.
Termination of this Contract under this paragraph does not affect the right of either
party to seek remedies for breach of the Contract as allowed by law, including any
damages or costs suffered by either party.
(3) Multi-Year Contracts and Funding. If this Contract extends beyond the City's
fiscal year in which it becomes effective or provides for the City to make any payment
during any of the City's fiscal years following the City's fiscal year in which this
Contract becomes effective and the City fails to appropriate funds to make any
required Contract payment for that successive fiscal year and there are no funds
from the City's sale of debt instruments to make the required payment, then this
Contract automatically terminates at the beginning of Mk'first day of the City's
successive fiscal year of the Contract for which the City has not appropriated funds
or otherwise provided for funds to make a required payment under the Contract.
D. Liability and Indemnity. Any provision of any attached contract document that limits the
Contractor's liability to the City or releases the Contractor from liability to the City for actual
or compensatory damages, loss, or costs arising from the performance of this Contract or
that provides for contractual indemnity by one party to the other party to this Contract is not
applicable or effective under this Contract. Except where an Additional Contract Document
provided by the City provides otherwise, each party to this Contract is responsible for
defending against and liable for paying any claim, suit, or judgment for damages, loss, or
costs arising from that party's negligent acts or omissions in the performance of this Contract
in accordance with applicable law. This provision does not affect the right of either party to
this Contract who is sued by a third party for acts or omissions arising from this Contract to
bring in the other party to this Contract as a third-party defendant as allowed by law.
E. Assignment. The Contractor shall not assign this Contract without the prior written
consent of the City.
F. Law Governing and Venue. This Contract is governed by the law of the State of Texas
and a lawsuit may only be prosecuted on this Contract in a court of competent jurisdiction
located in or having jurisdiction in Brazoria County, Texas. •
G. Entire Contract. This Contract represents the entire Contract between the City and the
Contractor and supersedes all prior negotiations, representations,or contracts,either written
or oral. This Contract may be amended only by written instrument signed by both parties.
H. Independent Contractor. Contractor shall perform the work under this Contract as an
independent contractor and not as an employee of the City. The City has no right to
supervise, direct, or control the Contractor or Contractor's officers or employees in the
means, methods, or details of the work to be performed by Contractor under this Contract.
The City and Contractor agree that the work performed under this Contract Is not inherently
dangerous, that Contractor will perform the work in a workmanlike manner, and that
Contractor will take proper care and precautions to insure the safety of Contractor's officers
and employees.
I. Dispute Resolution Procedures. The Contractor and City desire an expeditious means to
resolve any disputes that may arise between them regarding this Contract. If either party
disputes any matter relating to this Contract, the parties agree to try in good faith, before
bringing any legal action,to settle the dispute by submitting the matter to mediation before a
third party who will be selected by agreement of the parties. The parties will each pay one-
half of the mediator's fees.
J. Attorney's Fees. Should either party to this Contract bring suit against the other party for
breach of contract or for any other cause relating to this Contract, neither party will seek or
be entitled to an award of attorney's fees or other costs relating to the suit.
K. Severability. If a court finds or rules that any part of this Contract is invalid or unlawful,
the remainder of the Contract continues to be binding on the parties.
IV. Special Terms or Conditions. None.
V. Additional Contract Documents. The following specified documents attached to this Contract
are part of this Contract, except as follows: any provision contained in any of the Contractor's
Additional Contract Documents specified below that conflicts with a Contract provision not included
in the Contractor's Additional Contract Documents, does not apply to this Contract.
A. Contractor's Additional Contract Documents:
1. The contractor's response to Bid#0716-47 shall be construed as additional contract
documents.
B. City's Additional Contract Documents:
1. City standard insurance requirements.
2. Scope of Services, Exhibit A.
Exhibit A
CONTRACTOR'S SCOPE OF SERVICES
Scope of services provided shall consist of conducting road striping services as needed for the City
of Pearland Bid#0716-47 and Contractor's response to the same, as listed below:
Lone Star
Pavement
Specification Responses Services, LLC
Line Description UOM QTY Unit
0AAt7-.-.,Z.RIPlNG SERV1GE T 2Plad
4" SOLID OR BROKEN WHITE LINE(PAINT) -MATERIAL
1.1 COST PER LINEAR FOOT LF 1 $0.11
4"SOLID OR BROKEN WHITE LINE(PAINT) -LABOR COST
1.2 PER LINEAR FOOT LF 1 $0.07
4"SOLID OR BROKEN YELLOW LINE (PAINT)-MATERIAL
1.3 COST PER LINEAR FOOT LF 1 $0.11
4"SOLID OR BROKEN YELLOW LINE(PAINT)-LABOR COST
1.4 PER LINEAR FOOT LF 1 $0.07
8"SOLID WHITE LINE (PAINT) -MATERIAL COST PER
1.5 LINEAR FOOT LF 1 $0.86
8"SOLID WHITE LINE (PAINT)-LABOR COST PER LINEAR
1.6 FOOT LF 1 $0.12
12"SOLID WHITE LINE(PAINT)-MATERIAL COST PER
1.7 LINEAR FOOT LF 1 $0.61
12" SOLID WHITE LINE (PAINT)- LABOR COST PER LINEAR
1.8 FOOT LF 1 $0.41
24"SOLID WHITE LINE(PAINT)-MATERIAL COST PER
1.9 LINEAR FOOT LF 1 $1.23
24"SOLID WHITE LINE(PAINT)- LABOR COST PER LINEAR
1.10 FOOT LF 1 _ $0.82
6"LANE LINE SHADOW PAINT(8 FOOT WHITE/8 FOOT
1.11 BLACK) -MATERIAL COST PER LINEAR FOOT LF 1 $0.27
6" LANE LINE SHADOW PAINT(8 FOOT WHITE/8 FOOT
1.12 , BLACK)-LABOR COST PER LINEAR FOOT LF 1 $0.18
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING-
1.13 LABOR COST PER LINEAR FOOT-4"Line LF 1 $0.45
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING-
1.14 LABOR COST PER LINEAR FOOT-6" Line LF 1 $0.60
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING-
1.15 LABOR COST PER LINEAR FOOT-8" Line LF 1 $0.70
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING-
1.16 LABOR COST PER LINEAR FOOT- 12" Line LF 1 $1.25
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING-
1.17 LABOR COST PER LINEAR FOOT-24" Line LF 1 $2.00
ELIMINATION OF PAVEMENT MARKINGS BY GRINDING -
1.18 LABOR COST PER LINEAR FOOT for Arrow or Words LF 1 $50.00
1.19 WHITE ARROW(PAINT)-MATERIAL COST EA 1 $33.00
1.20 WHITE ARROW(PAINT)-LABOR COST EA 1 $22.00
1.21 ONLY LEGEND(PAINT)-MATERIAL COST EA 1 $33.00
1.22 ONLY LEGEND (PAINT) -LABOR COST EA 1 $22.00
RAILROAD CROSSING LEGEND COMPLETE(PAINT)-
1.23 _ MATERIAL COST EA 1 $123.36
RAILROAD CROSSING LEGEND COMPLETE(PAINT)-LABOR
1.24 COST EA 1 $82.24
_1.25 SCHOOL ZONE LEGEND (PAINT) -MATERIAL COST EA 1 $46.26
1.26 SCHOOL ZONE LEGEND (PAINT) - LABOR COST EA 1 $30.84
g4.i
L2 _ROAD STRIPING SERVICES-THERMO-PLAS.T(( ,'. " �;,
4"SOLID OR BROKEN WHITE LINE (THERMO-PLASTIC)-
2.1 MATERIAL COST PER LINEAR FOOT LF 1 $0.37
4" SOLID OR BROKEN WHITE LINE(THERMO-PLASTIC)-_2.2 LABOR COST PER LINEAR FOOT LF 1 $0.24
4" SOLID OR BROKEN YELLOW LINE(THERMO-PLASTIC) -
2.3 MATERIAL COST PER LINEAR FOOT LF $0.37
4"SOLID OR BROKEN YELLOW LINE(THERMO-PLASTIC)-
2.4 LABOR COST PER LINEAR FOOT LF $0.24
8"SOLID WHITE LINE (THERMO-PLASTIC)- MATERIAL COST
2,5 PER LINEAR FOOT $0.43
8" SOLID WHITE LINE(THERMO-PLASTIC) -LABOR COST
2.6 PER LINEAR FOOT $0.28
12"SOLID WHITE LINE (THERMO-PLASTIC)-MATERIAL •
2.7 COST PER LINEAR FOOT 1 $0.86 •
12" SOLID WHITE LINE (THERMO-PLASTIC)- LABOR COST
2.8 PER LINEAR FOOT 1 $0.57 •
24"SOLID WHITE LINE(THERMO-PLASTIC) -MATERIAL
2.9 COST PER LINEAR FOOT 1 $1.78 •
24"SOLID WHITE LINE (THERMO-PLASTIC)- LABOR COST •
2.10 PER LINEAR FOOT 1 $1.19
2.11 WHITE ARROW(THERMO-PLASTIC)-MATERIAL COST 1 $60.00
2.12 WHITE ARROW(THERMO-PLASTIC)-LABOR COST 1 $40.00
2.13 ONLY LEGEND(THERMO-PLASTIC)-MATERIAL COST EA 1 $75.00
2.14 ONLY LEGEND(THERMO-PLASTIC -LABOR COST EA 1 _$50.00 •
RAILROAD CROSSING LEGEND COMPLETE(THERMO-
2.15 PLASTIC)-MATERIAL COST EA 1 $77.10
RAILROAD CROSSING LEGEND COMPLETE (THERMO-
2.16 PLASTIC)-LABOR COST EA 1 $51.40
SCHOOL ZONE LEGEND (THERMO-PLASTIC)-MATERIAL
2.17 _COST EA 1 $74.01
2.18 SCHOOL ZONE LEGEND_(THERMO PLASTIC LABOR COST EA _ 1 $49.34
3.1 REMOVAL OF TRAFFIC BUTTONS/MARKERS EA 1 $1.00
SUPPLY AND INSTALL ONE SIDED REFLECTOR ON
3.2 CONCRETE EA 100 $5.25
SUPPLY AND INSTALL ONE SIDED REFLECTOR ON
3.3 ASPHALT EA 100 $4.00
SUPPLY AND INSTALL TWO SIDED REFLECTOR ON
3.4 CONCRETE EA 100 $5.25
SUPPLY AND INSTALL TWO SIDED REFLECTOR ON
3.5 ASPHALT EA 100 _ $4.00
.